17 asmgcs human factors plan asmgcs levels 1 2

Upload: lauramariadumitriu

Post on 09-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    1/31

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    2/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    This page is intentionally left blank

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    3/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    DOCUMENT IDENTIFICATION SHEET

    DOCUMENT DESCRIPTION

    Document Title

    Human Factor Plan for A-SMGCS level 1 & 2

    EDITION: 2.0

    EDITION DATE: 06 Jan 2004

    Abstract

    This document describes the Human Factors Plan in support of the study of the A-SMGCSproject. It identifies a series of recommendations to ensure that A-SMGCS can deliver thedesired performance improvements.

    Keywords

    Human Factors, A-SMGCS

    AUTHORS :

    M. Woldring

    JP. Lesueur

    L. Moulin

    TEL: ++ 31 433661554 DIVISION:

    EATMP/DAS/HUM

    EATMP/DAT/APT

    SOFREAVIA

    DOCUMENT STATUS AND TYPE

    STATUS CATEGORY CLASSIFICATION

    Working Draft Executive Task General Public

    Draft Specialist Task Restricted

    Proposed Issue Lower Layer Task Internal Use

    Released Issue

    ELECTRONIC BACK-UP

    INTERNAL REFERENCE NAME :

    HOST SYSTEM MEDIA SOFTWARE(S)

    Microsoft Windows Type: Hard disk Name: MS Word

    Media Identification: Text processor Version: 97

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    4/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    DOCUMENT APPROVAL

    AUTHORITY NAME AND SIGNATURE DATE

    Authors of theDocument

    M. Woldring

    JP. Lesueur

    L. Moulin

    MANAGEMENT APPROVAL

    AUTHORITY NAME AND SIGNATURE DATE

    Human FactorsExpert M. Woldring

    Operational Expert,A-SMGCS Expert J.P. Lesueur

    A-SMGCS ProjectManager P. Adamson

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    5/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    DOCUMENT CHANGE RECORDThe following table records the complete history of the successive editions of the present document.

    EDITION DATE REASON FOR CHANGE

    SECTIONS OR

    PAGESAFFECTED

    0.1 07 January2004

    Inclusion of conclusions and recommendations All

    REFERENCE DOCUMENTS

    N TITLE DATE

    1 The Human Factors Case: Guidance for HF Integration Draft doc.

    2 A-SMGCS Project Management Plan APR/PMP1/A-SMGCS

    Edition 2.13 A-SMGCS Safety Policy Edition V0.1

    4 EATMP Safety Policy SAF.ET1.ST01.1000-POL-01-00,

    edition 2.0

    5 EATMP Safety Plan Edition 2.0

    6 EATMP Safety Assessment Methodology, Part I SAF.ET1.ST03.10.00-MAN-01-00,

    edition 1.2

    7 EATMP Safety Assessment Methodology, Part II SAF.ET1.ST03.1000-MAN-02-00,

    edition 1.0

    8 EATMP Safety Assessment Methodology, Part III SAF.ET1.ST03.1000-MAN-03-00,

    edition 0.2

    9 EUROCONTROL Safety regulatory Requirement) RiskAssessment & Mitigation in ATM

    ESARR 4, edition

    1.00

    10 ICAO Manual of Surface Movement Control and GuidanceSystems (SMGCS)

    DOC 9476,

    11 ICAO European Manual on Advanced Surface MovementControl and Guidance Systems (A-SMGCS)

    AOPG, Final Draft,

    Nov 2001

    12 Manual on Advanced Surface Movement Guidance andControl System (A-SMGCS)

    Air Navigation

    Conference 11,

    Information Paper 4

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    6/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    13 ECAC Surveillance Strategy for ECAC Jan 1998

    14 A-SMGCS Project Strategy D1

    15 Definition of A-SMGCS Implementation Levels D2

    16 A-SMGCS Level I Operational Concept and Requirements D3

    17 A-SMGCS Level II Operational Concept and Requirements D4

    18 Functional Specification for A-SMGCS ImplementationLevel I

    D5

    19 Functional Specification for A-SMGCS ImplementationLevel II

    D6

    20 Validation Master Plan for A-SMGCS Implementation LevelI

    VMP I

    21 Validation Master Plan for A-SMGCS Implementation Level

    II

    VMP II

    22 ICAO Annex 14, Volume I, Chapter 8 Annex 14

    23 Concept Justification and User Requirements, workingpaper

    (AOT/10 / 10-12

    June 2002)

    WP/3

    24 EUROCAE WG-41, MASPS for A-SMGCS, Edition ED-87A,January 2001

    ED-87A

    25 MAEVE Validation Guideline Handbook MAEVE

    26 ECAC Ground and Taxi Accidents Rates

    Conformance with A-SMGCS Target Level of Safety

    Version 01

    27 JAR-OPS

    Low Visibility Procedures (LVP)

    -

    ABBREVIATIONS

    AO Airport Operations

    ATFM Air Traffic Flow Management

    ATM Air Traffic Management

    ATC Air Traffic Control

    A-SMGCS Advanced Surface Movement Guidance and Control System

    ANSP Air Navigation Service Provider

    APR Airport Operations Program

    APT Airport Throughput Business Division

    EATMP European Air Traffic Management Program

    HF Human Factors

    HFIA Human Factors Issue Analysis

    HFICs Human Factors Issue Components

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    7/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    HMI Human Machine Interface

    ICAO International Civil Aviation Organisation

    SHAPE Solutions for Human Automation Partnerships in European ATM

    SMGCS Surface Movement Guidance and Control System

    SMR Surface Movement Radar

    TRM Team Resource Management

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    8/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    TABLE OF CONTENTS

    DOCUMENT APPROVAL _______________________________________________________________ 4MANAGEMENT APPROVAL ____________________________________________________________ 4DOCUMENT CHANGE RECORD_________________________________________________________ 5REFERENCE DOCUMENTS_____________________________________________________________ 5ABBREVIATIONS _____________________________________________________________________ 6TABLE OF CONTENTS ________________________________________________________________ 81 INTRODUCTION __________________________________________________________________ 91.1 GENERAL CONTEXT OF THE PROJECT___________________________________________________ 91.2 SPECIFIC CONTEXT OF THE PROJECT ___________________________________________________ 92 APPROACH_____________________________________________________________________ 112.1 METHODOLOGICAL PRINCIPLES ______________________________________________________ 112.2 PARTICIPANTS __________________________________________________________________ 113 DEVELOPMENT OF THE A-SMGCS HUMAN FACTOR PLAN ____________________________ 123.1 1ST STEP:FACT FINDING ___________________________________________________________ 123.2 2ND STEP:HUMAN FACTOR ANALYSIS __________________________________________________ 15

