101838175-health-and-safety-method-statements.doc
TRANSCRIPT
Health and Safety Method Statements
Health and Safety Method Statements for ClientsClick Method Statements in list below to viewTo use the buttons, double click on them.
MACROBUTTON ShowForm
MACROBUTTON CreateListData
2HEALTH AND SAFETY PROJECT OVERVIEW (HSPO)
5HAZARDOUS AREAS AND SITUATIONS (HA)
6Confined Spaces (HA1)
7Fire on Site (HA2)
8Fragile Roofs (HA3)
9Roadways (HA4)
10Working Adjacent to Water (HA5)
11Working at Heights (HA6)
12Working Near to Overhead Power Lines (HA7)
13Working Near to Underground Services (HA8)
14Working Alone (HA9)
15Working in Occupied Premises (HA10)
16Electrical Work Not Exceeding 415 Volts (HA11)
17Working in Roof Spaces (HA12)
18Working with Hot Pitch (HA13)
19Working with Oxygen and Acetylene (HA14)
20Working near Sewage (HA15)
21Working with Glass Panels (HA16)
22Brick Stacks (HA17)
23Site Trespassers (HA18)
24Work in Schools (HA19)
25Working on Tiled or Slated Roofs (HA20)
26Trainees in the Workplace (HA21)
27Rooms containing Generators (HA22)
28Rooms containing Batteries (HA23)
29Rooms containing High Voltage Equipment (HA24)
30Blank (HA25)
31Blank (HA26)
32Blank (HA27)
33Blank (HA28)
34Blank (HA29)
35HAZARDOUS SUBSTANCES (HS)
36Asbestos (HS1)
37Discharge Lamps (HS2)
38Flammable Liquids (HS3)
39Insulation Materials - Non Asbestos (HS4)
40Lead (HS5)
41LPG (HS6)
42PCB (HS7)
43Site Materials (HS8)
44Solvents and Cleaning Agents (HS9)
45Blank (HS10)
46Blank (HS11)
47Blank (HS12)
48Blank (HS13)
49Blank (HS14)
50INSTALLATION METHODS (IM)
51Working with Batteries (IM1)
52Cable Pulling (IM2)
53Excavations (IM3)
54Plumbing Work (IM4)
55Testing and Commissioning (IM5)
56Trunking and Tray (IM6)
57Installation of Lamps and Tubes (IM7)
58Lifting of Loads by Slings (IM8)
59Site Electrical Supplies (IM9)
60Chasing Walls (IM10)
61Demolition Work (IM11)
62Electric Arc Welding (IM12)
63Lifting Operations (IM13)
64Site Management (IM14)
65Replacement of Lamps or Tubes (IM15)
66Fire Alarm Testing (IM16)
67Blank (IM17)
68Blank (IM18)
69Blank (IM19)
70Blank (IM20)
71Blank (IM21)
72PLANT AND TOOLS (PL)
73Cartridge Operated Tools (PL1)
74Chasing Machine (PL2)
75Compressors and Pneumatic Tools (PL3)
76Disk Cutters (PL4)
77Excavators (PL5)
78Hand Tools (PL6)
79Ladders (PL7)
80Lifting Equipment (PL8)
81Mobile Cranes (PL9)
82Mobile Elevating Platforms (PL10)
83Mobile Tower Scaffolding (PL11)
84Portable Electrical Equipment (PL12)
85Scaffolding - Fixed (PL13)
86Skips (PL14)
87Trestles (PL15)
88Company Vehicles on Site (PL16)
89Hoists (PL17)
90Site Offices (PL18)
91Site Thread Cutting Machines (PL19)
92Chainsaws (PL20)
93Circular Saws (PL21)
94Abrasive Wheels (PL22)
95Debris Chutes (PL23)
96Dumper Trucks (PL24)
97Electrical Generators (PL25)
98Festoon Lighting (PL26)
99Use of HIABS (PL27)
100Vibrating Tools (PL28)
101Blank (PL29)
102Blank (PL30)
103Blank (PL31)
104Blank (PL32)
105Blank (PL33)
106Employee Acceptance Form (EA)
PreviousMain MenuNext
HEALTH AND SAFETY PROJECT OVERVIEW (HSPO)
PreviousMain MenuNext
Project Information Sheet
Scope of work to be carried out
Site personnel details:
Site accommodation:
Vehicles and plant:
Hazardous substances:
Hazardous areas or situations:
Health and safety overview:Produced by: (block capitals) ROBERT DYBELL
SignatureDate produced 17 March 2011
PreviousMain MenuNext
Risk Assessment and Method Statement Overview
SubjectCodeSpecific Method Statements
PreviousMain MenuNext
HAZARDOUS AREAS AND SITUATIONS (HA)
PreviousMain MenuNext
Confined Spaces (HA1)
PreviousMain MenuNext
Fire on Site (HA2)
PreviousMain MenuNext
Fragile Roofs (HA3)
PreviousMain MenuNext
Roadways (HA4)
PreviousMain MenuNext
Working Adjacent to Water (HA5)
PreviousMain MenuNext
Working at Heights (HA6)
PreviousMain MenuNext
Working Near to Overhead Power Lines (HA7)
PreviousMain MenuNext
Working Near to Underground Services (HA8)
PreviousMain MenuNext
Working Alone (HA9)
PreviousMain MenuNext
Working in Occupied Premises (HA10)
PreviousMain MenuNext
Electrical Work Not Exceeding 415 Volts (HA11)
PreviousMain MenuNext
Working in Roof Spaces (HA12)
PreviousMain MenuNext
Working with Hot Pitch (HA13)
PreviousMain MenuNext
Working with Oxygen and Acetylene (HA14)
PreviousMain MenuNext
Working near Sewage (HA15)
PreviousMain MenuNext
Working with Glass Panels (HA16)
PreviousMain MenuNext
Brick Stacks (HA17)
PreviousMain MenuNext
Site Trespassers (HA18)
PreviousMain MenuNext
Work in Schools (HA19)
PreviousMain MenuNext
Working on Tiled or Slated Roofs (HA20)
PreviousMain MenuNext
Trainees in the Workplace (HA21)
PreviousMain MenuNext
Rooms containing Generators (HA22)
PreviousMain MenuNext
Rooms containing Batteries (HA23)
PreviousMain MenuNext
Rooms containing High Voltage Equipment (HA24)
PreviousMain MenuNext
Blank (HA25)
PreviousMain MenuNext
Blank (HA26)
PreviousMain MenuNext
Blank (HA27)
PreviousMain MenuNext
Blank (HA28)
PreviousMain MenuNext
Blank (HA29)
PreviousMain MenuNext
HAZARDOUS SUBSTANCES (HS)PreviousMain MenuNext
Asbestos (HS1)
PreviousMain MenuNext
Discharge Lamps (HS2)
PreviousMain MenuNext
Flammable Liquids (HS3)
PreviousMain MenuNext
Insulation Materials - Non Asbestos (HS4)
PreviousMain MenuNext
Lead (HS5)
PreviousMain MenuNext
LPG (HS6)
