Table of Contents
1. ICON Details on SAP Screen
1.1 General Information for all transactions
2.0 Works Contract Process
2.1 Supply & Installation Process
2.1.1 Creation of Purchase Requisition
2.1.2 Reporting on Services
2.1.3 Service Entry Sheet
2.2 Installation Process
2.2.1 Creation of service PR
2.2.2 Service Entry Sheet
2.2.3 Reporting on Services2.3 Printing of Service Entry Sheet
3.0 Operation Outsourcing
3.1 Changing the control key
3.2 Info Record
-
7/30/2019 14 Works Contract
3/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 3 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
1.0 ICON Details on SAP Screen
General Information for all Transactions
Icons Quick Reference
ICON Details (Short Keys) Description Action Taken on Screen
(F3)Back Go back one screen
(F12) Cancel Cancel the activity
(F7)Display Display the Details
(Enter)Enter Continue
(F8)Execute Run Program
(Shift+F3)Exit Exit the Window
New Window Create New Window
(Shift+F8) Overview Display the History
(Ctlr+S)Save Save the records
(F1)Help Get Help
(Shift+F2)Delete Delete records
(Shift+F9)Copy Copy records
(F5)Create Create New Data
(F6)Change Change the Records
(F4)Pick List Select the possible Entries
Command Field Command Field
(Ctlr+Shift+F2)Details Data Information
(Ctlr+F)Search Search for records
-
7/30/2019 14 Works Contract
4/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 4 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
2.0 Works Contract Process
There are two scenarios in Works contract process
1. Supply & Installation When the service is provided by contractor along with supply of required material.
2. Installation - When the service is provided by contractor and material is supplied by ICF.
2.1 Supply & Installation Process
2.1.1 Creation of Purchase Requisition
Type the T-code ME51N in command field and press enter or select from Works Contract Menu.
Create a purchase requisition for material. Enter the material number and quantity. Press enter and save.
-
7/30/2019 14 Works Contract
5/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 5 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Purchase Order will be created by the concerned person in the purchasing organization. An item with Accountassignment category U and Item category D will be added for installation work or service, with quantity as 1.
A service number is entered for this item. A service master record is maintained by planning office and new
record is to be created, whenever a new service gets added.
2.1.2 Reporting On Services
Go to T-code MSRV3. Enter a service number, plant and execute or press F8.
-
7/30/2019 14 Works Contract
6/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 6 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
A below report will appear, which shows the purchase orders, created for that particular service number.
Once the service is completed by contractor, the respective production person will fill the service entry sheetto acknowledge the completion of work and trigger the payment to the contractor.
2.1.3 Service Entry Sheet
Go to T-code ML81N. Enter the purchase order number and purchase order item number. Both numbers can benoted from previous report.
-
7/30/2019 14 Works Contract
7/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 7 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Select the account assignment category as F.
Click on the Service selection button
A below window will appear. Click on continue.
Service item from the purchase order number entered, will be available for selection. Select the item andclick on service as shown below.
-
7/30/2019 14 Works Contract
8/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 8 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Below window appears, which enter the production order number, to which the cost of service will be
charged.
Fill the acceptance data and save the entry sheet.
:
-
7/30/2019 14 Works Contract
9/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 9 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Multiple entries are possible in same service entry sheet, with cost allocation to different production orders.
-
7/30/2019 14 Works Contract
10/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 10 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
2.2 Installation Process
2.2.1 Creation of Service PR
Go to T-code ME51N and create a purchase requisition (Requisition type SRPR) for service with accountassignment category U and item category D. Go to services tab and select the service number for servicemaster record.
Enter the quantity for the service and sae the requisition.
-
7/30/2019 14 Works Contract
11/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 11 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
A purchase order (order type SRPR) will be created against the purchase requisition, by the concerned
purchase authority.
2.2.2 Service Entry Sheet
Once the contractor completes the work, the concerned production person, need to make a service sheetentry, to acknowledge the completion of work and trigger the payment to the contractor.
Go to t-code ML81N and click on Other Purchase Order. Enter the purchase order number and item number, forwhich you want to make the service sheet entry.
Select the account assignment category as F and click on the Service Selection button at the bottom of the
screen.
-
7/30/2019 14 Works Contract
12/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 12 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Below screen will appear. Click on continue.
Select the service item from this purchase order and click on services.
-
7/30/2019 14 Works Contract
13/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 13 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Below pop-up window will appear. Enter the production order number to which the cost of the service will be
charged.
Enter the quantity completed and save.
-
7/30/2019 14 Works Contract
14/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 14 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
2.2.3 Reporting on Services
Go to t-code MSRV3 and enter the plant. Enter the service number, for which you want to display the existingpurchase orders and service entry sheets. Execute.
Below report shows the service entry sheet and POs for given service number.
-
7/30/2019 14 Works Contract
15/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 15 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
2.3 Printing of Service Entry Sheet
Go to t-code ML83 and enter the purchase order number, for which you want to print the service entry sheetand click on execute.
A list will appear as shown below.
-
7/30/2019 14 Works Contract
16/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 16 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Select the service sheet entry and click on display output as shown below.
Select the printer and click on print or print preview as required.
-
7/30/2019 14 Works Contract
17/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 17 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
3.0 Operation Outsourcing
3.1 Changing the Control Key
Below screen shows the production order routing.
Change the control key of the operation to be outsourced to ZP02 External Processing and save the order.
-
7/30/2019 14 Works Contract
18/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 18 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
When the order is released, a purchase requisition is created for the outsourced operation. This can be seen inexternal processing tab in the operation details.
Click on the button shown below, to see the purchase requisition details.
-
7/30/2019 14 Works Contract
19/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 19 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Below screen shows the PR created for operation outsourcing.
3.2 Info Record
An info record must exist for the vendor performing the outsourced operation. Info record contains the vendorinformation along with the price and quantity conversion data.
Go to T-code ME11, for creating info record. This activity will be done by concerned purchasing authority.
-
7/30/2019 14 Works Contract
20/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 20 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
-
7/30/2019 14 Works Contract
21/21
D3304-CRIS-ICF-PP- End User Manual
SAP-MTI- Page 21 of 21
Ver 1.0/15-Oct-11 L&T InfoTech Confidential
Below screen shows that, a new operation with external processing control key (ZP02) can be created, after
the deleting the original operation, which is being outsourced. This will ensure no material movements andconfirmations, against the operation which is outsourced.