    3.2.1 Check list items ____________________________________________________________ 153.2.2 Human Factors issue components _____________________________________________ 173.2.3 Determine likely impact ______________________________________________________ 173.2.4 Identify current and planned initiatives __________________________________________ 173.2.5 Rated Recommendations_____________________________________________________ 18

    4 CONCLUSION___________________________________________________________________ 185 APPENDIX 1: HUMAN FACTORS ISSUE COMPONENTS (HFICS) FOR THE A-SMGCS _______ 206 APPENDIX 2: LIKELY IMPACT, SAFEGUARDS (ACTION ALREADY CARRIED OUT, ACTIONSTO BE DONE AND URGENCY RATING __________________________________________________ 247 APPENDIX 3: CHECK-LIST FOR SIMULATION TRIALS,_________________________________ 29

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    9/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    1 Introduction

    1.1 General context of the project

    The Airport Operations Programme (APR) has been developed by the AirportThroughput Business Division (APT) in consultation with the Airport OperationsTeam (AOT). While the overall EATMP aim is harmonisation and integration ofEuropean ATM, the APR will, in full recognition of the complex interdependenciesof ATM and Airport Operations (AO), generate activities focused on their jointoptimisation at airports in the ECAC area. This will be achieved through bestexploitation of available technical and operational solutions for the short term (upto 2006). The planning and implementation of the programme is undertaken withinthe strategic framework and the specific requirements laid down in agreed AirportOperations ATM Concept and Strategy documents.

    The APR comprises the four following activities:

    a. Improved traffic management on the movement area, improving safety and theefficiency of surface operations, in particular during reduced visibility conditions,through the phased development and implementation of the Advanced SurfaceMovement, Guidance and Control System (A-SMGCS) functionality, i.e. improvedsurface movement surveillance, conflict detection & alert, development of runwaysafety nets based on A-SMGCS;

    b. Information sharing & capacity management, ensuring that relevant stakeholderswill be provided with timely information that is essential for their operations in orderto efficiently utilise the en-route and airport capacity in an integrated fashion,through the application of Collaborative Decision Making between ATC, ATFM,Aircraft and Airport Operators;

    c. Airport airside capacity enhancement practices and initiatives, establishing andrecommending best practices that enhance runway capacity and achieveharmonisation of Ground Control, ATC and aircrew operating procedures foroperations on the movement area, with the goal to reduce runway occupancy andtaxi times to the minimum safely practicable. Studying the possibility to safelylower the present separation minima for arriving and departing aircraft in view ofimproved knowledge of the wake vortex phenomenon and its unambiguousdetection by means of ground and/or airborne means.

    d. Runway safety, ensuring the harmonised implementation of the European ActionPlan for the Prevention of Runway Incursions.

    This document has been developed in the frame of the Human Factors support toImproved traffic management on the movement area.

    1.2 Specific context of the project

    Today, the ICAO Manual of Surface Movement Guidance and Control Systems(SMGCS) (Doc.9476) describes how traffic should be controlled on the surface ofan airport, based upon the principle of see and be seen. However, it is recognised

    that the current SMGCS is not capable of delivering the required capacity,particularly on complex airports and under conditions of reduced visibility.

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    10/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    Therefore, work has commenced on developing the concept of Advanced SurfaceMovement Guidance and Control Systems (A-SMGCS). To date a considerableamount of work has been performed by ICAO (AOPG PT/2), EUROCAE (WG.41)and the European Commission (DGTREN).

    The need for A-SMGCS is also recognised through the ATM Strategy for the Years

    2000+. This Strategy contains a number of Directions for Change andcomplementary Operational Improvements, which contribute towards a realisationof the overall concept for the ATM Network within ECAC.

    The Direction for Change applicable to A-SMGCS is entitled Improved TrafficManagement on the Movement Area and the associated OperationalImprovements are:

    1. Improvement of Aerodrome Control Service on the Manoeuvring Area;2. Improvement of Conflict Detection and Alert for all Traffic on the Movement

    Area;3. Improvement of Planning and Routing on the Movement Area;

    4. Improvement of Guidance and Control on the Movement Area.

    These Operational Improvements are to be met through the A-SMGCS Project ofthe EATMP Airport Operations Programme (APR), which aims to facilitate the earlyimplementation of A-SMGCS Implementation Levels 1 & 2 through thedevelopment of appropriate operational concepts, requirements and procedures. Italso aims at addressing related operational issues such as human factors andlicensing of controllers.

    The first phase of the project has involved the development of agreedrequirements for A-SMGCS Levels 1 & 2, namely:

    Agreed User Requirements; A Concept of Operations;

    Operational Requirements;

    Functional Requirements.

    In parallel, work has progressed on the identification and development of theprocedures supporting the implementation of A-SMGCS. These procedures focusupon enabling the controller, when appropriate, to issue ATC instructions andclearances to aerodrome traffic on the basis of surveillance data alone.

    The second phase of the project will involve the validation of the concept,

    requirements and procedures for Implementation Levels 1 & 2. Validation willinvolve the use of simulations (both fast time and real time) and pre-operationaltrials at one (or more) representative airports through which the benefits andfeasibility of A-SMGCS (Implementation Levels 1 & 2) shall be assessed,demonstrated and confirmed.

    A principle aim of the validation process is to assess the Human Factors impact ofA-SMGCS Level 1 and/or 2 implementation, with data obtained during thevalidation process being used to develop appropriate Human Factor Cases (i.e.Human Factor Cases for Implementation Levels 1 & 2).

    To help identify and ensure that the appropriate data is available for the validation

    a Human Factor Plan has to be developed.

    Sofreavia has been required to develop the Human Factor Plan for the APR A-SMGCS Project. This plan shall define the Human Factor activities to be

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    11/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    undertaken within the A-SMGCS project (particularly during the validation process)following EUROCONTROLs guidelines for Human Factors Integration.

    2 Approach

    2.1 Methodological principles

    As a working basis, the Human Factors case process has been used.

