Public Procurement System in Tanzania
Presentation in the SADCOPAC / EAAPAC Accountability Conference 2012 Windhoek
Namibia
Presentation prepared by:Mathew N. KILEOClerkPublic Accounts Committee TanzaniaP.O. Box 9133Tel: +255 22 2112065/7, Fax: +255 22 2112538Email: [email protected]: www.parliament.go.tzDar-es-Salaam Tanzania
WelcomeKaribuni
Reforms in Public Procurement Regime
Procurement reforms in Tanzania started way back in 1997.
The reforms led to enactment of Public Procurement Act No. 3 in March 2001 (PPA 2001). It became operational in July 2001.
Reforms in Public Procurement Regime
In 2002 a Country Procurement Review Assessment was carried out which suggested further reforms from centralized to decentralized procurement System
The Reforms culminated in enactment of Public Procurement Act 2004.
-
PPA N0.3 of 2001
PPA No. 21 of 2004
Central Tender Board
PPRA
Head of PEs
chairperson of TB
Head of PEs not chairperson of TB but they
appoint members
Not applicable to Parastatals
not receiving Gov.
subvention
Applicable to all public
bodies including those not receiving
subvention
PP
AA
has chairperson
and Four Mem
bers
PPAA
has chairperson
and six mem
bers
Procurement Thresholds
No Procurem
ent Thresholds
Major differences between PPA 2001 and PPA 2004
Public Procurement Act No. 21 of
2004
The Public Procurement (Goods, Works, Non-Consultant Services and Disposal of Public Assets by Tender) Regulations GN. No 97 of 2005
The Public Procurement (Employment and Selection of Consultants) Regulations GN. No 98 of 2005
Sta
nd
ard
Ten
der
Do
cum
ents
Ten
der
Eva
luat
ion
Gu
idel
ines
Gu
idel
ines
fo
r P
rep
ara
tio
n o
f
Res
po
nsi
ve
bid
s
Oth
er
Cir
cu
lars
pe
rio
dic
ally
iss
ued
by
PP
RA
Regulatory Framework of Procurement in Tanzania
Lo
cal
Go
vern
men
t
Ten
der
Bo
ard
(Est
abli
shm
ent
and
Pro
ceed
ing
s)
Reg
ula
tio
ns
SET UP OF PROCURING ENTITIES
ACCOUNTING OFFICERACCOUNTING OFFICER
TENDER BOARDTENDER BOARD
Evaluation committeesEvaluation committees
TB submits to AO approved bidder for notification of award
Mem
bers
recom
men
ded
by P
MU
and
app
roved
by A
OPMU Submit Recommendations to TB for Approval
Rep
ort
s to
AO
Evaluation report submitted to PMU
Provisions toHandle
disagreements
User DepartmentsUser Departments
PROCUREMENT MANAGEMENT UNITPROCUREMENT MANAGEMENT UNIT
initiate Requirements, inputs to specifications and in evaluation
PPRA
PPAA
INTERVENTIONS FOR
COMPLIANCE WITH PPA 2004
Strong oversight
body (PPRA)
Capacity of PEs and
bidders to implement
the Act
Proper implementation Guidelines
Proper system for checking
and Monitoring
Proper System of Sharing
Information
8
THE JOURNEY TOWARDS 2015
Yes it is achievable as long as every PE aims to achieve Vfm
THE JOURNEY- IS IT ACHIEVABLE ????