PreviousMain MenuNext
PCB (HS7)
PreviousMain MenuNext
Site Materials (HS8)
PreviousMain MenuNext
Solvents and Cleaning Agents (HS9)
PreviousMain MenuNext
Blank (HS10)
PreviousMain MenuNext
Blank (HS11)
PreviousMain MenuNext
Blank (HS12)
PreviousMain MenuNext
Blank (HS13)
PreviousMain MenuNext
Blank (HS14)
PreviousMain MenuNext
INSTALLATION METHODS (IM)PreviousMain MenuNext
Working with Batteries (IM1)
PreviousMain MenuNext
Cable Pulling (IM2)
PreviousMain MenuNext
Excavations (IM3)
PreviousMain MenuNext
Plumbing Work (IM4)
PreviousMain MenuNext
Testing and Commissioning (IM5)
PreviousMain MenuNext
Trunking and Tray (IM6)
PreviousMain MenuNext
Installation of Lamps and Tubes (IM7)
PreviousMain MenuNext
Lifting of Loads by Slings (IM8)
PreviousMain MenuNext
Site Electrical Supplies (IM9)
PreviousMain MenuNext
Chasing Walls (IM10)
PreviousMain MenuNext
Demolition Work (IM11)
PreviousMain MenuNext
Electric Arc Welding (IM12)
PreviousMain MenuNext
Lifting Operations (IM13)
PreviousMain MenuNext
Site Management (IM14)
PreviousMain MenuNext
Replacement of Lamps or Tubes (IM15)
PreviousMain MenuNext
Fire Alarm Testing (IM16)
PreviousMain MenuNext
Blank (IM17)
PreviousMain MenuNext
Blank (IM18)
PreviousMain MenuNext
Blank (IM19)
PreviousMain MenuNext
Blank (IM20)
PreviousMain MenuNext
Blank (IM21)
PreviousMain MenuNext
PLANT AND TOOLS (PL)PreviousMain MenuNext
Cartridge Operated Tools (PL1)
PreviousMain MenuNext
Chasing Machine (PL2)
PreviousMain MenuNext
Compressors and Pneumatic Tools (PL3)
PreviousMain MenuNext
Disk Cutters (PL4)
PreviousMain MenuNext
Excavators (PL5)
PreviousMain MenuNext
Hand Tools (PL6)
PreviousMain MenuNext
Ladders (PL7)
PreviousMain MenuNext
Lifting Equipment (PL8)
PreviousMain MenuNext
Mobile Cranes (PL9)
PreviousMain MenuNext
Mobile Elevating Platforms (PL10)
PreviousMain MenuNext
Mobile Tower Scaffolding (PL11)
PreviousMain MenuNext
Portable Electrical Equipment (PL12)
PreviousMain MenuNext
Scaffolding - Fixed (PL13)
PreviousMain MenuNext
Skips (PL14)
PreviousMain MenuNext
Trestles (PL15)
PreviousMain MenuNext
Company Vehicles on Site (PL16)
PreviousMain MenuNext
Hoists (PL17)
PreviousMain MenuNext
Site Offices (PL18)
PreviousMain MenuNext
Site Thread Cutting Machines (PL19)
PreviousMain MenuNext
Chainsaws (PL20)
PreviousMain MenuNext
Circular Saws (PL21)
PreviousMain MenuNext
Abrasive Wheels (PL22)
PreviousMain MenuNext
Debris Chutes (PL23)
PreviousMain MenuNext
Dumper Trucks (PL24)
PreviousMain MenuNext
Electrical Generators (PL25)
PreviousMain MenuNext
Festoon Lighting (PL26)
PreviousMain MenuNext
Use of HIABS (PL27)
PreviousMain MenuNext
Vibrating Tools (PL28)
PreviousMain MenuNext
Blank (PL29)
PreviousMain MenuNext
Blank (PL30)
PreviousMain MenuNext
Blank (PL31)
PreviousMain MenuNext
Blank (PL32)
PreviousMain MenuNext
Blank (PL33)
PreviousMain Menu
Employee Acceptance Form (EA)
UNIT 126 STOCKTON BUSINESS CENTRE
70-74 BRUNSWICK STREET
STOCKTON ON TEES
TS18 1DW
08455191047
Site Details
Health and Safety
Project Overview
HazardsRisk RatingExplosive atmospheres being presentHighDanger of asphyxiation HighDanger of personnel being trappedHigh
Planned Methods to Reduce Risks
A communication system will be established to personnel within the confined space.
A permit to work system will be implemented for entry into the area.
Rescue equipment will be on site.
Adequate ventilation will be maintained.
Breathing apparatus or airlines will be provided.
Detection equipment will be present and used prior to entry into the confined space.
Monitoring will be maintained during the presence of persons within the confined space, to check the level of oxygen and presence of toxic or explosive substances.
Personal protective equipment suitable for the working environment will be provided.
The electrical contractor will ensure all staff entering or managing confined spaces will be fully trained.
The electrical contractor will ensure compliance with all prevailing legislation and codes of practice with respect to working in confined spaces.
HazardsRisk RatingAsphyxiation HighBurnsHighInjury in evacuationMedium
Planned Methods to Reduce Risks
Designated emergency exit routes will be kept free of obstruction at all times.
Staff to be given training on site fire and evacuation procedures
Those involved in using highly flammable materials or carrying out hot work will be given additional training in fire prevention measur
Hot work and the use of naked flame appliances will be controlled by a permit to work system.
The electrical contractors staff will comply with the site fire safety procedures.
HazardsRisk RatingDanger of personnel falling through the roof HighDanger of objects falling on personnel belowHigh
Planned Methods to Reduce Risks
All staff involved in work on fragile roofs will be trained in the safe system of work to be used.
Barriers and signs will be provided so as to isolate the working area below while work is in progress.
Suitable means of access will be provided to the roof, such as roof ladders, crawling boards, scaffolding and staging.
Suitable personal protective equipment will be provided to personnel.
The electrical contractor will identify, before any work commences, the type of material used in the fragile roof.
