10 th cohesion fund 1164/94/ispa monitoring committee meeting – 25 january 2012 general report on...
TRANSCRIPT
10th Cohesion Fund 1164/94/ISPA MonitoringCommittee Meeting – 25 January 2012
GENERAL REPORT ON MEASURES managed by
Ministry of Transport, Information Technology and Communications
Presented by Galina Vassileva, Dipl. EngDeputy Head of CF 1164/94 MA
Danube Bridge at Vidin – Calafat
Danube Bridge Vidin – Calafat
Presentation: C O NSTRUC C IO N, S.A.
Contract Details
Contract 1: New Cross Border Combined Bridge over the Danube River at Vidin – Calafat
Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC)
Contractor: FCC Construccion SA (Spain)Engineer: Ingerop / High-Point Rendel / JV (France/UK) Contract Value: € 105 432 747.03
Commencement Date: 1st March 2007Revised Completion Date: 9th June 2011
Paid from 01.05.2011 to 31.12.2011 € 10 251 170.82Paid total until 31.12.2011 € 90 793 434.89
Physical progress until 31.12.2011 72% Financial progress until 31.12.2011 86%
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
40m Spans Rail Approach Bridge – General View
Abutment A1 to Pier PA10 – January 2012
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
80m Spans Road Approach Bridge
Piers PB6 to PB1 – January 2012
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Main Bridge 180 Spans
Pier PB9 – January 2012
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Main Bridge 180 Spans – General View
Abutment A3 to PB9 – January 2012
Contract Details
Contract 3: Danube Bridge Vidin – Calafat:Adjoining Bulgarian Infrastructure Works
Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC)
Contractor: FCC Construccion SA (Spain)Engineer: High-Point Rendel / Ingerop / Salfo (UK/France/Greece)
Contract Value: € 62 600 456.00
Commencement Date: 28 December 2007Revised Completion Date: 3 June 2011
Paid from 01.05.2011 to 31.12.2011 € 12 530 329.97Paid total until 31.12.2011 € 48 074 310.39
Physical progress until 31.12.2011 87% Financial progress until 31.12.2011 77%
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Approach to New Border Freight Station from Sofia
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Bregovo Road Junction
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
Main Highway Under Novo Selo Road Overpass
Danube Bridge Vidin – Calafat
Presentation:C O NSTRUC C IO N, S.A.
General Arrangement of Bridge -
Actual October 2011
General Arrangement of Bridge -
Artists Impression
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Plovdiv – Svilengrad Electrification & Upgrading of Corridors IV and IX
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Project/Contracts Details
Phase 1: EuropeAid/117495/D/W/BG Electrification & Upgrading of the Railway Section Kroumovo - Parvomai
Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC)
Contractor: TERNA S.A. (Greece)Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco
Contract Value: € 99 792 441.00
Commencement Date: 25th May 2006Revised Completion Date: 31st December 2011Status as per 31.12.2011: Operational, Taking-Over Certificate signed on 21.12.2011
Paid from 01.05.2011 to 31.12.2011: € 4 336 977.71Paid Total until 31.12.2011: € 93 624 124.86
Physical Progress until 31.12.2011: 100%Financial Progress until 31.12.2011: 94%
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Railway bridge at Katunitsa Station
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Kochovo Halt
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Popovitsa Station
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
The Prime Minister Mr. Borisov and the Minister of TITCMr. Moskovski traveling in the driver’s cabin of an
electrical locomotive along Krumovo – Parvomai section at a speed of 163.6 kmph
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Project/Contracts Details
Phase 2: EuropeAid/123600/D/WKS/BG Electrification & Upgrading of the Railway Section Parvomai - Dimitrovgrad
Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC)
Contractor: ASTALDI S.P.A. (Italy)Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco
Contract Value: € 68 000 000.00
Commencement Date: 02nd October 2007Revised Completion Date: 09th November 2011Status as per 31.12.2011: Operational, Taking-Over Certificate signed on 20.12.2011
Paid from 01.05.2011 to 31.12.2011: € 7 050 493.31Paid Total until 31.12.2011: € 61 780 662.73
Physical Progress until 31.12.2011: 100%Financial Progress until 31.12.2011: 91%
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Karadzhalovo Station
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Karadzhalovo Road Overpass
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Yabalkovo Station
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Project/Contracts Details
Systems: EuropeAid/124429/D/WKS/BG Signalling and Telecommunications Systems and SCADA for the
Whole of the Line
Employer: Ministry of Transport, Information Technology and Communications, Republic of Bulgaria (MTITC)
Contractor: THALES (Austria)/ALCATEL-LUCENT (Romania)Engineer: Typsa/Systra/Louis Berger/Rubicon Engineering/Trademco
Contract Value: € 38 615 986.66
Commencement Date: 16th October 2007Revised Completion Date: 31st March 2012Status as per 31.12.2011: Operational for Plovdiv – Dimitrovgrad section
Paid from 01.05.2011 to 31.12.2011: € 6 312 383.66Paid Total until 31.12.2011: € 23 756 937.28
Physical Progress for Plovdiv – Dimitrovgrad section: 90%Financial Progress until 31.12.2011: 62%
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
Passenger Information Systems at Katounitsa Station
Plovdiv – Svilengrad Electrification and Upgrading of Corridors IV and IX
Presentation:
GSM-R Tower at Cheshnegirovo Halt
Ljulin Motorway – Sofia Ring Road to Daskalovo Junction Project
Ljulin Motorway – Sofia Ring Road to Daskalovo Junction Project
Commemorative plague
Commemorative Plague
10th Cohesion Fund 1164/94/ISPA MonitoringCommittee Meeting – 25 January 2012
Thank you for your attention!