Page 1: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

1

SICBDST and BrunelSICBDST and Brunel

Migration status and plansMigration status and plans

Page 2: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

2

Migration Step 1:Migration Step 1:SICBMC/SICBDST splitSICBMC/SICBDST split

Last LHCb week:Last LHCb week: Split done but not tested

Software week (5-7 April)Software week (5-7 April) SICBDST v232 released Extensively tested and used in ECAL production No pileup

Current statusCurrent status SICBDST v233r2 in production Includes pileup

Split is complete. Monolithic SICB has been Split is complete. Monolithic SICB has been retired.retired.

Page 3: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

3

Step 2: Wrap SICBDST Step 2: Wrap SICBDST Fortran in Gaudi Fortran in Gaudi

(Brunel)(Brunel) Reminder of structure:Reminder of structure:

Main program, job steering, event input handled by Gaudi FORTRAN algorithms wrapped as Gaudi algorithms

One algorithm per sub-detector per “phase”Brunel.Digi.ECAL calls ECDIGI()Brunel.Trigger.TRIGGER calls TRIGGER()Brunel.Reco.RICH calls RIRECO()Brunel.FinalFit.TRAC calls AXRECO()

Independent of SICBDST version - just link to latest libraries Input RAWH file defined in jobOptions, FORTRAN code steered

by sicb.dat as before

StatusStatus v1 released yesterday It works! Similar results to SICBDST

Pileup not yet tested Must start large scale tests with sub-detector experts.

Page 4: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

4

Step 2: Brunel testing Step 2: Brunel testing planplan

This week:This week: Produce preliminary user guide 100 events available for first checks by sub-detector

experts SICBMC: $LHCBHOME/data/mc/sicb_bpipi_v233_100ev.raw SICBDST: $LHCBHOME/data/mc/sicb_bpipi_v233_100ev.dst Brunel: $LHCBDEV/BrunelTest/sicb_bpipi_v233_100ev.dst

Work out detailed test plan with each sub-detector contact

Testing procedure as for SICBDSTTesting procedure as for SICBDST Sub-detector expert checks Data quality histograms Status reports at weekly computing meeting

Page 5: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

5

Step 2: Brunel Step 2: Brunel commissioningcommissioning

In parallel to testing SICBDST functionality, In parallel to testing SICBDST functionality, commission GAUDI functionality:commission GAUDI functionality:

Pile-up in Gaudi Integration of OO algorithms

Histograms, Converters, OO DST

SICBDST can evolve in parallelSICBDST can evolve in parallel Brunel simply links latest SICBDST libraries Trivial to switch if no changes to SICB I/O mechanisms

Aim to make decision on SICBDST retirement at Aim to make decision on SICBDST retirement at next software week (July 3-7)next software week (July 3-7)

Frozen SICBDST version during summer New features added to Brunel only

Page 6: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

6

Step 3: Gradually Step 3: Gradually replace Fortran with replace Fortran with

C++C++ Much progress since last LHCb week:Much progress since last LHCb week:

Design reviews of Calorimeters, Tracking, RICH (February,March)

Software week (April)

Identified needs for:Identified needs for: Guidelines for common approaches to event data model

Access to MonteCarlo truth, access to contained objects Definition of public event data classes

Sequencing of algorithms, sharing and updating of data between subdetectors

Catalogue of existing convertershttp://lhcb.cern.ch/computing/Support/html/ConvertedSICBBanks.htm

Common language, common solutions Adaptors, Associators, Tools

Discussion forum to agree on the above

Page 7: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

7

Step 3: the way Step 3: the way forwardforward

Define a project teamDefine a project team Will ask sub-detector contacts to nominate OO

reconstruction representatives Start frequent brainstorming meetings (one or more per

week) To make progress on common issues (see previous slide) To identify candidates for integration in Brunel

Define a project planDefine a project plan Will approach each sub-detector contact in the next few

days to understand sub-detector software plans Agree on deliverables and milestones with project team

Page 8: 1 SICBDST and Brunel Migration status and plans. 2 Migration Step 1: SICBMC/SICBDST split  Last LHCb week: Split done but not tested  Software week

8

Summary of migration Summary of migration statusstatus

Step 1: Split SICB into SICBMC and SICBDSTStep 1: Split SICB into SICBMC and SICBDST Complete and in production

Step 2: Wrap SICBDST algorithms into Gaudi Step 2: Wrap SICBDST algorithms into Gaudi framework: Brunelframework: Brunel

First release available and ready for testing Pile-up to be commissioned In production by the summer

Step 3: Replace Fortran with C++Step 3: Replace Fortran with C++ Much progress in many sub-detectors Time to co-ordinate the work into one project