2
Current Status
• Targeted this RMS meeting for “Base” process preferences/recommendations– Retain ESI or Replace/Retire ESI
• Task Force:– has not yet reached consensus
– has had additional discussion re: need to continue work
– has requested PUCT staff input
– has market survey outstanding (responses to be provided 10/22)
– will adjust schedule and deliverables based on review/discussion of survey results
3
Transition Process Alternatives
• Seven process alternatives are being considered– Retain original ESI for service delivery point and transition that ESI from
“losing” TDSP to “gaining” TDSP;
• Alternative X1 – new 814_20 that changes TDSPs
• Alternative X2 – new transaction to switch/drop TDU
• Alternative X6 – manual process to be defined
OR
– Establish new ESI for service delivery point, transition retail service from old ESI to new ESI, retire old ESI
• Alternative X3 – Use existing move in and move out transactions
• Alternative X4 – new 814_20 that copies/creates new ESI
• Alternative X5 – new ESI transfer transaction
• Alternative X7 – manual process to be defined
4
Transition Scenario Variables• Variables that were determined to be important in developing recommendations for
the business processes and transactions to use include:– Time Frame
• Short Term (prior to new trx) vs. Long Term (post system changes) – Transition Date
• Date certain vs. on cycle vs. off-cycle– Volume of ESI IDs in transition
• < 500 • 501 to 5000• > 5000
– “Gaining” TDU territory competitive status• Opt-In IOU vs. Opt-In MCTDU vs. Non Opt-In
– “Losing” TDU status in market• Maintains a presence in Texas market vs. exits Texas market
– TDU tariff applied by “Gaining” TDU• “Gaining” TDU tariff vs. “Losing” TDU tariff vs. N/A
5
Alternative Evaluation CriteriaPotential evaluation criteria
– Impact on customer• Ongoing service (billing etc..)• Impact on Choice
– Lead time for implementation– Cost
• Development• Maintenance• Execution• Post Execution
– Cost per use– Degree of difficulty– Impact of future market activity– Existing Market Constraints
• Protocol Revisions• TX SET Versions• Regulatory Rules
– Impact on Day to Day Processing• Transaction Volumes• Monitoring• In Flight Transactions or Processes
6
Market Survey
• Request for market participants (and ERCOT) to express an initial preference for the appropriate process alternative for a designated scenario (specified combination of variables) and in consideration of the proposed evaluation criteria
– Retain or replace
– Given that preference, which process alternative should be applied
7
Market Survey Excerpt
Customer Transition Task Force
TDSP to TDSP Scenario Matrix
Variables:
Time Frame *On/off cycle Volume Gaining TDU Status Losing TDU Status Tariff Applied
Short Term Date Certain Sm (500 or less) Opt-in IOU Remain in TX Mkt Gaining TDU
Long Term On-cycle Med (501 - 5000) Opt-in MCTDSP Exiting TX Mkt Losing TDU
Off-cycle Lg (> 5000) NOIE NA
* If timeframe is "Short Term", alternatives X1, X2, X4 and X5 are not available
Example Scenarios:
Scenario A (e.g. Highway Relocation) - Short Term/On-Cycle/Sm (500 or less)/NOIE/Remain in TX Mkt/NA
Scenario B - Short Term/On-cycle/Sm (500 or less)/Opt-in IOU/Remain in TX Mk/Gaining TDU
Scenario C - Short Term/On-cycle/Sm (500 or less)/Opt-in IOU/Remain in TX Mk/Losing TDU
Scenario D - Short Term/Date Certain/Sm (500 or less)/Opt-in IOU/Remain in TX Mkt/Losing TDU
Scenario E - Short Term/Date Certain/Med (501 - 5000)/Opt-in MCTDSP/Remain in TX Mkt/Gaining TDU
Scenario F - Short Term/Date Certain/Lg (> 5000)/Opt-in IOU/Remain in TX Mkt/Gaining TDU
ERCOT TDSP Preferred
Time Frame On/off cycle Volume Gaining TDU Status Losing TDU Status Tariff Applied Replace ESI Retain ESI Dealbreaker Dealbreaker Alternative
1 Short Term Date Certain Sm (500 or less) Opt-in IOU Remain in TX Mkt Gaining TDU
2 Short Term Date Certain Med (501 - 5000) Opt-in IOU Remain in TX Mkt Gaining TDU
3 Short Term Date Certain Lg (> 5000) Opt-in IOU Remain in TX Mkt Gaining TDU
4 Short Term Date Certain Sm (500 or less) Opt-in MCTDSP Remain in TX Mkt Gaining TDU
5 Short Term Date Certain Med (501 - 5000) Opt-in MCTDSP Remain in TX Mkt Gaining TDU
6 Short Term Date Certain Lg (> 5000) Opt-in MCTDSP Remain in TX Mkt Gaining TDU
7 Short Term Date Certain Sm (500 or less) NOIE Remain in TX Mkt Gaining TDU NA NA
8 Short Term Date Certain Med (501 - 5000) NOIE Remain in TX Mkt Gaining TDU NA NA
9 Short Term Date Certain Lg (> 5000) NOIE Remain in TX Mkt Gaining TDU NA NA
10 Short Term Date Certain Sm (500 or less) Opt-in IOU Exiting TX Mkt Gaining TDU
11 Short Term Date Certain Med (501 - 5000) Opt-in IOU Exiting TX Mkt Gaining TDU
12 Short Term Date Certain Lg (> 5000) Opt-in IOU Exiting TX Mkt Gaining TDU
Check Preference
8
Next Steps
• Next steps
– Survey responses due COB 10/22
– Task Force meeting scheduled 10/29
• Review survey responses
• Discuss issues or concerns
• Work through process details for scenarios with consensus
– Updated/Revised plan at November RMS