HazardsRisk RatingDanger of personnel being hit by vehicles HighDanger to road users of worksHigh
Planned Methods to Reduce Risks
All appropriate authorities will be notified, and given a programme of the road works.
All staff to be trained and made conversant with the requirements of the New Roads and Street-works act.
All staff will be issued with appropriate personal protective equipment, which will be worn at all times.
Safety zones will be established to enable staff to operate effectively and safely.
The electrical contractor will ensure that traffic management complies with all current legislation and codes of practice.
HazardsRisk RatingPersonnel falling into waterHighPlant falling into waterHighFloodingMedium
Planned Methods to Reduce Risks
All gangways and areas adjacent to the water edge will be kept clear of obstructions.
Protection will be provided to the water edge where practicable. If this is not possible then staff will wear safety line and harnesses.
Rescue equipment and first aid equipment will be inspected daily.
Training will be given to staff on the use of harnesses and buoyancy aids, and in rescue procedures.
Lighting will be provided at the water edge.
Where fast-flowing waters are involved, grab lines will be provided downstream.
HazardsRisk RatingDanger of personnel falling HighDanger of objects falling onto personnel belowHigh
Planned Methods to Reduce Risks
Suitable access will be provided to the working area, and shall be inspected at regular intervals.
All operatives working on site shall wear safety helmets at all times.
Edge protection will be provided as necessary.
Signs and barriers will be positioned directly below the works to warn and prevent access to the working area.
All current legislation and codes of practice concerned with working at heights will be strictly complied with.
Training and instruction will be given to staff on the usage of lines and harnesses.
Chutes will be used to dispose of debris.
HazardsRisk RatingDanger of electrocution HighDanger of power lines coming into contact with plantHigh
Planned Methods to Reduce Risks
All work conducted near to or under overhead power lines will be carried out in accordance with current legislation and codes of practice.
All crane operations and movements in close proximity to overhead power lines will be supervised.
All drivers of visiting vehicles will be briefed on the site hazards.
Any operations involving the movement of potentially hazardous objects - such as ladders and scaffolding tubing, in the vicinity of overhead lines, will be subject to special supervision.
Before any work on site commences, a survey will take place to identify hazards and to establish safe working clearances.
Barriers and warning signs will be installed and continually monitored to ensure that they remain in place.
All staff will be briefed on the hazards and the requirements of working near to overhead power lines.
HazardsRisk RatingDanger to personnel of hitting other services HighDanger of damaging other servicesHigh
Planned Methods to Reduce Risks
All services encountered on site will be assumed to be live until proven otherwise.
All staff, machine operators and subcontractors will be fully briefed as to the site situations before any work is commenced.
All temporary service works will be clearly marked.
Before work is commenced, contact will be made with the relevant authorities, to obtain details of their services in the vicinity of the works.
Cable location devices will be used to verify the presence of any underground services.
All work in the vicinity of underground services will be carried out strictly in accordance with current legislation and codes of practice.
HazardsRisk RatingAccidents without help at hand MediumAttack by intrudersLow
Planned Methods to Reduce Risks
Mobile telephone or other suitable means of communication will be provided.
First aid kit to be at hand.
Only work suitable for one person to be carried out.
Time limit to be set for person to report back to supervisors.
HazardsRisk RatingDanger to electricians from occupied premises activities MediumDanger of occupied premises staff from electricians activitiesMediumNoiseHighDustHighFalling over site materialsHigh
Planned Methods to Reduce Risks
All staff and subcontractors will be fully briefed as to the site hazards before any work is commenced.
All works areas to be segregated and barriers erected as necessary.
Dust barriers will be erected as necessary.
A programme of works to be drawn up, with all parties informed.
Materials to be stored in designated areas.
HazardsRisk RatingElectrical shocks HighBurnsHighFireHighDamage to equipmentHigh
Planned Methods to Reduce Risks
All circuits involved with the proposed work will be assumed to be live until proved dead.
All adjacent live equipment shall be fully shrouded and warning signs put in position.
Only competent persons will be allowed to carry out work adjacent to live equipment.
All switchgear controlling the equipment to be worked on will be locked and warning labels put in place.
No live working will be carried out.
A permit to work system will be implemented.
HazardsRisk RatingFalling through ceilingHighTripping over cables or pipesHighPresence of dust or fibres in the airHigh
Planned Methods to Reduce Risks
Adequate lighting will be provided for working area.
Boarding will be provided as necessary.
Face masks will be worn.
HazardsRisk RatingBurnsHighCancerHighDamage to PropertyHighFireHigh
Planned Methods to Reduce Risks
Only competent personnel will work with hot pitch.
The pitch container will not be overfilled.
Personnel will wear protective clothing when working with pitch.
The pitch will only be transported in a suitable container with the lid on.
The temperature of the pitch will be carefully monitored.
HazardsRisk RatingExplosionsHighFireHighInjury due to falling cylindersMedium
Planned Methods to Reduce Risks
Only fully trained personnel shall operate the equipment.
Cylinders shall be made secure to stop them falling over.
All flammable material will be removed from the work area or shielded by means of fire resistant shields.
A fire extinguisher shall be situated adjacent to the work area.
Hoses to be inspected on a daily basis.
Oxygen cylinders shall be stored at least 3 metres from Acetylene cylinders.
Operatives shall wear the appropriate personnel protective equipment when using the equipment.
HazardsRisk RatingWeils Disease from RatsHighInfections High
Planned Methods to Reduce Risks
Personnel will not eat or drink in the working area.
Any cuts or scratches to be immediately attended to.
Personnel shall wear suitable gloves when handling materials that have been in contact with sewage.
HazardsRisk RatingCuts to operativesHighHazard of broken glass to the publicHigh
Planned Methods to Reduce Risks
All personnel working with glass shall be fully trained.
Personnel will wear gloves when transporting glass.
Suction pads and slings will be used as appropriate when transporting glass.
The glass shall be made secure during transportation.
Before transporting glass into the building, the route will be surveyed for obstructions and uneven or slippery surfaces.
When installing glass at high levels, the area below will be kept free of people.
Any broken glass will be cleared up immediately.
HazardsRisk RatingCollapse of brick stacksHighInjury to personnel when cutting brick stack bindingsHighBricks falling on personnelHigh
Planned Methods to Reduce Risks
Brick stacks will be on level stable ground.
Brick stacks areas shall be kept tidy.
Brick stacks to not exceed recommended heights - normally 2 packs high.
Personnel cutting brick stack bindings will wear gloves and eye protection and will use a safety cutter.
HazardsRisk RatingDeath or injury to trespassersHighDamage to plant HighTheftHighJoy riding of plantHigh
Planned Methods to Reduce Risks
The work site shall be made secure with warnings signs displayed.
