1 Network Innovation Competition: Full Submission Application (NGGTGN04) 1. Project Summary 1.1 Project Title HyNTS FutureGrid Phase 1 – Transmission Test Facility 1.2 Project Explanation FutureGrid aims to demonstrate that the Gas National Transmission System (NTS) can be repurposed to transport hydrogen. The initial phase involves building an offline hydrogen test facility, to assess the impact that blends of hydrogen will have on NTS assets. 1.3 Funding Licensee National Grid Gas Transmission (NGGT) 1.4 Project Description 1.4.1. The Problem(s) it is exploring Achieving the UK’s Net Zero targets will require decarbonisation across the whole energy system. Sectors such as heat are difficult to decarbonise, and the importance of the NTS to the UK’s current energy supply means we need to consider how to reliably and safely deliver low carbon energy to consumers. Existing research suggests hydrogen could be an alternative to natural gas, but there are several knowledge gaps that need addressing and a lack of physical trials. 1.4.2. The Method(s) that it will use to solve the Problem(s) The project will involve building a hydrogen test facility from a representative range of decommissioned NTS assets. Flows of hydrogen and natural gas blends (up to 100% hydrogen) will then be tested at NTS pressures, to better understand how hydrogen interacts with the assets. The data gathered will be used to assess the impact that a hydrogen conversion of NTS assets will have. 1.4.3. The Solution(s) it is looking to reach by apply the Method(s) The project will build on existing work under the HyNTS programme and increase understanding of the characteristics of hydrogen in the NTS, demonstrating what is required for hydrogen to be safely transported within the high-pressure gas transmission system. This learning will set the foundation for our longer-term goal to accelerate the decarbonisation of power, industry and heat and deliver a safe supply of low-carbon energy to all our customers. 1.4.4. The Benefit(s) of the project Hydrogen has the potential to play a role in the decarbonisation of heat, power, and industry. Repurposing the NTS will minimise

Upload: others

Post on 01-Feb-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    Network Innovation Competition: Full Submission Application (NGGTGN04)

    1. Project Summary

    1.1 Project Title HyNTS FutureGrid Phase 1 – Transmission Test Facility

    1.2 Project

    Explanation

    FutureGrid aims to demonstrate that the Gas National Transmission

    System (NTS) can be repurposed to transport hydrogen. The initial

    phase involves building an offline hydrogen test facility, to assess the

    impact that blends of hydrogen will have on NTS assets.

    1.3 Funding

    LicenseeNational Grid Gas Transmission (NGGT)

    1.4 Project

    Description

    1.4.1. The Problem(s) it is exploring

    Achieving the UK’s Net Zero targets will require decarbonisation

    across the whole energy system. Sectors such as heat are difficult to

    decarbonise, and the importance of the NTS to the UK’s current

    energy supply means we need to consider how to reliably and safely

    deliver low carbon energy to consumers. Existing research suggests

    hydrogen could be an alternative to natural gas, but there are

    several knowledge gaps that need addressing and a lack of physical

    trials.

    1.4.2. The Method(s) that it will use to solve the Problem(s)

    The project will involve building a hydrogen test facility from a

    representative range of decommissioned NTS assets. Flows of

    hydrogen and natural gas blends (up to 100% hydrogen) will then be

    tested at NTS pressures, to better understand how hydrogen

    interacts with the assets. The data gathered will be used to assess

    the impact that a hydrogen conversion of NTS assets will have.

    1.4.3. The Solution(s) it is looking to reach by apply the Method(s)

    The project will build on existing work under the HyNTS programme

    and increase understanding of the characteristics of hydrogen in the

    NTS, demonstrating what is required for hydrogen to be safely

    transported within the high-pressure gas transmission system. This

    learning will set the foundation for our longer-term goal to accelerate

    the decarbonisation of power, industry and heat and deliver a safe

    supply of low-carbon energy to all our customers.

    1.4.4. The Benefit(s) of the project

    Hydrogen has the potential to play a role in the decarbonisation of

    heat, power, and industry. Repurposing the NTS will minimise

  • 2

    disruption, and potentially cost, for customers and consumers when

    developing a hydrogen NTS. Using a hydrogen test facility that

    remains separate from the NTS will allow for testing to be undertaken

    in a controlled environment, with no risk to the safety and reliability

    of the existing NTS. FutureGrid provides a significant opportunity to

    increase collaboration across the gas networks, help share learning

    and increase hydrogen knowledge within the gas industry.

    1.5. Funding

    1.5.1. NIC Funding

    Request (£k)£9,073,785.97

    1.5.2. Network

    Licensee Compulsory

    Contribution (£k)

    £1,024,109.40

    1.5.3. Network

    Licensee Extra

    Contribution (£k)

    £257,313.94

    1.5.4. External

    Funding – excluding

    from NICs (£k)

    £2,304,000.00

    1.5.5. Total Project

    Costs (£k)£12,699,997.00

    1.6. List of Project

    Partners, External

    Funders and Project

    Supporters (and

    value of

    contribution)

    Project Partners & Contractors: DNV GL (£380k), NGN (£205k), HSE,

    Fluxys (£1.8m), Durham University (£100k)

    Project Supporters: Cadent, WWU, SGN, ENA, Gas Networks Ireland,

    GasUnie, Scottish Government, IGEM, GTC, GERG, Edinburgh

    University

    1.7. Timescale

    1.7.1. Project

    Start DateApril 2021

    1.7.2. Project

    End DateMarch 2023

    1.8. Project Manager Contact Details

    1.8.1. Contact

    Name and Job

    Title

    Tom Neal,

    Innovation Delivery

    Manager

    1.8.2. Email and

    Telephone

    Number

    [email protected]

    07785451353

    1.8.3. Contact

    Address

    National Grid, National Grid House, Gallows Hill, Warwick Technology

    Park, Warwick, CV34 6DA.

    1.9. Cross Sector Projects (only complete this section if your project is a Cross Sector

    Project, i.e. involves both the Gas and Electricity NICs).

    1.9.1. Funding requested from the

    [Gas/Electricity] NIC (£k, please state which

    other competition)

    N/A

    1.9.2. Please confirm whether this

    [Gas/Electricity] NIC Project could proceed in

    the absence of funding being awarded for the

    other Project.

    N/A

    1.10. Technology Readiness Level (TRL)

    1.10.1. TRL at

    Project Start Date4

    1.10.2. TRL at

    Project End Date6

  • 3

    2. Project Description

    2.1. Aims and objectives

    2.1.1 Problem

    The NTS is a critical national infrastructure that transports natural gas, in bulk, away from the

    import terminals (such as St Fergus, Bacton, Isle of Grain and South Hook) to large-scale

    customers such as gas fired power stations and Gas Distribution Network (GDN) offtakes. The

    most efficient way to move any gas is at high pressure and in large diameter pipelines, using

    compressors at strategic locations to maintain the flows. There are directly connected

    customers, such as the industrial and power generation sectors, and customers connected to

    the GDNs further downstream. The NTS currently transports over 97% of the natural gas that

    flows through the GDNs, much of which is delivered to 23 million domestic consumers for

    heat1.

    Research is urgently needed to address the UK net zero ‘heat challenge’ to establish whether,

    and how, the NTS could be converted to 100% hydrogen. This is on the critical path for a UK

    Government policy decision on the futures of both heat and the gas industry. The NTS is also

    vital for daily storage to maintain security of supply; the need for storage would increase as

    the energy content of hydrogen is approximately a third of that of natural gas2. In parallel to

    live hydrogen consumer trials proposed by the GDNs, work is also needed to establish whether

    the NTS could maintain current levels of safety and security of supply if it were converted to

    hydrogen. To address this challenge, NGGT set up the HyNTS programme of works to cover all

    hydrogen related projects for the NTS. The FutureGrid project falls within the HyNTS

    programme and has its own roadmap of three phases, the first of which forms the scope of

    this proposal. Phases 2 and 3 focus on key areas such as compression, deblending and in-line

    inspection and are detailed further in Section 3.3. The Hydrogen Programme Development

    Group (HPDG) set up by Business Energy and Industrial Strategy (BEIS) has identified

    potential end states for a decarbonised gas industry. The FutureGrid programme of work will

    provide the evidence for these and understand whether it is possible and safe to:

    Flow high-pressure hydrogen through existing NTS assets (pipelines, valves etc) - this

    forms the scope of this proposal

    Deblend hydrogen3 from natural gas during the system transition (outside scope of this

    proposal – to be developed in FutureGrid Phase 2)

    We have undertaken several desktop studies through the HyNTS programme of work which

    have confirmed, in principal, the suitability of hydrogen in the NTS. However, there are gaps

    1 The remaining 3% of gas in the GDNs is biomethane which is injected directly into the lowerpressure tiers.2 The calorific value of hydrogen is about 12 MJ/m3 which compares with a typical range of 38to 40 MJ/m3 for natural gas.3 It is possible that the NTS would need to transport both hydrogen and natural gas during anenergy transition. It would need to supply customers who have converted to hydrogen andthose waiting to convert whilst continuing to be safe, secure, affordable and low carbon.

