Page 1: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

11

Value Stream Mapping:Value Stream Mapping:Future State Future State

(Current Permitting Process)(Current Permitting Process)

Joanna FrenchJoanna FrenchOctober 26, 2006October 26, 2006

Page 2: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

22

Creating the Future StateCreating the Future State

Defined our future state – where we wanted to Defined our future state – where we wanted to be in one year:be in one year:

Internal first pass quality yield - 80%Internal first pass quality yield - 80%

Customer information quality - 80%Customer information quality - 80%

Administrative completeness - 100%Administrative completeness - 100%

Technical completeness - 80%Technical completeness - 80%

Construction permit issued within 90 daysConstruction permit issued within 90 days

Page 3: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

33

Page 4: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

44

Achieving Our Future StateAchieving Our Future State

Identified and scheduled specific tasks to Identified and scheduled specific tasks to accomplish. These tasks included the accomplish. These tasks included the following:following:

Visual tracking boardsVisual tracking boards

A First-In-First-Out systemA First-In-First-Out system

Subject Matter ExpertsSubject Matter Experts

Application Review MeetingsApplication Review Meetings

Permitting checklists and gatesPermitting checklists and gates

Performance metrics (Everett)Performance metrics (Everett)

More user friendly applications (Amy)More user friendly applications (Amy)

Page 5: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

55

Visual Tracking BoardVisual Tracking Board

Page 6: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

66

FIFO SystemFIFO System

FIFO – First-In-First-OutFIFO – First-In-First-Out Always had an unofficial first-in-Always had an unofficial first-in-

first-out policyfirst-out policy August 24, 2005 memo from Paul August 24, 2005 memo from Paul

Foster officially stated that Foster officially stated that applications would be processed applications would be processed in the order receivedin the order received

Page 7: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

77

Subject Matter Experts (SMEs)Subject Matter Experts (SMEs)

Formally identified internal Formally identified internal Subject Matter Experts (SMEs)Subject Matter Experts (SMEs)

All Engineers and Scientists All Engineers and Scientists have been assigned to an have been assigned to an area(s) of expertisearea(s) of expertise

SMEs are used to answer SMEs are used to answer internal permitting and technical internal permitting and technical questionsquestions

Page 8: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

88

Important Process Important Process ImprovementsImprovements

Future State includes three Future State includes three important changes to the permitting important changes to the permitting process:process:

Application Review Meeting Application Review Meeting

Administrative Completeness GateAdministrative Completeness Gate

Technical Completeness GateTechnical Completeness Gate

Page 9: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

99

Application Review MeetingApplication Review Meeting

Receive Permit Request/Assign EE/

ES

Pre-Meeting Prep Hold Meeting Receive Application

CustomerMeeting Request Application

Incomplete Application

Approximately 20 Days

To Be Defined

7-14 Days

2 Mins

1 Days

Page 10: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1010

Application Review MeetingApplication Review Meeting

Establish meeting date/time/locationEstablish meeting date/time/location Draft application must be received Draft application must be received 77

calendar days prior to meetingcalendar days prior to meeting Purpose of MeetingPurpose of Meeting

Evaluate draft applicationEvaluate draft application Determine if administratively/technically Determine if administratively/technically

completecomplete Establish timelinesEstablish timelines

Submission of required informationSubmission of required information To process permitTo process permit

Page 11: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1111

Administrative Completeness Administrative Completeness GateGate

Review, Sort, Copy, Distribute

Administrative Completeness Gate

FIFO

Incomplete Application

1 Days

20 Mins

16.5 Days

Includes Lead & Travel Time

Customer

Page 12: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1212

Administrative Completeness Administrative Completeness GateGate Administrative Specialist reviews Administrative Specialist reviews

applications per administrative applications per administrative checklistchecklist All boxes filled inAll boxes filled in Application signedApplication signed EmissionsEmissions Application and advertisement feesApplication and advertisement fees Proof of local zoningProof of local zoning Coastal Zone Approval, if requiredCoastal Zone Approval, if required Applicant Background Questionnaire, if Applicant Background Questionnaire, if

new facilitynew facility

Page 13: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1313

Administrative Completeness Administrative Completeness GateGate Complete applicationComplete application

