1-permit matrix for todd solar llc todd solar llc... · exhibit 1. permit matrix for todd solar llc...

75
4545874.1 48885/129410 12/15/2015 Exhibit 1. Permit Matrix for Todd Solar LLC Agency Permit / Approval 1 Regulation Required for Status Comments State of Maryland Public Service Commission (PSC) CPCN COMAR 20.79 Construction Application filed PJM Interconnection, LLC Interconnection Condition for Issuance of CPCN Operation Studies complete Facilities study completed August 2014 Maryland Department of the Environment (MDE) Permit for Impact to Intermittent Stream and Wetlands Buffer Not required NA Project avoids impacts to wetlands and buffers. US Army Corps of Engineers Permit for Impact to Intermittent Stream Section 404, Clean Water Act Not required NA Project avoids impacts to wetlands and buffers. Maryland Department of the Environment (MDE) NPDES General Permit for Construction Activity COMAR 26.08, Clean Water Act (CWA), Section 401, 40 CFR 122 Construction Later Dorchester County Forest Board 2 Forest Conservation Act (FCA) Natural Resources Article 5-1602(b)(5), 5-1603(f) Not required - exempt NA Does not apply provided CPCN incorporates Natural Resources Article 5-1603(f) and the cutting or clearing of the forest is conducted so as to minimize the loss of forest. Dorchester County Planning Commission Referral to BOA for Special Exception Review Dorchester County Zoning Code Construction Application in progress Application and conceptual plan to be filed in December 2015 Dorchester County Board of Appeals Special Exception Dorchester County Zoning Code, Table of Permitted Uses Construction Later Expected to be reviewed at BOA public meeting scheduled for January 2016. Dorchester County Planning Commission Site Plan Approval Dorchester County Zoning Code Construction Later Site Plan Permit will be applied for after BOA approval. Target submission date is 1 weeks after BOA decision. Anticipate 60-90 days for approval. Dorchester County Planning & Zoning Office Building Permit Dorchester County Zoning Code Construction Later Issued after approval of site plan and submittal of plans. To be requested by contractor Dorchester County Planning & Zoning Office Electrical Permit Dorchester County Zoning Code Construction Later Issued after approval of site plan and submittal of plans. To be requested by contractor Dorchester County Department of Public Works Grading Permit Dorchester County Zoning Code Construction Later Department of Public Works will determine if this permit is required. 1 Abbreviations: CPCN = Certificate of Public Convenience and Necessity; NPDES = National Pollution Discharge Elimination System; BOA = Board of Appeals 2 While the FCA is ordinarily implemented at the county level, the exemption for projects subject to a CPCN under Natural Resources Article 5-1602(b)(5) and 5-1603(f) supersedes county-level implementation with the Commission’s “due consideration [of] the need to minimize the loss of forest and the provisions of afforestation and reforestation set forth in [the FCA] together with all applicable electrical safety codes.” Md. Natural Resources Article 5-1603(f).

Upload: nguyenxuyen

Post on 01-Jul-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

4545874.1 48885/129410 12/15/2015

Exhibit 1. Permit Matrix for Todd Solar LLC

Agency Permit / Approval1 Regulation Required for Status Comments State of Maryland Public

Service Commission (PSC) CPCN COMAR 20.79 Construction Application filed

PJM Interconnection, LLC Interconnection Condition for Issuance of CPCN Operation Studies

complete Facilities study completed August 2014

Maryland Department of the Environment (MDE)

Permit for Impact to Intermittent Stream

and Wetlands Buffer Not required NA Project avoids impacts to wetlands and

buffers.

US Army Corps of Engineers

Permit for Impact to Intermittent Stream

Section 404, Clean Water Act Not required NA Project avoids impacts to wetlands and

buffers.

Maryland Department of the Environment (MDE)

NPDES General Permit for

Construction Activity

COMAR 26.08, Clean Water Act (CWA), Section

401, 40 CFR 122 Construction Later

Dorchester County Forest Board2

Forest Conservation Act (FCA)

Natural Resources Article 5-1602(b)(5), 5-1603(f)

Not required - exempt NA

Does not apply provided CPCN incorporates Natural Resources Article 5-1603(f) and the cutting or clearing of the forest is conducted so as to minimize the loss of forest.

Dorchester County Planning Commission

Referral to BOA for Special Exception

Review

Dorchester County Zoning Code Construction Application in

progress Application and conceptual plan to be filed in December 2015

Dorchester County Board of Appeals Special Exception

Dorchester County Zoning Code, Table of Permitted

Uses Construction Later Expected to be reviewed at BOA public

meeting scheduled for January 2016.

Dorchester County Planning Commission Site Plan Approval Dorchester County Zoning

Code Construction Later

Site Plan Permit will be applied for after BOA approval. Target submission date is 1 weeks after BOA decision. Anticipate 60-90 days for approval.

Dorchester County Planning & Zoning Office Building Permit

Dorchester County Zoning Code Construction Later

Issued after approval of site plan and submittal of plans. To be requested by contractor

Dorchester County Planning & Zoning Office Electrical Permit

Dorchester County Zoning Code Construction Later

Issued after approval of site plan and submittal of plans. To be requested by contractor

Dorchester County Department of Public Works Grading Permit Dorchester County Zoning

Code Construction Later Department of Public Works will determine if this permit is required.

1 Abbreviations: CPCN = Certificate of Public Convenience and Necessity; NPDES = National Pollution Discharge Elimination System; BOA = Board of Appeals 2 While the FCA is ordinarily implemented at the county level, the exemption for projects subject to a CPCN under Natural Resources Article 5-1602(b)(5) and 5-1603(f) supersedes county-level implementation with the Commission’s “due consideration [of] the need to minimize the loss of forest and the provisions of afforestation and reforestation set forth in [the FCA] together with all applicable electrical safety codes.” Md. Natural Resources Article 5-1603(f).

G

ener

atio

n In

terc

onne

ctio

n

Fea

sibili

ty S

tudy

Rep

ort

Que

ue P

ositi

on X

3-00

8 Th

e In

terc

onne

ctio

n C

usto

mer

(IC

) has

pro

pose

d a

20 M

WE

(7.6

MW

C; 2

0 M

W M

FO) s

olar

po

wer

ed g

ener

atin

g fa

cilit

y to

be

loca

ted

in D

orch

este

r Cou

nty,

Mar

ylan

d. P

JM st

udie

d X

3-00

8 as

a

20 M

W in

ject

ion

into

the

Del

mar

va P

ower

and

Lig

ht (D

PL) s

yste

m a

nd e

valu

ated

the

proj

ect f

or

com

plia

nce

with

relia

bilit

y cr

iteria

for s

umm

er p

eak

cond

ition

s in

201

5. T

he p

lann

ed in

-ser

vice

dat

e,

as st

ated

in th

e A

ttach

men

t N, i

s Jun

e 01

, 201

7.

Poin

t(s) o

f Int

erco

nnec

tion

Th

e In

terc

onne

ctio

n C

usto

mer

requ

este

d a

Prim

ary

and

Seco

ndar

y Po

int o

f Int

erco

nnec

tion

(PO

I) be

ev

alua

ted

for t

he X

3-00

8 pr

ojec

t. T

he P

rimar

y PO

I sel

ecte

d w

as a

25k

V d

istrib

utio

n le

vel

inte

rcon

nect

ion

at th

e To

dd 2

5kV

subs

tatio

n. T

he S

econ

dary

PO

I sel

ecte

d w

as a

69k

V tr

ansm

issio

n le

vel i

nter

conn

ectio

n al

so a

t the

Tod

d su

bsta

tion.

The

stud

y re

sults

are

pro

vide

d in

the

Tran

smis

sion

Net

wor

k Im

pact

s sec

tion

belo

w.

Pr

imar

y PO

I Opt

ion

X3-

008

will

inte

rcon

nect

with

the

Del

mar

va P

ower

and

Lig

ht s

yste

m a

t the

Tod

d 69

/25k

V su

bsta

tion

as fo

llow

s.

10

MW

s will

con

nect

to th

e ex

istin

g T1

tran

sfor

mer

; 10

MW

s will

con

nect

to th

e ex

istin

g T2

tra

nsfo

rmer

.

Dir

ect C

onne

ctio

n R

equi

rem

ents

Tra

nsm

issio

n O

wne

r Sc

ope

of W

ork

The

scop

e of

wor

k an

d es

timat

ed c

osts

for t

he d

irect

con

nect

ion

faci

litie

s is

as fo

llow

s:

1.

Es

tabl

ish

two

(2) n

ew 2

5 kV

feed

ers w

ith 9

54 a

lum

inum

con

duct

or fr

om th

e To

dd S

ubst

atio

n to

the

PV si

te –

app

roxi

mat

ely

1.5

mile

s eac

h.

2.

A u

tility

ope

rate

d re

clos

er w

ill b

e re

quire

d on

the

cust

omer

tap

that

will

hav

e pr

oper

rela

ying

an

d co

mm

unic

atio

n.

3.

Util

ity g

rade

prim

ary

met

erin

g w

ill b

e re

quire

d.

4.

Gen

erat

ion

tele

met

ry a

nd re

mot

e tri

p ca

pabi

litie

s w

ill b

e pr

ovid

ed to

the

cont

rol c

ente

r. 5.

Pe

rform

a d

etai

led

time

base

d st

udy.

6.

Pr

otec

tion,

Pla

nnin

g, a

nd o

ther

eng

inee

ring

depa

rtmen

ts w

ill p

erfo

rm st

udie

s, de

sign

wor

k,

and

prep

are

engi

neer

ing

estim

ates

. 7.

Tr

ansf

er tr

ip m

ay b

e re

quire

d.

Th

e es

timat

ed c

ost t

o pe

rform

this

wor

k is

as fo

llow

s:

2

$450

,000

954

AA

C E

xpre

ss F

eede

rM

iles

$600

,000

Fibe

r Ins

talla

tion

Mile

s$7

5,00

0$5

0,00

0$2

0,00

0$1

0,00

0$3

0,00

0$2

0,00

0$1

,255

,000

$1,4

80,9

00$1

,703

,035

Var

ious

Dep

artm

ents

Wor

kSu

btot

al C

ost

Subt

otal

Cos

t with

18%

Ove

rhea

dsA

ppro

xim

ate

Tota

l Cos

t with

15%

Con

tinge

ncy

Rec

lose

r w/ R

elay

ing

and

Com

mun

icat

ions

Util

ity G

rade

Met

erin

gSC

AD

A In

tegr

atio

n in

to E

MS

Det

aile

d Ti

me

Bas

ed S

tudy

Est

imat

ed C

osts

Tod

d Su

bsta

tion

T1

New

Fee

der T

erm

inal

, Bre

aker

, and

Upg

rade

s 1.5

$300

,000

954

AA

C E

xpre

ss F

eede

rM

iles

$600

,000

Fibe

r Ins

talla

tion

Mile

s$7

5,00

0$5

0,00

0$2

0,00

0$1

0,00

0$1

,055

,000

$1,2

44,9

00$1

,431

,635

SCA

DA

Inte

grat

ion

into

EM

SSu

btot

al C

ost

Subt

otal

Cos

t with

18%

Ove

rhea

dsA

ppro

xim

ate

Tota

l Cos

t with

15%

Con

tinge

ncy

Est

imat

ed C

osts

Tod

d Su

bsta

tion

T2

New

Fee

der T

erm

inal

, Bre

aker

, and

Upg

rade

s 1.5

Rec

lose

r w/ R

elay

ing

and

Com

mun

icat

ions

Util

ity G

rade

Met

erin

g

App

roxi

mat

e To

tal C

ost f

or T

wo

Feed

ers:

$3,

134,

670

The

estim

ated

tim

e to

com

plet

e th

is w

ork

is 12

- 18

mon

ths a

fter r

ecei

pt o

f a fu

lly e

xecu

ted

inte

rcon

nect

ion

agre

emen

t. N

ote:

the

abo

ve c

ost d

oes n

ot in

clud

e th

e C

ontri

butio

n in

Aid

of C

onst

ruct

ion

(CIA

C) t

ax.

Spec

ial O

pera

ting

Req

uire

men

ts

1.

PH

I will

requ

ire th

e ca

pabi

lity

to re

mot

ely

trip

the

gene

rato

r fro

m it

s Sys

tem

Ope

ratio

ns

faci

lity.

Suc

h tri

ppin

g m

ay b

e fa

cilit

ated

by

eith

er a

gen

erat

or b

reak

er, i

nver

ter (

if so

eq

uipp

ed),

or a

line

recl

oser

, dep

endi

ng u

pon

the

spec

ific

circ

umst

ance

s and

the

eval

uatio

n by

PH

I.

3

2.

It is

the

Inte

rcon

nect

ion

Cus

tom

er’s

resp

onsi

bilit

y to

send

the

data

that

PJM

and

the

Com

pany

re

quire

s dire

ctly

to P

JM.

The

Inte

rcon

nect

ion

Cus

tom

er w

ill g

rant

per

mis

sion

for P

JM to

se

nd th

e C

ompa

ny th

e fo

llow

ing

tele

met

ry th

at th

e In

terc

onne

ctio

n C

usto

mer

send

s to

PJM

: re

al ti

me

MW

, MV

AR

, vol

ts, a

mpe

res,

gene

rato

r/sta

tus,

and

inte

rval

MW

H a

nd M

VA

RH

.

3.

The

Inte

rcon

nect

ion

Cus

tom

er w

ill b

e re

quire

d to

mak

e pr

ovis

ions

for a

voi

ce q

ualit

y ph

one

line

with

in a

ppro

xim

atel

y 3

feet

of e

ach

Com

pany

met

erin

g po

sitio

n to

faci

litat

e re

mot

e in

terr

ogat

ion

and

data

col

lect

ion.

4.

A m

utua

lly a

ccep

tabl

e m

eans

of i

nter

rupt

ing

and

disc

onne

ctin

g th

e ge

nera

tor w

ith a

vis

ible

br

eak,

abl

e to

be

tagg

ed a

nd lo

cked

out

, sha

ll be

wor

ked

out w

ith P

HI E

ngin

eerin

g.

Inte

rcon

nect

ion

Cus

tom

er S

cope

of W

ork

The

Inte

rcon

nect

ion

Cus

tom

er (I

C) i

s res

pons

ible

for a

ll de

sign

and

con

stru

ctio

n re

late

d to

act

iviti

es

on th

eir s

ide

of th

e Po

int o

f Int

erco

nnec

tion.

Site

pre

para

tion,

incl

udin

g gr

adin

g an

d an

acc

ess r

oad,

as

nec

essa

ry, i

s ass

umed

to b

e by

the

IC.

Rout

e se

lect

ion,

line

des

ign,

and

righ

t-of

-way

acq

uisit

ion

of

the

dire

ct c

onne

ct fa

cilit

ies

is no

t inc

lude

d in

this

repo

rt, a

nd is

the

resp

onsi

bilit

y of

the

IC.

Th

e IC

will

be

requ

ired

to in

stal

l met

erin

g an

d te

lem

etry

equ

ipm

ent t

o pr

ovid

e re

venu

e m

eter

ing

and

real

-tim

e te

lem

etry

dat

a to

PJM

. The

requ

irem

ents

for t

his e

quip

men

t are

list

ed in

App

endi

x 2,

Se

ctio

n 8

of A

ttach

men

t O to

the

PJM

Tar

iff, a

s wel

l as P

JM M

anua

ls 01

and

14D

. Pro

tect

ive

rela

ying

and

met

erin

g de

sign

and

inst

alla

tion

mus

t com

ply

with

PH

I’s A

pplic

able

Sta

ndar

ds.

The

Inte

rcon

nect

ion

Cus

tom

er w

ill p

urch

ase

and

inst

all a

ll m

eter

ing

inst

rum

ent t

rans

form

ers a

s wel

l as

con

stru

ct a

met

erin

g st

ruct

ure

per P

HI's

spe

cific

atio

ns. T

he se

cond

ary

wiri

ng c

onne

ctio

ns a

t the

in

stru

men

t tra

nsfo

rmer

s will

be

com

plet

ed b

y th

e In

terc

onne

ctio

n C

usto

mer

's co

ntra

ctor

s and

in

spec

ted

by P

HI,

whi

le th

e se

cond

ary

wiri

ng w

ork

at th

e m

eter

ing

encl

osur

e w

ill b

e co

mpl

eted

by

PHI's

met

er te

chni

cian

s. Th

e m

eter

ing

cont

rol c

able

and

met

er c

abin

ets w

ill b

e su

pplie

d by

PH

I and

in

stal

led

by th

e In

terc

onne

ctio

n C

usto

mer

's co

ntra

ctor

s. PH

I's m

eter

tech

nici

ans w

ill p

rogr

am a

nd

inst

all t

wo

solid

stat

e m

ulti

func

tion

met

ers (

Prim

ary

& B

acku

p) fo

r the

new

met

erin

g po

sitio

n.

Inve

rter R

equi

rem

ents

and

Cap

abili

ties

The

inve

rter a

t the

DG

loca

tion

shal

l hav

e th

e fo

llow

ing

capa

bilit

ies:

1.

V

olta

ge fl

icke

r red

uctio

n th

roug

h dy

nam

ic V

AR

resp

onse

2.

Ram

p ra

te c

ontro

l 3.

SC

AD

A c

omm

unic

atio

ns

4.