  • 4

    in knowledge that are fundamental to, and underpin, the safe and reliable operation of

    hydrogen conversion. The Health and Safety Executive – Science Division (HSE-SD) carried

    out an initial study and highlighted impacts such as leakage, venting and the effects of

    hydrogen on the mechanical properties of some NTS materials. The main outcome of the

    research was that physical testing is required on a variety of NTS assets to understand the

    risks and mitigations required before more advanced operational studies such as deblending

    can be undertaken.

    In Europe, gas network transporters; GasUnie and SNAM have already trialled hydrogen

    injection into a section of pipeline to test the impact on some assets. NGGT has not been able

    to identify a similar suitable section of pipeline for testing as the NTS is highly interconnected.

    We would not be able to meet the need for flexibility in testing, trialling and developing a

    range of technologies alongside ensuring supply to our customers at this early stage. In the

    case of online testing (the day-to-day functioning NTS), there would be the risk of hydrogen

    penetrating into the downstream GDNs and being delivered to consumers in an uncontrolled

    manner. To add to this, our current Safety Case does not allow transportation of gases other

    than Methane and the Gas Safety (Management) Regulations 1996 clearly states that the limit

    for hydrogen is less than or equal to 0.2% molar. Both documents sit under the Gas Act 1986

    and to allow transportation of the proposed hydrogen blends in methane at this stage, will be

    a direct breach of our Gas Transporters Licence. Therefore, an off-line test facility constructed

    from decommissioned NTS assets will be the safest, most time-effective and cost-efficient way

    to understand the risks and demonstrate the capabilities of the NTS.

    The physical and chemical properties of hydrogen differ substantially from those of natural

    gas. We need to further investigate how these properties may affect the NTS pipelines, assets,

    materials, operational procedures and energy delivery. We need evidence from testing that

    demonstrates that a hydrogen NTS system can be operated safely with hydrogen and

    hydrogen blended with natural gas. Repurposing the NTS for hydrogen could be fundamental

    to the Great Britain (GB) Gas Networks’ transition to 100% hydrogen4 and would reduce

    reliance on costly, localised production of hydrogen from natural gas reforming with carbon

    capture. There would be benefits in producing blue hydrogen5 at existing gas terminals, which

    are already industrial chemical processing sites. This would negate the need for a new on-

    shore carbon dioxide transmission system that connects smaller reforming plants with offshore

    carbon capture and storage. Additionally, it is widely believed that blue hydrogen is an interim

    measure that is likely be replaced by green hydrogen6 generated from renewables. A fully

    converted NTS would be ready to support that transition. Maintaining the connection between

    the NTS and the GDNs will also support security of supply to customers by connecting

    hydrogen producers and providing line pack and connections to hydrogen storage facilities.

    4 Please note that 100% hydrogen could vary in composition due to impurities in the gasintroduced in production or from the NTS itself.5 Blue hydrogen is produced by converting natural gas using a process called methanereformation.6 Green hydrogen is produced by a process called electrolysis, using renewable power sources.

  • 5

    2.1.2 Overview of Method & Demonstration Activities

    The FutureGrid project detailed in this submission is Phase 1 of the HyNTS Programme and will

    test flows of hydrogen/natural gas blends and, for the first time in GB, 100% hydrogen at NTS

    pressures. The HyNTS FutureGrid programme consists of 3 key phases (see Appendix C figure

    10) and will culminate in an online trial on the NTS. The first phase is the basis for future

    validation work on hydrogen technologies that will enable the use of hydrogen in our current

    NTS system and will allow collaboration of many key stakeholders. The transmission test

    facility will connect upstream of the H21 gas distribution system currently under construction.

    By doing this, we will create a complete beach-to-meter gas network test system for

    hydrogen. This supports the HPDG ambition for a comprehensive programme of evidence

    ahead of a UK policy decision about converting the UK gas networks to hydrogen. Phases 2

    and 3 will focus on deblending, compression and in-line inspection.

    This NIC proposal is Phase 1 of NGGT’s HyNTS FutureGrid Programme. The programme seeks

    to demonstrate how the NTS can be repurposed for hydrogen.

    Phase 1 will be divided into:

    Phase 1a to build a hydrogen test facility at DNV GL Spadeadam.

    Phase 1b to test the compatibility and integrity of NTS assets with hydrogen blends up

    to 100% hydrogen.

    Phase 1c to update the NTS Quantitative Risk Assessment (QRA), prepare a

    commented version of the safety case and carry out a high-level review of the NGGT

    procedures and standards – this will highlight the procedures and standards affected by

    a change from natural gas to hydrogen / a hydrogen blend.

    2.1.3 Solutions enabled by FutureGrid

    Through the FutureGrid programme, NGGT will provide a robust plan for hydrogen in the NTS.

    The programme will enable:

    The provision of a collaborative research centre at Spadeadam for engagement of

    stakeholders, suppliers, customers and academic bodies, providing confidence on the

    feasibility of repurposing the existing NTS to transport hydrogen

    A test facility that can be used to identify gaps in knowledge and to deliver a strategy

    for the NTS to be hydrogen ready, validating that the NTS operations can be

    undertaken safely with hydrogen and that that the societal and individual risks are

    comparable to those of natural gas by supplying new data for Quantitative Risk

    Assessment (QRA)

    A vital competence and training facility for the gas networks and the wider industry

    The progression to FutureGrid Phase 2/3 and live trials to begin safely on the current

    NTS

    The development of key technologies that contribute to Net Zero Carbon by 2050

  • 6

    2.2. Technical description of Project

    2.2.1 Phase 1a Technical Description

    Phase 1a will deliver an off-line NTS test facility constructed mainly from decommissioned NTS

    assets, to demonstrate if hydrogen and hydrogen blends can be transported effectively,

    flexibly and safely in the existing NTS. Figure 1 demonstrates the assets and Figure 2 shows

    the proposed facility layout in infographic formats. A technical drawing of the site can be

    found in the Technical Appendix J (Figure 16).

    Figure 1 - Phase 1 Facility Infographic

    This will substantially mitigate risks when the time comes to inject hydrogen into the live NTS.

    The key steps for Phase 1a are:

    Relocating a representative range of decommissioned NTS assets to DNV GL

    Spadeadam, where they can be assessed for repurposing for hydrogen service

    Building, testing and commissioning of the NTS facility including hydrogen storage,

    hydrogen/natural gas blending and the link to the H21 gas distribution facility

    Developing safe operating procedures and risk assessments for the test programme

    Engagement with our Capital Delivery teams to share learning

    The majority of current NTS assets have been in service for more than 30 years. Therefore, to

    enable hydrogen to be safely transported through the NTS, we need to carry out research to

    provide safety evidence. We need to confirm that we can operate and maintain the system

    safely for the future. Research studies have been undertaken to review the viability of

  • 7

    hydrogen in the NTS7. However, very little physical testing has been possible to confirm the

    findings on the full the range of assets and components used today.

    The FutureGrid facility will enable us to carry out detailed and comprehensive hydrogen

    testing, to demonstrate whether the NTS can be safely converted to hydrogen. Detail of the

    types of assets is included in Appendix B. These assets will also be chosen, considering known

    issues with hydrogen from previous studies. The facility will be used more widely by gas

    industry suppliers and other industries for testing new and existing components with

    hydrogen. An infographic showing the function of the test facility is shown below.

    Figure 2 – DNV GL Spadeadam layout

    7 Refer to section 6.1 for further detail

  • 8

    The detailed design of the test facility is underway as part of the Roadmap to FutureGrid

    (NIA_NGGT0166) project. At the point of the project being awarded funding later this year,

    construction of the FutureGrid facility – by a joint team of technical experts from NGGT and

    DNV GL – will begin promptly in April 2021. The design is based on the use of assets that are

    planned or already being decommissioned to ensure the facility is representative of the current

    NTS.

    The selection of components would be based on the recommendations in the HSE-SD report

    commissioned by NGGT – a more detailed list and the reasons for the selection of each

    component is shown in Appendix B. It is also important for the facility design to include a

    representative cross-section of the types of materials in the NTS, including many components

    which are safety critical. A control room will be included as part of the design and

    construction, which will include systems for controlling pressures and flows and gathering test

    data, such as velocity, temperature, pressure and gas composition. Longer term, it is

    envisaged that end users, academia and other suppliers will also be able to use the facility for

    testing and validation of their equipment.

