14 works contract

Upload: karunamoorthy-periasamy

Post on 14-Apr-2018

228 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 14 Works Contract

    1/21

  • 7/30/2019 14 Works Contract

    2/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 2 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Table of Contents

    1. ICON Details on SAP Screen

    1.1 General Information for all transactions

    2.0 Works Contract Process

    2.1 Supply & Installation Process

    2.1.1 Creation of Purchase Requisition

    2.1.2 Reporting on Services

    2.1.3 Service Entry Sheet

    2.2 Installation Process

    2.2.1 Creation of service PR

    2.2.2 Service Entry Sheet

    2.2.3 Reporting on Services2.3 Printing of Service Entry Sheet

    3.0 Operation Outsourcing

    3.1 Changing the control key

    3.2 Info Record

  • 7/30/2019 14 Works Contract

    3/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 3 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    1.0 ICON Details on SAP Screen

    General Information for all Transactions

    Icons Quick Reference

    ICON Details (Short Keys) Description Action Taken on Screen

    (F3)Back Go back one screen

    (F12) Cancel Cancel the activity

    (F7)Display Display the Details

    (Enter)Enter Continue

    (F8)Execute Run Program

    (Shift+F3)Exit Exit the Window

    New Window Create New Window

    (Shift+F8) Overview Display the History

    (Ctlr+S)Save Save the records

    (F1)Help Get Help

    (Shift+F2)Delete Delete records

    (Shift+F9)Copy Copy records

    (F5)Create Create New Data

    (F6)Change Change the Records

    (F4)Pick List Select the possible Entries

    Command Field Command Field

    (Ctlr+Shift+F2)Details Data Information

    (Ctlr+F)Search Search for records

  • 7/30/2019 14 Works Contract

    4/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 4 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    2.0 Works Contract Process

    There are two scenarios in Works contract process

    1. Supply & Installation When the service is provided by contractor along with supply of required material.

    2. Installation - When the service is provided by contractor and material is supplied by ICF.

    2.1 Supply & Installation Process

    2.1.1 Creation of Purchase Requisition

    Type the T-code ME51N in command field and press enter or select from Works Contract Menu.

    Create a purchase requisition for material. Enter the material number and quantity. Press enter and save.

  • 7/30/2019 14 Works Contract

    5/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 5 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Purchase Order will be created by the concerned person in the purchasing organization. An item with Accountassignment category U and Item category D will be added for installation work or service, with quantity as 1.

    A service number is entered for this item. A service master record is maintained by planning office and new

    record is to be created, whenever a new service gets added.

    2.1.2 Reporting On Services

    Go to T-code MSRV3. Enter a service number, plant and execute or press F8.

  • 7/30/2019 14 Works Contract

    6/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 6 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    A below report will appear, which shows the purchase orders, created for that particular service number.

    Once the service is completed by contractor, the respective production person will fill the service entry sheetto acknowledge the completion of work and trigger the payment to the contractor.

    2.1.3 Service Entry Sheet

    Go to T-code ML81N. Enter the purchase order number and purchase order item number. Both numbers can benoted from previous report.

  • 7/30/2019 14 Works Contract

    7/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 7 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Select the account assignment category as F.

    Click on the Service selection button

    A below window will appear. Click on continue.

    Service item from the purchase order number entered, will be available for selection. Select the item andclick on service as shown below.

  • 7/30/2019 14 Works Contract

    8/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 8 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Below window appears, which enter the production order number, to which the cost of service will be

    charged.

    Fill the acceptance data and save the entry sheet.

    :

  • 7/30/2019 14 Works Contract

    9/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 9 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Multiple entries are possible in same service entry sheet, with cost allocation to different production orders.

  • 7/30/2019 14 Works Contract

    10/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 10 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    2.2 Installation Process

    2.2.1 Creation of Service PR

    Go to T-code ME51N and create a purchase requisition (Requisition type SRPR) for service with accountassignment category U and item category D. Go to services tab and select the service number for servicemaster record.

    Enter the quantity for the service and sae the requisition.

  • 7/30/2019 14 Works Contract

    11/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 11 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    A purchase order (order type SRPR) will be created against the purchase requisition, by the concerned

    purchase authority.

    2.2.2 Service Entry Sheet

    Once the contractor completes the work, the concerned production person, need to make a service sheetentry, to acknowledge the completion of work and trigger the payment to the contractor.

    Go to t-code ML81N and click on Other Purchase Order. Enter the purchase order number and item number, forwhich you want to make the service sheet entry.

    Select the account assignment category as F and click on the Service Selection button at the bottom of the

    screen.

  • 7/30/2019 14 Works Contract

    12/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 12 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Below screen will appear. Click on continue.

    Select the service item from this purchase order and click on services.

  • 7/30/2019 14 Works Contract

    13/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 13 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Below pop-up window will appear. Enter the production order number to which the cost of the service will be

    charged.

    Enter the quantity completed and save.

  • 7/30/2019 14 Works Contract

    14/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 14 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    2.2.3 Reporting on Services

    Go to t-code MSRV3 and enter the plant. Enter the service number, for which you want to display the existingpurchase orders and service entry sheets. Execute.

    Below report shows the service entry sheet and POs for given service number.

  • 7/30/2019 14 Works Contract

    15/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 15 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    2.3 Printing of Service Entry Sheet

    Go to t-code ML83 and enter the purchase order number, for which you want to print the service entry sheetand click on execute.

    A list will appear as shown below.

  • 7/30/2019 14 Works Contract

    16/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 16 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Select the service sheet entry and click on display output as shown below.

    Select the printer and click on print or print preview as required.

  • 7/30/2019 14 Works Contract

    17/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 17 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    3.0 Operation Outsourcing

    3.1 Changing the Control Key

    Below screen shows the production order routing.

    Change the control key of the operation to be outsourced to ZP02 External Processing and save the order.

  • 7/30/2019 14 Works Contract

    18/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 18 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    When the order is released, a purchase requisition is created for the outsourced operation. This can be seen inexternal processing tab in the operation details.

    Click on the button shown below, to see the purchase requisition details.

  • 7/30/2019 14 Works Contract

    19/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 19 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Below screen shows the PR created for operation outsourcing.

    3.2 Info Record

    An info record must exist for the vendor performing the outsourced operation. Info record contains the vendorinformation along with the price and quantity conversion data.

    Go to T-code ME11, for creating info record. This activity will be done by concerned purchasing authority.

  • 7/30/2019 14 Works Contract

    20/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 20 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

  • 7/30/2019 14 Works Contract

    21/21

    D3304-CRIS-ICF-PP- End User Manual

    SAP-MTI- Page 21 of 21

    Ver 1.0/15-Oct-11 L&T InfoTech Confidential

    Below screen shows that, a new operation with external processing control key (ZP02) can be created, after

    the deleting the original operation, which is being outsourced. This will ensure no material movements andconfirmations, against the operation which is outsourced.

    Quantity received after GR can be seen in operation details screen as shown below.