Security alarms will be fitted in high risk locations.
All plant to be immobilised out of working hours.
HazardsRisk RatingInjury to studentsHighInjury to school staffMediumInjury to electricians Medium
Planned Methods to Reduce Risks
Any working areas will be closed to students wherever possible by barriers
Plant and tools will be kept locked away or immobilised when no one is working in the area.
All waste materials will be removed wherever possible on a daily basis.
Ladders and platforms will be taken down or the working area locked off when no one is working in the area.
Switch rooms and distribution boards will be locked off when no one is working in the area.
HazardsRisk RatingFalling through roof lightsHighFalling from roof HighFalling through roofHighContact with overhead power linesMediumTools or materials falling off roofMedium
Planned Methods to Reduce Risks
No work will be carried out on roof during high winds
Scaffolding and edge protection barriers to be used where appropriate
Skylights or openings will be barriered off or personnel to wear safety belts
If the work is in a public area, appropriate barriers and signs will be installed
No work to be carried out near live overhead power lines unless access limitation barriers have been installed.
All staff will wear protective helmets.
Care will be taken to ensure that materials stored on the roof do not overload the roof structure.
Crawling boards and ladders will be used as appropriate.
Access to the roof after working hours to be securely locked off.
HazardsRisk RatingInjury to themselvesHighInjury to othersMediumDamage to tools and plantMedium
Planned Methods to Reduce Risks
Tasks given to trainees shall be within their capability and will be supervised at all times.
On site training will be given to identify the hazards present in the workplace.
Trainees will not be left to work on their own.
Training will be given to identify hazardous situations such as working at heights, or working adjacent to roadways etc.
A training record sheet record will be maintained to detail the training they receive.
Basic first aid training will be provided.
HazardsRisk RatingExplosion or damage to plantHighElectrocution or injury to personnelHighLoss of power HighElectrocution or injury to personnel working on cables remote from the generator roomHigh
Planned Methods to Reduce Risks
Access to generator rooms will be strictly limited to authorised personnel.
Access to generator rooms will be strictly controlled by locking arrangements with keys only issued to authorised personnel.
Work on the generator, will be carried out by authorised personnel working on a permit to work system.
Any automatic start up circuits will be disabled before work is commenced on the generator.
If the room has an automatically controlled fire suppression system, the system must be disabled before the room is entered, and reinstated after the permit to work has been cancelled.
The generator rooms will have the appropriate warning signs fixed to the access doors, complete with emergency telephone numbers.
Access to the generator rooms will be kept clear at all times.
No smoking or naked flames will be allowed in the generator room.
Ventilation grilles to be kept clear at all times.
HazardsRisk RatingExplosion or damage to plantHighElectrocution or injury to personnelHighLoss of power HighAcid burns to personnelHigh
Planned Methods to Reduce Risks
Access to the battery rooms will be strictly limited to authorised personnel.
Access to the battery rooms will be strictly controlled by locking arrangements with keys only issued to authorised personnel.
Work on the batteries, will be carried out by authorised personnel working on a permit to work system.
If the room has an automatically controlled fire suppression system, the system must be disabled before the room is entered, and reinstated after the permit to work has been cancelled.
All work within the battery rooms will be controlled under a permit to work system.
The battery rooms will have the appropriate warning signs fixed to the access doors, complete with telephone numbers to contact in case of an emergency.
Access to the battery rooms will be kept clear at all times.
First aid equipment, including eye washing, shall be available adjacent to battery rooms.
No smoking or naked flames will be allowed in the battery room.
Ventilation vents to be kept clear at all times.
HazardsRisk RatingExplosion or damage to plantHighElectrocution or injury to personnelHighLoss of power HighElectrocution or injury to personnel working on HV cables remote from the HV roomHigh
Planned Methods to Reduce Risks
Access to HV rooms will be strictly limited to authorised personnel.
Access to the HV rooms will be strictly controlled by locking arrangements, with keys only issued to authorised personnel
HV switching operations will be carried out by authorised personnel working on a permit to work system.
If the HV room has an automatically controlled fire suppression system, the system must be disabled before the HV room is entered, and reinstated after the permit to work has been cancelled.
All work on the HV system will be controlled under a permit to work system.
The HV room will have the appropriate warning signs fixed to the access doors, complete with emergency telephone numbers.
Access to the HV room will be kept clear at all times.
No smoking or naked flames will be allowed in the HV room.
Ventilation grilles to be kept clear at all times.
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk RatingContamination of the environmentHighBreathing in of hazardous fibresHigh
Planned Methods to Reduce Risks
Access to work areas will be strictly controlled.
Only a fully licensed contractor will carry out the testing, removal and disposal of asbestos.
All staff will be trained on the health hazards associated with asbestos.
Personal protective equipment will be issued to staff as necessary, with full training on its usage.
HazardsRisk RatingInjury to personnel handling lampsHighBreathing in of hazardous substancesHigh
Planned Methods to Reduce Risks
Any containers used for the storage of lamps awaiting disposal will be clearly marked.
If lamps are to be crushed on site, then a COSHH assessment will be carried out.
Broken lamps will be treated as special waste, and will be kept separate from other building waste.
All staff involved in handling, storage, maintenance and disposal of lamps will be fully trained.
First aid equipment to be provided.
All work involving the disposal of discharge lamps will be carried out in accordance with the relevant legislation and codes of practice.
HazardsRisk RatingFireHighExplosionHigh
Planned Methods to Reduce Risks
Lids of containers containing flammable liquids will be kept secure at all times.
Flammable liquids will not be used for unauthorised purposes.
Flammable liquids will only be stored in suitable containers, and clearly marked to show the exact description of content.
Staff using flammable liquids will be suitably trained, including fire precautions and use of extinguishers.
Suitable personal protective equipment will be provided and maintained.
Only the minimum quantities of flammable liquids needed shall be kept on site.
HazardsRisk RatingSkin irritationHighBreathing in of fibresHigh
Planned Methods to Reduce Risks
Personal protective equipment will be issued to staff prior to the work being undertaken, with full training on its usage.
The work area will be isolated by the use of enclosures or screens, to prevent the spread of dust and materials.
The work will fully comply with all current legislation and codes of practice.
The electrical contractor will carry out COSHH assessments on the materials to be used prior to work commencing.
Waste materials will be disposed of in sealed bags or containers, for disposal as classified waste.
Exposure levels to dust and fibres will be monitored.
HazardsRisk RatingAbsorbing lead through the skinHighBreathing in of leadHighIngestion of leadHigh
Planned Methods to Reduce Risks
Suitable enclosures will be provided to prevent the spreading of contaminated material or waste.