    2.2.2 Phase 1b Technical Description

    Phase 1b will deliver the master testing plan which will have been developed as part of the

    Roadmap to FutureGrid NIA project. We will inject and blend hydrogen with natural gas to

    provide a range of compositions up to 100% hydrogen. We will study strategic hydrogen

    concentrations including 2%, 20% and 100% hydrogen, with intermediate concentrations

    studied as necessary. The main steps for Phase 1b are:

    Operate the NTS hydrogen facility for 6-12 months according to the testing plan

    Review and evaluate the test results to assess the safe operation of the assets we are

    testing, extrapolating to the NTS and suggesting mitigations where possible

    Validating flow parameters such as gas velocities, pressures, energy delivery and other

    operating parameters for hydrogen blends up to 100% hydrogen, assumed as:

    o Velocity = up to 40m/s to reflect the change in hydrogen and capacity

    o Pressure = 50bar(g) up to 94bar(g)

    o Temperature = -20deg C to +50deg C

    o Flow to be determined as part of the design process and measured using

    ultrasonic / orifice plate flow meters

    Dissemination of results to enable international collaboration and accelerate Hydrogen

    development

    Our detailed test plan (Appendix B) is under development in the NIA project ‘Roadmap to

    FutureGrid’ and focuses primarily on the functionality of key assets in a hydrogen

    environment. The aims of the tests are to:

    Validate critical operational parameters like pressure, temperature, velocity and flow

    Provide new knowledge and understanding of the characteristics of hydrogen

    Gain new knowledge about the operability of some important NTS assets, such as

    valves, slam shut valves and pressure regulators

    Determine any impacts to existing asset lives and maintenance frequencies of

    operating and maintaining assets in a hydrogen environment

  • 9

    The test plans will be developed in consultation with NGGT, HSE-SD and experts from DNV GL

    in the areas of integrity, safety, process and operational backgrounds. The test plan will also

    include inputs from key project collaborators such as Fluxys (gas transporter in Belgium as

    detailed in section 4.4.3) and the academic teams from Durham and Edinburgh. As this is a

    research programme, the test plan will include flexibility to allow specific focus on certain

    areas as required. The test plans will be continuously reviewed to ensure that they are

    meeting the project objectives and any changes to the test plan will be approved by the

    project management team. Using DNV GL’s QRA methodology for NGGT’s Hazard Assessment

    of the Transmission System (HATS), the data gathered from FutureGrid Phase 1b will be used

    to understand the risks associated with introduction of hydrogen into the NTS.

    2.2.3 Phase 1c Technical Description

    Phase 1c will use the data from Phase 1b for a high-level assessment of the results. This will

    consider how converting NTS pipelines to transport up to 20% hydrogen blends and 100%

    hydrogen will affect public safety. Since NTS pipelines are defined as Major Accident Hazard

    Pipelines (MAHP)s under the Pipeline Safety Regulations (PSR), NGGT is required to develop

    and maintain a Major Accident Prevention Document (MAPD) that demonstrates that all

    hazards have been identified, the risks have been evaluated and that an appropriate safety

    management system is in place and kept under review. If the results from Phase 1b indicate

    that the failure frequencies of NTS components are different to those of natural gas, the new

    data will be used for the risk analysis.

    Hazard Assessment of the Transmission System (HATS) covers pipelines only, not compressor

    sites or other installations. Therefore, we will use this as the basis for the comparison and

    high-level assessment of risk, reflecting the actual pipelines and operating conditions of the

    NTS, combined with generic population assumptions. DNV GL undertake this periodically for

    NGGT, so the overall level of risk posed to the public by the NTS pipelines (not including

    installations) is monitored. We will present risk as societal risk for the entire system, with

    comparisons of the variation in individual risk with distance for selected typical pipelines. We

    will make the comparison on a like-for-like basis, in that all other parameters (pipeline

    properties, operating pressures, etc.) remain the same, other than the composition of the gas

    being transported. It is well known that releases of hydrogen into confined or congested

    regions have the potential for more significant explosion hazards than natural gas. This should

    be addressed subsequently in a separate study that considers the details of these sites and

    any research carried out to date, such as within the H21 programme of works.

    The Quantitative Risk Assessment (QRA) methodology adopted by NGGT for NTS assets

    transporting natural gas (defined in NGGT’s Hazard Assessment Methodology Manual – HAMM)

    is not fully applicable to hydrogen. Therefore, it will need to be adapted where appropriate.

    Where deviations are required, these will be recorded and will form a basis for updating HAMM

    at a later stage (outside the scope of this FutureGrid Phase 1). We will also modify software

    tools, e.g. PIPESAFE, for hydrogen and hydrogen blends to complete the QRA calculations

    required in FutureGrid.

  • 10

    Overpressure Risk (OR) - To check whether the existing natural gas methodology can be

    adapted for 100% hydrogen based on thermal radiation hazards alone, we need to obtain

    relevant evidence. This would need to support the assumption that overpressure hazards can

    be negated or, if not, to provide the data we need to develop an additional modelling approach

    to take overpressures into account. This evidence will be collected from large-scale testing of

    NTS pipework during the FutureGrid Phase 1. This will be based at a dedicated overpressure

    test area at the same Spadeadam site to prevent any impact to the larger NTS test facility. It

    will involve the deliberate rupture and delayed ignition of a 100% NTS hydrogen pipeline

    under controlled conditions, capturing essential data on hydrogen gas outflow, fire

    characteristics and overpressure levels. This will allow us to develop an appropriate

    methodology for risk analysis and emergency planning purposes. If the levels of risk are

    higher for hydrogen/natural gas mixtures or 100% hydrogen, we will consider possible

    mitigation options for live assets.

    The NGGT Safety Case was reviewed in the ‘Hydrogen Injection into the NTS’ NIA project at a

    high level. This included highlighting the revisions and gaps in knowledge we will need to

    address before we introduce hydrogen to the NTS. However, the safety management system

    involves many detailed policies, procedures and work instructions. We will triage the suite of

    NGGT documents so we can prioritise each for detailed review, as either “High” (hydrogen

    likely to have a significant impact), “Low” (hydrogen unlikely to have a significant impact) or

    “Not required” (not affected by hydrogen).

    A marked-up version of the Safety Case will identify where we will need to make updates,

    including hydrogen or hydrogen blends. This will also highlight where we need further

    evidence or testing to answer questions relating to safe operation not addressed in this

    FutureGrid Phase 1. The main output from Phase 1c will be a high-level comparison of the risk

    for 100% natural gas versus the various blends up to and including 100% hydrogen that we

    studied during the master test plan. This work will continue in parallel with the collaborative

    NIA ‘HyTechnical’ project being led by SGN. It will involve updating core policies as evidence

    for the impact of hydrogen. All the operational parameters (such as pressure, temperature,

    velocity and flow) for each of the NTS assets derived from Phase 1b will feed into a fast

    screening methodology developed by Fluxys. This methodology will focus on the effect of

    hydrogen on component parts and is detailed further in Section 4.4.3.

    2.2.4 Innovation through Phase 1 and enabling Phase 2 & 3

    The use of hydrogen in live trials of current NTS assets is innovative and is classed as high risk

    due to gaps in knowledge. We can address these knowledge gaps by using a combination of

    laboratory testing and off-line testing using the FutureGrid facility. Phase 1 will develop the

    unique facility and deliver evidence about the compatibility of the NTS with hydrogen. Through

    Phases 2 & 3 the facility will also enable the development of novel technologies that are

    stunted by the lack of application-based demonstration capability in the UK. FutureGrid is the

  • 11

    bridge across the technology development ‘Valley of Death’8 that will make sure the UK has

    the means to move forward with hydrogen infrastructure for the future.

    2.3 Description of design of trials

    2.3.1 Facility Design & Build to ensure robust results

    The facility design and build use decommissioned assets that are a representative sample of

    assets from the NTS. By designing the facility using assets that are near their end of life, we

    are making sure the test results show a worse-case situation. This will allow us to identify

    asset health requirements before undertaking live applications.

    2.3.2 Facility Test Plan to ensure robust results

    We will formulate a test plan based on recommendations and evidence gaps identified from

    the NIA report delivered to NGGT by HSE-SD. This sets out the necessary steps to prove that

    the NTS and its assets can operate safely and efficiently with hydrogen. Further development

    will be undertaken to ensure it is technically sound, fit for purpose and robust – in consultation

    with experts from within NGGT (including Gas System Operation), DNV GL and HSE-SD – in

    the areas of integrity, safety, process, balancing, metering and operation. In addition, the test

    plan will include inputs from key project collaborators, such as Fluxys and our academic

    partners. It will also use Design of Experiments (DoE) methodology to make sure the results

    seen from the tests are statistically sound, taking all associated variables across the system

    into account. This will ensure the validity of the results and their reliability as a basis for future

    work.

    2.3.3 Methods for capturing learning to ensure robust results

    We will document the build and test phases in accordance with NGGT and DNV GL Quality

    Management Systems (QMS). During project delivery, this will involve the project team

    identifying, documenting, analysing, storing and retrieving any lessons learnt. The lessons

    learnt will stem from both positive and negative impacts seen on the FutureGrid project. The

    dissemination of these lessons will make sure that any learning we have recorded throughout

    FutureGrid will benefit current or future projects. We will share lessons learnt with our

    technical leads for specific asset types (noted as the Subject Matter Experts (SME)

    community) within NGGT. Our aim will be to disseminate learning throughout the business and

    to any external suppliers or stakeholders. Please refer to Section 5 – Dissemination for further

    detail on the sharing.

    2.3.4 Source of the hydrogen to be used in the trials

    The hydrogen supply to this facility will be via road tanker trailer through a flow/control

    system to the reservoir or straight to the pipeline facility. The industrial grade hydrogen

    supplied by typical industrial supply companies e.g. Air Products, Air Liquide and BOC is

    suitable for the hydrogen testing programme. At this moment in time, the hydrogen comes

    from several production methods, including from by product, steam methane reforming and

    8 Refer to section 6.4

  • 12

    electrolysis. Further investigation will be made on the opportunity for green hydrogen for the

    test programme, however at this stage there are limited organisations able to supply the large

    quantities of hydrogen. On site hydrogen production is currently not an option due to planning

    restriction and large investment, however this will be periodically reviewed.