    The Human Factors Case approach has been developed by EurocontrolDAS/HUM to provide a comprehensive and integrated approach to ensure that thedesign of a technical, human, and/or procedural system can deliver desiredperformance improvements. The Human Factors Case is designed to be simple,practical and effective, with four key stages:

    Stage 1 Fact finding and Human Factors Issues Analysis (HFIA)

    Stage 2 Human Factors Integration

    Stage 3 Monitoring

    Stage 4 Human Factors Case Assessment

    The Human Factors Plan development consisted in the application of the firststage of the Human Factors Case Approach.

    2.2 Participants

    Participants met together four times using the standard group-based brainstorming

    technique. The work done by the group consisted in following different workingsteps:

    1. Fact findings

    2. Human Factors analysis

    Each of the corresponding outputs are presented in the paragraph 3 and theappendix 1 and 2.

    Table 1 shows the participants profiles.

    Table 1

    Person Attendance Group HFIA Role

    Human Factors Expert Eurocontrol (MW) Contributor / Facilitator

    Project Manager Eurocontrol (PA) Contributor

    Users (e.g. controllers) Eurocontrol (JPL) Contributor

    Training Expert Sofravia (LM) Contributor

    Other Human Factors Expert Sofravia (LM) Contributor / Facilitator

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    12/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    3 Development of the A-SMGCS Human Factor Plan

    3.1 1st

    step: Fact Finding

    Following the Human Factors Case: Guidance for HF Integration (EurocontrolDraft document in document reference list), the first part of the Human Factorscase should set the scene and provide the necessary background informationabout the proposed system or design change.

    In order to simplify this process, a standard form has been used to produce theminimum necessary factual information.

    HUMAN FACTORS CASE

    PART 1 - FACTUAL INFORMATION

    Date 07/01/04

    Project Name A-SMGCS

    Project Manager Paul Adamson Tel 32 2 7293308 E-mail [email protected]

    HF Coach Michiel Woldring Tel 32 2 729 35 66 E-mail [email protected]

    Type of Project Traffic / SituationDisplay

    Controller Tool Communication Navigation

    Surveillance

    System Control &

    Monitoring Other (state)

    High-Level ProjectObjectives

    The strategic objectives of the A-SMGCS are to optimise the airport capacity(throughput) in maintaining or even increasing safety of operations, minimising thecosts and impact on environment.

    Safety means to minimise the air navigation services contribution to the risk of an

    aircraft accident as far as is reasonably practicable.

    Capacity (throughput) results will be achieved through a better use of traffic

    surveillance especially in bad weather and with connection with others airportsystems.

    Cost effectiveness will be achieved through the ability to provide an agreed level

    of service at the least cost with different level of A-SMGCS

    Environment will be also impacted by A-SMGCS: By smoothing ground flow of

    traffic in all weather conditions and avoiding ground delays to engines runningaircraft, the noise and gaseous emissions at and around airport will be reduced.

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    13/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    HUMAN FACTORS CASE

    PART 1 - FACTUAL INFORMATION

    Project Background Despite implementation of SMGCS in the ECAC area, some European airportshave faced severe runway incursions lately, which ended up as major incidents oraccidents. The progressive growth in traffic, the complexity of aerodrome layouts

    and the increasing number of operations, which take place in low visibilityconditions, are amongst the contributing factors in the increasing of delays andnumber of ground incidents. The existing systems demonstrate weaknesses incoping with the present situation and the future systems should tackle thefollowing concerns and needs.

    The Airport Operations Strategy derived from ATM 2000+ Strategy has beendeveloped to perform in priority the task of improving traffic management on themovement area.

    -Improvement of Aerodrome and ground control service,-Improvement of conflict detection and alert for the movement area-Improvement of Planning and routing on the movement area-Improvement of guidance and control on the movement area

    System Description The A-SMGCS is a system resulting in a technical chronological improvement ofexisting tools (including an alert system) associated with updated procedures:

    Surface Movement Radar (SMR), come first which gives only a non identified targetof mobiles moving on the ground. the low level of integrity, the ATC workload tokeep the individual identification lead ICAO to accept it only to "assist andaugment" the visual and procedural ATC service (It will remain to detectunidentified targets and to help to provide contingency procedures)

    Improvements to SMR updated the initial tool into an integrated system, using ornot using (depending on traffic level) connection with automated lighting system,magnetic loop and radar tracking (SMGCS concept) but without connection withonboard system, that kept the integrity of the information at a non acceptable levelfor all weather operations.

    The A-SMGCS Levels 1 & 2 (mainly the ATC surveillance display and associatedalarm system) introduces the concept of "co-operative targets" that provide a highlevel integrity link between aircraft and vehicles and the ground tracking system. Itis initially based mainly upon Mode "S" transponder transmissions for aircraft andsome other different systems for vehicles.

    With the resulting integrity and accuracy in positioning mobiles, an alarm systemcan be set up, providing acoustic and visual alert to the controller in case ofpotential conflict on the runway and it's vicinity.

    System Lifecycle Stage Early Phases Middle Phases Late Phases

    Initiation Planning Feasibility Develop-

    ment

    Pre-

    operational

    Implement-

    ation

    Local

    Implement-ation

    Operations

    Human Factors Case Version

    Preliminary Human Factors Case Interim Human Factors Case Operational Human Factors Case

    Related or Similar Existing / Predecessor Systems (inc. Operational Experience and Data)

    SMRSMGCS

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    14/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    HUMAN FACTORS CASE

    PART 1 - FACTUAL INFORMATION

    Key Safety Documentation (e.g. Previous FHA Documentation, Safety Case/Assessments)

    Local documents linked to individual airports.

    See attached file.

    Key Design and Testing Documentation (e.g. Design Documentation, Trial/Simulation Data)

    Design: Doc numbered 2,10 to 19 and 22 in the reference documents list page 6.

    Testing (Validating): Doc numbered 20,21 and 24 in the reference documents list page 6.

    Human Centred Automation Principles ?Rate the principles below in terms of whether the subject system adheres to these principles.

    1. The human must be in command. 2. To command effectively, the human must be involved. 3. To be involved, the human must be informed. 4. Functions must be automated only if there is good reason for doing so. 5. The human must be able to monitor the automated system. 6. Automated systems must, therefore, be predictable. 7. Automated systems must be able to monitor the human operator. 8. Each element of the system must have knowledge of the others intent. 9. Automation must be designed to be simple to learn and operate. Number Notes

    Key Stakeholders

    Name Role Tel Email

    ANSP, ATC guild

    Airports Operators

    Industry, National Researchcentres

    Airlines, Pilots guilds

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    15/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    3.2 2nd

    step: Human Factor Analysis

    3.2.1 Check list items

    Because the task context is so critical in HF, it is often necessary to research thearea prior to conducting the HFIA study.