Personal protective equipment will be provided to the staff, together with training on its usage.
Health surveillance will be put in place for staff working with lead.
Hygiene facilities will be provided for the staff working with lead.
Staff will be fully briefed on the health risks of working with lead, and the necessary safety measures involved.
All work on site shall fully comply with current legislation.
HazardsRisk RatingAsphyxiaMediumExplosionHighFireHigh
Planned Methods to Reduce Risks
All works on site shall comply with all current legislation and codes of practice
Any vehicle used to transport LPG will be suitably marked and vented.
Cylinders will be stored on site upright, and in an open mesh lockable compound.This will be sited away from drains and excavations.
Only cylinders connected to equipment will be situated in the working area.
Only the minimum working quantities of LPG are to be kept on site.
Staff will be fully trained in the use of LPG, together with the approved method of leak detection, fire precautions and the use of fire extinguishers.
Suitable fire extinguisher(s) will be positioned on site.
HazardsRisk RatingDamage to liver and skin resulting from contact with PCBHighContamination of the environmentHigh
Planned Methods to Reduce Risks
Before any work commences, all equipment containing PCB will be inspected for signs of leakage.
In the event of equipment containing PCB found to be leaking, the electrical contractor will report the situation to the site owners.
Staff involved with equipment containing PCB will be made aware of the potential health hazards of PCB and the precautions to be put in place.
Only a fully licensed waste disposal company will move or dispose of PCB.
HazardsRisk RatingInjury due to liftingHighCuts due to handling sharp objectsHighPersonnel falling over loose materialMedium
Planned Methods to Reduce Risks
All materials held on site will be in stored in suitable, clearly marked containers or skips etc.
The storage area is to be sited as close as practicable to the working area of use, in order to minimise the extent of manual handling.
Suitable personal protective equipment will be provided to staff handling waste materials.
Training will be given to staff on the lifting and handling of heavy objects.
HazardsRisk RatingSkin and Eyes IrritationHighContamination of food MediumInadvertent usage of substancesHigh
Planned Methods to Reduce Risks
Personal protective clothing to be issued and used at all times.
All food preparation areas to be covered by 5mm polythene sheeting with any spillages cleaned immediately.
All substances to be contained in correct containers and no decanting of substances into non-standard containers.
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk RatingExposure of personnel to acidHighExplosion and fireMediumDamage to plantMedium
Planned Methods to Reduce Risks
Batteries will be isolated from circuit, with the earth terminal being disconnected first.
Battery charging will only be carried out in designated well-ventilated areas.
Charging operations will be monitored to ensure that smoking and naked light restrictions are observed and charging rates and ventilation standards are maintained.
All staff working with batteries will wear suitable protective equipment.
Metal objects will be not be worn by staff working with batteries.
No Smoking and No Naked Light signs will be displayed in the work area.
Staff will be fully trained in working with batteries.
Suitable fire extinguishers will be in position on site.
Suitable personal protective equipment will be provided, and monitored to ensure its correct use.
First aid equipment will be provided on site, including eye-washing facilities.
All work on site will comply with current legislation and codes of practice.
HazardsRisk RatingInjury to personnelHighDamage to cablesHigh
Planned Methods to Reduce Risks
All staff will wear personal protective equipment.
Adequate rollers etc will be provided to make for easy cable pulling, and to ensure no damage is caused to the cable.
The electrical contractor shall ensure compliance with all current legislation and codes of practice with respect to cable installation.
The proposed cable route shall be surveyed before any work commences, to establish the labour force required and to identify site hazards.
HazardsRisk RatingCollapsing of excavations HighFlooding of excavationMediumDebris falling on staffMedium
Planned Methods to Reduce Risks
Full training will be given to site staff on the proposed work.
Excavations shall be inspected daily before any work is commenced.
Suitable means will be provided to access to the excavations.
Shuttering will be provided to comply with current legislation.
Spoil and materials will be stacked away from the trench areas.
Barriers shall be erected as necessary to prevent personnel or vehicles from entering excavations.
Suitable personal protective equipment will be provided for staff.
Suitable signs and barriers shall be provided to warn of the works.
The electrical contractor will ensure all work, in and with excavations, shall comply with all current legislation and codes of practice.
The location and identification of existing services will be assessed before any work commences.
Where a flooding risk exists, pumps will be available on site.
HazardsRisk RatingFireHighBreathing in of fumesHighBurnsHigh
Planned Methods to Reduce Risks
All flammable materials will be removed from the work area.
All plumbing works will be in accordance with all current legislation and codes of practice
If the work area has poor ventilation, then the relevant personal protective equipment will be issued to the staff.
The staff shall be fully trained and qualified to carry out the work.
Suitable fire extinguishers and first aid equipment will be provided at the workplace.
The work will be carried out in such a manner as to ensure that the occupants within the building are not exposed to fumes or risk.
HazardsRisk RatingElectrical shocks to site staffHigh
Planned Methods to Reduce Risks
If necessary, a permit to work system will be operated.
Only competent persons with suitable test equipment shall carry out the testing and commissioning.
Planning will include liaison with other contractors and those in control of the premises to ensure that all are aware of the work to be carried out.
The electrical contractor shall carry out all testing and commissioning strictly in accordance with the current legislation.
HazardsRisk RatingCuts from sharp edgesMediumRisk of falling objectsHigh
Planned Methods to Reduce Risks
The electrical contractor will ensure that all installations of cable trunking and cable tray shall comply with all current legislation and good trade practices.
Work planning will include liaison with the client and other contractors, to co-ordinate the installation work.
Adequate platforms or ladders etc will be provided to ensure safe working conditions exist.
HazardsRisk RatingDropping of lamps or tubes on personnel belowHighExposure of personnel to contents of lamps or tubes if breakage occursMediumPersonnel fallingHigh
Planned Methods to Reduce Risks
The working area below will be kept clear.
The lighting fittings will be isolated before work is commenced.
Care will be taken to not break lamps or tubes.
The disposal of the lamps and tubes will be in line with current legislation.
HazardsRisk RatingDropping loadHighInjury to personnelHighDamage to propertyHighContact with power linesMedium
Planned Methods to Reduce Risks
The slings will be the correct type and capacity for the weight of the load.
All sharp edges will be protected.
Personnel will wear the correct protective head, hand and foot protection.
Personnel will not stand under the suspended load.
The lifting operation will be correctly supervised.
The personnel operating the crane will be fully trained.