    2.3. Changes since the Initial Screening Process (ISP)

    A summary of the headline changes is shown below

    Modification to ISP Plan Description

    Reduction in

    decommissioning costs

    The costs associated with sourcing and transporting the

    decommissioned assets to the DNV GL Spadeadam facility have

    been reduced.

    Reduced requirement for

    additional valve purchases

    The requirement to purchase additional valves for the test facility

    has been reduced, as these are now part of the decommissioning

    programme.

    Additional labour costAdditional labour cost to provide a greater range of technical

    expert input, delivery review and broader project management.

    Recompression and

    Aftercooling additional cost

    Additional funds to provide the recompression unit and required

    aftercooling equipment for the recompression of the gas.

    Northern Gas Networks

    (NGN)

    NGN have confirmed contribution of 2% (£204,821.88) funding

    towards the total cost of the FutureGrid project.

    Health & Safety Executive

    – Science Division (HSE-

    SD) Support

    Additional costs associated with the HSE-SD providing

    independent advice and assurance throughout the FutureGrid

    Phase 1 project.

    Fluxys Partnership

    Fluxys owns and operates the transmission network in Belgium.

    With a similar network composition, we have identified

    opportunities to collaborate and share applied research to improve

    efficiency and maximise the benefit of FutureGrid Phase 1.

    Academia

    Durham University and Edinburgh University have joined as

    academic partners. Both universities will be key stakeholders to

    the project, supporting the Phase 1 deliverables and identifying

    opportunities for further work.

    Table 1 - Modification to ISP Plan

  • 13

    3. Project business case

    Global interest in climate change and the drive to net zero emissions for Great Britain is seeing

    a surge in interest from both policy makers and the public. Our journey to net zero is one of

    the most important economic, technical and social challenges facing the country today and the

    use of hydrogen offers a significant step towards reaching this goal. The current NTS and GB

    GDNs have been operational for more than 30 years and in this time businesses and homes

    have relied on its supply of energy for cooking, heating and power. These gas networks are

    established, resilient and have been operated and maintained throughout, to ensure the

    demand in energy has been met. Hydrogen could play a key role in enabling the transition to

    net zero.

    The NTS is at a pivotal point. We need to address the challenges that have been raised and

    test whether the existing NTS can be repurposed to support a clean and affordable transition.

    Our FutureGrid proposal is uniquely placed to be at the forefront of hydrogen research and is a

    key enabler to accelerate the transition to hydrogen. The project business case can be

    summarised in the following:

    3.1 Collaborative Test Facility

    In some areas, the NTS has been operated for over 50 years and the majority for between 30

    and 40 years. This existing NTS is relied on by 80% of the UK’s 29 million homes and,

    additionally, many large industrial and commercial consumers, to deliver the energy they need

    daily. It is vitally important that this existing infrastructure is adapted and transitioned to help

    facilitate the net zero target and the reduction of greenhouse gas emissions. Without it, new

    pipeline corridors could be required to span the country to transport hydrogen from source to

    large urban and remote areas of Great Britain. It has been estimated that this could cost over

    £8bn9 and lead to significant disruption, cost and delay to any energy transition plans.

    Conversely if it can be proved that the existing NTS is capable of transporting a blend of

    hydrogen all the way up to 100% then the impact to consumers will be significantly reduced

    9 Energy Networks Association, Pathways to Net Zero: Hydrogen: Cost to customer, May 2020

    CollaborativeTest Facility

    A representativehydrogen

    transmission testfacility built fromdecommissioned

    assets toaccelerate ourmove to zero

    carbon

    Validation ofNational

    TransmissionSystem

    Readiness

    Demonstration &verification of theability to operate

    the NTS with up to100% hydrogen

    AcceleratingTechnology

    Development

    Improvedcollaboration

    across industriesinternationally and

    with otherindustries looking

    to decarbonise

    Skills andcompetenciesfor the future

    World-classtraining facility toprovide employeeswith the skills they

    need fortransmission

    assets in hydrogen

  • 14

    and costs saved. The FutureGrid proposal will lead the way for gas transmission in

    understanding this. It will aim to show that our existing assets can continue to provide the UK

    with the energy it needs as we transition to a low-carbon hydrogen future.

    The key to providing this proof and a large part of our NIC submission is that the FutureGrid

    test facility will be built using decommissioned assets from the NTS. This has a few important

    benefits. Firstly, by exposing existing NTS assets which have seen more than 30 years of

    active service to a hydrogen blend up to 100%, we can simulate how the large parts of the

    NTS will respond. To do this, we will ensure that where possible the assets will be of a

    representative type and grade of steel to the rest of our NTS. The result will be a small test

    facility but a significant development in our understanding of how the wider NTS will operate

    with hydrogen. Figure 3 illustrates the type and quantity of assets we can repurpose from

    various decommissioned sites across the NTS.

    Figure 3 - UK Assets

  • 15

    A working example of this is the ball valves that we will install on the test facility. Ball valves

    are installed throughout the NTS and carry out many significant roles including; enabling

    effective isolation for sections of the NTS, limiting gas losses in an emergency and managing

    flow direction. There are over 10,000 valves - with diameters ranging from 4" to 48” –

    installed on the NTS. The test facility will comprise of multiple 36” ball valves, and to ensure

    these are representative the most common types will be installed. When comparing the 36”

    ball valves, over 75% are either Cameron T31 or Cort CB-5 type and as such these will be

    installed at the facility following decommissioning.

    In the case of ball valves, there will be multiples of each type of valve, so comparisons across

    a fleet of them will be possible, to further strengthen the results of the master test plan.

    Similar scenarios can be seen for other asset types, such as meters. We will represent as

    many of the different types as we have on the NTS as possible, including ultrasonic, turbine

    and orifice plate. For filters we currently have assets from Swinney, Plenty and GD

    Engineering and we will bring these into the facility where possible. Additionally, we will cover

    the two major types of door enclosure on our pig traps (band lock and the older ring lock

    style). Finally, several pipe grades will be covered including the most prevalent steel grade on

    the NTS; X60. We will also include X80 which is on newer sections of the NTS. Historic data on

    the pipeline sections will be analysed before installation including any stress accumulation and

    dents / gouges, this will provide valuable understanding into how aged assets will interact with

    hydrogen.

    Our RIIO-2 decommissioning strategy has highlighted these assets as no longer required but,

    in most cases, they are fully operational. To ensure they are fully operational and to make

    sure they are of a representative type and age, we will carry out studies in situ before

    relocating the asset to the DNV GL Spadeadam test facility. Once confirmed and removed from

    the NTS we will clear and store them following existing NGGT procedures, ready for transport.

    If, during the early studies and investigations, the highlighted assets do not operate fully or do

    not represent the wider NTS then we will not use them, and we will find alternative assets. By

    re-using these parts, we have been able to reduce the overall cost of FutureGrid, compared to

    buying a similar new asset. By completing the test on existing assets, we can prove that the

    NTS can be used into the future and increase the return on investment for these assets.

    3.2 Validate NTS Readiness

    FutureGrid Phase 1 will allow NGGT to validate how a transmission network with 100%

    hydrogen could operate in the future. It will also provide the foundation for future NIA

    innovation projects and large-scale trials as part of the wider FutureGrid roadmap, focusing on

    compression, deblending and testing in-line inspection tools in collaboration with Original

    Equipment Manufacturers (OEM’s).

    One of the significant benefits surrounding our decision to build an offline test facility at the

    DNV GL Spadeadam site is that the H21 gas distribution array is also being built there in 2020

    – NGGT is a contributing partner to the project, supplying several lengths of 48” pipework to

  • 16

    act as a High-Pressure storage reservoir. Designing and building FutureGrid at the same site

    will allow the project to use this storage and connect to the gas distribution pipework, allowing

    pressure reduction equipment that we currently operate at our offtake sites to be tested.

    Further downstream at the same site is the HyStreet and H21 facility project, funded by H21

    Phase 1 which built several terrace houses with full hydrogen connectivity. This means that

    once FutureGrid Phase 1 is complete, there will be a complete gas network set up representing

    NTS pressures down to GDN’s and home appliances. FutureGrid Phase 1 is very much building

    the foundations for a much longer roadmap of projects for NGGT and hydrogen, under the

    HyNTS programme banner.

    Our HyNTS FutureGrid programme is looking to provide the required evidence and to do this,

    our proposed offline test facility will rapidly increase and validate this understanding.

    Previously completed innovation projects10 have started to develop a list of knowledge gaps

    and questions to be answered for NTS assets in hydrogen. Such topics will make up the

    master test plan and include:

    How could hydrogen permeation and embrittlement affect NTS pressure pipework?

    How could hazardous area distances change with hydrogen?

    Will our inspection and maintenance techniques need to be updated with a hydrogen

    blend in the pipework?

    How can an NTS hydrogen pipeline be safely vented and purged?

    How do failure modes for the pipework change with hydrogen?

    Will the soft seals on our valves be adversely affected by hydrogen?

    How will metering / gas quality sampling change with a blend of gas within the pipe?

    There are studies on the topics listed above which go some way to alleviate concerns.