    A default checklist is shown in Table 2, developed by Eurocontrol DIS/Hum(Human Factors Case: Guidance for HF Integration).

    Table 2: Checklist items.

    Human Factors Area Item

    1. Human-Machine Interface

    and Working Environment

    Input devices, visual displays, information requirements,

    alarm handling, console/working area, HMI usability, userrequirements, health risks, fatigue, distraction andconcentration, noise, lighting, temperature/humidity/airquality, workplace arrangement, workplace accommodation.

    2. Organisation and Staffing Staff requirements, manpower availabil ity, ATCOprofile/selection criteria, job attractiveness, ageing, shiftorganisation.

    3. Training and Development Training needs, performance/competence standards, trainingcontent, training methods and media, negative transfer oftraining, trainer role/responsibilities/competency, transitionfrom classroom to OJT, emergency/unusual situation training,testing of training effectiveness, negative effects onoperational task performance.

    4. Procedures, Roles andResponsibilities

    Allocation of function, involvement, workload,trust/confidence, skill degradation, procedure format andpositioning, procedure structure, procedure content,procedure realism.

    5.Teams and Communication Team structures/dynamics/relations, (inter-) team co-ordination, position handover processes, communicationworkload, phraseology, national language differences,changes in communication methods, interference effects andinformation content.

    6. Recovery from Failures Human error potential, error prevention/detection/recovery,detection of and recovery from system failures.

    From this by default list, the following was selected during a brainstorming session of theworking group, in order to specifically address the A-SMGCS issue:

    Procedures, Roles and Responsibilities

    Trust and confidence, important for acceptance, link to reliability

    Continuous involvement of operational people, inclusion of non ATC population(e.g. APRON management)

    Workload (hypothesis: workload decrease)

    Skill diversification increased use of surveillance data, head down / head uptime?

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    16/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    Procedure format and structure should reflect the way people act or try to acttoday. Current/existing and new procedures.

    ATC procedure applicability and relevance. Safe, useful, up to date.

    Human Machine Interaction

    Generic advice for HMI and workplace accommodation such as input devices,visual displays / lay-out, and console area,

    a default setting intuitive interface limited settings for colours/ fonts/ number of windows etc. consoles/displays shouldnt obstruct controllers view ergonomics (distances, size of screens)

    Local requirements may add specifics

    (False) alarm handling

    Integration with other systems (electronic flight strips, runway incursionmonitoring)

    Use A-SMGCS procedures group as user group

    Specifics of tower lighting,

    Health/fatigue: head up/down and eye-muscle (colours, brightness)

    Impacts of new displays etc. on temperature/humidity/air quality

    Training and Development

    Identification of additional training needs, content and methods - includingrecurrent training - for Aerodrome Control Surveillance Ratings or qualification.(Skill diversification, Head up Head down issue, understanding of howmultilateration works)

    Definition of additional competence standards

    Negative transfer of training

    Trainer role and competency, as for all new tools/developments

    Transition - changes to pilot and driver communications, procedures incl.Transponders

    Recovery and contingency training

    Teams and Communication

    Team structures/dynamics, better shared SA (e.g. CDG: monitors for the TMAcontroller) will reduce need for co-ordination

    Hand over, (new) tool specific, visual support will make hand over easier

    Communication workload will decrease, to what extend?

    Changes in communication methods, e.g. silent hand over, less need for co-ordination, changing feedback loops

    Decreasing or increasing interference effects

    Team differences (e.g. in use of tools) and transfer of individuals, different fromcurrent?

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    17/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    This list has been used as a working basis to carry out the next steps.

    3.2.2 Human Factors issue components

    Human Factors Issue Components (HFICs) are aspects of the HF Issue specific tothe system that need to be considered, that is to say the A-SMGCS. The HFICsmaybe expressed as a question. For instance, they may be pertinent questionsabout deviations from expectations or intentions (users, designers, managers,etc.). All the HF items were analysed.

    Following the checklist item, several questions have been identified for each of theitems (see appendix 1: Human Factors issues list).

    3.2.3 Determine likely impact

    Once all of the HF Issue Components for a particular category have beenanswered, the likely impacts are detailed for each HF Issue Component. These are

    generated using the question: What if the HF Issue Component is not

    addressed adequately? Group HFIA requires the input of the project teamexperts to evaluate the likely impact or the consequences of not addressing eachissue appropriately. Impacts may be concrete or abstract.

    The list below present the more frequently likely impacts identified when using theA-SMGCS:

    Increased likelihood of errors No use of part of the system functions by the controllers

    Under-skilled controllers

    3.2.4 Identify current and planned initiatives

    Once the impacts have been detailed, current or planned initiatives that shouldhelp to address (e.g. prevent, control or mitigate) the HF Issue Component, or itsimpact, were examined.

    Initiatives must be currently under development OR formally planned and

    documented within the overall project plan.

    When the initiative identified was not a concrete under process project, it had beenrecorded under the Recommendations/Comments column. It is important thatcommon-sense safeguards are recorded to make sure they are not forgotten.

    The main current and planned initiatives identified in response to the listed impactsare:

    Safety assessment study

    Group working on procedure design

    Ergonomic design of the HMI display TRM

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    18/31

    Human Factors Plan for A-SMGCS Levels 1 & 2

    3.2.5 Rated Recommendations

    All the Human Factors issues (components, impacts and actions) had been ratedby the working group thanks to different criteria provided by the Human FactorCase Guidance for FH Integration approach:

    The Importance of the issue: taking into account the severity of the impact andthe probability (likelihood) of the impact in light of the current or plannedinitiatives.

    The Urgency of the issue: degree to which the FH issue component requiresspeedy attention and/or action.

    Priority: using a scale going from 1 (Low), 2 (Medium), to 3 (High) to rateImportance and Urgency. Priority was calculated by the summing of theImportance and Urgency ratings.

    The priority ratings help to plan the level of effort that should be spent onimplementing recommendations.

    Appendix 2 shows all the ratings for each Human Factors Issues.

    4 Conclusion

    The output of the Human Factor Plan for A-SMGCS level 1 & 2 study is a list ofrecommendations. A first expert overlook let to an importance scale of 2 (low) to 6(high) indicating recommendation for priority (see appendix 2).From those recommendations a proposal for checklists that can be used insimulation trials, validation process, training design, and preparation or installationof A-SMGCS in order to guide the work to be carry out, is presented in appendix 3.