Cur

tailm

ent o

r oth

er m

itiga

tion

abili

ty if

hig

h vo

ltage

wer

e to

occ

ur

5.

Low

vol

tage

and

sys

tem

dist

urba

nce

ride

thro

ugh

6.

Abi

lity

to re

ceiv

e an

d re

spon

d to

a tr

ansf

er tr

ip o

r SC

AD

A s

igna

l

4

The

inve

rter s

hall

oper

ate

in a

ccor

danc

e w

ith th

e IE

EE 1

547

serie

s of s

tand

ards

that

hav

e be

en

appr

oved

. W

hile

inve

rters

shou

ld b

e ca

pabl

e of

vol

tage

stab

iliza

tion

thru

dyn

amic

VA

R re

spon

se

and

capa

ble

of lo

w v

olta

ge a

nd s

yste

m d

istur

banc

e rid

e th

roug

h, n

eith

er o

f the

se c

apab

ilitie

s sha

ll be

im

plem

ente

d un

til su

ch ti

me

that

the

IEEE

154

7 se

ries o

f sta

ndar

ds a

re re

vise

d an

d ap

prov

ed to

in

clud

e st

anda

rds

for t

hese

cap

abili

ties.

At s

uch

time

as th

ese

revi

sed

stan

dard

s bec

ome

avai

labl

e,

the

PV o

wne

r/ope

rato

r sha

ll co

oper

ate

with

the

Com

pany

(the

‘Com

pany

’ ref

errin

g to

AC

E, D

PL, o

r PE

PCO

) to

impl

emen

t the

se c

apab

ilitie

s with

setti

ngs a

ccep

tabl

e to

the

Com

pany

. U

ntil

such

tim

e,

the

inve

rters

shal

l ope

rate

with

a fi

xed

pow

er fa

ctor

sche

dule

as s

uppl

ied

by th

e C

ompa

ny.

Tra

nsm

issi

on N

etw

ork

Impa

cts

Pote

ntia

l tra

nsm

issio

n ne

twor

k im

pact

s are

as f

ollo

ws:

G

ener

ator

Del

iver

abili

ty

(Sin

gle

or N

-1 c

ontin

genc

ies f

or th

e Ca

paci

ty p

ortio

n on

ly o

f the

inte

rcon

nect

ion)

N

one

Mul

tiple

Fac

ility

Con

tinge

ncy

(D

oubl

e Ci

rcui

t Tow

er L

ine,

Lin

e wi

th F

aile

d Br

eake

r and

, Bus

Fau

lt co

ntin

genc

ies f

or th

e Fu

ll en

ergy

out

put.

N

one

Con

trib

utio

n to

Pre

viou

sly Id

entif

ied

Ove

rloa

ds

(Thi

s pro

ject

con

tribu

tes t

o th

e fo

llowi

ng c

ontin

genc

y ov

erlo

ads,

i.e. “

Netw

ork

Impa

cts”

, ide

ntifi

ed

for e

arlie

r gen

erat

ion

or tr

ansm

issio

n in

terc

onne

ctio

n pr

ojec

ts in

the

PJM

Que

ue)

Non

e Sh

ort C

ircu

it N

o iss

ues

iden

tifie

d.

Stab

ility

Ana

lysis

N

ot re

quire

d du

e to

pro

ject

size

. D

ynam

ic A

naly

sis

DPL

will

com

men

ce a

tim

e-ba

sed

dyna

mic

stud

y du

ring

the

Syst

em Im

pact

Stu

dy p

hase

to e

valu

ate

the

proj

ect’s

impa

ct o

n th

e D

PL d

istrib

utio

n sy

stem

. O

nce

com

plet

e, th

e re

sults

of t

he st

udy

will

be

revi

ewed

and

the

prop

osed

pro

ject

will

be

eval

uate

d fo

r pro

tect

ion

and

coor

dina

tion

issue

s. O

ther

re

quire

d up

grad

es m

ay b

e id

entif

ied

at th

at ti

me.

5

Syst

em P

rote

ctio

n Pr

otec

tive

rela

ying

and

met

erin

g de

sign

and

inst

alla

tion

mus

t com

ply

with

PH

I’s a

pplic

able

st

anda

rds.

Any

oth

er c

osts

det

erm

ined

by

syst

em p

rote

ctio

n as

a re

sult

of th

e sh

ort c

ircui

t stu

dies

will

be

supp

lied

in th

e ne

ar fu

ture

. O

ther

Cha

rges

PH

I res

erve

s the

righ

t to

char

ge th

e In

terc

onne

ctio

n C

usto

mer

Ope

ratio

n an

d M

aint

enan

ce e

xpen

ses

to m

aint

ain

the

Inte

rcon

nect

ion

Cus

tom

er’s

Atta

chm

ent F

acili

ties,

incl

udin

g m

eter

ing

and

tele

com

mun

icat

ions

faci

litie

s whi

ch a

re o

wne

d by

PH

I. N

ew S

yste

m R

einf

orce

men

ts

(Upg

rade

s req

uire

d to

miti

gate

relia

bilit

y cr

iteria

vio

latio

ns, i

.e. “

Netw

ork

Impa

cts,”

initi

ally

cau

sed

by th

e ad

ditio

n of

this

proj

ect’s

gen

erat

ion)

N

one

Con

trib

utio

n to

Pre

viou

sly Id

entif

ied

Syst

em R

einf

orce

men

ts

(Ove

rload

s ini

tially

cau

sed

by p

rior Q

ueue

pos

ition

s with

add

ition

al c

ontri

butio

n to

ove

rloa

ding

by

this

proj

ect.

N

one

Pote

ntia

l Con

gest

ion

due

to L

ocal

Ene

rgy

Del

iver

abili

ty

(PJM

also

stud

ied

the

deliv

ery

of th

e en

ergy

por

tion

of th

e su

rrou

ndin

g ge

nera

tion.

Any

pot

entia

l pr

oble

ms i

dent

ified

bel

ow a

re li

kely

to re

sult

in o

pera

tiona

l res

trict

ions

to th

e pr

ojec

t und

er

study

. Th

e de

velo

per c

an p

roce

ed w

ith N

etwo

rk U

pgra

des t

o el

imin

ate

the

oper

atio

nal r

estr

ictio

n at

th

eir d

iscr

etio

n by

subm

ittin

g a

Tran

smiss

ion

Inte

rcon

nect

ion

Requ

est.

Not

e: O

nly

the

mos

t sev

erel

y ov

erlo

aded

con

ditio

ns a

re li

sted

belo

w. T

here

is n

o gu

aran

tee

of fu

ll de

liver

abili

ty fo

r thi

s pro

ject

by

fixin

g on

ly th

e co

nditi

ons l

isted

in th

is se

ctio

n. W

ith a

Tra

nsm

issio

n In

terc

onne

ctio

n Re

ques

t, a

subs

eque

nt a

naly

sis w

ill b

e pe

rfor

med

whi

ch a

naly

zes a

ll ov

erlo

ad c

ondi

tions

ass

ocia

ted

with

the

iden

tifie

d ov

erlo

aded

ele

men

t(s).

As a

resu

lt of

the

aggr

egat

e en

ergy

reso

urce

s in

the

area

, the

fo

llowi

ng v

iola

tions

wer

e id

entif

ied:

Th

ese

are

not r

equi

red

relia

bilit

y up

grad

es.

1.

The

(DP&

L/PE

CO

) Cla

ymon

t-Lin

woo

d 23

0 kV

line

(fro

m b

us 2

3100

0 to

bus

213

750

ckt 1

) lo

ads

from

100

.00%

to 1

00.0

7% (D

C p

ower

flow

) of i

ts e

mer

genc

y ra

ting

(805

MV

A) f

or th

e op

erat

iona

l con

tinge

ncy

'220

-85'

. Th

is pr

ojec

t con

tribu

tes a

ppro

xim

atel

y 3.

53 M

W to

the

ther

mal

vi

olat

ion.

6

Seco

ndar

y PO

I Opt

ion

PJM

stud

ied

X3-

008

as a

20

MW

inje

ctio

n at

the

Todd

69k

V su

bsta

tion.

T

rans

mis

sion

Net

wor

k Im

pact

s Po

tent

ial t

rans

mis

sion

netw

ork

impa

cts a

re a

s fol

low

s:

Gen

erat

or D

eliv

erab

ility

(S

ingl

e or

N-1

con

tinge

ncie

s for

the

Capa

city

por

tion

only

of t

he in

terc

onne

ctio

n)

Non

e M

ultip

le F

acili

ty C

ontin

genc

y

(Dou

ble

Circ

uit T

ower

Lin

e, L

ine

with

Fai

led

Brea

ker a

nd, B

us F

ault

cont

inge

ncie

s for

the

Full

ener

gy o

utpu

t.

Non

e C

ontr

ibut

ion

to P

revi

ously

Iden

tifie

d O

verl

oads

(T

his p

roje

ct c

ontri

bute

s to

the

follo

wing

con

tinge

ncy

over

load

s, i.e

. “Ne

twor

k Im

pact

s”, i

dent

ified

fo

r ear

lier g

ener

atio

n or

tran

smiss

ion

inte

rcon

nect

ion

proj

ects

in th

e PJ

M Q

ueue

) N

one

Shor

t Cir

cuit

No

issue

s id

entif

ied.

Po

tent

ial C

onge

stio

n du

e to

Loc

al E

nerg

y D

eliv

erab

ility

(P

JM a

lso st

udie

d th

e de

liver

y of

the

ener

gy p

ortio

n of

the

surr

ound

ing

gene

ratio

n. A

ny p

oten

tial

prob

lem

s ide

ntifi

ed b

elow

are

like

ly to

resu

lt in

ope

ratio

nal r

estri

ctio

ns to

the

proj

ect u

nder

stu

dy.

The

deve

lope

r can

pro

ceed

with

Net

work

Upg

rade

s to

elim

inat

e th

e op

erat

iona

l res

tric

tion

at

thei

r dis

cret

ion

by su

bmitt

ing

a Tr

ansm

issio

n In

terc

onne

ctio

n Re

ques

t. N

ote:

Onl

y th

e m

ost s

ever

ely

over

load

ed c

ondi

tions

are

liste

d be

low.

The

re is

no

guar

ante

e of

full

deliv

erab

ility

for t

his p

roje

ct b

y fix

ing

only

the

cond

ition

s list

ed in

this

sect

ion.

With

a T

rans

miss

ion

Inte

rcon

nect

ion

Requ

est,

a su

bseq

uent

ana

lysi

s will

be

perf

orm

ed w

hich

ana

lyze

s all

over

load

con

ditio

ns a

ssoc

iate

d wi

th th

e id

entif

ied

over

load

ed e

lem

ent(s

). A

s a re

sult

of th

e ag

greg

ate

ener

gy re

sour

ces i

n th

e ar

ea, t

he

follo

wing

vio

latio

ns w

ere

iden

tifie

d:

Thes

e ar

e no

t req

uire

d re

liabi

lity

upgr

ades

. 1.

Th

e (D

P&L/

PEC

O) C

laym

ont-L

inw

ood

230

kV li

ne (f

rom

bus

231

000

to b

us 2

1375

0 ck

t 1)

load

s fro

m 1

00.0

0% to

100

.07%

(DC

pow

er fl

ow) o

f its

em

erge

ncy

ratin

g (8

05 M

VA

) for

the

7

oper

atio

nal c

ontin

genc

y '2

20-8

5'.

This

proj

ect c

ontri

bute

s app

roxi

mat

ely

3.53

MW

to th

e th

erm

al

viol

atio

n.

Gen

erat

ion

Inte

rcon

nect

ion

Sy

stem

Impa

ct S

tudy

Rep

ort

Fo

r PJ

M G

ener

atio

n In

terc

onne

ctio

n Re

ques

t Q

ueue

Pos

ition

X3-

008

“T

odd

69kV

July

201

2

©

PJM

Inte

rcon

nect

ion

2012

. All

right

s res

erve

d.

PJM

DO

CS-

# 70

6907

-v1

X3-

008

Todd

69k

V

2

Pref

ace

The

inte

nt o

f the

Sys

tem

Impa

ct S

tudy

is to

det

erm

ine

a pl

an, w

ith a

ppro

xim

ate

cost

and

co

nstru

ctio

n tim

e es

timat

es, t

o co

nnec

t the

subj

ect g

ener

atio

n in

terc

onne

ctio

n pr

ojec

t to

the

PJM

ne

twor

k at

a lo

catio

n sp

ecifi

ed b

y th

e In

terc

onne

ctio

n C

usto

mer

. As a

requ

irem

ent f

or

inte

rcon

nect

ion,

the

Inte

rcon

nect

ion

Cus

tom

er m

ay b

e re

spon

sibl

e fo

r the

cos

t of c

onst

ruct

ing:

N

etw

ork

Upg

rade

s, w

hich

are

faci

lity

addi

tions

, or u

pgra

des t

o ex

istin

g fa

cilit

ies,

that

are

nee

ded

to

mai

ntai

n th

e re

liabi

lity

of th

e PJ

M sy

stem

. All

faci

litie

s req

uire

d fo

r int

erco

nnec

tion

of a

gen

erat

ion

inte

rcon

nect

ion

proj

ect m

ust b

e de

sign

ed to

mee

t the

tech

nica

l spe

cific

atio

ns (o

n PJ

M w

eb si

te) f

or

the

appr

opria

te tr

ansm

issi

on o

wne

r. In

som

e in

stan

ces a

n In

terc

onne

ctio

n C

usto

mer

may

not

be

resp

onsi

ble

for 1

00%

of t

he id

entif

ied

netw

ork

upgr

ade

cost

bec

ause

oth

er tr

ansm

issi

on n

etw

ork

uses

, e.g

. ano

ther

gen

erat

ion

inte

rcon

nect

ion

or m

erch

ant t

rans

mis

sion

upg

rade

, may

als

o co

ntrib

ute

to th

e ne

ed fo

r the

sam

e ne

twor

k re

info

rcem

ent.

The

poss

ibili

ty o

f sha

ring

the

rein

forc

emen

t cos

ts w

ith o

ther

pro

ject

s may

be

iden

tifie

d in

the

Feas

ibili

ty S

tudy

, but

the

actu

al a

lloca

tion

will

be

defe

rred

unt

il th

e Sy

stem

Impa

ct

Stud

y is

per

form

ed.

The

Syst

em Im

pact

Stu

dy e

stim

ates

do

not i

nclu

de th

e fe

asib

ility

, cos

t, or

tim

e re

quire

d to

obt

ain

prop

erty

righ

ts a

nd p

erm

its fo

r con

stru

ctio

n of

the

requ

ired

faci

litie

s. Ty

pica

lly, t

he p

roje

ct

deve

lope

r is r

espo

nsib

le fo

r rig

ht o

f way

, rea

l est

ate,

and

con

stru

ctio

n pe

rmit

issu

es.

For p

rope

rties

cu

rren

tly o

wne

d by

Tra

nsm

issi

on O

wne

rs, t

he c

osts

may

be

incl

uded

in th

e st

udy.

G

ener

al

Inve

nerg

y So

lar D

evel

opm

ent L

LC, t

he In

terc

onne

ctio

n C

usto

mer

(IC

), ha

s pro

pose

d a

20 M

WE

(7.6

MW

C; 2

0 M

W M

FO) s

olar

pow

ered

gen

erat

ing

faci

lity

to b

e lo

cate

d in

Dor

ches

ter C

ount

y,

Mar

ylan

d. P

JM st

udie

d X

3-00

8 as

a 2

0 M

W in

ject

ion

into

the

Del

mar

va P

ower

and

Lig

ht (D

PL)

dist

ribut

ion

syst

em a

t the

Tod

d 69

/25k

V su

bsta

tion

and

eval

uate

d th

e pr

ojec

t for

com

plia

nce

with

re

liabi

lity

crite

ria fo

r sum

mer

pea

k co

nditi

ons i

n 20

15.

The

plan

ned

in-s

ervi

ce d

ate,

as s

tate

d in

the

Atta

chm

ent N

, is J

une

01, 2

017.

Po

int o

f Int

erco

nnec

tion

X

3-00

8 w

ill in

terc

onne

ct w

ith th

e D

elm

arva

Pow

er a

nd L

ight

syst

em a

t the

Tod

d 69

/25k

V

subs

tatio

n as

follo

ws (

see

Atta

chm

ent 1

):

10

MW

s will

con

nect

to th

e ex

istin

g 69

/25k

V T

1 tra

nsfo

rmer

; 10

MW

s will

con

nect

to th

e ex

istin

g 69

/25k

V T

2 tra

nsfo

rmer

. D

irec

t Con

nect

ion

Req

uire

men

ts

Crit

eria

Lim

its fo

r Dis

tribu

ted

Ener

gy R

esou

rce

Con

nect

ions

to th

e D

PL D

istri

butio

n Sy

stem

s (le

ss

than

69k

V)

1. E

xist

ing

Dis

tribu

tion

Circ

uit C

apac

ity L

imits

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

3

The

aggr

egat

e lim

it of

larg

e (2

50 k

W a

nd o

ver)

gen

erat

or in

ject

ion

to a

sing

le, e

xist

ing

dist

ribut

ion

circ

uit i

s 0.5

MW

s on

the

4kV

, 3M

Ws o

n th

e 12

kV

, 6 M

Ws o

n th

e 25

kV

, and

10

MW

s on

the

34

kV.