    However, there is no way to be sure until a trial is completed using the unique setup of the

    NTS. FutureGrid Phase 1 and the follow-on phases that are proposed will go a long way to

    answer the concerns of the industry and show that there is another viable option before new

    pipelines are required for hydrogen transmission. We will develop the master test plan we

    have proposed for the project in close collaboration with Gas System Operation (who now sit

    under NGGT), as there are key questions that need to be answered regarding how a hydrogen

    NTS would be balanced, operated and, importantly, metered.

    3.3 Accelerating Technology Development

    Hydrogen research and understanding is gathering pace for the GB gas networks. However, to

    allow policy makers to decide on the future of heat in the country, they will need empirical

    data that shows the NTS can continue its role in providing energy to homes and businesses as

    it does today. Projects such as H21, H100 and HyNet run by Northern Gas Networks, SGN and

    Cadent respectively, alongside many others, are focusing on the challenges of hydrogen gas

    distribution. FutureGrid Phase 1 and the wider ongoing HyNTS FutureGrid programme will look

    to answer the key questions being asked of the NTS.

    10 NIA_NGGT0139 - Hydrogen in the NTS – foundation research and project roadmapNIA_NGGT0155: Hydrogen Injection into the NTS

  • 17

    Having the FutureGrid Test Facility operational and in place will mean that we can look to

    FutureGrid Phase 2 and the introduction of compressor units (also decommissioned from the

    NTS or supplied on trial from our suppliers). This will allow us to understand the impact on our

    rotating machinery fleet, both for compressing the hydrogen blends as a process gas and

    using hydrogen as a fuel gas. Phase 2 will also incorporate the latest thinking behind gas

    separation and ‘deblending’, offering the opportunity to pilot the technology on the Phase 1

    facility. A feasibility study led by NGGT has seen the concept of deblending researched further

    to establish if the pressure drop between transmission and distribution can be used to power

    the separation process. The findings were positive. We could deploy such technology across

    our NTS to allow certain areas to receive a blend of hydrogen, while still protecting those that

    are not ready to move from natural gas in the short term. Without the base foundation

    provided by Phase 1, neither trialling deblending technologies nor compression in hydrogen

    will be able to take place.

    During the project we are also using the innovation techniques and products developed during

    RIIO-1, such as the composite pipe supports on the build of the test facility. Additionally,

    some of the repair techniques, such as Valve Care Toolbox can be trialled in a hydrogen

    environment to assess if there are any impacts. We are also keen to use the Gas Robotic Agile

    Inspection Device (GRAID) test loop, which was built at the same Spadeadam site for the

    successful 2018 NIC project led by NGGT. Allowing access to part of the test facility for the

    GRAID robot will allow the team to confirm its operation in a hydrogen blend. The team will be

    able to show that the tool can still operate and provide integrity information on our above

    ground installations during and following the transition to hydrogen.

    We will carry out FutureGrid Phase 1 and potential future additions to the test facility in co-

    operation with the suppliers themselves, so we can collaborate and innovate together. An

    example of this will be to increase the overall length of the pipework and allow in-line

    inspection companies to test their tools in a transmission-scale hydrogen environment.

    Building this themselves would be cost prohibitive, so by working together we can accelerate

    innovation for the whole industry, a key requirement for Ofgem funding. We will develop and

    discuss this model initially in Phase 1, putting in place the framework for later phases and

    opening the test facility to many smaller suppliers and third parties to use. The FutureGrid test

    facility will also be the foundation for many other HyNTS programme hydrogen related

    projects of the future, providing a base to innovate from. These projects will be driven from

    the HPDG and help to answer the key questions raised from that forum.

    Additionally, we can facilitate other GDN-led projects on the test site, such as the Local

    Transmission System (LTS) Futures work, which is also a part of the HPDG delivery plan. LTS

    pipework is similar to NTS pipework and in some cases is operated at NTS pressures of greater

    than 50 bar(g), so studies on the LTS pipework can be carried out on the FutureGrid site.

  • 18

    3.4 Skills and competencies for the future

    Once built, FutureGrid linked to H21 will become a unique training facility to upskill the gas

    transmission and distribution workforce across the industry in the new ways of thinking and

    working with hydrogen. The ambition will be for a Gas Goes Green (GGG) branded office on

    site, which will house the telemetry and controls for the facility. This could be extended in

    collaboration with the H21 team to provide training and learning facilities. Gas Goes Green

    (GGG) is an Energy Networks Association (ENA) led programme. It brings together the

    engineering expertise from GB’s five gas network operators, building on the foundations of our

    existing grid infrastructure, innovation projects and the wider scientific community. This will

    allow joint dissemination events, meetings and desktop training to take place close to both

    facilities. It will bring the technology to life and allow physical demonstrations or on the job

    training to also take place. We will encourage teams from across our Gas Transmission

    business to be a part of the project, from Capital Delivery at the start with construction and

    commissioning, through to Plant Operations and Pipelines Maintenance Centre (PMC),

    understanding how to operate, maintain and repair assets with hydrogen in the NTS. This

    facility will be made available to the wider gas industry to facilitate and accelerate

    technological development and skills in order to drive the transition to a low carbon future for

    the UK.

    Converting the existing NTS to a hydrogen NTS will generate new opportunities for the

    country, with the hydrogen for transport sector rapidly growing. As the technology improves,

    vehicles, heavy haulage, trains and large vessels could all see a move towards hydrogen. A

    hydrogen NTS will also accelerate and enable industries that could supply the nation’s

    requirements for hydrogen including innovation to produce ‘green’ hydrogen from our wind

    and solar sources around the country. The introduction of hydrogen will also see a closer

    connection between gas and electricity. A ‘whole energy system’ as ‘green’ electricity can be

    produced on or offshore and converted to hydrogen for storage, or for transporting across the

    country. This would drive an increase in capacity for more renewable technology and

    importantly, greater network resilience and flexibility.

    The requirement, not just to understand the physical impacts of hydrogen, but also the

    workforce impact, has been a challenge raised by many in the industry. FutureGrid will provide

    this platform and help to lead the way in this area. It has recently been suggested to

    Government that a hydrogen network could help stimulate the economy and lead to the

    creation of more than 200,000 new jobs 11in the wider gas industry by 2050. This facility could

    help start to shape what these roles could entail.

    11 As described in the letter to the chancellor from the collective gas networks

  • 19

    4. Benefits, timelines, and partner

    4.1 Accelerates the development of a low carbon energy sector and/or delivers

    environmental benefits whilst having the potential to deliver net financial benefits to

    future and/or existing Customers

    FutureGrid will build on the learning from several desktop-based studies. It will provide a

    comprehensive off-line test facility to generate the critical evidence we need to operate the

    NTS with hydrogen. We will define the evidence we need to gather in the master test plan.

    This sets out the steps required to prove that the NTS and its assets can operate safely and

    efficiently with hydrogen.

    It is widely reported that the most feasible way the UK can meet its Net Zero 2050 target is

    through a balanced energy mix, where one energy form e.g. electricity is not the answer. The

    ENA’s ‘Pathways to Net Zero’ report12 found that that the balanced scenario, using

    decarbonised gas, is lower in cost than the electrified scenario by £13bn/yr, equivalent to 12%

    of total energy system cost in 2050. This creates a huge cost saving for end consumers in the

    run up to 2050 and avoids costly capital investment in a new NTS, which would ultimately be

    funded through consumer bills. Furthermore, Element Energy’s ‘Hy-Impact’ report13 states

    that decarbonising the UK economy is expected to lead to a four-fold increase in UK Gross

    Value Added (GVA), which would benefit customers and consumers; this decarbonised

    economy involves ‘large scale hydrogen usage’ and a hydrogen-carrying NTS would enable

    this. This view is echoed in the ‘Energy Innovation Needs Assessment’14 by BEIS, which

    identifies ‘low cost hydrogen delivery infrastructure’ as a key investment area to meet

    decarbonisation targets.

    Referring to the desire for a balanced energy mix, the National Infrastructure Commission’s

    Net Zero report15 states that hydrogen supports the development of a highly renewable

    electricity supply and is therefore beneficial to decarbonising beyond the gas component of the

    energy mix. It was also found that using hydrogen in hydrogen-powered turbines could reduce

    renewable electricity costs by up to 30% by 2050. 16 will enable the NTS to supply power

    stations with hydrogen, therefore enabling this cost reduction. Hydrogen also compliments the

    electricity system through the potential to convert excess renewable electricity to hydrogen

    via electrolysis. This hydrogen can be used for transport, for example. It is also reported to be

    at least a tenth the cost to store than battery technology17 with this margin being improved if

    12 Energy Networks Association, Pathways to Net Zero: Decarbonising the Gas Networks in

    Great Britain, 201913 Element Energy, Hy-Impact Series Study 1: Hydrogen for economic growth, 201914 BEIS, Energy Innovation Needs Assessment, 201915 National Infrastructure Commission, Net Zero – Opportunities for the power sector, 202016 Sustainable Gas Institute, The flexibility of gas: what is it worth? 202017 Linepack is the gas stored within the pipelines of the NTS

  • 20

    the NTS could be used as a storage mechanism (line pack). Hydrogen is beneficial to a

    whole energy system transformation, and FutureGrid is a key enabler for this transformation.