    This checklist has to be adapted according to specific objectives.

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    19/31

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    20/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    5

    App

    endix1:HumanFacto

    rsIssuecomponents(

    HFICs)fortheA-SMGC

    S

    1.Procedures/roleandresponsibilities.

    a.Trustandconfidence,importantforacceptance,linktoreliability

    i.Whatiffrequenttechnicalfailuresoccur(unreliableprovideddata)?

    ii.Howtoinsureuse

    rconfidenceinthesystem?

    iii.Couldbepossible

    thatthe(different)useofthesystemimpactconfidencewithintheteam?

    b.Continuousinvolvementofoperationalactors(inclusion

    ofnonATCpopulation)

    i.Whatiftheinvolvementofthedifferentactorsis

    notcontinuousorunbalanced?

    ii.WhatifOperationalactorssampleisnotreprese

    ntative?

    c.Workload(hypothesis:workloadisdecreased)

    i.Whatifworkloadisincreasing?

    ii.Whatifworkloadisthesame?

    iii.Whatifworkloadisdecreasing?

    iv.Whatiftheinform

    ationdiscriminationrequireah

    ighattentiondemand?

    d.Skilldiversificationincrea

    seduseofsurveillancedata,h

    eaddown/headuptime.

    i.Whatifheaddowntimeisincreased?

    ii.Whatifskillsnece

    ssarytouseA-SMGCSaresp

    ecific?

    e.Procedureformatandstructureshouldreflectthewaypeopleactortrytoacttoday.Current/existingandnewprocedures.

    i.Whatiftheuseof

    thesystemcreatestheneedo

    fnewprocedure?

    ii.Whatiftheneede

    dnewproceduresarefarfrom

    thecurrentpractices?

    iii.Whatiftheneede

    dnewproceduresareclosefro

    mthecurrentpractices?

    iv.Whatiftheprocedurecontentisnotspecifieden

    ough?

    f.

    ATCprocedureapplicabilityandrelevance.Safe,useful,uptodate.

    i.Couldtheactual(

    current)proceduresbesufficie

    nttousethesystem?

    ii.Howtodesignrelevantprocedures?

    iii.Howtodesignala

    rmmanagementprocedurein

    ordertoguarantysafety?

    g.Skilldegradation

    i.Whatiftheuseof

    thesysteminducesriskofskilldegradation

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    21/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    ii.Howtoidentifyskilldegradationrisks?

    2.HumanMachineInteraction

    a.GenericadviceforHMIandworkplaceaccommodationsuchasinputdevices,visuald

    isplays/layout,andconsolearea

    i.WhatifHMIhave

    adefaultsetting?

    ii.WhatifHMIprese

    ntanewvisualdisplay?

    b.Localrequirementsmayaddspecifics

    i.Howtomatchthe

    localspecifics?

    ii.Whatifinsufficien

    tconsiderationhasbeengiven

    totheaccommodationofloca

    lequipment(spaceorganisatio

    nandfurniture)?

    c.Falsealarmhandling

    i.Whatiffalsealarm

    sarefrequent(linktoreliability,trustandconfidence)?

    ii.Whatiffalsealarm

    saredifficult/impossibletodiscriminatefromrightones?

    iii.Whatiftheobject

    ofthealarmisdifficulttoidentify?

    iv.Whatifthealarm

    isveryloudandimpossibletoacknowledgeduringseveralm

    inutes(noisedistraction)?

    v.Whatifthecontro

    llercaneasilyacknowledgethealarm?

    d.Integrationwithothersystems

    i.Whatifprocedure

    sarenotcompatible?

    ii.WhatifHMIused

    differentorcontradictoryvisua

    lcodes?

    e.Specificsoftowerlighting

    i.Whatiftherearenolocalmeanstolimitthesun

    lightinthetower?

    f.

    Health/fatigue:headup/headdownandeye-muscle(co

    lourandbrightness)

    i.Whatifuserscom

    plainaboutmorefatigue?

    ii.Whatifuserscom

    plainabouteyefatigue?

    3.Tr

    ainingandDevelopment

    a.Identificationofadditionaltrainingneeds,contentsandmethodsincludingrecurrenttrainingforaerodromecontro

    lsurveillance

    ratingsorqualification(sk

    illdiversification,headupheaddownissue,understandingo

    fhowmultilaterationworks)

    i.Whatifneedsfor

    newknowledgeandskillareid

    entify?

    ii.Whatifnothingex

    istinthecurrentsyllabustoad

    dressthenewknowledgeneeds?

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    22/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    b.Definitionofadditionalco

    mpetencestandards

    i.Whatifthesystem

    requiresthedefinitionofadditionalcompetencestandards?

    c.Negativetransferoftraining

    i.Whatifnegativetransferoftrainingareidentified

    ?

    ii.Whatifalltherequiredskillsorknowledgeareallnew?

    d.Trainerroleandcompete

    ncy,asforallnewtools/develo

    pments

    i.Itispossiblethatthesysteminducespecifictrainercompetency?

    e.Transitionchangestop

    ilotanddrivercommunications

    ,proceduresincludingtranspo

    nder.

    i.Whatifpilotordriverarenotawareofthesystem

    specifics

    ii.See1.b

    f.

    Recoveryandcontingenc

    ytraining

    i.Couldtheuseoft

    hesysteminducearecoverya

    ndcontingencytraining?

    ii.Howtotrainthecontrollertoreacttoalarm?

    4.Te

    amsandcommunication

    a.Teamstructures/dynamic

    s,bettersharedSA(monitorsfortheTMAcontroller)willreduceneedforco-ordination

    i.Whatifco-ordinationneedsisnotreduced?

    ii.Whatiftheteamdynamicsislesscomplex?

    iii.Whatifco-ordinationneedsdecreasedbutappe

    armorecriticalinsomeprecisesituation(scenariosorconfiguration)?

    iv.Whatifthesystem

    failedordowngraded?

    b.Handover,toolspecific,visualsupportwillmakehandovereasier

    i.Whatiflackoftraininginducesdifferentusesan

    dunderstandingamongusers?

    ii.Whatifsystemdo

    wngraded?

    c.Communicationworkload

    willdecrease,towhatextend?

    i.Whatifverbalcom

    municationdisappeared?

    ii.Howdropincomm

    unicationwillimpactteambuilding?

    d.Changesincommunicationmethods,e.g.silenthandover,lessneedforco-ordination

    ,changingfeedbackloops

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    23/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    i.Whatiffeedbackloopschange?

    e.Decreasingorincreasing

    interferenceeffects

    i.Whatifthesystem

    inducesincreasedinterferenceeffects(alarm)?

    f.