2. E

xpre

ss C

ircui

t Cap

acity

Lim

its

Dis

tribu

ted

gene

ratio

n in

stal

latio

ns w

hich

exc

eed

the

limit

for a

n ex

istin

g ci

rcui

t req

uire

an

expr

ess

circ

uit.

The

max

imum

gen

erat

or si

ze fo

r exp

ress

circ

uits

shal

l be:

� 4

kV

0.

5 M

W

� 12

– 1

3.8

kV

10 M

Ws

� 23

– 2

5 kV

10 M

Ws

� 33

.26

– 34

.5 k

V

15 M

Ws

3. D

istri

butio

n Po

wer

Tra

nsfo

rmer

Lim

it Th

e ag

greg

ate

limit

of la

rge

(250

kW

and

ove

r) g

ener

ator

inje

ctio

n to

a si

ngle

dis

tribu

tion

trans

form

er o

f 22.

5 M

VA

nam

epla

te o

r lar

ger i

s 10

MW

s. Tr

ansf

orm

ers w

ith n

amep

late

ratin

gs

low

er th

an 2

2.5

MV

A w

ill b

e gi

ven

low

er ra

tings

on

an in

divi

dual

bas

is. I

f the

tran

sfor

mer

ratin

g is

si

gnifi

cant

ly g

reat

er th

an 4

0 M

VA

it m

ay b

e po

ssib

le to

con

side

r a g

reat

er a

mou

nt o

f inj

ectio

n.

Add

ing

a ne

w tr

ansf

orm

er w

ill b

e co

nsid

ered

if th

ere

is n

o av

aila

bilit

y on

any

of t

he e

xist

ing

trans

form

ers a

nd sp

ace

is a

vaila

ble

in a

n ex

istin

g su

bsta

tion.

Any

pro

pose

d tra

nsfo

rmer

s wou

ld b

e PH

I's st

anda

rd d

istri

butio

n tra

nsfo

rmer

(37

MV

A n

amep

late

ratin

g.)

4. E

xpre

ss C

ircui

t Len

gth

Lim

it If

ther

e is

no

mor

e in

ject

ion

capa

city

or s

pace

for a

n ad

ditio

nal t

rans

form

er a

t the

clo

sest

subs

tatio

n,

the

next

clo

sest

subs

tatio

n w

ill b

e co

nsid

ered

. The

leng

th o

f an

expr

ess c

ircui

t is l

imite

d to

5 m

iles,

or fo

r the

sake

of t

he fe

asib

ility

stud

y, 3

.8 st

raig

ht li

ne m

iles.

This

sim

plifi

catio

n is

use

d be

caus

e th

e fe

asib

ility

stud

y ph

ase

does

not

allo

w fo

r the

tim

e an

d re

sour

ces t

o ex

amin

e ro

utes

in d

etai

l (in

clud

ing

exis

ting

pole

line

s, ea

sem

ents

, RO

W, a

nd e

nviro

nmen

tal i

ssue

s etc

.)

5. W

hen

a N

ew S

ubst

atio

n is

Req

uire

d If

a d

istri

butio

n ex

pres

s circ

uit c

an’t

be b

uilt

from

an

exis

ting

subs

tatio

n fo

r a p

roje

ct, i

t will

be

nece

ssar

y to

con

stru

ct a

new

dis

tribu

tion

subs

tatio

n w

ith a

stan

dard

ring

bus

des

ign.

It w

ill b

e su

pplie

d by

ext

endi

ng e

xist

ing

trans

mis

sion

line

s. It

is th

e de

velo

per's

resp

onsi

bilit

y to

ver

ify

elig

ibili

ty o

f thi

s con

figur

atio

n fo

r sol

ar re

new

able

ene

rgy

certi

ficat

es w

ith N

ew Je

rsey

's C

lean

En

ergy

Pro

gram

if d

esire

d.

All

inje

ctio

n lim

its, g

iven

abo

ve in

MW

s, ar

e su

bjec

t to

mor

e de

taile

d st

udy

to e

nsur

e fe

asib

ility

. T

rans

mis

sion

Ow

ner

Scop

e of

Wor

k Th

e sc

ope

of w

ork

and

estim

ated

cos

t for

the

dire

ct c

onne

ctio

n fa

cilit

ies i

s as f

ollo

ws:

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

4

1.

Con

stru

ct tw

o (2

) new

25

kV fe

eder

s with

954

kcm

il A

ll A

lum

inum

Con

duct

or (A

AC

) fro

m

the

Todd

Sub

stat

ion

to th

e PV

site

– a

dis

tanc

e of

app

roxi

mat

ely

2.2

mile

s.

2.

Con

stru

ct tw

o (2

) new

25

kV fe

eder

term

inal

pos

ition

s at t

he T

odd

subs

tatio

n.

3.

A u

tility

ope

rate

d re

clos

er e

quip

ped

with

the

prop

er re

layi

ng a

nd c

omm

unic

atio

ns w

ill b

e in

stal

led

for e

ach

feed

er se

rvin

g th

e PV

gen

erat

or.

4.

Util

ity g

rade

prim

ary

met

erin

g w

ill b

e re

quire

d fo

r eac

h fe

eder

. 5.

Th

e in

verte

r sha

ll be

des

igne

d to

acc

omm

odat

e fu

ture

cap

abili

ty to

adj

ust o

utpu

t and

pow

er

fact

or if

nee

ded.

6.

A

det

aile

d, ti

me-

base

d st

udy

may

be

perf

orm

ed d

urin

g la

ter s

tudy

pha

ses.

7.

Pr

otec

tion,

Pla

nnin

g, a

nd o

ther

eng

inee

ring

depa

rtmen

ts w

ill p

erfo

rm st

udie

s, de

sign

wor

k,

and

prep

are

engi

neer

ing

estim

ates

. 8.

Tr

ansf

er tr

ip w

ill b

e re

quire

d. A

ppro

xim

atel

y 2.

2 m

iles o

f 48S

M A

DSS

fibe

r opt

ic c

able

was

es

timat

ed fo

r thi

s rep

ort t

o pr

ovid

e th

e co

mm

unic

atio

n ch

anne

l fro

m T

odd

Sub

to th

e PV

si

te.

Th

e es

timat

ed c

ost t

o pe

rfor

m th

is w

ork

is a

s fol

low

s:

$480

,000

954

AA

C E

xpre

ss F

eede

rM

iles

$455

,000

Fibe

r Ins

talla

tion

Mile

s$1

10,0

00$5

0,00

0$2

0,00

0$1

0,00

0$3

0,00

0$2

0,00

0$1

,175

,000

$1,3

86,5

00$1

,594

,475

Rec

lose

r w/ R

elay

ing

and

Com

mun

icat

ions

Util

ity G

rade

Met

erin

gSC

AD

A In

tegr

atio

n in

to E

MS

Det

aile

d Ti

me

Bas

ed S

tudy

Est

imat

ed C

osts

Tod

d Su

bsta

tion

T1

New

Fee

der T

erm

inal

, Bre

aker

, Upg

rade

s

2.2

Var

ious

Dep

artm

ents

Wor

kSu

btot

al C

ost

Subt

otal

Cos

t with

18%

Ove

rhea

dsA

ppro

xim

ate

Tot

al C

ost w

ith 1

5% C

ontin

genc

y

$330

,000

954

AA

C E

xpre

ss F

eede

r2.

2M

iles

$455

,000

$50,

000

$20,

000

$10,

000

$865

,000

$1,0

20,7

00$1

,173

,805

Est

imat

ed C

osts

Tod

d Su

bsta

tion

T2

New

Fee

der T

erm

inal

, Bre

aker

, Upg

rade

s

Subt

otal

Cos

tSu

btot

al C

ost w

ith 1

8% O

verh

eads

App

roxi

mat

e T

otal

Cos

t with

15%

Con

tinge

ncy

Rec

lose

r w/ R

elay

ing

and

Com

mun

icat

ions

Util

ity G

rade

Met

erin

gSC

AD

A In

tegr

atio

n in

to E

MS

A

ppro

xim

ate

tota

l cos

t for

bot

h fe

eder

s: $

2,76

8,28

0

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

5

Spec

ial O

pera

ting

Req

uire

men

ts

1.

D

PL w

ill re

quire

the

capa

bilit

y to

rem

otel

y tri

p th

e ge

nera

tor f

rom

its S

yste

m O

pera

tions

fa

cilit

y. S

uch

tripp

ing

may

be

faci

litat

ed b

y ei

ther

a g

ener

ator

bre

aker

, inv

erte

r (if

so

equi

pped

), or

a li

ne re

clos

er, d

epen

ding

upo

n th

e sp

ecifi

c ci

rcum

stan

ces a

nd th

e ev

alua

tion

by D

PL.

2.

It

is th

e In

terc

onne

ctio

n C

usto

mer

’s re

spon

sibi

lity

to se

nd th

e da

ta th

at P

JM a

nd D

PL

requ

ires d

irect

ly to

PJM

. Th

e In

terc

onne

ctio

n C

usto

mer

will

gra

nt p

erm

issi

on fo

r PJM

to

send

to D

PL th

e fo

llow

ing

tele

met

ry th

at th

e In

terc

onne

ctio

n C

usto

mer

send

s to

PJM

: rea

l tim

e M

W, M

VA

R, v

olts

, am

pere

s, ge

nera

tor/s

tatu

s, an

d in

terv

al M

WH

and

MV

AR

H.

3.

Th

e In

terc

onne

ctio

n C

usto

mer

will

be

requ

ired

to m

ake

prov

isio

ns fo

r a v

oice

qua

lity

phon

e lin

e w

ithin

app

roxi

mat

ely

3 fe

et o

f eac

h D

PL m

eter

ing

posi

tion

to fa

cilit

ate

rem

ote

inte

rrog

atio

n an

d da

ta c

olle

ctio

n.

4.

A

mut

ually

acc

epta

ble

mea

ns o

f int

erru

ptin

g an

d di

scon

nect

ing

the

gene

rato

r with

a v

isib

le

brea

k, a

ble

to b

e ta

gged

and

lock

ed o

ut, s

hall

be w

orke

d ou

t with

DPL

Dis

tribu

tion

Engi

neer

ing.

In

terc

onne

ctio

n C

usto

mer

Sco

pe o

f Dir

ect C

onne

ctio

n W

ork

The

Inte

rcon

nect

ion

Cus

tom

er (I

C) i

s res

pons

ible

for a

ll de

sign

and

con

stru

ctio

n re

late

d ac

tiviti

es o

n th

eir s

ide

of th

e Po

int o

f Int

erco

nnec

tion.

Site

pre

para

tion,

incl

udin

g gr

adin

g an

d an

acc

ess r

oad,

as

nece

ssar

y, is

ass

umed

to b

e by

the

IC.

Rou

te se

lect

ion,

line

des

ign,

and

righ

t-of-

way

acq

uisi

tion

of

the

dire

ct c

onne

ct fa

cilit

ies i

s not

incl

uded

in th

is re

port

and

is th

e re

spon

sibi

lity

of th

e IC

. Pr

otec

tive

rela

ying

and

met

erin

g de

sign

and

inst

alla

tion

mus

t com

ply

with

DPL

’s a

pplic

able

st

anda

rds.

The

IC is

als

o re

quire

d to

pro

vide

reve

nue

met

erin

g an

d re

al-ti

me

tele

met

erin

g da

ta to

PJ

M in

con

form

ance

with

the

requ

irem

ents

con

tain

ed in

PJM

Man

uals

M-0

1 an

d M

-14

and

the

PJM

Ta

riff.

Th

e in

verte

r at t

he D

G lo

catio

n sh

all h

ave

the

follo

win

g ca

pabi

litie

s:

� V

olta

ge fl

icke

r red

uctio

n th

roug

h dy

nam

ic V

AR

or f

ixed

PF

resp

onse

� R

amp

rate

con

trol

� SC

AD

A c

omm

unic

atio

ns

� C

urta

ilmen

t or o

ther

miti

gatio

n ab

ility

if h

igh

volta

ge w

ere

to o

ccur

� Lo

w v

olta

ge a

nd s

yste

m d

istu

rban

ce ri

de th

roug

h

� A

bilit

y to

rece

ive

and

resp

ond

to a

tran

sfer

trip

sign

al

� A

bilit

y to

adj

ust P

F or

VA

Rs b

ased

on

utili

ty si

gnal

� A

bilit

y to

Adj

ust R

eal P

ower

Out

put b

ased

on

utili

ty si

gnal

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

6

The

inve

rter s

hall

oper

ate

in a

ccor

danc

e w

ith th

e IE

EE 1

547

serie

s of s

tand

ards

that

hav

e be

en

appr

oved

. W

hile

inve

rters

shou

ld b

e ca

pabl

e of

vol

tage

stab

iliza

tion

thru

dyn

amic

VA

R re

spon

se

and

capa

ble

of lo

w v

olta

ge a

nd s

yste

m d

istu

rban

ce ri

de th

roug

h, n

eith

er o

f the

se c

apab

ilitie

s sha

ll be

im

plem

ente

d un

til su

ch ti

me

that

the

IEEE

154

7 se

ries o

f sta

ndar

ds a

re re

vise

d an

d ap

prov

ed to

in

clud

e st

anda

rds f

or th

ese

capa

bilit

ies.

At s

uch

time

as th

ese

revi

sed

stan

dard

s bec

ome

avai

labl

e,

the

PV o

wne

r/ope

rato

r sha

ll co

oper

ate

with

the

Com

pany

(the

‘Com

pany

’ ref

errin

g to

AC

E, D

PL, o

r PE

PCO

) to

impl

emen

t the

se c

apab

ilitie

s with

setti

ngs a

ccep

tabl

e to

the

Com

pany

. U

ntil

such

tim

e,

the

inve

rters

shal

l ope

rate

with

a fi

xed

pow

er fa

ctor

sche

dule

as s

uppl

ied

by th

e C

ompa

ny, a

nd b

e ab

le to

ope

rate

in th

e ra

nge

of 0

.95

lead

ing

to 0

.95

lagg

ing,

as s

peci

fied

by P

JM.

Tra

nsm

issi

on N

etw

ork

Impa

cts

Pote

ntia

l tra

nsm

issi

on n

etw

ork

impa

cts w

ere

as fo

llow

s:

Gen

erat

or D

eliv

erab

ility

(S

ingl

e or

N-1

con

tinge

ncie

s for

the

Capa

city

por

tion

only

of t

he in

terc

onne

ctio

n)

Non

e M

ultip

le F

acili

ty C

ontin

genc

y

(Dou

ble

Cir

cuit

Tow

er L

ine,

Lin

e w

ith F

aile

d Br

eake

r and

, Bus

Fau

lt co

ntin

genc

ies f

or th

e Fu

ll en

ergy

out

put.

N

one

Con

trib

utio

n to

Pre

viou

sly

Iden

tifie

d O

verl

oads

(T

his p

roje

ct c

ontr

ibut

es to

the

follo

win

g co

ntin

genc

y ov

erlo

ads,

i.e. “

Net

wor

k Im

pact

s”, i

dent

ified

fo

r ear

lier g

ener

atio

n or

tran

smis

sion

inte

rcon

nect

ion

proj

ects

in th

e PJ

M Q

ueue

) N

one

Shor

t Cir

cuit

Ana

lysi

s N

o pr

oble

ms i

dent

ified

. N

ew S

yste

m R

einf

orce

men

ts

(Upg

rade

s req

uire

d to

miti

gate

relia

bilit

y cr

iteri

a vi

olat

ions

, i.e

. “N

etw

ork

Impa

cts,”

initi

ally

ca

used

by

the

addi

tion

of th

is p

roje

ct’s

gen

erat

ion)

N

one

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

7

Con

trib

utio

n to

Pre

viou

sly

Iden

tifie

d Sy

stem

Rei

nfor

cem

ents

(O

verl

oads

initi

ally

cau

sed

by p

rior

Que

ue p

ositi

ons w

ith a

dditi

onal

con

tribu

tion

to o

verl

oadi

ng b

y th

is p

roje

ct.

This

pro

ject

may

hav

e a

% a

lloca

tion

cost

resp

onsi

bilit

y.

Non

e St

abili

ty A

naly

sis

Not

requ

ired.

O

ther

Cha

rges

D

PL re

serv

es th

e rig

ht to

cha

rge

the

Inte

rcon

nect

ion

Cus

tom

er o

pera

tion

and

mai

nten

ance

exp

ense

s to

mai

ntai

n th

e In

terc

onne

ctio

n C

usto

mer

’s A

ttach

men

t Fac

ilitie

s, in

clud

ing

met

erin

g an

d te

leco

mm

unic

atio

ns fa

cilit

ies t

hat a

re o

wne

d by

DPL

. D

eliv

ery

of E

nerg

y Po

rtio

n of

Inte

rcon

nect

ion

Req

uest

PJ

M a

lso

stud

ied

the

deliv

ery

of th

e en

ergy

por

tion

of th

is in

terc

onne

ctio

n re

ques

t. A

ny p

robl

ems

iden

tifie

d be

low

are

like

ly to

resu

lt in

ope

ratio

nal r

estri

ctio

ns to

the

proj

ect u

nder

stud

y. T

he

deve

lope

r can

pro

ceed

with

net

wor

k up

grad

es to

elim

inat

e th

e op

erat

iona

l res

trict

ion

at th

eir

disc

retio

n by

subm

ittin

g a

Mer

chan

t Tra

nsm

issi

on In

terc

onne

ctio

n re

ques

t. O

nly

the

mos

t sev

erel

y ov

erlo

aded

con

ditio

ns a

re li

sted

. The

re is

no

guar

ante

e of

full

deliv

ery

of

ener

gy fo

r thi

s pro

ject

by

fixin

g on

ly th

e co

nditi

ons l

iste

d in

this

sect

ion.