    In the RIIO-1 period, NGGT gas turbines used methane, taken from the NTS, and produced a

    total of CO218 CO2 was also vented19. Transporting 100%

    hydrogen through the NTS could have avoided over CO2 during the RIIO-1 period.

    The NTS delivers nearly 900 TWh of energy to Great Britain (including GDNs, industry, power

    generation and exports) each year, which equates to tonnes of carbon dioxide. If

    this natural gas were replaced with green hydrogen, generated from renewable energy, all

    carbon dioxide emissions would be avoided. Similarly, if the natural gas were replaced with

    blue hydrogen (produced via steam reforming) tonnes of carbon dioxide

    emissions would be avoided. This assumes a current 92.5% capture, although plants such as

    Cadent’s Low Carbon Hydrogen (LCH) plant are expecting capture rates of 97%20, which would

    improve carbon savings further. Even as the earlier-referenced ENA’s ‘Pathways to Net Zero’

    report1 predicts 2050 gas demand to drop to 440 TWh, this still equates to tonnes

    carbon dioxide for 2050. The earlier we can replace natural gas in the NTS with hydrogen, the

    earlier we can start to make carbon savings; therefore, it is imperative that FutureGrid is not

    delayed. There are further details about potential carbon savings in Appendix A.

    Currently, some of the biggest questions to answer in building a hydrogen economy are

    regarding blue and green hydrogen; where should each technology be implemented, and in

    what timescale? Blue hydrogen could likely be the pathway to green hydrogen, since blue

    offers the more scalable and cheaper option in the near future, while green hydrogen

    technology is expected to mature and drop in cost in the mid-to-long term. The NTS can

    facilitate this transition from blue to green.

    Repurposing the NTS for hydrogen reduces the need for in-land steam methane reformers21 to

    produce hydrogen around GB and the associated pipelines to remove carbon dioxide. The

    installation of methane reformers at coastal locations such as St Fergus and Grain LNG

    terminals is more likely to be achieved under planning regulations. This is due to the existing

    land use, proximity to Carbon Capture Utilisation & Storage (CCUS) and a local skilled

    workforce. Conversely, more populated areas of GB will not be able to have such hydrogen

    production facilities nearby, so transportation of hydrogen in the NTS to the GDNs will be vital.

    Transitioning to green hydrogen at these terminal locations can also be an ideal solution due

    to similar reasons, as well as the proximity to renewable offshore wind energy. However, in

    addition to this coastal green hydrogen, smaller scale electrolysers could possibly connect to

    the NTS further in-land because CCUS infrastructure is not needed.

    19 Internal NG data via the Safety, Health & Sustainability Team20 BEIS Low Carbon Hydrogen Supply Programme, HyNet Low Carbon Hydrogen Plant21 A process that converts methane into hydrogen, also producing CO2

  • 21

    Decarbonising the gas in the NTS can help to tackle the harder-to-reach sectors such as heat

    (domestic, commercial and industrial), which contributes to a third of the UK’s current carbon

    emissions. While this is true, the UK government has prioritised decarbonising industry and

    transport before heat (as heat is more difficult). However, as stated in the BEIS ‘Innovation

    Needs Assessment’3 report:” proving the ability of the existing NTS to be repurposed to

    hydrogen is essential to enabling widespread hydrogen to use in heat and could also reduce

    deployment barriers to use in industry and transport”. The FutureGrid project achieves exactly

    that; it assesses the ability to repurpose the existing NTS and therefore aligns with the views

    of BEIS. Since the NTS supplies industry and power, the ability to deliver hydrogen will

    encourage fuel switching, accelerating the decarbonisation of industry and power. The NTS,

    with its nationwide coverage, could also supply large amounts of hydrogen to enable large-

    scale hydrogen transport, such as hydrogen bus depots, train depots, shipping depots and

    HGV refuelling.

    The HPDG, chaired by BEIS, aims to build an evidence base to inform heat policy. The HPDG

    want evidence that hydrogen is technically and economically feasible, whilst maintaining

    safety with minimal disruption to customers. FutureGrid directly aligns with the needs of the

    HPDG, as the project will build an evidence base on the capabilities of the NTS to transport

    hydrogen safely, with no direct disruption to customers since the FutureGrid Test Facility is

    offline. Therefore, the outcomes of the FutureGrid project will inform heat policy that is

    essential to the transformation of the energy sector. Moreover, the three workstreams run by

    GB gas networks in the HPDG are Network safety and operational impacts, Integrated trials

    and System transformation. The FutureGrid project satisfies all three of these workstreams.

    Without FutureGrid, the learning and decarbonisation achievable from a UK wide approach to

    hydrogen will be curtailed. The NTS is uniquely placed to roll out hydrogen delivery and

    decarbonisation at scale across Great Britain.

    4.2 Provides value for money to gas network customers

    There are over 280,000 km of transmission and distribution pipelines delivering gas to over 20

    million customers (domestic and non-domestic) in GB. This includes heating 80% of homes,

    meeting over 40% of the UK’s industrial energy demand and providing around 40% of the

    UK’s electricity generation. Although the electricity network supplies a steady load of power, it

    cannot meet the seasonal or intraday demand for heat. Therefore, significant additional

    infrastructure would be required to replace the NTS, which already provides this resilience.

    The additional infrastructure would come at a financial cost to consumers and cause

    considerable disruption, this is expanded on further, below.

    A social carbon price can be applied to CO2 emissions, which relates to society ultimately

    paying for emissions that cause climate change; NGGT currently sets this price at £ per

    tonne CO2 equivalent. As stated earlier, the NTS emitted a total of over CO2 in RIIO-1

    via its compressors and venting, equating to a social carbon price of over 22. Enabling

    the NTS to transport up to 100% hydrogen could remove up to 100% of the social carbon

    22 This figure is an underestimate, as the social carbon price is expected to rise in the future

  • 22

    price from this source. Acting now to introduce hydrogen into the NTS will minimise the social

    carbon cost from transporting gas through the NTS.

    As mentioned previously, the National Infrastructure Commission's report finds that using

    hydrogen in hydrogen turbines can lower the cost of the electricity system by up to 30%.

    Since the NTS delivers gas to many power turbines, enabling hydrogen transmission can lower

    the cost of electricity for consumers in the future.

    Repurposing the NTS will minimise disruption to customers in the road to net zero. This is

    reflected in the Future Energy Scenarios (FES) 202023 report produced by National Grid ESO.

    The report shows that a large-scale adoption of hydrogen allows the UK to meet net zero by

    2050 with the least disruption to consumer behaviour. Following the conversion of home

    boilers to hydrogen, consumers could continue to use gas in a very similar way to how they do

    now. This would remove the need to switch over to heat pumps, which have high upfront costs

    and would cause a lot of disruption in the process of installation. This also avoids creating a

    fuel poverty issue, where vulnerable customers could be left behind because they cannot

    afford to buy expensive heat pump technology. FutureGrid could also enable a future where

    consumers could have a choice of energy (gas or electricity), as customers do today. Re-

    purposing the NTS also ensures that the existing infrastructure that UK consumers have

    already paid for continues to be utilised and avoids significant costs from decommissioning the

    current NTS.

    We will construct the proposed FutureGrid test facility from redundant assets. These are

    planned to be decommissioned from the NTS during RIIO-2, providing a cost saving compared

    to procuring new assets. It will also benefit the industry more widely, as learning could be

    applied to the LTS operated by the GDNs, and to some directly connected transmission

    customers, due to similar construction materials and processes. In addition, this facility can

    support the testing needs of LTS based projects, such as the LTS Futures project currently

    under development by SGN and the other GDNs. Their plans require offline testing and are

    now planning on using this FutureGrid facility to deliver this work. Furthermore, transporting

    hydrogen through the NTS will have benefits to transmission customers across the UK, by

    allowing large industrial users and power stations to more easily fuel switch.

    Creating a single test facility using as many NTS assets as possible, removes the need for

    separate test projects to address each individual asset in isolation; this increases value for

    money as all the learning can be attained from a single test facility, which will require less

    land than several facilities and is more cost efficient. Also, several lengths of 48” NTS pipeline,

    which are being used on the collaborative H21 NIC project for hydrogen storage will be further

    used for FutureGrid, again reducing costs overall. Furthermore, FutureGrid will come in at just

    over £10m in cost, whereas, as detailed in section 4.6, direct financial benefits from

    FutureGrid are over £70m. These savings will trickle down to consumers bills, making the

    scale of the project justifiable and beneficial to consumers.

    23 National Grid ESO – Future Energy Scenarios, 2020

  • 23

    Our RIIO-1 Innovation portfolio has delivered a wide range of innovation projects, many of

    which have a direct impact on developing, building and maintaining our NTS. Wherever

    possible, these projects will support the development, building and testing of the FutureGrid

    facility. For example, the Composite Pipe Supports NIA project will replace traditional concrete

    pipe supports. The tools and techniques developed under the Valve Care Toolbox NIA project

    can be utilised to inspect the valves used as part of the test facility, to identify the impact of

    hydrogen. This approach will make sure the FutureGrid project is delivered in the most

    innovative and efficient way. It will also allow us to validate tools and techniques designed for

    natural gas in a hydrogen environment.