    Teamdifferences(e.g.in

    useoftools)andtransferofin

    dividuals,differentfromcurrent?

    i.Whatifdifferentp

    racticesarepossiblewiththeu

    seofthesystem?

    g.Phraseology

    i.Whatifthecurren

    tphraseologyisnotapplicable

    orsufficient?

    ii.Whatiftheuseof

    thesysteminducedtheneedofaspecificphraseology?

    5.Recoveryfromfailure(Managing

    systemdisturbances)

    a.Systemfailuremanagement

    i.Whatifthesystem

    failedordowngraded?

    b.Errormanagement

    i.Howtofacilitatee

    rrordetectionwhenusingthes

    ystem?

    ii.Whatifrecoverytimeisshort?

    c.Humanerrorpotential

    i.Whatiftheuseofth

    esystemmakesthehumanm

    orevulnerable,createsignifica

    nterrorrisk?(Errorresistance

    ortolerance)

    6.Organisationandstaffing

    a.Staffrequirement

    i.Whatifthestaffrequirementsaredifferentthanthelocalonesbecauseofthes

    ystem?

    b.ATCOprofile/selectioncr

    iteria

    i.Whatifthesystem

    inducesspecificskillsoraptitude?

    c.Ageingi.Whatifsomeaptitu

    deorskillrequirementsareag

    esensitive?

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    24/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    6

    App

    endix2:Likelyimpact,safeguards(actionalreadycarriedout,ActionstobedoneandUrgencyrating

    HFISSUE

    HFissue

    s

    compone

    ntLikelyimpact

    S

    afeguards(currentor

    p

    lanned)

    Importance

    Urgency

    Priority

    Reco

    mmendations

    1.a.i

    Pooruserconfidence

    2

    2

    4

    Simula

    tiontrials

    2

    1

    3

    Check

    ifthecontinuousinvolvementofalloperational

    actors

    ismentionedinthesafetyassessment/

    1.a.ii

    Nouseofthesystem(orpart

    ofthesystem)bythe

    controller

    2

    1

    3

    Trainin

    gonthesystem

    1.a.iii

    Poorconfidencewithinthe

    team

    2

    2

    4

    Trainin

    gonthesystem

    Noconsiderationforsome

    aspectsofthesystemuse

    S

    afetyassessmentstudy

    3

    2

    5

    Check

    ifthecontinuousinvolvementofalloperational

    actors

    ismentionedinthesafetyassessment

    1.b.i

    Noconsiderationforthe

    systemimpactonnon-ATC

    operators

    S

    afetyassessmentstudy

    1

    1

    2

    Check

    ifthecontinuousinvolvementofalloperational

    actors

    ismentionedinthesafetyassessment

    1.b.ii

    Noidentificationofpotential

    criticalaspects

    3

    3

    6

    Methodtoselectrepresentativesampleofn

    onATC

    people

    3

    3

    6

    Trainin

    gonthenewworkingmethod

    3

    3

    6

    Workin

    gmethodoptimisationstudy

    1.c.i

    Increasedlikelihoodoferrors

    andpossiblerisksforsafety

    3

    3

    6

    Worklo

    adassessment

    3

    3

    6

    Trainin

    gonthenewworkingmethod

    3

    3

    6

    Workin

    gmethodoptimisationstudy

    1.c.ii

    Nobenefitinthemental

    resourcemanagementfor

    thecontroller

    3

    3

    6

    Worklo

    adassessment/

    1.c.iii

    Morementalresourcesare

    available(+)

    3

    3

    6

    Worklo

    adassessment

    1.c.iv

    Riskofincreasedworkload

    becauseofattention

    demands

    3

    3

    6

    Worklo

    adassessment(taskanalysis)

    1.d.i

    Controllerlessdependenton

    externalconditions(+)

    S

    afetyassessmentstudy

    3

    3

    6

    Head

    up/headdownissuesStudy

    1.d.ii

    Controllersunderskilled

    1

    1

    2

    Skillch

    angeprediction(SHAPEToolkit)

    Postim

    plementationtrainingneedsassessm

    ent

    1.e.i

    Currentproceduresnot

    adapted

    G

    roupworkingonproceduredesign

    2

    2

    4

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Needs

    toDefinenewprocedures.

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    25/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    1.e.ii

    Trainingneedstolearnthe

    requirednewprocedures

    2

    2

    4

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Trainin

    gonnewprocedures/

    Jobaids(newproceduresmemo)

    1.e.iii

    Riskofnegativetransferof

    knowledge

    2

    2

    4

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Contro

    llertaskanalysistoidentifythepoten

    tialnegative

    transfe

    rrisks/

    Trainin

    gontheidentifiednegativetransferr

    isks/

    Jobaids(listoftraps)

    Riskofviolation

    G

    roupworkingonproceduredesign

    3

    3

    6

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Jointtrainingonnewprocedures/

    Simula

    tiontrials(proceduresandtraining)

    1.e.iv

    individualisationofthe

    practices

    3

    3

    6

    Jointtrainingonnewprocedures

    Noneedforadditional

    training(+)

    1

    3

    4

    Simula

    tiontrials

    1.f.i

    Needforproceduredesign

    3

    3

    6

    Simula

    tiontrials

    1.f.ii

    Needsforgroupworking

    1

    3

    4

    Workin

    ggrouponprocedureswithOpspeo

    ple

    1.f.iii

    Creationofhazards

    Workin

    ggrouponprocedureswithOpspeo

    ple

    1.g.i

    Inthelongterm,,riskofhigh

    controllerdependenceon

    thesystem

    2

    2

    4

    Trainin

    gonUnusualsituation(downgrade

    dsystem)

    SHAPEskillchangespredictions

    1.g.ii

    Findoutthecontrollers

    workingstrategyinthe

    currentconditions

    2

    2

    4

    Contro

    llertaskanalysisasabasisforthee

    mergencyor

    unusualsituationtraining.

    SHAPESkillchangespredictions

    Increasedworkload

    E

    rgonomicdesignoftheHMIdisplay

    3

    3

    6

    HMIev

    aluation(usertest)

    IncreasedlikelihoodoferrorsE

    rgonomicdesignoftheHMIdisplay

    3

    3

    6

    HMIev

    aluation(usertest)

    2.a.i

    Riskoflimiteduseofthe

    system

    E

    rgonomicdesignoftheHMIdisplay

    3

    3

    6

    HMIev

    aluation(usertest)

    2.a.ii

    Riskofincoherenceofthe

    newvisualdisplaywiththe

    currentones(colorcode,

    airportgraphical

    representation).