HazardsRisk RatingElectrical shocksHighDamage to site electrical installationHighFire damage to siteHigh
Planned Methods to Reduce Risks
The section of equipment will fully comply with the current regulations.
All cable routes will be carefully planned to avoid damage from site works.
Equipment and cabling will be clearly marked with warning signs.
The installation will be inspected at regular intervals.
HazardsRisk RatingDustHighHitting other servicesHighNoiseHigh
Planned Methods to Reduce Risks
Before work commences, the surface is to be surveyed to ensure that no other services are present.
Ear, eye, and respiratory protection will be provided as required by the assessment of site conditions.
If power tools are to be used, they will have integral dust extraction.
Suitable personal protective equipment will be provided and monitored to ensure its correct use.
Supervisory staff and operatives will be instructed in the hazards of noise and dust.
Work will be planned to minimise the number of persons exposed to the dust and noise.
HazardsRisk RatingFalling or flying debrisHighContact with live servicesHighUnpredictable collapse of buildingHighHealth risk from dust or asbestos fibresHigh
Planned Methods to Reduce Risks
Confirmation to be sought from all service providers that all services have been disconnected before any work is commenced.
The site must have been surveyed for the presence of asbestos or other dangerous materials.
Staff will be provided with and will wear the necessary protective clothing.
Barriers and signage will be installed to separate the general public or other site staff from the demolition area.
If the presence of pre-stressed concrete is suspected, a structural engineer will survey the building and his recommendations adhered to.
HazardsRisk RatingEye FlashHighFireHighElectric ShockMediumToxic FumesHigh
Planned Methods to Reduce Risks
Area of work to be screened off.
Ventilation to be used in restricted areas.
Fire extinguisher to be situated near to the work area.
The welding equipment to be maintained in a good condition.
Only competent personnel shall operate welding apparatus.
Flammable material near to work area shall be removed or a fire resistant screen utilised.
The operative shall wear the appropriate protective shields and clothing.
HazardsRisk RatingOverturning of lift MediumObjects falling off liftMediumContact with overhead power linesMedium
Planned Methods to Reduce Risks
The lifting appliance will be installed by qualified personnel.
The base for the lifting appliance will be on a firm and level base.
All staff using the lift will wear helmets.
The loads will be made secure before lifting.
All slings and hooks will be maintained and inspected at the appropriate time intervals.
The maximum safe working load of the lifting apparatus and associated equipment will not be exceeded.
If any overhead power lines are in the area of the lifting apparatus, there must be barriers installed.
Only suitably qualified staff shall operate the lifting apparatus.
During out of working hours the lifting apparatus shall be made secure.
HazardsRisk RatingCollapse of stored materialsMediumBlocked access routesHighContact with plantHighTripping, slipping and fallingHighFireLow
Planned Methods to Reduce Risks
All materials to be stored correctly and kept separate from work areas.
All access routes to be kept clear.
The creation of dust and noise to be strictly controlled.
Any leads or cables crossing access areas to be covered or run at high levels.
All excavations will be barriered off with appropriate signage.
Any spillages will be immediately dealt with.
All waste materials to be disposed of in the appropriate skips or receptacles.
HazardsRisk RatingElectric shockMediumCutsHighPersonnel fallingHighGlass in eyesHighBurnsMediumDropping of lamps and tubes fallingHighExposure to staff to hazardous substancesMedium
Planned Methods to Reduce Risks
The lighting fittings will be isolated from the electrical supply before being worked on.
Gloves and eye protection will be worn by staff.
The lamps will be allowed time to cool before being replaced.
Staff will use the correct method of access to the lighting fittings.
The replacement lamps will be checked for damage prior to fitting.
The disposal of the lamps and tubes will be carried out in accordance with current legislation.
HazardsRisk RatingFalse alarm calls to Fire Service in Fire Brigade linked systemsHighStaff and visitors unaware of the testing of alarm soundersMediumRecords of testing not kept up to dateMedium
Planned Methods to Reduce Risks
The Fire Brigade to be notified before testing is started in linked systems.
The Fire Brigade to be notified before any maintenance work is carried out.
All staff and visitors will be made aware of the timing of the testing.
The fire alarm logbook will be kept up to date each time testing is carried out.
The fire alarm logbook will be kept up to date each time the system operates.
The fire alarm logbook will be kept up to date if alterations are carried out.
The testing of the system will be in accordance with current regulations.
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk RatingTheft of explosive materialMediumEye injury due to flying masonryHighInjury to other site personnelMedium
Planned Methods to Reduce Risks
Only fully trained operatives over the age of 18 will be authorised to operate cartridge tools.
Only tools with a captive plunger tool will be used.
Planning will be carried out to ensure strict control of use of the cartridge tool, to prevent injury to users and others in the vicinity.
Secure storage will be provided for cartridges.
The electrical contractor will ensure that all works requiring the use of cartridge operated tools will comply with all current legislation and codes of practice.
HazardsRisk RatingDustHighHitting other servicesHighNoiseHigh
Planned Methods to Reduce Risks
All works requiring the use of a chasing machine will comply with all current legislation and codes of practice.
Before work commences, the surface will be surveyed to ensure that no other services are present.
Ear, eye, and respiratory protection will be provided as required by the assessment of site conditions.
Power tools with integral dust extraction will be used.
Signs and barriers will be used to establish noise zones as required.
Suitable personal protective equipment will be provided and monitored to ensure its correct use.
Supervisory staff and operatives will be instructed in the hazards of noise and dust.
Work will be planned to minimise the number of persons exposed to the dust and noise.
HazardsRisk RatingNoise MediumEye injuriesMediumExposure to exhaust fumes and oil mistLow
Planned Methods to Reduce Risks
All guards and covers will be fitted and in place over moving parts of compressors.
Continuous monitoring of noise will be carried out.
Hose connections will be checked regularly for security and damage.
Operatives will be trained in the safe use of pneumatic tools and the precautions necessary.
Personal protective equipment will be worn as necessary.
Suitable personal protective equipment will be provided and will be monitored to ensure its correct use.
The electrical contractor will ensure that any works that require the use of compressors and pneumatic tools shall comply with all current legislation and codes of practice.
Where work takes place in areas of poor ventilation, action will be taken to ensure there is no build up of oil mist.
HazardsRisk RatingCutting through other servicesHighOperative breathing in dustHighDisk breaking upMediumPlanned Methods to Reduce Risks
Before work commences the surface is to be surveyed, to ensure that no other services are present.
Ear, eye and respiratory protection will be provided as required by the assessment of site conditions.
Signs and barriers will be used to establish noise zones as required.
Suitable personal protective equipment will be provided and monitored to ensure its correct use.