With

a T

rans

mis

sion

In

terc

onne

ctio

n R

eque

st, a

subs

eque

nt a

naly

sis w

ill b

e pe

rfor

med

, whi

ch w

ill st

udy

all o

verlo

ad

cond

ition

s ass

ocia

ted

with

the

over

load

ed e

lem

ent(s

) ide

ntifi

ed.

The

se a

re n

ot r

equi

red

relia

bilit

y up

grad

es.

1.

The

LIN

WO

OD

-CH

ICH

ST2

230

kV li

ne (f

rom

bus

213

750

to b

us 2

1349

0 ck

t 2) l

oads

from

10

3.92

% to

104

.03%

(AC

pow

er fl

ow) o

f its

nor

mal

ratin

g (8

31 M

VA

) for

non

-con

tinge

ncy

cond

ition

. Thi

s pro

ject

con

tribu

tes a

ppro

xim

atel

y 1.

98 M

W to

the

ther

mal

vio

latio

n.

2.

The

LIN

WO

OD

-CH

ICH

ST2

230

kV li

ne (f

rom

bus

213

750

to b

us 2

1349

0 ck

t 1) l

oads

from

12

6.16

% to

126

.33%

(AC

pow

er fl

ow) o

f its

em

erge

ncy

ratin

g (9

83 M

VA

) for

the

sing

le li

ne

cont

inge

ncy

outa

ge o

f CO

NTI

NG

ENC

Y D

ESC

RIP

TIO

N ('

220-

39').

Thi

s pro

ject

con

tribu

tes

appr

oxim

atel

y 3.

72 M

W to

the

ther

mal

vio

latio

n.

3.

The

LIN

WO

OD

-CH

ICH

ST2

230

kV li

ne (f

rom

bus

213

750

to b

us 2

1349

0 ck

t 2) l

oads

from

12

6.61

% to

126

.78%

(AC

pow

er fl

ow) o

f its

em

erge

ncy

ratin

g (9

83 M

VA

) for

the

sing

le li

ne

cont

inge

ncy

outa

ge o

f CO

NTI

NG

ENC

Y D

ESC

RIP

TIO

N ('

220-

43').

Thi

s pro

ject

con

tribu

tes

appr

oxim

atel

y 3.

73 M

W to

the

ther

mal

vio

latio

n.

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

8

4.

The

X2-

066

TAP-

SHA

RN

GTN

138

kV

line

(fro

m b

us 9

0934

0 to

bus

232

114

ckt 1

) loa

ds fr

om

138.

15%

to 1

38.3

8% (A

C p

ower

flow

) of i

ts n

orm

al ra

ting

(242

MV

A) f

or n

on-c

ontin

genc

y co

nditi

on. T

his p

roje

ct c

ontri

bute

s app

roxi

mat

ely

1.25

MW

to th

e th

erm

al v

iola

tion.

5.

Th

e X

2-06

6 TA

P-SH

AR

NG

TN 1

38 k

V li

ne (f

rom

bus

909

340

to b

us 2

3211

4 ck

t 1) l

oads

from

13

8.09

% to

138

.35%

(AC

pow

er fl

ow) o

f its

em

erge

ncy

ratin

g (2

57 M

VA

) for

the

sing

le li

ne

cont

inge

ncy

outa

ge o

f CO

NTI

NG

ENC

Y D

ESC

RIP

TIO

N ('

CK

T 67

37').

Thi

s pro

ject

con

tribu

tes

appr

oxim

atel

y 1.

48 M

W to

the

ther

mal

vio

latio

n.

© P

JM In

terc

onne

ctio

n 20

12. A

ll rig

hts r

eser

ved.

P

JMD

OC

S-#

7069

07-v

1

X

3-00

8 To

dd 6

9kV

9

Att

achm

ent 1

Tod

d69

/25

kVSu

bsta

tion

25K

VB

us

Tod

dSu

bsta

tion

T169

/25

kV25

MV

A

New

Feed

erM

Dxx

xx

Inve

nerg

ySo

lar

Dev

elop

men

tLL

C

Prop

osed

Gen

erat

or10

MW

Met

erow

ned

By

DPL

25K

VB

us

T269

/25

kV28

MV

AA

ppro

xim

atel

y2.

2m

ileso

fPA

CC

able

POI

M

VIP

ERR

eclo

ser

New

Feed

erM

Dxx

xxPr

opos

edG

ener

ator

10M

W

Met

erow

ned

By

DPL

App

roxi

mat

ely

2.2

mile

sof

PAC

Cab

le

VIP

ERR

eclo

ser

MD

2221

East

New

Mar

ket

69kV

Sour

ce

East

onPr

esto

n69

kVSo

urce

POI

M

MD

2267

12K

VB

usT3

69/1

2kV

10.5

MV

A

MD

0439

Alle

n69

kVSo

urce

Vie

nna

69kV

Sour

ce

Gen

erat

ion

Inte

rcon

nect

ion

Faci

litie

s Stu

dy

Repo

rt

For

PJM

Gen

erat

ion

Inte

rcon

nect

ion

Requ

est

Que

ue P

ositi

on X

3-00

8

“Tod

d 69

kV”

Au

gust

2014

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

2

A. T

rans

mis

sion

Ow

ner

Faci

litie

s Stu

dy S

umm

ary

1. D

escr

iptio

n of

Pro

ject

Inve

nerg

y So

lar D

evel

opm

ent,

LLC

, the

Inte

rcon

nect

ion

Cus

tom

er (I

C),

has p

ropo

sed

a 20

MW

E (7

.6 M

WC

; 20

MW

MFO

) sol

ar p

ower

ed g

ener

atin

g fa

cilit

y to

be

loca

ted

in

Dor

ches

ter C

ount

y, M

aryl

and.

PJM

stud

ied

X3-

008

as a

20

MW

inje

ctio

n in

to th

e D

elm

arva

Pow

er a

nd L

ight

(DPL

) sys

tem

at t

he T

odd

Subs

tatio

n an

d ev

alua

ted

it fo

r co

mpl

ianc

e w

ith re

liabi

lity

crite

ria fo

r sum

mer

pea

k co

nditi

ons i

n 20

15.

The

plan

ned

in-

serv

ice

date

, as s

tate

d in

the

Atta

chm

ent N

, is J

une

1, 2

017.

2.

Am

endm

ents

to th

e Sy

stem

Impa

ct S

tudy

or S

yste

m Im

pact

Stu

dy R

esul

ts

Th

is st

udy

is b

ased

on

the

Impa

ct S

tudy

dat

ed J

uly,

201

2 an

d is

bas

ed o

n co

nnec

ting

20

MW

of P

V to

Tod

d Su

bsta

tion

via

two

(2) n

ewly

con

stru

cted

25

kV fe

eder

s. A

dditi

onal

ly th

e sc

hedu

le h

as b

een

adju

sted

to m

eet a

stan

dard

con

stru

ctio

n sc

hedu

le.

The

DPL

por

tion

of th

e pr

ojec

t is p

roje

cted

to b

e co

mpl

eted

in a

ppro

xim

atel

y 18

-22

mon

ths f

ollo

win

g an

exe

cute

d In

terc

onne

ctio

n Se

rvic

e A

gree

men

t (IS

A) a

nd

Con

stru

ctio

n Se

rvic

e A

gree

men

t (C

SA).

3.

Inte

rcon

nect

ion

Cus

tom

er’s

Mile

ston

e Sc

hedu

le

Th

e pl

anne

d in

-ser

vice

dat

e, a

s ide

ntifi

ed in

Atta

chm

ent N

, was

June

1, 2

017.

Thi

s in-

serv

ice

date

can

be

met

pro

vide

d D

elm

arva

Pow

er is

giv

en 1

8-22

mon

ths t

o de

sign

, pr

ocur

e m

ater

ial a

nd c

onst

ruct

afte

r rec

eipt

of a

fully

exe

cute

d In

terc

onne

ctio

n Se

rvic

e A

gree

men

t (IS

A) a

nd In

terc

onne

ctio

n C

onst

ruct

ion

Serv

ice

Agr

eem

ent (

CSA

).

4. C

usto

mer

’s S

cope

of W

ork

Th

e IC

pro

pose

s the

con

stru

ctio

n of

one

pho

tovo

ltaic

syst

em w

ith a

max

imum

gen

erat

ion

capa

city

of 2

0 M

W.

X

3-00

8 w

ill in

terc

onne

ct to

the

Del

mar

va P

ower

and

Lig

ht d

istri

butio

n sy

stem

at t

he

Todd

69

kV su

bsta

tion

as fo

llow

s:

10 M

Ws w

ill c

onne

ct to

the

exis

ting

T1 tr

ansf

orm

er

via

a ne

w 2

5 kV

dis

tribu

tion

feed

er a

nd 1

0 M

W w

ill c

onne

ct to

the

exis

ting

T2

trans

form

er v

ia a

new

25

kV d

istri

butio

n fe

eder

. Ea

ch fe

eder

is n

ot p

erm

itted

to c

arry

m

ore

than

10

MW

. Th

e tw

o di

strib

utio

n fe

eder

s con

stru

cted

by

Del

mar

va P

ower

will

be

cons

truct

ed o

n on

e po

le li

ne.

The

IC a

ssum

es fu

ll re

spon

sibi

lity

for d

esig

n, p

erm

ittin

g an

d co

nstru

ctio

n of

all

faci

litie

s as

soci

ated

w

ith

the

X3-

008

gene

ratin

g st

atio

n on

th

eir

side

of

th

e Po

int

of

Inte

rcon

nect

ion

(PO

I.)

The

IC w

ill i

nter

conn

ect

X3-

008

with

the

DPL

sys

tem

via

the

tw

o ne

w d

istri

butio

n fe

eder

s.

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

3

This

pro

pose

d in

terc

onne

ctio

n w

ill b

e re

quire

d to

satis

fy th

e re

quire

men

ts o

utlin

ed in

IE

EE15

47 in

clud

ing

but n

ot li

mite

d to

ove

r/und

er v

olta

ge, o

ver/u

nder

freq

uenc

y an

d an

ti-is

land

ing

requ

irem

ents

. D

PL’s

syst

em p

rote

ctio

n gr

oup

will

nee

d to

rece

ive

the

prop

osed

se

tting

s for

revi

ew to

ens

ure

com

plia

nce

with

this

stan

dard

.

This

pro

pose

d in

terc

onne

ctio

n w

ill b

e re

quire

d to

satis

fy th

e re

quire

men

ts o

utlin

ed in

D

PL’s

“Te

chni

cal C

onsi

dera

tions

Cov

erin

g Pa

ralle

l Ope

ratio

ns o

f Cus

tom

er O

wne

d G

ener

atio

n” d

ocum

ent f

or u

nits

gre

ater

than

1 M

W.

DPL

’s sy

stem

pro

tect

ion

grou

p w

ill

need

to re

ceiv

e th

e pr

opos

ed se

tting

s and

ass

ocia

ted

sche

mes

for r

evie

w to

ens

ure

com

plia

nce

with

this

stan

dard

. If

the

IC e

lect

s to

use

a st

ep u

p tra

nsfo

rmer

with

a d

elta

hig

h si

de w

indi

ng, a

dditi

onal

m

easu

res a

re re

quire

d in

ord

er to

pre

vent

Tem

pora

ry-O

ver-

Vol

tage

(TO

V) d

urin

g ab

norm

al c

ondi

tions

. Th

ree

phas

e vo

ltage

sens

ing

mus

t be

inst

alle

d at

the

25 k

V si

de o

f th

e ge

nera

tor's

tran

sfor

mer

. PT’

s can

not b

e in

stal

led

on lo

wer

vol

tage

bus

. Thi

s re

quire

men

t can

be

avoi

ded

by u

sing

a g

roun

ded-

wye

/gro

unde

d-w

ye st

ep u

p tra

nsfo

rmer

.

Inve

rter R

equi

rem

ents

This

sect

ion

cont

ains

setti

ng re

quire

men

ts fo

r the

ope

ratio

n of

the

IC’s

pro

pose

d eq

uipm

ent.

The

inve

rter

at t

he D

G lo

catio

n sh

all h

ave

the

follo

win

g ca

pabi

litie

s:

� V

olta

ge fl

icke

r red

uctio

n th

roug

h dy

nam

ic V

AR

resp

onse

� R

amp

rate

con

trol

� SC

AD

A c

omm

unic

atio

ns

� C

urta

ilmen

t or o

ther

miti

gatio

n ab

ility

if h

igh

volta

ge w

ere

to o

ccur

� Lo

w v

olta

ge a

nd s

yste

m d

istu

rban

ce ri

de th

roug

h

� A

bilit

y to

rece

ive

and

resp

ond

to a

tran

sfer

trip

or S

CA

DA

sign

al

The

inve

rter s

hall

oper

ate

in a

ccor

danc

e w

ith th

e IE

EE 1

547

serie

s of s

tand

ards

that

hav

e be

en a

ppro

ved.

Whi

le in

verte

rs sh

ould

be

capa

ble

of v

olta

ge st

abili

zatio

n th

ru d

ynam

ic

VA

R re

spon

se a

nd c

apab

le o

f low

vol

tage

and

sys

tem

dis

turb

ance

ride

thro

ugh,

nei

ther

of

thes

e ca

pabi

litie

s sha

ll be

impl

emen

ted

until

such

tim

e th

at th

e IE

EE 1

547

serie

s of

stan

dard

s are

revi

sed

and

appr

oved

to in

clud

e st

anda

rds f

or th

ese

capa

bilit

ies.

At s

uch

time

as th

ese

revi

sed

stan

dard

s bec

ome

avai

labl

e, th

e PV

ow

ner/o

pera

tor s

hall

coop

erat

e w

ith th

e C

ompa

ny to

impl

emen

t the

se c

apab

ilitie

s with

setti

ngs a

ccep

tabl

e to

the

Com

pany

. U

ntil

such

tim

e, th

e in

verte

rs sh

all b

e ca

pabl

e of

ope

ratin

g at

a fi

xed

pow

er

fact

or v

alue

bet

wee

n 0.

95 le

ad a

nd 0

.95

lag

as sp

ecifi

ed b

y th

e C

ompa

ny. T

he v

alue

is

supp

lied

belo

w:

1.

Ope

rate

inve

rters

at u

nity

pow

er fa

ctor

(“PF

”)

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

4

Not

e: In

the

futu

re, t

he c

ompa

ny re

serv

es th

e ri

ght t

o is

sue

new

fixe

d po

wer

fact

or se

tting

re

quir

emen

ts (0

.95

lead

to 0

.95

lag)

if n

eces

sary

.

It

is th

e re

spon

sibi

lity

of th

e ow

ner

to s

ecur

e th

e in

verte

r fr

om a

ny u

naut

horiz

ed a

cces

s (in

clud

ing

phys

ical

and

rem

ote

acce

ss) w

hich

cou

ld a

lter s

ettin

gs o

r adv

erse

ly a

ffec

t the

in

verte

r’s a

bilit

y to

ope

rate

as

requ

ired.

Sec

urity

mea

sure

s sh

ould

incl

ude

utili

zing

sec

ure

pass

wor

d se

tting

s and

/or p

hysi

cal l

ocks

on

cabi

net d

oors

.

A m

utua

lly a

ccep

tabl

e m

eans

of

inte

rrup

ting

and

disc

onne

ctin

g th

e ge

nera

tor

with

a

visi

ble

brea

k, a

ble

to b

e ta

gged

and

loc

ked

out,

shal

l be

wor

ked

out

with

Com

pany

D

istri

butio

n En

gine

erin

g pe

rson

nel.

5. D

escr

iptio

n of

Fac

ilitie

s Inc

lude

d in

the

Faci

litie

s Stu

dy (D

PL S

cope

of W

ork)

� C

omm

unic

atio

ns –

Fib

er o

ptic

cab

le w

ill c

onne

ct T

odd

Subs

tatio

n to

the

IC’s

de

mar

catio

n ca

bine

t at t

he so

lar s

ite to

faci

litat

e D

PL’s

requ

irem

ents

for t

rans

fer t

rip a

nd

rem

ote

trip.

App

roxi

mat

ely

1.42

mile

s of 4

8SM

AD

SS a

eria

l cab

le a

nd 2

00 fe

et o

f un

derg

roun

d fib

er w

ill b

e us

ed.

Con

stru

ctio

n w

ill b

e on

the

new

ly in

stal

led

pole

s int

o th

e su

bsta

tion.

One

new

25

kV fe

eder

term

inal

will

be

inst

alle

d on

the

T1 tr

ansf

orm

er a

t Tod

d Su

bsta

tion

to c

onne

ct o

ne 1

0 M

W e

xpre

ss d

istri

butio

n ci

rcui

t.

One

new

25

kV fe

eder

term

inal

will

be

inst

alle

d on

the

T2 tr

ansf

orm

er a

t Tod

d Su

bsta

tion

to c

onne

ct o

ne 1

0 M

W e

xpre

ss d

istri

butio

n ci

rcui

t.