216 PEsTshs 2.96
trillion
264 PEsTshs 3.10
trillion
315 PEsTshs 4.52
trillion
The need to improve efficiency – High Expenditure in Public Procurement
11
39%
50%55%
73%68%
49%
59%
69%
80%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
2006/07 2007/08 2008/09 2009/10 2010/11
AV
ERA
GE
COM
PLIA
NCE
LEV
ELS
ACTUAL TARGET
TREND OF PROCURING ENTITIES COMPLIANCE WITH PUBLIC PROCUREMENT ACT AND ITS REGULATIONS
SINCE FINANCIAL YEAR 2006/07
The need to improve efficiency – Low levels of Compliance
Efforts to increase efficiency
Many efforts are being undertaken – only few shall be highlighted in this presentation
-
83
57
57
42
56
68
26
79
79
66
31
32
52
0 20 40 60 80 100
Establishment and composition ofTender Board
Establishment and composition of PMU
Functioning of AO, TB and PMU
Preparation of Annual ProcurementPlan
Approvals
Advertisement of bid opportunities
Publication of aw ards
Time for preparation of bids
Method of Procurement
Use of standard tender documents
Records keeping
Quality Assurance
Contract implementation
Series1AR
EA
S O
F F
OC
US
DIVISION OF INFORMATION AND COMMUNICATION
TECHNOLOGY
DIVISION OF CAPACITY BUILDING
AND ADVISORY SERVICES
Research and Documentation
Section
Guidelines Development and
Dissemination Section
Training and Advisory Services
Section
Finance and Accounting Section
Administration and Human Resources
Section
DIVISION OF CORPORATE
SERVICES
Contract Performance
Section
Monitoring and Evaluation
Section
DIVISION OF MONITORING
AND COMPLIANCE
Systems Development and
Maintenance Section
BOARD OF DIRECTORS
CHIEF EXECUTIVE OFFICER
INTERNAL AUDIT UNIT
Systems Support and Administration
Section
PROCUREMENT MANAGEMENT UNIT
Planning and Coordination
Section
DIVISION OF LEGAL AND PUBLIC AFFAIRS
Public Relations Section
Legal and Secretariat Affairs Section
Investigation and Anti-Corruption
Section
Zonal Services Section
NORTHEN ZONE
LAKE ZONE
COAST ZONE
CENTRAL AND SOUTHERN ZONE
New Structure-From 51 Staff (2001)
to 142 Staff (2004)
Expanding PPRA Outreach
MwanzaArusha
Iringa
D’Salaam
PPRA TO REACH LGAs – opening of
zonal offices
-Submits copies of Call Off Orders
to PPRA and GPSA
-Places and
pays for Call
Off Order
16
SYSTEM OF PROCUREMENT OF COMMON USE ITEMS AND SERVICES – REDUCED PROCUREMENT
TRANSACTION COSTS
PROCURING ENTITY
SUPPLIER/SERVICE PROVIDER
PPRA
GPSA
-Compiles a list of CUIS-List of CUIS
approved
-Sub
mits
a li
st
of C
UIS to
GPSA
-Aggregates all CUIS from PEs-Decides on the
appropriates Procurement Method
Invit
es
Tenders
Ente
rs into
Fr
am
ew
ork
A
gre
em
ent
wit
h
win
ners
-Prepares and Maintains CUIS and Suppliers Data
Base-Maintains Data on placed Call Off orders as
received from PEs-Sub
mits
a li
st o
f
Fram
ewor
k
Agre
emen
ts
-Supplies and paid
for the call off
order
17
Efficiency in sharing procurement information to the public
18
Efficiency in sharing procurement information to the public
19
Efficiency in procurement transactions – e-procurement – Tanzania has done a feasibility study and is currently
working on issues relating to system selection, hosting, infrastructure, application, operation and maintenance, as
well security
20
Amendments to the Act –Notable Amendments to Complaints Review
Mechanism
21
Bidders complaint
HEAD OF PE
Presented within 28 days from the day of the event
leading to complaint
Copy of complaints submitted to PPRA
and the RC
Befo
re t
he s
ign
ing
of
con
tract
Conduct investigations
Decision within 30
days
Copy of decision
submitted to PPRA and
the RC
Suspend procurement proceedings
PPRA-if not satisfied with the decision or after the expiry of a 30 days period
PPAA-if not satisfied with the decision of PPRA or after the expiry of a 30 days period
Aft
er
sig
nin
g o
f con
tract
System for Procurement Complaints Review
TO
TA
L 1
05 D
AY
S
22
Amendments to the Act –Notable Amendments: Integration of
procurement plan with budgeting process
Challenges
Failure by Some PEs to utilize the opportunity for reducing procurement transaction cost e.g use framework contracts for procurement of CUIS and advertize in the TPJ and Authority website
Corrupt and fraudulent practices in procurement process despite the effort being spent to prevent and combat them
Challenges
Commercial operators such as suppliers and service providers, as well as CSOs have not effectively used the opportunities availed by the PPRA to build their capacity
PEs to be encouraged to do procurement capability review assessment and allocate resources for capacity building of their staff
Way Forward
Action to be taken against PEs not demonstrating commitment to reduction of procurement transaction cost
Commercial operators should be sensitized to register as appropriate and take part in improving their capacity to withstand the competitive procurement market in the country as well as in the region
-
Way Forward
The CSOs should be empowered to actively participate in advocacy of good governance in public procurement and monitoring of process and outcome in delivery of services
The fight against fraud and corruption in public procurement should be intensified by more collaborative initiatives among key stakeholders
-
WE can all overcome
Thank you for Thank you for listeninglistening