    E

    rgonomicdesignoftheHMIdisplay

    3

    3

    6

    HMIev

    aluation

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    26/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    2.b.i

    TheHMIwillnotbeadapted

    tolocalspecifics

    2

    1

    3

    Adapta

    bleHMIwithshoppinglistofdifferen

    tdisplay

    modes

    2.b.ii

    Installationdifficulties,use

    difficultiesofthematerial

    2

    1

    3

    Materialinstallationaccompaniedbyapprop

    riate

    introdu

    ction

    Riskoflossofconfidencein

    thesystemreliability

    S

    afetyassessmentstudy

    3

    3

    6

    2.c.i

    Riskoflimiteduseofthe

    systembythecontrollers

    1

    1

    2

    Technicalissue:Advicethetechnicaldesig

    nersonthis

    issue.

    2.c.ii

    Riskforsafety

    S

    afetyassessmentstudy

    3

    3

    6

    2.d.i

    Workcomplexity

    W

    orkinggrouponproceduresdesign

    3

    3

    6

    2.d.ii

    Riskofconfusion

    E

    rgonomicdesignoftheHMIdisplay

    basedoncurrentvisualdisplay

    3

    1

    4

    2.d.iii

    Safetyimpact

    S

    afetyassessmentstudy

    3

    3

    6

    Check

    ifithasbeentakenintoconsiderationifthe

    safety

    assessment

    2.d.iv

    Riskofinterference

    (attentionprocess)

    S

    afetyassessmentstudy

    3

    3

    6

    Check

    ifithasbeentakenintoconsiderationifthe

    safety

    assessment

    2.d.v

    Riskofproceduredeviation

    3

    3

    6

    Contro

    llertaskanalysis

    2.ei

    Visualdifficulties

    1

    1

    2

    Screen

    sunglasses

    2.f.i

    Fatigue/Increased

    likelihoodoferror

    2

    1

    3

    Workin

    ggrouponprocedures/workingmethoddesing

    2.f.ii

    Fatigue/Increasedlikelihood

    oferror

    2

    1

    3

    Adapta

    bleHMIwithshoppinglistofdifferen

    tdisplay

    modes

    3.a.i

    Pooruserperformance

    (comparedtothecurrent

    wayofworking)

    3

    3

    6

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Trainin

    gdevelopmentonnewrequiredskills

    ApplytheSkillChangepredictionmethodology(SHAPE

    toolkit)

    3.a.ii

    Pooruserperformance

    3

    3

    6

    Define

    aTrainingManual

    3.b.i

    Underskilledusers

    2

    3

    5

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    -Integratenewrequiredskillstraininginab-initio

    syllabu

    s

    -Integratenewrequiredskillsintheselectionprocess

    -Postimplementationtrainingneedsassess

    ment

    3.c.i

    Increasedlikelihoodoferror

    3

    3

    6

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Trainin

    gontheidentifiednegativetransferr

    isks/

    Jobaids(listoftraps)

    3.c.ii

    Learningdifficulties/poor

    usersperformanceduring

    learningcurve

    2

    3

    5

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    Trainin

    gdevelopmentonnewrequiredskills

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    27/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    3.d.i

    Underskilledtrainer

    2

    2

    4

    Workin

    ggroupontrainingneedsanddevelopment

    3.e.i

    Poorsystem/users

    performance

    1

    1

    2

    Advice

    theexistingWorkingGroupstotake

    thefollowing

    issue(s)intoaccount:

    System

    usetraining/

    Jobaids(memo)/

    Information,awarenesscampaign

    3.e.ii

    See1.b.

    1.b

    2

    2

    4

    Advice

    theexistingworkinggroupsonthefo

    llowing

    issues:

    Continuousinvolvementoftheoperationala

    ctors

    (inclus

    ionofnonATCpopulation).

    Aerodr

    omeResourceManagement(ARM)

    3.f.i

    Pooruserperformance/

    underskilleduser

    3

    2

    5

    ContingencyTraining

    3.f.ii

    Poorreactionperformance

    3

    2

    5

    ContingencyTraining

    4.a.i

    Workloadwillnotbereduced

    2

    2

    4

    Trainin

    gonnewco-ordinationmethods

    4.a.ii

    Worksimplification/

    decreasedworkload(+)

    N

    A

    Increasedlikelihoodofco-

    ordinationsurprises

    2

    3

    5

    Simula

    tiontrials(validation)toidentifycriticalscenarios

    ofuse

    4.a.iii

    Lossofpotentialrecovery

    loops

    TRMmoduledealingwithSituation

    A

    warenessandteamwork

    3

    1

    4

    Simula

    tiontrialstoanalysetheteamworkingimpactof

    theA-S

    MGCS

    4.a.iv

    Lossofco-ordination

    skills/proceduresamongthe

    team

    2

    2

    4

    ContingencyplanintheProcedureWorking

    Groups

    (initiated)

    4.b.i

    Increasedlikelihoodof

    misunderstandingduring

    handover

    TRMmoduledealingwithhandover

    processandcommunication

    3

    1

    4

    Analys

    etheimpactofA-SMGCSontheefficiency

    (safety

    )onhandoverprocess

    4.b.ii

    Needforexhaustivehand

    over(workload)

    1

    1

    2

    Jobaids(handoverchekclist)

    4.c.i

    Lossofarecoveryloop/

    Lossofcommunicationskills

    (phraseology)

    TRMtrainingoncommunication

    3

    1

    4

    TRMtrainingoncommunication

    3

    1

    4

    Worka

    nalysisofsimilarsituations(working

    positions

    usingsamekindofgroundcontrolsystem)

    4.c.ii

    Difficultiestobuildan

    efficientteam

    1

    1

    2

    Trainin

    gonnewworkingmethods

    4.d.i

    Nouseofthenewfeedback

    andsafetyloops

    3

    3

    6

    Trainin

    gonnewworkingmethods

    4.e.i

    Increasedmonitoring

    workload/increased

    likelihoodoferror

    3

    3

    6

    Ergono

    micdesignofalarmsdisplay

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    28/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    4.f.i

    Increasedlikelihoodof

    misunderstandingamong

    teams

    3

    3

    6

    Jointtraining

    4.g.i

    Needsforanew

    phraseology

    S

    tudyonphraseologyneedsmadeby

    th

    eEUROASMGCSproject.