Esta

blis

h tw

o (2

) new

25

kV fe

eder

s with

954

AA

C p

rimar

y co

nduc

tors

from

the

Todd

Su

bsta

tion

to th

e ge

nera

ting

site

alo

ng S

keet

Clu

b R

oad

and

Har

per R

oad,

a d

ista

nce

of

appr

oxim

atel

y 1.

42 m

iles.

The

feed

ers w

ill b

e co

nstru

cted

on

the

sam

e po

le li

ne e

xcep

t th

ey w

ill se

para

te a

t the

sola

r site

and

at t

he su

bsta

tion.

The

T1

feed

er m

ust b

e co

nstru

cted

in o

rder

to c

ompl

ete

the

T2 fe

eder

. Th

is w

ork

will

incl

ude:

� In

stal

ling

appr

oxim

atel

y fo

rty-tw

o (4

2) n

ew 5

5’ w

ood

dist

ribut

ion

pole

s al

ong

Skee

t Clu

b an

d H

arpe

r Roa

ds in

Sta

te H

ighw

ay ri

ght o

f way

to

acco

mm

odat

e th

e ne

w 2

5kV

feed

ers

� In

stal

ling

appr

oxim

atel

y 8,

300

feet

of d

oubl

e ci

rcui

t 3 p

hase

954

AA

C

prim

ary

and

8,30

0 fe

et o

f 1-4

/0 A

AA

C n

eutra

l �

Perf

orm

ing

any

nece

ssar

y tre

e tri

mm

ing

and

rem

oval

alo

ng th

e pu

blic

ro

adw

ays

� In

stal

ling

one

(1) a

utom

atic

circ

uit r

eclo

ser a

t the

sola

r site

on

each

circ

uit

for a

tota

l of t

wo

(2) r

eclo

sers

Inst

allin

g on

e (1

) aer

ial p

rimar

y m

eter

clu

ster

at t

he so

lar s

ite o

n ea

ch

circ

uit f

or a

tota

l of t

wo

(2) m

eter

ing

clus

ters

DPL

will

inst

all a

min

imum

of t

hree

pol

es o

n th

e IC

sola

r site

for e

ach

feed

er.

One

pol

e w

ill b

e to

acc

omm

odat

e th

e pr

imar

y m

eter

clu

ster

, one

will

be

to a

ccom

mod

ate

the

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

5

auto

mat

ic c

ircui

t rec

lose

r and

the

final

pol

e w

ill b

e th

e se

para

tion

poin

t bet

wee

n D

PL

owne

d fa

cilit

ies a

nd IC

ow

ned

faci

litie

s for

the

circ

uit.

The

IC is

resp

onsi

ble

to ta

ke th

e ov

erhe

ad p

rimar

y 25

kV fe

ed fr

om th

at p

oint

on.

D

PL w

ill re

quire

the

capa

bilit

y to

rem

otel

y di

scon

nect

the

gene

rato

r fro

m th

e gr

id b

y co

mm

unic

atio

n fr

om it

s Sys

tem

Ope

ratio

ns fa

cilit

y. S

uch

disc

onne

ctio

n m

ay b

e fa

cilit

ated

by

eith

er a

gen

erat

or b

reak

er, a

line

recl

oser

, or o

ther

met

hod

depe

ndin

g up

on

the

spec

ific

circ

umst

ance

s and

the

eval

uatio

n of

the

Com

pany

. 6.

Tot

al C

ost o

f Dis

tribu

tion

Ow

ner F

acili

ties I

nclu

ded

in th

e Fa

cilit

ies S

tudy

A

ttach

men

t Fac

ilitie

s

$2,6

61,9

01

A

ttach

men

t Fac

ilitie

s with

15%

Con

tinge

ncy

$3,0

61,1

87

7. S

umm

ary

of th

e Sc

hedu

le fo

r Com

plet

ion

of W

ork

for t

he F

acili

ties S

tudy

Th

e ov

eral

l est

imat

ed ti

mel

ine

for t

his p

roje

ct is

app

roxi

mat

ely

18-2

2 m

onth

s fro

m th

e da

te o

f the

PJM

rele

ase

for d

esig

n/co

nstru

ctio

n. T

his t

imel

ine

may

be

able

to b

e im

prov

ed w

ith p

refe

rred

sys

tem

out

ages

. Th

e sc

hedu

le p

rovi

ded

is a

n es

timat

e of

the

nece

ssar

y tim

efra

mes

to c

ompl

ete

the

wor

k.

Subs

tatio

n D

esig

n, P

rocu

rem

ent a

nd C

onst

ruct

ion

18-

22 m

onth

s D

istri

butio

n Li

ne D

esig

n, P

rocu

rem

ent a

nd C

onst

ruct

ion

1

6-18

mon

ths

Out

side

Pla

nt C

omm

. Des

ign,

Pro

cure

men

t and

Con

stru

ctio

n 1

0-12

mon

ths

DPL

will

be

able

to m

eet t

he sc

hedu

le su

pplie

d by

the

IC fo

r thi

s PJM

que

ue p

roje

ct

prov

ided

that

the

IC e

xecu

tes t

he in

terc

onne

ctio

n ag

reem

ents

in th

e pr

oper

tim

efra

me

to

allo

w th

e de

sign

and

con

stru

ctio

n pe

riod

outli

ned

in th

is re

port.

B

. Tra

nsm

issi

on O

wne

r Fa

cilit

ies S

tudy

Res

ults

This

sect

ion

desc

ribes

faci

litie

s ide

ntifi

ed to

be

inst

alle

d, re

plac

ed, a

nd/o

r upg

rade

d by

D

PL to

acc

omm

odat

e th

e pr

ojec

t. D

urin

g de

taile

d de

sign

and

ana

lysi

s oth

er c

ompo

nent

s m

ay b

e in

dent

ified

for i

nsta

llatio

n or

repl

acem

ent d

ue to

this

inte

rcon

nect

ion.

1.

Tra

nsm

issi

on L

ines

- N

ew

Not

app

licab

le

2. T

rans

mis

sion

Lin

e –

Upg

rade

s N

ot a

pplic

able

3.

New

Sub

stat

ion/

Switc

hyar

d Fa

cilit

ies

Not

app

licab

le

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

6

4. U

pgra

des t

o Su

bsta

tion/

Switc

hyar

d Fa

cilit

ies

Wor

k ac

tiviti

es in

clud

e th

e in

stal

latio

n, re

plac

emen

t and

exp

ansi

on o

f exi

stin

g eq

uipm

ent a

nd

prot

ectiv

e re

layi

ng a

t Tod

d Su

bsta

tion

to c

reat

e an

add

ition

al fe

eder

pos

ition

on

both

the

T1 a

nd

T2 tr

ansf

orm

ers.

This

wor

k co

nsis

ts o

f the

follo

win

g:

Th

e ne

w T

1 fe

eder

will

con

sist

of t

he fo

llow

ing:

one

new

25

kV, 1

200A

, 20

kA p

ower

circ

uit

brea

ker,

with

rela

ted

disc

onne

ct sw

itche

s, an

d fo

unda

tion;

one

new

feed

er b

ay w

ith d

isco

nnec

t sw

itche

s, su

rge

arre

ster

s, st

ruct

ure

and

foun

datio

ns;

one

thre

e-ph

ase

set o

f 69k

V c

apac

itor

volta

ge tr

ansf

orm

ers,

stru

ctur

e an

d fo

unda

tion;

a p

re-f

abric

ated

con

trol h

ouse

with

rela

y, c

ontro

l an

d co

mm

unic

atio

n pa

nels

, AC

and

DC

supp

ly s

yste

ms,

and

foun

datio

ns;

grou

ndin

g, c

ondu

it,

cabl

e tro

ugh,

and

ston

ing;

con

trol c

able

s and

all

mis

cella

neou

s ite

ms f

or a

com

plet

e in

stal

latio

n.

The

prot

ectiv

e re

layi

ng w

ill c

onsi

st o

f new

fron

t-lin

e an

d ba

ck-u

p fe

eder

rela

ys a

nd o

ne se

t of

bus d

iffer

entia

l rel

ays.

A n

ew O

rion

LX- b

ased

rem

ote

term

inal

uni

t will

pro

vide

in

terc

onne

ctio

n to

all

prot

ectiv

e an

d co

ntro

l rel

ays.

Fo

r the

T1

feed

er, t

he w

ork

incl

udes

the

inst

alla

tion

of th

e fo

llow

ing

new

equ

ipm

ent:

� O

ne (1

) 25

kV, 1

200

A, 2

0 kA

circ

uit b

reak

er

� Si

x (6

) 25

kV, 1

200

A si

ngle

-pol

e ho

okst

ick

disc

onne

ct sw

itche

s �

Thre

e (3

) 25

kV st

atio

n cl

ass s

urge

arr

este

rs

� Th

ree

(3) 6

9 kV

CV

T’s

� O

ne (1

) fro

nt-li

ne &

bac

k-up

feed

er re

layi

ng p

rote

ctio

n pa

nel

� O

ne (1

) bus

diff

eren

tial r

elay

ing

prot

ectio

n pa

nel

� O

ne (1

) sup

ervi

sory

pan

el (O

rion

LX a

nd e

ther

net s

witc

h)

� O

ne (1

) gal

vani

zed

stee

l thr

ee-p

hase

CV

T st

and

� O

ne (1

) pre

-fab

ricat

ed c

ontro

l hou

se w

ith A

C a

nd D

C a

uxili

ary

syst

ems

� O

ne (1

) 25k

V b

ox st

ruct

ure

bay

� Lo

t of c

ondu

ctor

s, co

nnec

tors

, and

insu

lato

rs fo

r the

bus

syst

ems

� Lo

t of s

tatio

n gr

ound

con

duct

ors a

nd c

onne

ctor

s �

Lot o

f con

trol c

able

s �

Lot o

f cab

le tr

ench

and

con

duit

for n

ew ra

cew

ay sy

stem

s �

Lot o

f fou

ndat

ions

for a

bove

list

ed e

quip

men

t

The

new

T2

feed

er w

ill c

onsi

st o

f the

follo

win

g: o

ne n

ew 2

5 kV

, 120

0A, 2

0 kA

pow

er c

ircui

t br

eake

r, w

ith re

late

d di

scon

nect

switc

hes,

and

foun

datio

n; o

ne th

ree-

phas

e se

t of 6

9kV

cap

acito

r vo

ltage

tran

sfor

mer

s, st

ruct

ure

and

foun

datio

n; g

roun

ding

, con

duit,

cab

le tr

ough

, and

ston

ing;

co

ntro

l cab

les a

nd a

ll m

isce

llane

ous i

tem

s for

a c

ompl

ete

inst

alla

tion.

The

pro

tect

ive

rela

ying

w

ill c

onsi

st o

f new

fron

t-lin

e an

d ba

ck-u

p fe

eder

rela

ys a

nd o

ne se

t of b

us d

iffer

entia

l rel

ays.

For t

he T

2 fe

eder

, the

wor

k in

clud

es th

e in

stal

latio

n of

the

follo

win

g ne

w e

quip

men

t: �

One

(1) 2

5 kV

, 120

0 A

, 20

kA c

ircui

t bre

aker

Six

(6) 2

5 kV

, 120

0 A

sing

le-p

ole

hook

stic

k di

scon

nect

switc

hes

� Th

ree

(3) 2

5 kV

stat

ion

clas

s sur

ge a

rres

ters

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

7

� Th

ree

(3) 6

9 kV

CV

T’s

� O

ne (1

) set

of f

ront

-line

& b

ack-

up fe

eder

rela

ys

� O

ne (1

) bus

diff

eren

tial r

elay

ing

prot

ectio

n pa

nel

� O

ne (1

) gal

vani

zed

stee

l thr

ee-p

hase

CV

T st

and

� Lo

t of c

ondu

ctor

s, co

nnec

tors

, and

insu

lato

rs fo

r the

bus

syst

ems

� Lo

t of s

tatio

n gr

ound

con

duct

ors a

nd c

onne

ctor

s �

Lot o

f con

trol c

able

s �

Lot o

f cab

le tr

ench

and

con

duit

for n

ew ra

cew

ay sy

stem

s �

Lot o

f fou

ndat

ions

for a

bove

list

ed e

quip

men

t

Any

nec

essa

ry v

aria

nces

and

per

mits

to p

erfo

rm th

e ab

ove

wor

k w

ill b

e ob

tain

ed.

Out

ages

are

ava

ilabl

e fr

om fa

ll to

sprin

g.

It

is D

PL p

ract

ice

to u

se se

para

te c

ontra

ctor

s for

: �

Inst

alla

tion

of fo

unda

tions

All

prim

ary

and

rela

ying

wor

k

� Te

stin

g an

d co

mm

issi

onin

g

D

PL w

ill re

view

the

IPR

cab

inet

dra

win

g PR

IOR

TO

TH

E PU

RC

HA

SE O

F EQ

UIP

MEN

T th

en te

st fo

r pro

per r

elay

ope

ratio

n af

ter i

nsta

llatio

n of

the

requ

ired

prot

ectio

n eq

uipm

ent a

t the

sola

r site

. 5.

Met

erin

g &

Com

mun

icat

ions

DPL

’s M

eter

Dep

artm

ent w

ill c

onst

ruct

two

(2) 2

5kV

thre

e ph

ase

prim

ary

met

erin

g cl

uste

r mou

nt a

ssem

blie

s with

inst

alle

d m

eter

ing

devi

ce e

quip

ped

with

load

pro

file,

te

lem

etry

, and

I/O

s, in

clud

ing

DN

P ou

tput

s. A

con

tract

or o

r a D

PL o

verh

ead

line

crew

w

ill b

e re

quire

d to

put

the

clus

ter m

ount

ass

embl

ies i

nto

serv

ice,

and

Met

er D

epar

tmen

t te

chni

cian

s will

com

plet

e th

e se

cond

ary

wiri

ng a

nd re

late

d m

eter

wor

k at

the

base

of t

he

met

erin

g po

les.

A m

eter

tech

nici

an w

ill a

ssis

t the

con

tract

or o

r DPL

ove

rhea

d lin

e cr

ew

in e

nerg

izin

g th

is e

quip

men

t. Th

e m

eter

tech

nici

an w

ill a

lso

prog

ram

and

inst

all t

wo

solid

st

ate

mul

ti fu

nctio

n m

eter

s (Pr

imar

y &

Bac

kup)

for e

ach

new

met

erin

g po

sitio

n.

The

IC w

ill b

e re

quire

d to

mak

e pr

ovis

ions

for a

voi

ce q

ualit

y ph

one

lines

with

in

appr

oxim

atel

y 3

feet

of e

ach

met

erin

g po

sitio

n to

faci

litat

e re

mot

e in

terr

ogat

ion

and

data

co

llect

ion

by D

PL.

Tele

met

ry

It is

the

IC’s

resp

onsi

bilit

y to

send

the

data

, tha

t PJM

and

the

Com

pany

requ

ires,

dire

ctly

to

PJM

. Th

e IC

will

gra

nt it

s per

mis

sion

to P

JM fo

r PJM

to se

nd th

e C

ompa

ny th

e fo

llow

ing

tele

met

ry d

ata

that

the

IC se

nds t

o PJ

M: r

eal t

ime

meg

awat

ts, m

egav

ars,

volts

, am

pere

s, ge

nera

tor s

tatu

s, an

d in

terv

al m

egaw

att-h

ours

, and

meg

avar

-hou

rs.

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

8

6. E

nviro

nmen

tal,

Rea

l Est

ate

and

Perm

ittin

g Is

sues

Rea

l Est

ate

Rea

l Est

ate

invo

lvem

ent w

ill b

e a

curs

ory

chec

k of

exi

stin

g pr

oper

ty ri

ghts

alo

ng th

e pr

opos

ed d

istri

butio

n ro

ute

and

ther

e m

ay a

lso

be th

e ne

ed to

acq

uire

righ

ts fo

r pol

e an

chor

s and

guy

wire

s in

a fe

w lo

catio

ns.

Als

o, R

eal E

stat

e m

ay b

e in

volv

ed in

obt

aini

ng

the

nece

ssar

y St

ate

Hig

hway

per

mits

. En

viro

nmen

tal

The

Envi

ronm

enta

l Dep

artm

ent w

ill p

rovi

de a

che

ck o

f ava

ilabl

e pu

blic

dat

a as

far a

s w

etla

nds a

nd th

reat

ened

and

end

ange

red

spec

ies a

re c

once

rned

. Th

ey w

ill p

rovi

de in

put

to m

inim

ize

any

impa

cts d

urin

g th

e de

sign

pha

se o

f the

pro

ject

. Th

ey w

ill p

rovi

de a

ny

addi

tiona

l pro

ject

revi

ew, a

vian

des

ign

revi

ew a

nd fi

nal p

roje

ct p

erm

ittin

g th

at is

ne

cess

ary.

Thi

s est

imat

e as

sum

es th

e ne

ed fo

r per

mits

and

revi

ews m

ay b

e re

duce

d by

pl

acin

g th

e po

le li

ne a

long

the

Stat

e H

ighw

ays.

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

9

7.