Supervisory staff and operatives will be instructed in the hazards of noise and dust, and the control measures which are likely to be effective for this type of work.
The electrical contractor will ensure that all works requiring the use of a disk-cutting machine will comply with all current legislation and codes of practice.
Where long cable runs are planned, power tools with integral dust extraction will be used.
Work will be planned to minimise the number of persons exposed to the dust and noise.
HazardsRisk RatingDanger of personnel being hit by excavators HighHitting underground servicesHighHitting overhead linesHigh
Planned Methods to Reduce Risks
No staff will be allowed to work within the operating radius of the excavator.
Overhangs will not be permitted on high work faces.
The electrical contractor will ensure that all excavators and their use will comply with all prevailing legislation and local operational requirements.
The electrical contractor will ensure that all staff employed to operate the excavator are fully trained, and hold relevant certificates.
Travel and operations on a gradient will be strictly controlled.
HazardsRisk RatingPersonnel injuries to handsHighDamage to workplaceMediumOperative exposed to high noise levelsMediumEye damageMedium
Planned Methods to Reduce Risks
All staff will be trained in the correct method of use of hand tools.
Eye protection will be provided and worn by the operatives where appropriate.
In flammable atmospheres, non-ferrous (spark-free) tools will be used.
The electrical contractor will ensure that the use of hand tools will comply with current legislation, good engineering practice and trade training.
Tools will be inspected regularly.
HazardsRisk RatingPersonnel falling off ladders HighObjects falling from laddersHighLadders breakingLowLadders slippingMediumRisk of electrocution with aluminium laddersMedium
Planned Methods to Reduce Risks
Ladders will be checked to ensure correct length, type and condition before use.
Ladders will be secured at the top or at the bottom to prevent slipping.
Staff will be suitably trained in the safe use of ladders.
Ladder work will be restricted to that which can be carried out using one hand only.
Ladders will only be used on a firm and level base.
All work carried out using ladders will be in compliance with current legislation and codes of practice.
Aluminium ladders will not be allowed on site where unguarded electrical equipment is present
HazardsRisk RatingFalling of loadsHighCrushing of personnel High
Planned Methods to Reduce Risks
All items of lifting equipment will be identified individually and stored so as to prevent physical damage or deterioration.
Before selection of lifting equipment, due consideration will be taken of current legislation together with the weight, size, shape and centre of gravity of the load.
Staff involved in slinging or lifting of loads will have been trained in such operations and in the use of the lifting equipment.
Suitable personal protective equipment will be issued.
The electrical contractor will, when using lifting equipment, ensure the equipment complies with all prevailing legislation and codes of practice.
The safe working loads of lifting equipment will be established before use.
Packing will be used to protect slings from sharp edges on the load.
HazardsRisk RatingFalling of loadsHighContact with overhead power linesHighContact of loads with personnelHigh
Planned Methods to Reduce Risks
All personnel involved with lifting operations will be fully trained, and will wear safety helmets, gloves and safety footwear.
At the planning stage, the weight of the load, radius of lift, overhead clearance, ground conditions, positioning of the crane and lifting equipment required will be considered.
Loads will not be swung over personnel, site huts, buildings or public areas.
Relevant test certificates for the equipment to be used will be inspected prior to the work being undertaken.
The electrical contractor shall ensure strict compliance with all current legislation and codes of practice regarding the use of lifting operations using a mobile crane.
The working area of the crane will be fenced off to prevent unauthorised persons entering.
HazardsRisk RatingDanger of personnel falling HighDanger of objects falling to personnel belowHighPlatform falling overMedium
Planned Methods to Reduce Risks
All staff that will be using the platform will be trained in its use and operation.
Control of traffic and pedestrians will be planned
Only trained and authorised personnel will use the platform.
Platform capacity will be checked to ensure sufficient height and safe working load for the work being undertaken.
Platforms will not be left unattended in the raised position.
Platforms will not be moved until they are clear of all loose material.
Stabilisers, if provided, will be extended before raising the platform.
Suitable personal protective equipment will be provided and monitored to ensure its correct use.
The area of work will be fenced off to prevent unauthorised access.
The electrical contractor will ensure that all works undertaken with mobile elevating work platforms will comply with all legislation and codes of practice.
The electrical contractor will use a registered and approved specialist company to provide mobile elevating work platforms, which will comply with all relevant legislation.
The operating area will be firm and level.
HazardsRisk RatingDanger of personnel falling HighDanger of falling objects to personnel belowHighScaffolding collapsing MediumScaffolding falling overMedium
Planned Methods to Reduce Risks
Ladder access will be provided internally and fixed to the narrowest side.
Suitable personal protective equipment will be provided for the staff.
Only suitably qualified staff shall erect and dismantle the mobile tower scaffolding.
All works involving mobile tower scaffolding will comply with all current legislation and codes of practice.
The type and size of the mobile tower scaffolding will take into account the ground type, height restrictions, and any obstructions.
Tower scaffolding will be fully boarded and fitted with toe-boards and guard rails.
A competent person will inspect the towers daily.
Wheels will be braked or locked when the tower is in use.
HazardsRisk RatingElectrocutionHighBurns to operativesMediumStaff tripping over leadsHigh
Planned Methods to Reduce Risks
Leads and extension cables shall be routed so as to minimise the likelihood of damage and trip hazards.
Portable electrical equipment will be fit for the purpose of use, with respect to voltage, power and environmental conditions.
Portable electrical equipment will be identified individually and will be subject to planned maintenance.
The electrical contractor will ensure that all portable electrical equipment complies with current legislation and codes of practice.
The electrical contractor will ensure that only trained and competent persons operate, test, repair and maintain portable electrical equipment.
HazardsRisk RatingDanger of personnel falling HighDanger of falling objects to personnel belowHighScaffolding collapsing MediumVehicles hitting scaffoldingLow
Planned Methods to Reduce Risks
Scaffolding shall be inspected daily before use.
Guards and debris netting will be installed as necessary.
Personal protective equipment will be provided for the staff.
Scaffolds will be inspected regularly to ensure that no unauthorised alterations have been made to the structure.
Only suitably qualified staff will install and dismantle the scaffolding.
The electrical contractor will ensure all the scaffolding complies with current legislation and codes of practice.
Traffic movement will be restricted around the base of the scaffolding.
HazardsRisk RatingContents set on fireMediumVehicles running into skipsHighContents not disposed of correctlyMedium
Planned Methods to Reduce Risks
Waste skips provided by the electrical contractor will comply with prevailing legislation, and be marked with the usage.
If sited on a public highway, skips will be provided with adequate lighting and signage.