    3

    3

    6

    Workin

    ggrouponnewphraseologydesign(initiated)

    4.g.ii

    Poorusersperformance

    duringlearningcurve

    3

    3

    6

    Workin

    ggrouponnewphraseologydesign(initiated)

    5.a.i

    Needstoreturntopast

    procedures/Lossofskill

    level

    D

    onebytheEUROA-SMGCSproject

    2

    3

    5

    Advice

    EUROASMGCSprojectGroupwork

    ingon

    Contingencyplantotakeintoaccountthecontingency

    workingmethods

    5.b.i

    Undetectedcriticalerror,

    increasedlikelihoodofsafety

    issues

    3

    3

    6

    Advice

    theContingencyplanWorkingGrouptotakeinto

    accoun

    tthefollowingissues:

    HMIer

    gonomicdesign/

    Trainin

    gontheHMI

    TRMo

    nErrorManagement

    5.b.ii

    Training/emergency

    procedureneeds

    3

    3

    6

    Advice

    theContingencyplanWorkingGrouptotakeinto

    accoun

    tthefollowingissues:

    Needs

    todesignEmergencyprocedures

    5.c.i

    IncreasedlikelihoodoferrorH

    umanFactorcases

    3

    3

    6

    Advice

    theContingencyplanWorkingGrouptotakeinto

    accoun

    tthefollowingissues:

    OperationalrequirementswithHFconsidera

    tion/

    ValidationMasterplanincludingHFconside

    ration

    2

    2

    4

    System

    integrationaccompaniedbyappropriate

    introdu

    ction

    Difficultchangeinthestaff

    organisation/difficult

    acceptability

    2

    2

    4

    Feasib

    ilitystudy

    6.a.i

    nouseofthesystem

    2

    2

    4

    Feasib

    ilitystudy

    6.b.i

    Underskilledusers

    2

    1

    3

    Simula

    tiontrialstoidentifydifficultiesofuse

    (HFexpert

    analysis)/Skillchangespredictionstudy(Shape)

    6.c.i

    Underskilledusers

    2

    1

    3

    Simula

    tiontrialstoidentifydifficultiesofuse

    (HFexpert

    analysis)/Skillchangespredictionstudy(Shape)

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    29/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    7

    App

    endix3:Check-listfor

    simulationtrials,

    Simulationtrials

    Check-list

    Priority

    Ref.HFICs

    Comments

    1

    Stu

    dytheneedsfornewproceduresandprocedure

    design

    6

    1.f.ii

    -

    2

    Stu

    dytheriskofViolation/individ

    ualisationof

    pra

    ctice

    6

    1.e.iv

    -

    3

    Stu

    dytheneedsofadditionaltraining

    4

    1.f.i

    Seenextite

    m:Trainingdesignandevalua

    tion

    4

    Stu

    dytheUserconfidencemeasu

    res

    4

    1.a.i

    -

    5

    Sim

    ulatecriticalscenarioofusetostudyco-

    ord

    inationandteamrecoveryloops

    4

    4.a.iii

    -

    6

    Stu

    dytheskilllevelrequestedtousethesystem

    3

    6.b.i/6.c.iSeeitem:skillchangespredictionstudy

    Training

    needsanddesign

    Check-list

    Priority

    Ref

    Comments

    1

    Tra

    iningonHMIspecificity

    6

    5.b.i

    Seeitem:H

    MIdesignandevaluation

    2

    Tra

    iningonnewrequiredskills

    6

    3.a.i/3.c.iiSeeitem:s

    killchangespredictionstudy

    3

    (Jo

    int)trainingonnewprocedures(toavoid

    ind

    ividualisationofpracticeandteam

    misunderstanding)

    4to6

    1.e.iv/4.f.i

    /1.e.ii

    -

    4

    Tra

    iningoferrormanagement

    6

    1.c.i/1.c.ii-

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    30/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    5

    Tra

    iningonnewworkingmethods

    6

    1.c.i/1.c.ii

    /4.c.ii/

    4.d.i

    -

    6

    Postimplementationtrainingneedsassessment

    5

    3.b.i

    -

    7

    Co

    ntingencytraining(unusualsituation,downgraded

    sys

    tem)

    4to5

    3.f.i/1.g.i/

    1.g.ii

    -

    8

    Tra

    iningonriskofnegativetransferofknowledge

    4

    1.e.iii

    -

    9

    Tra

    iningonnewco-ordinationme

    thodrequiredbythe

    sys

    tem

    4

    4.a.i

    -

    10

    Tra

    iningofallthefunctionofthe

    systemtoavoidthe

    sys

    temtobeunderused.

    3

    1.a.ii/3.e.i-

    11

    Tra

    ining

    should

    enhance

    the

    confidence

    in

    the

    sys

    tem

    3

    1.a.ii

    -

    Workloadassessment

    Check-list

    Priority

    Ref

    Comments

    1

    Wo

    rkloadassessmentinthefram

    eoftheerror

    ma

    nagement(likelihoodoferrora

    nderrorrecovery)

    6

    1.c.i

    -

    2

    Wo

    rkloadassessmentinthefram

    eofthemental

    res

    ourcemanagement

    6

    1.c.ii/

    1.c.iii

    -

    3

    Wo

    rkloadassessmentinthefram

    eoftheattention

    demand

    6

    1.c.iv

    -

  • 8/8/2019 17 Asmgcs Human Factors Plan Asmgcs Levels 1 2

    31/31

    HumanFactorsPlanforA-SMGCSLevels1&2

    lyof

    theSkillChangesPrediction

    method(Shape)

    Check-list

    Priority

    Ref

    Comments

    To

    avoidpooruserperformanceanddesigntraining

    2to6

    1.d.ii/3.a.i

    /6.b.i/6.c.i

    -

    Pre

    viouslytocontingencytraining

    6

    1.g.i

    desi

    gnandevaluation

    Check-list

    Priority

    Ref

    Comments

    ImpactoftheHMIonworkload

    6

    2.a.i

    -

    ImpactoftheHMIonerrormanag

    ement

    6

    2.a.i/5.b.i-

    ImpactofHMIontheuseofthesystem

    6

    2.a.i

    -

    AssesstheneedforaHMIwithseveraldisplay

    mo

    des

    3

    2.b.i/2.f.ii

    Co

    herencewithcurrentsystemHMI(colour,codes,

    ico

    ns)

    3

    2.b.ii