Sum

mar

y of

Res

ults

of S

tudy

T1

Fee

der

Pr

ojec

t Nam

e: X

3-00

8 To

dd 6

9 kV

In

dire

ct

Dire

ct

TOTA

L ($

) 10

MW

T1

Tran

sfor

mer

and

New

Fee

der

Mat

eria

l La

bor

Mat

eria

l La

bor

Rea

l Est

ate

1

,400

8,6

00

10

,000

S

yste

m P

lann

ing

400

2,60

0 3,

000

Dis

tribu

tion

Ove

rhea

d C

onst

ruct

ion

74,7

65

1

16,6

32

250,

050

390,

383

831,

830

Proj

ect M

anag

emen

t & S

peci

al B

illin

g

5

00

3,

500

4,00

0 O

utsi

de P

lant

Com

mun

icat

ions

2

,400

17

,000

13

,867

10

5,45

5 13

8,72

2 S

yste

m P

rote

ctio

n

5

00

3,

500

4,00

0 In

terc

onne

ctio

n A

rrang

emen

ts

400

2,60

0 3,

000

Sys

tem

Ope

ratio

ns

400

2,60

0 3,

000

Met

erin

g

1

,141

196

15

,159

2,

604

19,1

00

Env

ironm

enta

l

900

6,

600

7,50

0 S

ubst

atio

n E

ngin

eerin

g &

Con

stru

ctio

n

30

,000

25

,000

34

1,00

0 29

4,00

0 69

0,00

0 TO

TAL

CO

ST

108,

306

163,

328

620,

076

822,

442

1,71

4,15

2 15

% C

ontin

genc

y 16

,246

24

,499

93

,011

12

3,36

7 25

7,12

3

GR

AN

D T

OTA

L

124,

552

187,

827

713,

087

945,

809

1,97

1,27

5 T2

Fee

der

Proj

ect N

ame:

X3-

008

Todd

69

kV

Indi

rect

D

irect

TOTA

L ($

) 10

MW

T2

Tran

sfor

mer

and

New

Fee

der

Mat

eria

l La

bor

Mat

eria

l La

bor

Rea

l Est

ate

S

yste

m P

lann

ing

D

istri

butio

n O

verh

ead

Con

stru

ctio

n

50

,200

60

,164

16

0,52

9 23

0,76

1 50

1,65

4 Pr

ojec

t Man

agem

ent &

Spe

cial

Bill

ing

Out

side

Pla

nt C

omm

unic

atio

ns

2

25

9

48

1,50

0 6,

322

8,99

5 S

yste

m P

rote

ctio

n

Inte

rcon

nect

ion

Arra

ngem

ents

Sys

tem

Ope

ratio

ns

210

2,79

0 3,

000

Met

erin

g

1

,141

196

15

,159

2,

604

19,1

00

Env

ironm

enta

l

Sub

stat

ion

Eng

inee

ring

& C

onst

ruct

ion

11,0

00

17,0

00

149,

000

238,

000

415,

000

TOTA

L C

OST

62

,566

78

,518

32

6,18

8 48

0,47

7 94

7,74

9 15

% C

ontin

genc

y 9,

385

11,7

78

48,9

28

72,0

72

142,

163

GR

AN

D T

OTA

L

71,9

51

90,2

96

375,

116

552,

549

1,08

9,91

2

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

10

Gen

erat

ion

proj

ects

mee

ting

IRS

"Saf

e H

arbo

r" p

rovi

sion

s gen

eral

ly d

o no

t inc

ur "C

IAC

" (C

ontri

butio

n in

Aid

to C

onst

ruct

ion)

, a ta

x co

llect

ed b

y th

e ut

ility

for t

he st

ate

or fe

dera

l go

vern

men

t. If

for a

ny re

ason

, "C

IAC

" wou

ld b

e re

quire

d fo

r thi

s pro

ject

, it w

ould

be

the

resp

onsi

bilit

y of

the

party

ow

ning

the

gene

rato

r to

pay

this

cos

t.

DPL

rese

rves

the

right

to c

harg

e th

e IC

ope

ratio

n an

d m

aint

enan

ce e

xpen

ses t

o m

aint

ain

the

IC’s

at

tach

men

t fac

ilitie

s, in

clud

ing

met

erin

g an

d te

leco

mm

unic

atio

ns fa

cilit

ies,

owne

d by

DPL

. Sc

hedu

les a

nd A

ssum

ptio

ns

This

pro

ject

con

stru

ctio

n sc

hedu

le o

f 18-

22 m

onth

s was

com

plet

ed w

ith th

e as

sum

ptio

n th

at it

w

ould

not

be

impa

cted

by

stor

m d

amag

e an

d re

stor

atio

n, ti

me

of y

ear l

imita

tions

, per

mitt

ing

issu

es, o

utag

e sc

hedu

ling,

syst

em e

mer

genc

ies,

and

cont

ract

or a

nd e

quip

men

t ava

ilabi

lity.

It

is im

porta

nt to

not

e th

at th

is p

roje

ct w

ill b

e in

corp

orat

ed in

to th

e ex

istin

g pr

ojec

t wor

k lo

ad a

t D

PL a

t the

tim

e of

con

tract

exe

cutio

n. I

f the

wor

kloa

d of

exi

stin

g pr

ojec

ts is

ext

ensi

ve, r

esou

rce

cons

train

ts m

ay c

ause

this

pro

ject

to b

e de

laye

d be

yond

the

proj

ecte

d in

-ser

vice

dat

e.

© P

JM In

terc

onne

ctio

n 20

14. A

ll rig

hts r

eser

ved.

X

3-00

8 To

dd 6

9 kV

11

Atta

chm

ent #

1

Todd

69/2

5kV

Subs

tatio

n

25K

VBu

s

Todd

Subs

tatio

n

T169

/25

kV25

MV

A

New

Feed

erM

Dxx

xx

Inve

nerg

ySo

lar

Dev

elop

men

tLLC

Prop

osed

Gen

erat

or10

MW

Met

erow

ned

ByD

PL25

KV

Bus

T269

/25

kV28

MV

AA

ppro

xim

atel

y1.

42m

ileso

f95

4A

AC

POI

M

VIP

ERRe

clos

er

New

Feed

erM

Dxx

xxPr

opos

edG

ener

ator

10M

W

Met

erow

ned

ByD

PL

App

roxi

mat

ely

1.42

mile

sof

954

AA

C

VIP

ERRe

clos

er

MD

2221

East

New

Mar

ket

69kV

Sour

ce

Easto

nPr

esto

n69

kVSo

urce

POI

M

MD

2267

12K

VBu

sT3

69/1

2kV

10.5

MV

A

MD

0439

Alle

n69

kVSo

urce

Vie

nna

69kV

Sour

ce

POI

Poin

tofI

nter

conn

ectio

n

'alo) qleg :ot lleut ^q

1o (dor palu;rd llulqns

S t lZ't, 1o-l :aleo

NollvwuoJNl ]vNoIttoov irslnOru rHw E seluadord ruolsrr.l uo lflJlr lsuinov oN aneq lltr pafo.ra ",n E

salyedord rgolslq uo Sl)llll ISUIAOV ereq ;;rm pafolA ,qf Esaruadord )r.rols!r.l uo rllltl oN a^eq ;1rm paford aqr flSNOIIIONO) HII/IA l)llJl ISuIAOV ON eneq ;;rrvr pafo.ta aq.l f] peJle lp[uatod Jo eare aql ut s]tIuIdOUd )tUOlStH ON are aJerll

,c

?

:uollPu!uralao IHUII

'()la ,sasn ;ern1;nt1r6e'pado;anap'paulu 'papoo/$) eare t>aford ul sasn puel luasard pue lsed;o uot1d1::sa6 B

'saJnpn4s pue s6ugp;1nq ;;e;o sa6eu.r; 6ulpnpu1 alrs lrafo.td aql Eu;rrroqs 1lelt6tR ro 1u;rd) sqdel6oloq6 X's6urnnerq uorDnrlsuoJ.lo\pue'ueld alts !IolAlo ado>5 'uo11d1rlsaq nafold ffi

'palteu rlrea;: na[ord ]o sauepunoq pue uor]p)ol rlllM uolpas deyrl pen6 sgsn Io qder6oloqd lertay E]'luaLuutof ]noqlli\^ peurnlar aq ro sr(e1ap u! llnsal ,(eu sleiltuqns alalduorul 'patlnbat ale sluaurq)Plle llV

:sluauq)el}V

au e51 uodag\pulslc\/q.radord

suorle6rlsaru g 1e:16o1oaqrre ol pa[qns r(lsnotAeld

luauuureno6 lero; e r(q lt.lolstq paleu6rsaq I seruadord )!.lo]s!H ]o,Oo]uanul pue1,fuey1 aq] ul papnl)ul flIHhl

^q plaq lueuresee ue o1 lrafqns f] ralsg6ag leuor]eN aq] ul patsl"l I :(elqerlldde lle llaq)) saruado.rd se^lo^ur paford s1q1

'atueqtn$!p punorb leu!ulru qtlrvr pauueld rtg;1re; re;os a;ers {r11;tn aq plnom stql:uo1ld;r>sa6 leuotltppv\.laqlO

spu e;tapys(eMrateg/au! laloqS nuorlelrpqeilauT6ullapouag f]

a)uPqlnlsrcl punoig/uollene:q [}uorlrlotuag f, uorpnrlsuoJ /vlaN

sllpar) xel uorlpllllqpLlau lp.rapel ro a1e15 f:(alqerldde lle l)aql) sapry)ulpa[ord stql tr

o8_r.uorssrruuro) a)r^ras )!lqnd cw'('r1a llrurad l9f/l6N 19SOl

lonu:* raldeql 'EIoz loueol lllE puo6 't'a) asuelslsse

JaLllo Jo 'slured 'tu1pun1losaf,Jnos alels pue leJapaj ls!'l

EUltpar) xPI luaulsa^ul

(alqEr!ldde r!)raqtunN 6up;re,r1t1urra67pe[or6

aueN l!urrad7urer6o167l(:ua6yadl(1l(>ua6y

:uopdyrsa6 pa[or6

>1aar1 adoqr(qsreylIenruateMEt8'SLapnr16uo1LL9'8€apnllel :(uMou)| l) saleutproo)

ow lrot,0tutrlfurt!fpeog radre;1ssarppv

:uo!le)o-I pafor6

€rr9-0r9 (roE) r+raqurnN euoqdtuor':1;(6raua^uI@Jal IIttlalleuJl

II)

sserppV 6u11;e61

eueN peluo)

9bozzdtzerur6rylalelsq)rnLl) sllel

laaJls ael 'N 0z I

,(rua6y/ueduo3lalllw )ul

:pe1uo1 l(rerup6

Jalsaq)roo,0uno)retue) relos ppolatueN t:aford

TSNUJ i 1:e,!:l;1.:*

.l

"t\'.)tll( ).l sll I(l\\'l.tuvt\

1C,;# r,l,r/olaqunp 6o1 I

:pa^tareu

A]NO lsn lHl,ll

s6uDleuapun lerepal pue alels uo OdHSOW

Asnll le)ltolslH puel^Jew aq] txolj sluaululo) lo, ]senbeu ,S'Iufuol l,l]nlu l)Iroud

Cultural Resource Assessment for the

Todd Solar Center Site

Hurlock, Dorchester County, Maryland

Prepared for

Invenergy, LLC

One South Wacker Drive

Suite 1800

Chicago, Illinois 60606

Prepared by

Mechelle Kerns, PhD, RPA

Kerns CRM Consultants, LLC

94 West Earleigh Heights Road 410-409-5187

Severna Park, Maryland 21146 www.KernsCRMConsultants.com

October 15, 2015

Cultural Resource Assessment for the Todd Solar Center Site,

Hurlock, Dorchester County, Maryland

Table of Contents

Figures............................................................................................................................................. 1

Introduction ..................................................................................................................................... 2

Property Description ....................................................................................................................... 5

Cultural Context .............................................................................................................................. 6

Regional Prehistory ..................................................................................................................... 6

Paleo-Indian Period ................................................................................................................ 6

Archaic Period ........................................................................................................................ 6

Woodland Period .................................................................................................................... 6

Prehistoric Occupation in the Immediate Area ....................................................................... 7

Historical Context ....................................................................................................................... 8

Site Conditions .............................................................................................................................. 10

Local Environmental Setting .................................................................................................... 10

Topography ............................................................................................................................... 10

Soils........................................................................................................................................... 11

Surface Conditions and Signs of Disturbance .......................................................................... 12

Historic Resources ........................................................................................................................ 14

Archaeological Resources ............................................................................................................. 15

Planned Alterations ....................................................................................................................... 16

Findings and Recommendations ................................................................................................... 18

Bibliography ................................................................................................................................. 19

Appendix I: Qualifications ............................................................................................................ 21

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

Figures

Figure 1: Project Location in Maryland .......................................................................................... 2

Figure 2: Maryland Archaeological Research Units Map .............................................................. 3

Figure 3: Maryland Watershed Map ............................................................................................... 3

Figure 4: Project Location 1988 Rhodesdale USGS Topo Map ..................................................... 4

Figure 5: Proposed Project Property ............................................................................................... 5

Figure 6: Project Area Topography .............................................................................................. 11

Figure 7: Project Area Typical Soil Profile .................................................................................. 11

Figure 8: Project Area, Wright’s Branch ...................................................................................... 12

Figure 9: Project Area, After Harvest ........................................................................................... 13

Figure 10: Project Area, Under Cultivation .................................................................................. 13

Figure 11: Recorded Sites in the Immediate Area ........................................................................ 15

Figure 12: Typical Solar Panel Facility ........................................................................................ 16

Figure 13: Planned Alterations to the Property............................................................................. 17

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

2

Introduction

Invenergy, a developer of solar power collection and transmission utility sites, is considering a

location for the installation of a new facility. This report addresses the potential for historical

and cultural resources (Phase Ia archaeological and historic structures survey) within the project

area and the Area of Proposed Effect (APE). The proposed site for the Todd Solar Center is

located on the near the town of Hurlock, on Harper Road, on the Eastern Shore of Maryland in

Dorchester County, approximately 14 miles southwest of the county seat of Cambridge (Figure

1). The site is located within the Coastal Plain Province, Maryland Archaeological Research Unit

3 - Nanticoke-Wicomico-Manokin-Big Annemessex Drainage (Figure 2).

Figure 1: Project Location in Maryland

The project property is located approximately 1.5 miles southwest of Hurlock, Maryland, a small

town of 2.88 square miles at the intersection of MD Routes 331 and 392. The project area is not

within the town boundaries. The immediate area is rural and agricultural.

The site is located within the Nanticoke River watershed (Figure 3). The property consists of a

143.3-acre parcel of agriculture land currently under cultivation with soybeans and potatoes. The

parcel is bisected by Wright’s Branch that runs into Marshyhope Creek, a tributary of the

Nanticoke River. The property’s eastern boundary is approximately one-quarter mile from

Marshyhope Creek.

The property is bounded by Harper Road to the east, Ennals Rd to the south, Skeet Club Road to

the north, and the Hurlock Sewage Treatment Plant (on Jones Villa Drive) to the west: large

wastewater treatment ponds abut the project property (Figure 4).

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

3

Figure 2: Maryland Archaeological Research Units Map

Figure 3: Maryland Watershed Map

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

4

Figure 4: Project Location 1988 Rhodesdale USGS Topo Map

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

5

Property Description

The proposed project area is situated in a rural setting abutting a wastewater treatment plant and

levied management ponds. The 143.8-acre site has been cleared of vegetation, save a buffer of

trees that bisects the property, following a creek that runs through the parcel (Figure 5). The

land is flat with virtually no variation in elevation. It is currently utilized a farmland and has

been such for the last century. There is very little residential development in the immediate area

with the largest concentration of housing located 1.5 miles to the northwest.

Figure 5: Proposed Project Property

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

6

Cultural Context

Regional Prehistory

The following summaries of regional prehistory of the Potomac River Valley and the Mid-

Atlantic Region have been taken from the works of LeeDecker, Martin, and Friedlander (1988)

and Weinberg, Lawrence and Schopp (2007). The prehistory of the Potomac River Valley and

Mid-Atlantic region has been traditionally divided into three major periods, the Paleo-Indian,

Archaic, and Woodland. A fourth time period, the Contact Period, marks the final phase of

occupation by Native American groups in the Mid-Atlantic region.

Paleo-Indian Period (circa 11,000 to 8,000 B.C.) is characterized by a hunting and gathering

subsistence pattern, followed by small kin-base bands who hunted cold-adapted animals such as

caribou, mastodon, and woodland bison (Weinberg, Lawrence and Schopp 2007). Fish and

foraging for plant resources were also presumably important in their diet. Paleo-Indian finds in

Maryland are poorly represented, with only a few intact sites including the Higgins Site and over

a hundred isolated stone tools found (Dent 1995 and Ebright 1992).

Archaic Period (circa 8,000 to 1000 B.C.) lifeways are characterized by hunting and gathering

of a variety of food resources within a relatively well-defined territorial area, while continuing

the traditions from the Paleo-Indian Period. Settlements expanded into more diverse

environments, gathering a wide variety of shellfish, fish, game and plant food resources such as

nuts, berries, and roots (Dent 1995). The appearance of the Corner-Notched Tradition (7,500-

6000) and the Bifurcate Tradition (6,800 to 6,000) represent tool style changes characteristic of

the Early Archaic Period.