Administrative Specialist will send Administrative Specialist will send a letter stating the application is a letter stating the application is administratively completeadministratively complete Letter will include your assigned Letter will include your assigned

Engineer or Environmental Scientist Engineer or Environmental Scientist with their phone number and office with their phone number and office locationlocation

Letter will include where to track your Letter will include where to track your permit application’s progresspermit application’s progress

http://www.dnrec.state.de.us/DNRECeis/http://www.dnrec.state.de.us/DNRECeis/

Page 14: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1414

Administrative Completeness Administrative Completeness GateGate Incomplete applicationIncomplete application

Administrative Specialist will call to request the Administrative Specialist will call to request the missing informationmissing information

14 calendar days to submit missing information14 calendar days to submit missing information If information is not received by the If information is not received by the

deadlinedeadline A certified letter is sent requesting the missing A certified letter is sent requesting the missing

information within 14 calendar daysinformation within 14 calendar days If information is not received by the If information is not received by the

deadlinedeadline The application and fees will be returned by The application and fees will be returned by

certified lettercertified letter

Page 15: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1515

Technical Completeness GateTechnical Completeness Gate

Customer

Technical ReviewEngineering Review

Technical Completeness Gate

FIFO

Incomplete Application

Dover/New Castle

Processing Time Hrs4

Processing Time Days7

Processing Time Hrs24

Production Lead Time Days1

Production Lead Time Days30

Production Lead Time Days15

Travel Time Days1.5

% Complete & Accurage %90

16.5 Days

Includes Lead & Travel Time

24 Hrs

30 Mins

Min

Max

Avg

Min

Max

Avg

Page 16: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1616

Technical Completeness GateTechnical Completeness Gate

Assigned Engineer/Environmental Assigned Engineer/Environmental Scientist reviews the application Scientist reviews the application for technical completeness using for technical completeness using technical checklist (see handouts)technical checklist (see handouts)

If application is complete, If application is complete, Engineer/Environmental Scientist Engineer/Environmental Scientist prepares public noticeprepares public notice

Page 17: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1717

Technical Completeness GateTechnical Completeness Gate

Application not completeApplication not complete Engineer/Scientist will call to discuss missing Engineer/Scientist will call to discuss missing

information and will follow up with a summary information and will follow up with a summary emailemail

14 calendar days to correct deficiency14 calendar days to correct deficiency Information not received by deadlineInformation not received by deadline

Engineer/Environmental Scientist will send a Engineer/Environmental Scientist will send a certified letter requesting missing informationcertified letter requesting missing information

Letter states application will be returned if Letter states application will be returned if information is not received within 14 calendar information is not received within 14 calendar daysdays

Information not received by deadlineInformation not received by deadline Application will be returned without the fees by Application will be returned without the fees by

certified lettercertified letter

Page 18: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1818

Prepare Legal Notice/Draft Prepare Legal Notice/Draft PermitPermit

Draft Legal Notice Place Public Notice Develop Permit and Technical Memo

Obtain Information from Customer

% Complete & Accurate %90

30 Mins

30 Mins

7 Days

30 Mins

30 Days

40 Hrs

2 Days

Page 19: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

1919

Permit Review and IssuancePermit Review and Issuance

PMI Review

% Complete & Accurate %80

PMII Sign Copy, Log, and Distribute

Customer

Construction Permit

2 Days

4 Hrs

2 Days

30 Mins

1 Days

30 Mins

Page 20: 1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006

2020

SummarySummary

Lead Time to issue a construction Lead Time to issue a construction permit is 58.5 days (compared to permit is 58.5 days (compared to 104.5 days)104.5 days)

Process Time to issue a construction Process Time to issue a construction permit is 70 hours (compared to 74.4 permit is 70 hours (compared to 74.4 hours)hours)

We can now guarantee permit We can now guarantee permit issuance with 90 calendar days of an issuance with 90 calendar days of an administratively complete administratively complete application!application!