    Phase 1a Phase 1b Phase 1c

    9 months 9 months 6 months

    Total costs for each stage

    Labour NGGT

    number of people - average

    number of days

    average cost per day

    Total - from actual resourceprofile

    Labour DNVGL

    number of people - average

    number of days

    average cost per day

    Total - from actual resourceprofile

    Equipment Total

    Travel

    IT

    Communications

    Contractors HSE

    Contingency

    Table 2 - Cost per Phases (Please note averages have been used, for full details please see

    Appendix G)

    The base cost assumptions can be found in Appendix G and are based on the costs seen in

    H21 and other large testing programmes undertaken by both NGGT and DNV GL. Further to

    this, the project costs have been developed using base cost data from ongoing work at DNV

    GL Spadeadam and a breakdown of the costs can be seen in table 2. For further detail on the

    base cost assumptions and for more detailed resource profiles, please refer to Appendix G.

  • 24

    4.3 Is innovative (i.e. not business as usual) and has an unproven business case where the

    innovation risk warrants a limited Development or Demonstration Project to demonstrate its

    effectiveness

    We have carried out extensive work into the early stage research and development of

    hydrogen impacts on the UK gas networks, indicating a pathway for both NTS and GDNs.

    While there are synergies, there are also significant challenges exclusive to transmission or

    distribution. Progress through projects such as the H21, HyDeploy and HyNet have advanced

    knowledge and understanding of hydrogen impacts. They tackle several important challenges

    facing GDNs. However, a key challenge that remains for the NTS is to demonstrate that

    transporting hydrogen will not affect its safe operation.

    This requirement is set out in the HPDG transformation plan, which highlights the importance

    of testing and trialling hydrogen within the NTS, as an enabler to transforming the UK gas

    networks. There is currently no precedent for converting a gas transmission system to

    hydrogen. This can only be achieved with comprehensive testing and trialling of the impacts

    that hydrogen has on the NTS.

    There is a clear and compelling need for an offline transmission test facility that provides this

    capability and helps quicken the deployment of online trials of hydrogen injection on the NTS.

    The transmission test facility must be able to replicate a range of conditions and be fully

    representative of existing assets to provide compelling results. The test conditions must also

    allow us to extrapolate data over a longer time period, so we can fully assess the longer-term

    impacts of transitioning the NTS to hydrogen. Achieving this will allow for the next stage of the

    transition to begin. It will allow us to identify opportunities for online test and trial facilities,

    while providing a platform to develop larger-scale hydrogen transformation plans for the NTS.

    This meets the needs of our customers who also have ambitious plans to transition their

    operations to low-carbon gas alternatives, with hydrogen being a significant option.

    Creating this high-pressure transmission test facility is the foundation of an ambitious

    programme of work. We are looking to provide a platform for the UK gas industry to

    accelerate innovation and develop expertise in hydrogen, test and trial solutions, and facilitate

    a full transition of the NTS to hydrogen. All this will help achieve the UK’s Net Zero 2050

    targets.

    To date, no such facility exists within the UK, due to barriers such as technical complexities,

    scale and cost involved in creating such a facility, and coordinating an industry-wide approach

    to generating and disseminating the associated knowledge. There are complimentary regional

    schemes that seek to develop solutions for the transition to low carbon alternatives. However,

    none of these are focused on creating large-scale, high-pressure test facilities or focus on the

    direct impact on the NTS. Instead, they are focusing on end consumers, industry and early

    stage research and development into low carbon technologies.

  • 25

    Without NIC funding, achieving this significant milestone to provide a transmission test facility

    for the UK gas industry will not be possible. This is due to the high risk, high cost and high

    levels of uncertainty associated with a development of this kind, which would carry significant

    commercial risk beyond acceptable parameters. If we do not provide a comprehensive testing

    and trialling facility, the pathway to transitioning the NTS to hydrogen will not be achievable

    against the ambitious plan currently set out by the HPDG and GGG programme.

    4.4 Involvement of other partners and external funding

    The FutureGrid project on conception concluded that the optimum facility location would be at

    Spadeadam, alongside the H21 facility and therefore linking a transmission and distribution

    demonstration system. As Northern Gas Network (NGN) and DNV GL already partners on H21

    delivering the distribution facility, they became natural partners to enable the FutureGrid

    project to maximise learning and utilise the capability already on site. Recognising the

    strategic importance and opportunity of future testing and training with the GGG facility (joint

    transmission and distribution facility). NGN have committed to 2% of the total project cost on

    top of shared costs for facilities on the Spadeadam site; this will be a basis for our future

    collaborative technology development and therefore driving down our total costs between H21

    and FutureGrid. DNV GL a key partner to both projects, are ensuring the avoidance of

    duplication and maximising efficiencies in the build and testing across the projects, this is

    supplemented by their own in-kind contributions made to support the development and use of

    the facility.

    The GDNs have all provided letters of support and will be a key part of future work using the

    facility to ensure that hydrogen development is not done in silo activities. The HSE are

    contracted into the project to ensure that our build and testing is representative of the NTS

    and give us assurance that the data produced can be extrapolated to allow our future online

    activities. IGEM whom we and the GDNs are running collaborative projects with, are reviewing

    the standards associated with hydrogen implementation will ensure that we do not cover

    activities already resolved in other projects.

    Internationally, transmission system operators (TSO) are also progressing hydrogen

    technologies, with some more advanced than the UK. Therefore, key to the project was

    securing an international collaborator that could accelerate our initial studies and provide a

    partnership to further advance future research. Fluxys the Belgium TSO has committed to

    providing in kind data and resource to the project. Fluxys have taken an academic route to

    hydrogen development which marries well to the FutureGrid application-based approach.

    GasUnie and SNAM, other TSOs, have also supported the project, however these discussions

    are at an earlier stage and will be developed through the project period for future phases of

    FutureGrid. Our engagement plan scope includes international communication to improve

    collaborations into the future.

    Although the facility is application focused and allows for testing of our assets, it is key that

    we have academic partners that can provide technical insights and maximise the value of the

    platform through research and teaching our future workforce. Durham and Edinburgh

  • 26

    universities are geographically well placed to make the most out of the facility and are

    partners in the project; with an aim to develop NIAs and future phases of the project, aligned

    to gaps and technologies required for online facilitation. Further information on the project

    partners can be found in Appendix F.

    4.5 Relevance and timing

    There are challenges to overcome in implementing hydrogen to help meet the UK’s Net Zero

    targets. The HPDG is set up to inform heat policy, which is required for widespread use of

    hydrogen. To inform heat policy, the HPDG needs to build an evidence base that shows

    hydrogen is safe, technically feasible and economically viable. The FutureGrid project satisfies

    the needs of the HPDG by building an evidence base for these criteria. This helps inform heat

    policy and is therefore entirely relevant.

    In the earlier mentioned ‘Energy Innovation Needs Assessment’ published by BEIS, it is stated

    that action is needed now if the UK is to be competitive in a hydrogen economy. Therefore, it

    is imperative that the FutureGrid project, which assesses the UK’s ability to transmit hydrogen

    on a national level, is completed now and is not delayed. BEIS will also be starting to make big

    decisions on the future of hydrogen, around 2023. The current FutureGrid timeline will enable

    NGGT to have built an evidence base and to start informing those BEIS decisions.

    The Gas Goes Green (GGG) initiative, which was run by the ENA and UK gas network

    operators, outlines a timeline24 of what action is required for the UK to reach net zero by 2050

    by decarbonising gas. In this timeline, 2020-2025 is the ‘preparing for transition’ stage that

    aims to test technology. This aligns with the FutureGrid project timeline. This stage also

    involves developing the skills and labour capacity required for a hydrogen economy. The

    FutureGrid project holds the potential to start up a training facility in Spadeadam, which will

    help develop a skilled workforce for the future. Also, in the GGG timeline, 2025-2030 is the

    period of ‘expanding supply’ – completing the FutureGrid project in the proposed timeline will

    prepare the UK to expand hydrogen supply on a national level, aligning with the GGG timeline.

    Table 3 shows the cumulative spend and benefits, to demonstrate the break-even point for the

    project based on 2020/2021 figures and using the RRP benefits as described below. We

    predict that the breakeven point will be in 2023. Please see Appendix A for more details about

    the methods and assumptions. The base cost presented is the cheapest option available as the

    site is already in construction phases for H21 and the resources and capabilities are already on

    site.

    24 Energy Networks Association – Gas Goes Green (GGG), Delivering the pathway to net zero

  • 27

    (m) Cost 2021 2022 2023 2024 2025 2026 2027 2028 2029

    Phase 1a -£6.9 -£6.9

    Phase 1b -£2.3 -£2.3

    Phase 1c -£1.1 -£1.1

    Method 1 £4.0 £4.0 £8.2 £4.2

    Method 2 £7.8 £7.8 £7.8 £7.8 £7.8 £7.8

    -£2.9 -£2.3 £5.9 £17.9 £25.7 £33.5 £41.3 £49.1 £56.9

    Table 3- Break Even Point

    4.6 Financial Benefits

    Although hydrogen has not been fully proven in this country, the alternatives for supplying

    energy in the future are of a higher cost in comparison. The ENA’s ‘Pathways to Net Zero’

    report found that the balanced scenario, using decarbonised gas, is lower in cost than the

    electrified scenario by £13bn/year, equivalent to 12% of total energy system cost in 2050.