While the Middle Archaic tool kits continued to resemble those of previous periods, several

types of ground-stone tools were added for processing an expanded resource base. A variety of

grinding tools, such as mortars and pestles, indicate the increased reliance on plants in their diet.

The Late Archaic Period (circa 4,000 to 1000 B.C.) is marked by a greater emphasis on local

resource exploitation. Settlement patterns are found more along interior drainages, with larger

social groupings and increased sedentism (Mouer 1991 and Steponaistis 1980). Regionally,

evidence for permanent housing began to appear at this time (Griffin 1978). The establishment

of extensive trade networks and the introduction of complex mortuary practices are characteristic

of this period (Thomas 1973). Carved, lug-handled steatite bowls are one of the most noted

types of artifacts to be introduced to the Chesapeake Bay Region, indicating a more sedentary

pattern of existence (Dent 1995 and Tuck 1978).

Woodland Period (circa 1,000 B.C. to A.D. 1600) is better known than the Paleo-Indian and

Archaic Periods. The Early Woodland Period (1,000 - 300 B.C.) represents an increased

sedentary lifestyle for the native population, with larger, long-term sites being serviced by

outlying extraction sites (Mouer 1991). Domesticated cultigens, such as corn, beans, and squash,

together with wild glasses, such as amaranth and chenopodium, where gradually incorporated

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

7

into the daily diet. The flaked tool industry reflects Late Archaic technology with small bifaces,

drills, scrapers, and utilized flakes. Antler and bone tools have been recovered as well (Dent

1995). A rapid rise in ceramic technology flourished during the Early Woodland Period. The

earliest ceramics, Marcey Creek wares, were tempered with crushed steatite and formed in a

similar fashion as steatite bowls of the previous period (Mouer 1991). Other types of ceramics,

including Selden Island, Bushnell, and Croaker Landing wares, are possibly distinctive forms for

the Chesapeake Bay area (Custer 1989). Accokeek wares, featuring sand and quartz temper and

coil construction, eventually replaced Marcey Creek ceramics (Steponaitis 1980 and Wright

1973).

The Middle Woodland Period (300 B.C. to A.D. 900) witnessed the continued elaboration of

mortuary practices, including burial mounds and elaborate, exotic ceremonial grave goods

related to the Adena culture (Griffin 1967). These grave practices and goods indicate a shift

from a band level of social organization to complex rank societies, along with the emergence of

extensive trade associations beyond the immediate interior of Maryland. Pottery styles

continued to shift. Popes Creek, a thick-walled, and sand-tempered, net-impressed ware, and

Mockley, a shell-tempered cord-and net-impressed ware, are two dominant styles (Custer 1989,

Dent 1995, Steponaitis 1980 and Wright 1973).

In the Late Woodland Period (A.D. 900 to 1607), settlement patterns begin to reflect permanent

towns with a subsistence base focused on cultivated foodstuffs, such as corn, beans, and squash.

Floodplain locales are the favored locations for villages, based on the availability of fertile

bottomland soils for agricultural practices. Smaller base camps and procurement sites tend to

serve as specialized function sites with periods of multiple re-use. Ceramic diversity continues,

with a variety of motifs likely associated with the borrowing of designs from other societies

through established trade networks. Food sources were diverse and plentiful, including shellfish

and anadromous fish, nuts, starchy tubers, amaranth and goosefoot (Dent 1995).

Prehistoric Occupation in the Immediate Area

During the contact period (post 1607) and throughout the 17th century, the colony of Maryland

generally had good relations with the native inhabitants through a number of treaties. Some

persistent issues that caused strife were due to inter-tribal relations that arose when groups

traveled into or out of competing territories. The names of native groups on the Eastern Shore of

Maryland are memorialized in the names of the rivers that flow into the Chesapeake Bay and the

Atlantic Ocean; Wicomiss, Choptank, Nanticoke, Assteague, Pocomoke and Accomac (Dent

1995). The Choptank and Nanticoke groups are associated with Dorchester County, Maryland

and the adjacent area of what is now Delaware. The territories they occupied are related to the

watersheds that share their name. The proposed project area is located between the Choptank (to

the west) and Nanticoke (to the west) Rivers.

The Nanticoke Indians, and other groups on the Eastern Shore present during the initial contact

period (early 17th

century), do not appear to have the numbers or political groupings as those on

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

8

the Western Shore such as the Powhatan and Susquehannocks (Dent 1955). Of the groups

occupying the mid-shore (in sections of modern Maryland and Delaware) region during the Late

Woodland, the Nanticoke consisted of approximately 650 people (Dent 1995; after Feest 1978).

They were considered a distinct group that occupied the “… territory bounding the drainage

system of the Nanticoke River.” (Porter 1979: 326). As with many of the Algonquin associated

tribal groups in Tidewater Region, the Nanticoke began to leave the Maryland and Delaware

region in the mid-eighteenth century after agreements with colonial governments failed and after

white settlers did not honor Indian-land boundaries (Porter 1979). Many groups moved north into

the Pennsylvania but some remained on the Eastern Shore up to the period of the American

Revolution (Porter 1979).

Historical Context

Dorchester County, Maryland was formed by 1669 from sections of Somerset (1666) and Talbot

(1662) Counties. The countryseat of Cambridge was established by 1684. As with most colonial

settlement in the Chesapeake region, the navigable rivers and adjacent areas were settled first,

with interior settlement by subsequent generations. By 1790, Dorchester County had nearly

16,000 residents with 30% percent of the population consisting of slaves but the majority of the

population was concentrated near Cambridge, the seat of government and the court, and along

the Choptank River (US Census 1996).

The Town of Hurlock was not part of the colonial period development but was one of the towns

established along the railways in Maryland during the railroad build-out after the US Civil War

(mid 19th

century). The town is located at a crossroads and was not incorporated until 1892. It

was first settled in 1869 after to the construction of the Dorchester and Delaware Railroad. The

first resident and businessman in the area was John M. Hurlock. His storehouse was constructed

the year the rail line was complete in 1869 and he built a house in 1872: the town is named for

him (Jones 1902). By 1902, the town had 450 residents (Jones 1902). The most significant

period of growth was from 1890 to 1930. Currently, Hurlock is the second largest town in

Dorchester County and has a large historic district (D-653) (MHT 2008).

The subject property is currently owned by W & J McWilliams Farms, LLC and they have held

the property since 2009. The previous owner, Warren M. Saunders purchased in the land,

(consisting of three tracks) in 1979 from Ruth Ann Gadekar who inherited the land from her

father Samuel Harold Phillips in 1971 (Dorchester County 1971). Previous to 1971, the subject

property was owned by Olin P Conway (1925), George Hertzog (1907) and John L. and Charles

M Scott (1905). The Scotts purchased the land from John P. and Sarah R. Harper (1882) and it

was combined with a track from D W Davis (1899). In 1882, a 74-acre section of the parcel was

conveyed from Thomas Hubbert to the Harpers and is referred to as “being part of a track of land

called Airey’s Chance” (Dorchester County 1882). Thomas Hubbert purchased the land from

Robert W. and Mary Randall in 1879 and property the was also referred to as part of “Airey’s

Chance.” The Randalls had held it prior to 1872: they purchased it from Lewis Ross and Caleb

Shepherd (Dorchester County 1879). Prior to 1872, the land records did not provide chain-of-

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

9

title information. However, the track of Airey’s Chance was patented by John Pitt Airey in 1766

and was made up of parts of three previously patented parcels; Govert’s Chance (1704), Brooms

Chance (1704) and True Dealing (1686) consisting of 563 ½ acres (Dorchester County 1766).

The numerous conveyances in the 19th

century appear to be related to investments in the land

surrounding Hurlock and the development related to the railroad. A number of the owners lived

outside of the state. Land records indicate that it has historically been part of larger parcels and

used and/or leased for farming not residential occupation.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

10

Site Conditions

Local Environmental Setting

As with much of the Eastern Shore, Dorchester County is sparsely populated with little

development. The majority of land use is agricultural or recreational due to the many waterways

and nature areas. “Dorchester County’s primary economies are agriculture and forestry-based.

Seafood processing from catching, cleaning, packing, and shipping, to the preparation of

seafood- is the primary economy in many of the village areas” (Cole 2008: 4). According to the

Maryland Department of the Environment,

Dorchester County covers approximately 354,870 land acres. Forty-eight percent (48%)

or 170,338 acres are zoned agricultural. Agricultural land dominates most of the

northeast portion of the county. Approximately 4% of Dorchester’s total land area is

developed. The remaining area is comprised of resource lands including forests,

agricultural lands, and wetlands. Tidal wetlands account for roughly 25% of the county’s

land area. Dorchester County’s wetlands account for approximately 39% of the entire

state’s wetlands (MDNR 2000).

As of 2005, “…woodland is a dominant feature of Dorchester County and… commercial

woodland consists of good quality loblolly pine as well as upland oaks, sweetgum, blackgum,

Virginia pine, holly, beech, or red maple, depending on soil wetness” (DSCD 2000:6).

The proposed project site in Hurlock is located between the Choptank and Nanticoke Rivers with

many feeder streams in the area. The two nearest bodies of water are Wrights Branch (which

bisects the project property) and Marshyhope Creek, a tributary of the the Nanticoke River. The

intersection of the Marshyhope Creek and the Nanticoke is approximately 7.5 miles downstream

from the project area. According to the Maryland Department of the Environment, “Marshyhope

Creek is existing stream valley greenways. This corridor is undeveloped and consists of

wetlands, marsh, and wooded banks that provide valuable habitat and stream protection”

(MDNR 2000).

Topography

Generally, the Eastern Shore of Maryland is flat with very little vibration in elevation. The

highest point in Dorchester County is at 57 feet AMLS between the upper reaches of the

Choptank and Nanticoke Rivers (MGS 2008). The proposed project area is nearly level at 25

AMSL and slopes to the southeast as it approaches the Marshyhope Creek.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

11

Figure 6: Project Area Topography

Soils

The USDA, Natural Resources Conservation Service, classifies the dominate soil within the APE

as Galestown loamy sand (GaA) with 0 to 2 percent slopes. The setting consists of flats and

fluviomarine terraces with linear down- and across-slopes and the project area is nearly level.

The soils are somewhat excessively drained with the water table at 80 inches.

Horizon Depth Soil Texture

Ap 0 to 11 inches Loamy Sand

Bt 11 to 40 inches Loamy Sand

BC 40 to 51 inches Sand

C 51 to 80 inches Sand

Figure 7: Project Area Typical Soil Profile

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

12

Surface Conditions and Signs of Disturbance

The portion of the project area considered for development consists of previously disturbed land

characterized by agricultural fields with a plow zone (Ap-the top most layer of the soil disturbed

to depth that a plow will penetrate, 12 to 25 cm, resulting in homogenizes soil layer), irrigation

well sites, drainage swales (some with culverts), and access roads. Wright’s Branch Creek

bisects the parcel and both sides of the creek are lined with a buffer of trees (Figure 8).

Figure 8: Project Area, Wright’s Branch

A review of historic topographic maps dating to 1905 indicates the northern section of the

proposed project site has been under cultivation since in early 20th

century: this was likely the

case in the 19th

century (based on the land records and land use patterned in the area). The

southern section of the parcel (below the creek) was mostly wooded until the mid-20th

century

but cleared converted to farmland by 1975. There is no domestic structure associated with the

current property configuration and only agricultural buildings and water-pumping infrastructure

are present. A review of aerial photographs dating to the 1960s, illustrate only farm-related

buildings. At the time of survey and reporting part of the property had recently been harvested

and the remainder cultivated with soybeans (Figures 9 and 10).

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

13

Figure 9: Project Area, After Harvest

Figure 10: Project Area, Under Cultivation

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

14

Historic Resources

There is no dwelling structure associated with the property and it’s current configuration.

According to the files and the GIS system at the Maryland Historical Trust/MD-SHPO, there are

no recorded historic structures extant within the APE (within a half of a mile) of the proposed

project area. However, there is a location with a MIHP number on the abutting parcel directly to

the north on Harper Road: the structure was town down ca. 2000. The Andrew Phillips Farm (D-

123) was recorded in 1975 and was noted as “a two-part frame dwelling, the earliest part being

one and one-half story, three bay long with a lean to on one gable and a two story, two bay long

structure on the other” (Bourne 1975). It was recorded as a 19th

century vernacular domestic

structure in deteriorated condition: it was not determined eligible for listing on the National

Register. The Phillips family owned the property from 1925 until 1979.

The housing abutting the property on the eastern boundary (near the intersection of Harper Road

and Palmer Mill Road) consists of trailer homes and small manufactured one level “ranch style”

houses. Similar types of housing are present on Ennall Road on the southern boundary of the

property near the water treatment plant facility.

The Hurlock Historic District (D-653) is located over 1.5 miles from the proposed project area

(to the northwest) and is outside the APE for direct effect. The Petersburg Survey District (D-

766) is located 0.60 miles from the proposed project area and it is outside the APE for direct

effect. The survey district and has not been formally evaluated for listing on the National

Register. Located at the southeastern most boundary of the survey district is the Zorah ME

Church, which dates to 1898, and although the Maryland Historical Trust in 1975 recorded it in

and in 2008 it has not been evaluated or determined eligible for the National Register.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

15

Archaeological Resources

According to the files at the Maryland Historical Trust/MD-SHPO, there are six recorded

archaeology sites within 2 miles (the APE) of the proposed Todd Solar Center project area. All

are located east of the project site and east of Palmers Mill Road adjacent to Marshyhope Creek.

No Phase I surveys have been conducted on the subject property on or adjacent properties: there

are no recorded archaeological sites on the subject property.

Site # Site Name Type Recorded

18DO08 Orchard Woodland short-term procurement camp and

historic field scatter 1954

18DO09 Blanchard Archaic and Late Woodland short-term resource

procurement camp 1954

18DO14 Waddell River Farm Late Archaic and Early & Late Woodland short-

term procurement camp 1953

18DO15 Unk Harper Woodland lithics and ceramics 1954

18DO26 Tub Island Late Woodland and possible Archaic base camp 1955

18DO29 G. Coventry / Ennal's Wharf Middle and Late Woodland short-term resource

procurement camp 1955

Figure 11: Recorded Sites in the Immediate Area

The sites date from the Archaic (8,000 to 6,000 BCE) to through the historic period. The

environmental context falls within the generally accepted type for prehistoric settlement as

established by predictive models for the region. Land areas within 200 meters (656 feet) of

stream terraces, stream confluences, and water features generally have a moderate to high

probability for evidence of prehistoric occupation and settlement (A.D. Marble & Company

2006: 37-44). The subject property is located in an area with documented archaeological sites

and the environmental setting (proximity to Wright’s Branch) is one associated with prehistoric

occupation and settlement.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

16

Planned Alterations

The proposed development of the subject property calls for minimal ground disturbance and

some limited excavation related to the installation of infrastructure for a solar energy collection

and distribution facility. As planned, the project would consist of photovoltaic (PV) panels and

steel racks installed in rows in the agricultural fields (Figure 12).

Figure 12: Typical Solar Panel Facility

Ground disturbance would be related to buried electric transmit cables, the installation of

approximately nine electricity inverters, and a small switchyard to be built on the site. An

electric circuit connecting the two fields of panels would be installed by underground directional

bore or overhead circuit. An eight-foot fence will surround the facility and a gravel road is

expected to be installed around the perimeter of the panel arrays. As the site is largely flat, little

to no grading is expected. The PV racks will be mounted on piles that can be installed without

excavation via boring. The area of the stream and wooded buffers would not be developed as

part of the project and appropriate setbacks will be established based on state/local regulations

(Figure 13).

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

17

Figure 13: Planned Alterations to the Property

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

18

Findings and Recommendations

There are no recorded historic resources, nor were any discovered during this survey, that

suggest that this planned undertaking would have a direct effect on historic resources. Moreover,

the abutting water treatment plant and related water treatment ponds have previously altered the

view shed of the property. No further study related to historic resources is warranted.

The subject property is located near an area with documented archaeological sites and the

environmental setting is one associated with prehistoric occupation and settlement therefore

there is a high to moderate likelihood that prehistoric or historic archaeological resources maybe

located within the APE and could be disturbed or destroyed by this planned undertaking. Phase I

archaeological testing is warranted to establish the presence or absence within the proposed APE

to determine the impact of development on archaeological resources.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

19

Bibliography

A.D. Marble & Company

2006 U.S. 301 Project Development, Archaeological Predictive Model. Prepared for the

Delaware Department of Transportation in association with Rummel, Klepper, & Kahl

Bourne, Michael

1975 Maryland Historical Trust Worksheet. Nomination Form for the National Register of

Historic Places, National Park Service. “Andres Phillips Farm (D-123).” On File at the

Maryland Historical Trust, Crownsville, MD.

Cadzow, Donald A.

1939 “Archaeological Studies of the Susquehannock Indians of Pennsylvania.” Safe Harbor

Report, No. 2, Harrisburg, PA: Pennsylvania Historical Commission.

Cole, Wanda Diane

2008 Sea Level Rise: Technical Guidance for Dorchester County. Maryland Eastern Shore

Resource Conservation & Development Council. Maryland Department of Natural

Resources Coastal Zone Management Division. Annapolis, Maryland.

Dent, Richard J.

