1415 h24mpp lecture 12 - alternative dispute resolution
TRANSCRIPT
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
1/14
Ioannes Tang
Senior University Teaching Fellow
Department of Civil Engineering
Faculty of Engineering
Room: B1C16, Telephone: 03-8924 8346
Email: [email protected]
Based on original notes by
W H Askew
H24MPP Lecture 12
Alternative Dispute Resolution
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
2/14
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
3/14
Types of Dispute
Resolution Systems
Engineers decision
Negotiation
Mediation
Conciliation
Adjudication
Arbitration
Litigation
3
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
4/14
Engineers Decision
In ICE Conditions of Contract
4
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
5/14
Negotiation
Freestyle meetings
Can be formal or informal meetings
between the parties in dispute
May move to the structure of one of the
following systems involving a third party.
5
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
6/14
Mediation
Neutral 3rd party that gets things moving
Aims to find a middle ground by negotiation.
The formal procedure involves separate,
private negotiation with each party leading
to accelerated settlement discussions.
The outcome can be legally enforceable in
contracts.
The mediator does not express a view
publicly.
6
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
7/14
Conciliation
More formal procedure e.g. ICE Conciliation
Procedure in Clause 66(5)
Results are binding unless taken to
adjudication
Conciliator can (and may have to) express a
provisional view on the merits of the case
Decision to refer to adjudication is binding
7
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
8/14
Adjudication I
Summary process in which parties to a
contract refer disputes to a neutral 3rdparty
for a decision
Must be available in Britain under HGCRA1996 for a decision by an independent
adjudicator, usually an engineer with legal
knowledge Outcome of adjudication is binding on the
parties
8
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
9/14
Adjudication II
Adjudicator cannot be held liable for their
decision unless it can be proved they acted in
bad faith.
On the decision one party is compelled to makea payment to the other at least temporarily.
This act in itself can make the adjudication
decision the subject of another dispute if one
party feels dissatisfaction with it.
9
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
10/14
NEC3
Dispute clauses W1.1 or W2.1
A dispute arising under this contract is
referred to and decided by the Adjudicator.
W2.1 adds: A party may refer a dispute to
the Adjudicator at any time. Time periods
are in days excluding Christmas Day, Good
Friday and bank holidays.
10
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
11/14
Arbitration
Expensive.
Arbitration Act 1996 provides a statutory
framework for arbitration
Expert Arbitrator hears evidence in
private and makes decision.
Findings only made public if referred to
Appeal (on points of law only).
11
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
12/14
Litigation
Action taken through law courts (judge
and jury).
In the High Court would probably involve
the Technology and Construction Court.
Findings made public.
12
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
13/14
Partnering I
Key aim is to avoid disputes.
All key players involved from start with express
obligations to work together and individually in
a spirit of trust, fairness and mutualcooperation.
Use NEC 3 or
PPC2000
A Partnering Adviser supports the Partnering
Team and prepares the partnering charter and
advises on resolution of disputes
13
-
7/25/2019 1415 H24MPP Lecture 12 - Alternative Dispute Resolution
14/14
Partnering II
Procedure invokes hierarchy aimed at avoiding
arbitration or litigation.
Financial disputes can be avoided by open book
accounting and refunding contractor with actualcosts with extra for profit and overheads
This requires a Price Framework and Agreed
Maximum Price (subject to allowable change or
risk occurrence).
May be linked to performance as defined
through KPIs.
14