1. Presentation and Discussion Relating to the Long-TermCommunity Trails Construction Project and the Proposed FY22Actions - Community Services
2. Presentation and Discussion Relating to the Formation andFunding of a Community Marketing Organization - Greater CasaGrande Chamber of Commerce
Posted on July 1, 2021 by 7:00 p.m. at the below locations: City Hall510 E. Florence Blvd.
Casa Grande, Arizona
Police Dispatch520 N. Marshall
Casa Grande, Arizona
City Websitewww.casagrandeaz.gov.
Gloria Leija, MMCCity ClerkDisabled individuals with special accessibility needs may contact ADA Coordinator for the City of Casa Grande at 520-421-8600 or TDD520-421-8623. If possible, such requests should be made 72 hours in advance.
City Council Study Session 1. Meeting Date: 07/06/2021
Recommended by: Karla Lange, Deputy City Clerk Prepared by: Karla Lange, Deputy City Clerk
Subject:Presentation and Discussion Relating to the Long-Term Community TrailsConstruction Project and the Proposed FY22 Actions - CommunityServices
AttachmentsPresentation
Strategic Plan
KEY FOCUS AREASThrough a process of discovery and collaboration, the City Council
identified these 5 Key Focus Areas for the new strategic plan.
Quality of Life
Marketing
Education
Fiscal Responsibility
Infrastructure
Increase trail system by 5% annually over 5 years
• Review and prioritize current trail master plan
• Establish current size of trail system and materials used
• Expand trail system outline in CIP
Regional Trail System Master Plan
• Presented May, 2008
• Imbedded into General Plan
• Defined potential trail options
• Provide locations of potential trails
• Provide locations of potential trailheads
• Provide cross-section of typical trail types
Timeline of the project
• CIP project approved in FY21
• RFP process begun in November 2020
• Okanogan Trail Construction selected in
a competitive process December 2020
• J2 selected as Engineering Firm to assist
with floodway permit December 2020
• Approval from Transwestern Pipeline
Company January
• Aerial survey February
• Floodway permit approved May
• Final price proposal June 2020
Similar Trails in Casa Grande
• 14-Foot Wide Walking Trail at Carr McNatt Park• Stabilized granite surface, bordered in concrete• 8-Foot Wide Walking Trail at Recreation Center• Stabilized granite surface, unbordered
Casa Grande Community Trail
• 8-foot Wide Multi-Use Trail• Stabilized granite surface, bordered in rock• Designed for walking, hiking, and biking• Equestrian use for future phases
Other details of the project
• Tree trimming and brush removal
• Soil export
• Gabion entryway, both ends
• Rip Rap shoulder
• Sign Package and wayfinding signage
• No electrical, lighting, irrigation,
landscaping or other amenities at this
time
Options For The Future
• Future Years 2022 and beyond
• Acquire easements, land
agreements, or development east of
Peart and west of Trekell
• Casa Grande Community Trail
construction when land & funding
become available
• Connect Dave White Park to Ed
Hooper Park
• Connect Recreation Center to
Community Trail