Skips will be placed on firm level ground wherever possible.
A safe means of access into the skip will be provided, if tipping into the skip is necessary.
Fires will not be permitted in skips.
Disposal of waste to be accordance with current legislation.
HazardsRisk RatingPersonnel falling off HighObjects fallingHighTrestles breakingLowTrestles slippingMedium
Planned Methods to Reduce Risks
All staff moving, erecting or using trestles will be suitably trained in their safe use.
Platform width shall not be less than 0.43 metres.
The electrical contractor will ensure all work carried out using trestles will be in compliance with current legislation and codes of practice.
Trestles over 3.6 metres in height shall be fixed or tied to a permanent structure.
Trestles will not be used for access above 4.5 metres.
HazardsRisk RatingPersonnel injuries in accidentMediumProperty damage in accidentMedium
Planned Methods to Reduce Risks
Only licensed drivers will be allowed to drive on site or public highways.
All vehicles will be licensed for use on site or public highways.
All vehicles will be suitable for the tasks they perform.
All drivers will adhere to site instructions.
HazardsRisk RatingMaterials falling from hoistHighInjury to personnel HighPersonnel falling into hoist spaceHigh
Planned Methods to Reduce Risks
The hoist area will be correctly guarded.
The hoist will be inspected at regular intervals.
The safe working load of the hoist will be clearly marked.
No personnel will be permitted to use the hoist.
All loads will be made secure against falling off hoist.
HazardsRisk RatingFireLowSite hygiene deficienciesLowOffice accidentsLow
Planned Methods to Reduce Risks
Fire extinguishers and emergency procedures will be put in place, and staff trained accordingly.
Toilets and washing facilities will be provided.
First aid facilities will be provided, with staff being trained in first aid administration.
HazardsRisk RatingPersonnel injured by moving partsHighHealth risk from lubricating fluidsMedium
Planned Methods to Reduce Risks
The machine is to be fully guarded.
The working area will be kept free from lubricating fluids.
The machine is to be sited away from access routes.
No one will be allowed to operate the machinery unless correctly trained.
The machine will not be left unattended when in use.
HazardsRisk RatingSerious injuries to operative HighSerious injuries to adjacent personnel HighNoiseHighDustHighInjuries from flying splintersHigh
Planned Methods to Reduce Risks
Only fully trained personnel shall operate the chainsaw
Only fully trained staff shall assist in the operation of the chainsaw
The chainsaw shall have its guards fitted at all times of operation.
Both the operator and any assistants shall wear the appropriate personal protective equipment
The chainsaw will be inspected daily and maintained at regular intervals.
The chain saw shall only be operated from a stable base.
HazardsRisk RatingSevere injuries to operative from saw bladeHighSevere injuries to adjacent staff from saw bladeHighFlying material High
Planned Methods to Reduce Risks
Only suitably qualified personnel shall operate the circular saw.
All guards will be in place whenever the saw is operated.
A push stick will be used to complete the cutting operation.
The saw operative will wear eye protection when operating the saw.
Assistants shall wear eye protection.
The saw blade and machinery shall be regularly inspected.
Only the correct size of saw blade shall be fitted.
HazardsRisk RatingBusting of wheelHighInjuries to operative HighIngestion of dust HighNoiseHighFlying particlesHigh
Planned Methods to Reduce Risks
Only suitable trained personnel shall operate abrasive wheels.
Guards must be in position at all times.
The statuary signs shall be displayed adjacent to the abrasive wheel.
The wheel must be inspected regularly.
Changing of wheels must only be carried out by a suitably trained person.
HazardsRisk RatingCollapse of chuteHighFlying debrisHighCreation of dustHighCollapse of support scaffoldingHigh
Planned Methods to Reduce Risks
Only fully trained staff will carry out chute installation.
Helmets and protective clothing to be worn by staff at all times.
Barriers will be installed to keep the public or other site personnel from the chute area.
Care will be taken to ensure that no debris larger than the chute exit diameter will be put in chute.
The chute will be inspected regularly for blockages.
Chute to be inspected daily for damage or loose fixings onto scaffoldings.
HazardsRisk RatingContact with site personnelHighDumper truck overturning MediumSite mud being transferred to public roadsHighLoads spilling out of bucketHighOperator falling from seatMediumContact with building and plantMediumJoy riding by trespassersMedium
Planned Methods to Reduce Risks
Only competent drivers to operate dumper truck.
Stop blocks to be positioned at dangerous discharge points.
Guard rails to be placed along dangerous slopes.
The dumper truck shall not be driven with the bucket in the raised position.
If the dumper truck transfers mud onto public roads, warning signs will be displayed and road sweepers utilised as necessary.
The dumper truck will be immobilised out of working hours.
HazardsRisk RatingNoiseHighPollution from fumesHighTripping over cablesHighElectric shockHigh
Planned Methods to Reduce Risks
Only fully silenced generators to be used.
Generators shall only be operated in well ventilated locations.
Cables crossing working areas shall be protected.
The generator shall be regularly inspected and maintained.
The generator shall only be installed by a competent person.
HazardsRisk RatingTripping hazardHighElectric shockHighContact with glassLow
Planned Methods to Reduce Risks
The festoon lighting will operate at 110 volts or less.
Associated cables will be securely installed and mounted out of working areas.
The festoon lighting will be regularly inspected and tested.
Lamps must be installed in all outlets.
Only qualified personnel to carry out repairs to damaged cable.
HazardsRisk RatingOverturning of vehicleHighLoad fallingHighPersonnel being hit with loadHigh
Planned Methods to Reduce Risks
The HIAB will use outriggers which must be on firm ground.
The HIAB will not be used on soft ground.
Personnel to keep clear from the unloading area.
Helmets and foot protection shall be worn by personnel receiving goods.
Only competent personnel shall operate the HIAB.
HazardsRisk RatingVibration white finger damageHighEar damageHighBack injuriesHigh
Planned Methods to Reduce Risks
Anti vibration gloves will be worn at all times.
Ear protection shall be worn at all times.
Operatives will be fully trained in using vibrating tools to avoid back injuries.
The vibrating tool will be fitted with sound reducing mufflers.
A job rotation working pattern will be implemented to avoid prolonged exposure to the hazards of using vibrating tools.
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
HazardsRisk Rating
Planned Methods to Reduce Risks
I have read the Risk Assessment and Health and Safety Method Statements and have fully understood them.
I can sign and date the sheet below:
Signature_______________________Name (Block Capitals)_______________________Date_______________________
106 Hollycroft Software Ltd 2010 www.ecs2000.net