    As we described in Section 4, we have shown the wider benefits of proving the existing NTS

    has a role to play in the energy system of the future. The NTS has been relied upon by 80 per

    cent of the UK’s 29 million homes and, additionally, many large industrial and commercial

    consumers to deliver the energy they need every day. With the right evidence, the NTS can

    continue to serve the country. Studies have concluded that if a new NTS was required to be

    built for hydrogen, it could cost over £8bn25. This would be alongside the route corridor

    challenges currently faced by many utility projects. Benefits of using the existing NTS include:

    An existing, flexible network transporting energy around Great Britain from source on

    the coast to every part of the country,

    The NTS connects all major industrial clusters, so they can be decarbonised and

    transitioned to hydrogen together,

    Our gas terminals receive natural gas from around the world that is used by the NTS or

    traded with the rest of Europe via our interconnectors. Using the existing NTS, would

    mean Great Britain could continue to trade supplies of hydrogen from exporting

    countries with the rest of Europe.

    Unlocking green hydrogen produced from offshore wind farms will be accelerated with

    the existing NTS as the network can be used to transport the produced hydrogen from

    coastal regions, to areas of high demand around the country.

    The financial benefits of using the existing NTS are far reaching and would save many billions

    of pounds. However, our FutureGrid Phase 1 submission could not directly unlock these

    savings on its own. It can only do so as part of a larger roadmap of projects from all the gas

    networks. Therefore, for the purpose of this submission, we have set out two methods that

    produce direct savings following the completion of the FutureGrid Phase 1 project.

    Method 1 – In order to gather the required understanding and knowledge of how a hydrogen

    NTS would operate in this country, all the different types of assets and tests we would need to

    25 Energy Networks Association, Pathways to Net Zero: Hydrogen: Cost to customer, May 2020

  • 28

    carry out could either be completed separately (base case cost) or combined on a single test

    facility (method cost).

    Method 2 – Currently the most likely scenario for hydrogen transition and adoption will be at

    industrial clusters. The NTS will be used to join several clusters together by 2040. To facilitate

    this, safety critical assets such as valves would all need to be replaced for hydrogen operation

    (base case cost). Conversely, if the existing assets are proven to operate safely in hydrogen

    blends up to 100%, then a proportion of these valves will not need replacing (method cost).

    Gas NIC – financial benefits: Cumulative Financial Benefits (NPV terms; £m)

    Method Base Cost Method Cost 2030 2040 2050

    1 31.75 9.074 20.499 N/A N/A

    2 55.672 0 46.548 N/A N/A

    Table 4 - Benefits Table (See appendix A for detailed calculations)

    Table 4 shows an overview of the financial benefits. As described above method 2 is an

    example of one assets savings when looking to convert a connection between two clusters to

    hydrogen. It is likely that as we prove assets capability with hydrogen, we will be able to

    identify further savings by eliminating the need to replace assets in our NTS. Although this is

    not in any current business plans it is assumed that this will occur in the period post RIIO-2

    and is in consideration as part of our future planning. These savings will directly benefit

    consumers in reducing the costs of transition to Hydrogen but can only be achieved through

    validation of the assets.

    4.7 Carbon/Environmental Benefits

    We have split carbon benefits into two separate methods for the purpose of this submission:

    one to cover the wider NTS impact of converting to 100% hydrogen by 2050; and the other

    focusing on the specific valve replacement scenario. For the first scenario, we have assumed a

    linear reduction in demand towards 2050 as previously quoted in the ENA Pathways Report

    reducing from 880 TWh in 2020 to 440 TWh in 2050. Assuming 440 TWh and a CO2 emissions

    per energy demand of 0.0549 kg/ft3 26 by converting the NTS to 100% hydrogen by 2050 we

    will reduce carbon emissions by 81 million tonnes CO2 e. We expect the valve replacement

    scenario to provide savings of over 100,000 tonnes of CO2 e. This is due to not requiring valve

    replacement, as they will have been proven to work in a hydrogen environment. Table 5

    shows an overview of the carbon benefits.

    Gas NIC – carbon and/or environmental benefits: Cumulative Carbon Benefits

    (million tonnes CO2e)

    Method Base Cost Method Cost 2030 2040 2050

    1 81 0 81 N/A N/A

    2 0.1 0 0.1 N/A N/A

    Table 5 - Benefits Table (See Appendix A for detailed calculations)

    26 EPA – Greenhouse gases equivalences calculator

  • 29

    5. Knowledge dissemination

    5.1. Learning generated

    Evidence for the conversion of the NTS to hydrogen is on the critical path for UK Government

    policy decisions on the future of the gas industry. Although laboratory-scale testing capability

    for hydrogen-materials interaction is being developed by several commercial and academic

    entities in the UK, the FutureGrid test facility is the only advanced full-scale offline test facility

    planned. The FutureGrid project provides a unique opportunity to accelerate knowledge on

    capabilities of the NTS and will:

    Provide certainty on the feasibility of repurposing the NTS to transport hydrogen

    Confirm that NTS operations can be undertaken safely with hydrogen

    Confirm that the societal and individual risks are comparable to those of natural gas by

    supplying new data for quantitative risk assessment (QRA)

    Provide a platform to engage with stakeholders, users and customers about the

    transition to hydrogen

    Evaluate and validate results to enable progression to FutureGrid Phase 2.

    Contribute to the development of technologies that help the UK meet Net Zero 2050

    5.1.1 Optimisation of knowledge by using the Roadmap to FutureGrid NIA project

    The Roadmap to FutureGrid NIA project is developing the detailed design of the test facility

    and the master testing plan to ensure that, the learning generated from FutureGrid Phase 1 is

    optimised. Connections will be included for testing of safety critical pipeline equipment such

    as valves, pressure safety and pressure regulation devices. Many components also contain

    sub-components exposed to hydrogen; for example, elastomeric seals, susceptible high-

    strength steel springs for valves operation and valve seat/stems. The modular design and the

    space around the test facility will allow a range of equipment and alternative materials to be

    tested. As hydrogen-ready equipment is developed by suppliers it can be qualified in the

    FutureGrid test facility for use across the gas industry and other hydrogen users (e.g. power

    generation and process industries).

    5.1.2 Operations and procedures

    The new evidence from the master testing plan would provide information on the technical

    feasibility for operating the NTS based on the blends up to 100% hydrogen that were trialled

    throughout the test plan. NGGT currently uses a library of operational and technical

    procedures designed for natural gas operation. The output/data from FutureGrid Phase 1 will

    provide information about which parts of these documents we may need to review and update

    for hydrogen or hydrogen blends. It will also provide data on any additional measures and

    mitigations that may be necessary for future operation with hydrogen. We will use some of the

    information to inform and update the QRA for the NTS.

  • 30

    5.1.3 Selection of NTS assets

    We will test a representative selection of NTS assets as part of the master testing plan which

    will consider the availability of decommissioned and operational equipment. We will identify a

    cross section of NTS assets with a range of pipeline diameters and grades of steel. The tests

    generated as part of the Roadmap to FutureGrid project will cover a range of parameters to

    verify safety, pressures, velocities, temperature, measurement and operational processes.

    Extensive knowledge will be generated to support the wider assessment of the conversion of

    the NTS for operation with hydrogen and hydrogen blends. Some of the new evidence may

    also be applied to the Local Transmission Systems operated by the GDNs.

    5.1.4 Input to the Quantitative Risk Assessment (QRA)

    NTS pipelines are defined as Major Accident Hazard Pipelines (MAHP)s under the Pipeline

    Safety Regulations (PSR). This means NGGT is required to develop and maintain a Major

    Accident Prevention Document (MAPD) to demonstrate all hazards have been identified, risks

    have been evaluated and that an appropriate safety management system is place and kept

    under review. If results from FutureGrid indicate that failure frequencies of NTS components

    are different to those of natural gas, this new data will be used for the risk analysis.

    5.1.5 Gas Goes Green Training & Testing

    Through partnering with the H21 project, the test site facility would provide a complete beach

    to meter (end user) facility for the UK gas industry, including suppliers, to develop further

    knowledge and to train the next generation of gas industry engineers and scientists.

    The potential of the facility is significant for future learning, training and development of gas

    engineers, stakeholder organisations and other pipeline and asset organisations. Technical

    competence in the gas industry is very important, and this facility will provide real operational

    activities. If the hydrogen programme goes ahead, specific training will be required on areas

    of hydrogen and how these affect operational procedures.

    5.2. Learning dissemination

    FutureGrid is adopting a ‘digital first’ approach to engagement and dissemination, in order to

    be as open and inclusive as possible for stakeholders across the UK, and to open the

    collaborative opportunities internationally. In addition, given recent significant adaptations to

    ways of working due to Covid-19, a ‘digital first’ approach ensures a resilience to engagement,

    knowledge dissemination, and collaboration through virtual means rather than physically face-

    to-face. It does not remove the opportunity for face-to-face engagement, but it does mean

    that where physical events are planned, they will be supported digitally, such as with live

    stream technology, so stakeholders can participate and engage with us in ways that suit their

    personal circumstances through presentations, panel discussions and learning sessions.

    5.2.1 Engageme