1995 Chesapeake Prehistory: Old Traditions, New Directions. Plenum Press, New York.

Dorchester County Maryland

1971 Dorchester County Circuit Court (Land Records) PLC 169, p. 0546. MSA CE 47-220.

1929 Dorchester County Circuit Court (Land Records) JFD 25, p. 0110. MSA CE 47-79.

1907 Dorchester County Circuit Court (Land Records) CL 32, p. 0647. MSA CE 47-44.

1905 Dorchester County Circuit Court (Land Records) CL 31, p. 0229. MSA CE 47-4.

1882 Dorchester County Circuit Court (Land Records) CL 4, p. 0696. MSA CE 47-16.

1878 Dorchester County Circuit Court (Land Records). FJH 13 & CL 1, p. 0105. MSA CE 47-

13.

1766 Patented Certificates 350. Aireys Chance, John Pitt Airey, 563 1/2 Acres.

Dorchester Soil Conservation District (DSCD)

2000 Dorchester Soil Conservation District Strategic Plan. Maryland Association of Soil

Conservation Districts. Cambridge, MD. Accessed 10/15/2015

http://mascd.net/districts/dorchester/Dorchester%20Strategic%20Plan.pdf.

Ebright, Carol A.

1992 “Early Native American Prehistory on the Maryland Western Shore: Archaeological

Investigations at the Higgins Site.” Vols. 1 – 3, Baltimore, Maryland State Highway

Administration and Department of Natural Resources.

Griffin, James B.

1967 “Eastern North American Archaeology: A summary.” Science 156:175-191.

1978 “Eastern United States.” In: Chronologies in New World Archaeology edited by R. E.

Taylor and C. W. Meighan. Academic Press, New York.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

20

Jones, Elias

1902 History of Dorchester County, Maryland. Williams & Wilkins Company Press:

Baltimore, MD.

LeeDecker, Charles H. and John W. Martin, Amy Friedlander

1988 Archaeological Evaluation of the Greenbelt Storage Yard, WMATA Construction

Segment E-11, Prince George's County, Maryland. (tDAR ID: 166875)

Maryland Department of Natural Resources

2000 Maryland Atlas of Greenways, Water Trails, and Green Infrastructure. Maryland

Greenways Commission. Accesses October 14, 2015.

http://www.dnr.state.md.us/greenways/introduction.html

Maryland Geological Survey (MSG)

2008 Highest and Lowest Elevations in Maryland's Counties. Maryland Geology. Accessed

October 14, 2015. http://www.mgs.md.gov/geology/highest_and_lowest_elevations.html

Maryland Historical Trust

2008 Maryland Historical Trust. Determination of Eligibility Form for the Hurlock Historic

District (D-653). Multiple forms; Bourne 1975, Reinhart 2001 and Tourat 2008.

Porter III, Frank W.

1979 "Strategies for Survival: The Nanticoke Indians in a Hostile World.” Ethnohistory 26,

no. 4: 325.

State of Maryland, Department of Natural Resources

2014 “MERLIN- Maryland Environmental Resource and Land Information Network.”

http://geodata.md.gov/imaptemplate/?appid=a8ec7e2ff4c34a31bc1e9411ed8e7a7e

Steponaitis, Laurie C.

1980 A Survey of Artifact Collections from the Patuxent River Drainage, Maryland. (TDAR

ID: 116845)

Wright, Henry T.

1973 An Archeological Sequence in the Middle Chesapeake Region, Maryland. Baltimore:

Maryland Geological Survey.

US Census Bureau

1996 Population of States and Counties of the United States: 1790 to 1990. Washington, DC:

GPO.

USDA Natural Resources Conservation Service

1997 "Web Soil Survey.” National Resources Inventory.

http://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm (accessed April 8, 2015).

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

21

Appendix I: Qualifications

MECHELLE KERNS, PHD, RPA

Principal Archaeologist & Historian

Kerns CRM Consultants, LLC

94 West Earleigh Heights Rd

Severna Park, MD 21146

[email protected]

410-409-5187

EDUCATION

Doctor of Philosophy

Maritime History & Archaeology

University of St Andrews, Scotland, UK, 2003

Master of Arts

Historical Studies & Public History

University of Maryland Baltimore County,

1999

Bachelor of Arts

Ancient Studies

University of Maryland Baltimore County,

1996

EXPERIENCE AND QUALIFICATIONS:

Dr. Kerns has over seventeen years of experience with historical research, archeology, maritime

history, and cultural resource management in 11 states throughout the United States. She

exceeds the Secretary of the Interior’s standards for Archeology and History and is certified by

the Register of Professional Archaeologists (RPA). She has extensive experience with all phases

of archaeological field work (terrestrial and underwater) as well as research design development,

data analysis, report writing, public outreach and education programs and has directed

reconnaissance, intensive surveys, and data recovery investigations on both historic and

prehistoric sites. Clients have included the Federal government (FEMA, USACE, US BOP, and

VAMC), state and local infrastructure authorities; state governments; non-profit organizations;

and the private sector.

Representative projects include:

2013 Clifton Mansion (18BC178) Phase I Archaeological Testing: Geothermal Field, Porch

Foundation and Elevator Installation Project Areas. Clifton Mansion & Civic Works,

Baltimore, MD.

2013 Cambridge Solar Project: Phase I Archaeological Investigation of the Adams Farm at

4919 Bucktown Road, Cambridge, Dorchester County, Maryland. OneEnergy

Renewables, Seattle, WA.

2011 Survey Report: Staff Housing at the United State Penitentiary, Atlantic, Georgia. Federal

Bureau of Prisons.

2011 Cultural/Historical Research for Environmental Assessments (EA) for Five New England

Veteran Administration Medical Centers, US Veterans Administration.

Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland

2009 Hudson River Sediment Remediation Phase I Project Archeological Resources

Assessment Underwater Resource U-2. U.S. EPA, New York Department of

Environmental Quality, and General Electric.

2009 National Aeronautics and Space Administration, Wallops Flight Facility Shore Line

Restoration Environmental Impact Statement. NASA, Wallops Flight Facility.

2009 Phase II Archaeological Evaluation of Site 47BA199 (Forest Service Site 09-02-05-009)

Chequamegon-Nicolet National Forest Bayfield County, Wisconsin. DuPont Corporate

Remediation.

2009 Phase I Archaeological Survey of Locations 21 and 31, Dover Air Force Base, Dover DE.

DOD, US Air Force.

2009 Phase I Archaeological Survey of The Beauvoir Property (22HR1012) Harrison County,

Mississippi. Department of Homeland Security, FEMA.

2008 Iron Forge (18AN1386) Discovery Cultural Resources Documentation for the Maryland

Aviation Administration, Anne Arundel County, Maryland.

2008 Report of Investigations: Archival Research Concerning Center Hill Lake, Tennessee.

Department of the Army Nashville District, US Army Corps of Engineers.

2008 Phase I Archaeological Survey of the Black and White Inn (18MO669) Montgomery

County, Maryland. Montgomery County Department of Public Works and

Transportation.

2008 Phase I Archaeological Survey of Area I & Area J Trails at the Lorton Prison Facility.

Fairfax County Park Authority, Cultural Resource Management and Protection Section,

Fairfax, VA.

2007 Phase I Archaeological Survey of Area G & Area H Trails at the Lorton Prison Facility.

Fairfax County Park Authority, Cultural Resource Management and Protection Section,

Fairfax, VA.

2007 Phase II Archaeological Survey of the Homeland Property (18PR867 and 18PR868).

Prince George’s County, MD. Pulte Homes Corporation, 2007.

2006 Phase I Archaeological Survey Demiray Property (18FR857) 104-106 North Market

Street Frederick, Maryland. David Demiray, on file at the City of Frederick Office of

Planning and the MHT.

2006 Fountain Rock Park Phase II Archaeological Survey (18FR835 & 18FR836). Public

Works Division Frederick County Office of Project Management Frederick, MD.

2002 The Santa Rosa Island Shipwreck (Phase III) Project (8ES1905). Archaeology Institute,

The University of West Florida, Pensacola, FL.

1997-2005 Phase III Excavations at London Town (18AN48), Edgewater, Maryland. Anne

Arundel County’s Office of Environmental and Cultural Resources, Annapolis, MD.

U.S. Fish & Wildlife Service

Todd SolarIPaC Trust Resource ReportGenerated September 01, 2015 04:01 PM MDT

UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report

09/01/2015 04:01 Page 2 Information for Planning and ConservationIPaCVersion 2.2.3

US Fish & Wildlife Service

IPaC Trust Resource Report

Project DescriptionNAME

Todd Solar

PROJECT CODE

UFINC-DENQ5-HJXES-PBCI7-4H3CYQ

LOCATION

Dorchester County, Maryland

DESCRIPTION

20 MW solar energy project targetingconstruction in 3q and 4q 2016

U.S. Fish & Wildlife Contact InformationSpecies in this report are managed by:

Chesapeake Bay Ecological Services Field Office177 Admiral Cochrane DriveAnnapolis, MD 21401-7307 (410) 573-4599

UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report

09/01/2015 04:01 Page 3 Information for Planning and ConservationIPaCVersion 2.2.3

Endangered

Endangered SpeciesProposed, candidate, threatened, and endangered species that are managed by the

and should be considered as part of an effect analysisEndangered Species Programfor this project.

This unofficial species list is for informational purposes only and does not fulfill therequirements under of the Endangered Species Act, which states that FederalSection 7agencies are required to "request of the Secretary of Interior information whether anyspecies which is listed or proposed to be listed may be present in the area of aproposed action." This requirement applies to projects which are conducted, permittedor licensed by any Federal agency.

A letter from the local office and a species list which fulfills this requirement can beobtained by returning to this project on the IPaC website and requesting an OfficialSpecies List from the regulatory documents section.

Mammals Delmarva Peninsula Fox Squirrel Sciurus niger cinereus

CRITICAL HABITAT

has been designated for this species.No critical habitat

https://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=A00B

Critical HabitatsPotential effects to critical habitat(s) within the project area must be analyzed along withthe endangered species themselves.

There is no critical habitat within this project area

UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report

09/01/2015 04:01 Page 4 Information for Planning and ConservationIPaCVersion 2.2.3

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Migratory BirdsBirds are protected by the and the Bald and Golden EagleMigratory Bird Treaty ActProtection Act.

Any activity which results in the of migratory birds or eagles is prohibited unlesstakeauthorized by the U.S. Fish and Wildlife Service ( ). There are no provisions for1allowing the take of migratory birds that are unintentionally killed or injured.

You are responsible for complying with the appropriate regulations for the protection ofbirds as part of this project. This involves analyzing potential impacts and implementingappropriate conservation measures for all project activities.

American Oystercatcher Haematopus palliatus

Year-roundhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0G8

American Bittern Botaurus lentiginosus

Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0F3

Bald Eagle Haliaeetus leucocephalus

Year-roundhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B008

Black-billed Cuckoo Coccyzus erythropthalmus

Season: Breedinghttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0HI

Fox Sparrow Passerella iliaca

Season: Wintering

Gull-billed Tern Gelochelidon nilotica

Season: Breeding

Kentucky Warbler Oporornis formosus

Season: Breeding

Least Bittern Ixobrychus exilis

Season: Breeding

Least Tern Sterna antillarum

Season: Breeding

Lesser Yellowlegs Tringa flavipes

Season: Wintering

Marbled Godwit Limosa fedoa

Season: Wintering

Nelson's Sparrow Ammodramus nelsoni

Season: Wintering

Peregrine Falcon Falco peregrinus

Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0FU

Pied-billed Grebe Podilymbus podiceps

Year-round

UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report

09/01/2015 04:01 Page 5 Information for Planning and ConservationIPaCVersion 2.2.3

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern

Bird of conservation concern Prairie Warbler Dendroica discolor

Season: Breeding

Prothonotary Warbler Protonotaria citrea

Season: Breeding

Purple Sandpiper Calidris maritima

Season: Wintering

Red Knot Calidris canutus rufa

Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0DM

Red-headed Woodpecker Melanerpes erythrocephalus

Year-round

Rusty Blackbird Euphagus carolinus

Season: Wintering

Saltmarsh Sparrow Ammodramus caudacutus

Year-round

Seaside Sparrow Ammodramus maritimus

Year-round

Short-billed Dowitcher Limnodromus griseus

Season: Wintering

Short-eared Owl Asio flammeus

Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0HD

Snowy Egret Egretta thula

Season: Breeding

Wood Thrush Hylocichla mustelina

Season: Breeding

Worm Eating Warbler Helmitheros vermivorum

Season: Breeding

UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report

09/01/2015 04:01 Page 6 Information for Planning and ConservationIPaCVersion 2.2.3

RefugesAny activity proposed on lands must undergo a 'CompatibilityNational Wildlife RefugeDetermination' conducted by the Refuge. If your project overlaps or otherwise impacts aRefuge, please contact that Refuge to discuss the authorization process.

There are no refuges within this project area

UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report

09/01/2015 04:01 Page 7 Information for Planning and ConservationIPaCVersion 2.2.3

WetlandsImpacts to and other aquatic habitats from your project may be subject toNWI wetlandsregulation under Section 404 of the Clean Water Act, or other State/Federal Statutes.

Project proponents should discuss the relationship of these requirements to their projectwith the Regulatory Program of the appropriate .U.S. Army Corps of Engineers District

DATA LIMITATIONS

The Service's objective of mapping wetlands and deepwater habitats is to produce reconnaissance level informationon the location, type and size of these resources. The maps are prepared from the analysis of high altitude imagery.Wetlands are identified based on vegetation, visible hydrology and geography. A margin of error is inherent in the useof imagery; thus, detailed on-the-ground inspection of any particular site may result in revision of the wetlandboundaries or classification established through image analysis.

The accuracy of image interpretation depends on the quality of the imagery, the experience of the image analysts,the amount and quality of the collateral data and the amount of ground truth verification work conducted. Metadatashould be consulted to determine the date of the source imagery used and any mapping problems.

Wetlands or other mapped features may have changed since the date of the imagery or field work. There may beoccasional differences in polygon boundaries or classifications between the information depicted on the map and theactual conditions on site.

DATA EXCLUSIONS

Certain wetland habitats are excluded from the National mapping program because of the limitations of aerialimagery as the primary data source used to detect wetlands. These habitats include seagrasses or submergedaquatic vegetation that are found in the intertidal and subtidal zones of estuaries and nearshore coastal waters.Some deepwater reef communities (coral or tuberficid worm reefs) have also been excluded from the inventory.These habitats, because of their depth, go undetected by aerial imagery.

DATA PRECAUTIONS

Federal, state, and local regulatory agencies with jurisdiction over wetlands may define and describe wetlands in adifferent manner than that used in this inventory. There is no attempt, in either the design or products of thisinventory, to define the limits of proprietary jurisdiction of any Federal, state, or local government or to establish thegeographical scope of the regulatory programs of government agencies. Persons intending to engage in activitiesinvolving modifications within or adjacent to wetland areas should seek the advice of appropriate federal, state, orlocal agencies concerning specified agency regulatory programs and proprietary jurisdictions that may affect suchactivities.

Wetland data is unavailable at this time.

Inv* gvSeptember 4,2015

Lori ByrneDNR Wildlife &580 Taylor Ave.Tawes Office BuiAnnapolis, MD 21

Tel: 410-260-8573

Subject:Envi

Dear Ms. Byrne:

Invenergy Solaragricultural parcelMap 0023, Parcelwater treatment p ow

The attached sk

:ntage

ing E-101

for Todd Solar in Dorchester County, MD

LLC, is developing a 20 MW solar project on a 143-acreDo County, MD. The parcel is identified in the tax records as

1 and is located southeast of the Town of Hurlock, MD, adjacent to aby the Town of Hurlock.

Note that as part oshows

the projpreliminary project boundaries on a USGS 24,000 scale map.

, the local utility will be installing overhead electric linesbetween the solaryellow and black

ilities the Todd Substation which is represented on the sketch as a

Todd Solarreview of pspecles, rare specr

Please providelisted below.

Sincerel

J. MillerDirector, ProjectInvenergy LLC120 N. Lee Street,Falls Church, VA(301) 610-6413

i\\'l iNl ill( ;\' I J,(l One South Wacker

ectthe

proji. or

land Wildlife & Heritage Service perform an environmentalto identifr any potential impacts of the project to protectedhabitat.

environmental review to me at the Falls Church, VA address

l0uite,.046

, Suite 1800 Chicago, \L 60606 "l 31,2.224.1,4tJ0 F 312.224.7444 invenergSrllc.com

)^Cof) !-t{ ;gCJ.:;EH i:^r o 5l

-1tl-.t e

:)oo

-IUooL

oo

3r,

oaao.Euoo

P.E-r-E

*=UUFEflEIJiFEEfIi9lo olC rffi EIEERS i PI I

O i,.i-4o

IIItII

I"rI

1.*t-j

IMnRYLANDDEPARTMENT OF

NRruRnI RTSOURCES

Lorry Hogan, Governor

Boyd K. Ruthefiord, Lt. Governor

Mark J. Belton, Secretary

Mqrk L. Hoffman, Acting Deputy Secretory

September 24,2015

Eric MillerInvenergy, LLCOne South Wacker Dr., Suite 1800Chicago, IL 60606

RE: Environmental Review for Todd Solar, 20 MW solar project, TM 23 P l, Town ofHurlock, Dorchester County, MD.

Dear Mr. Miller:

The Wildlife and Heritage Service has determined that there are no State or Federal records forrare, threatened or endangered species within the boundaries of the project site as delineated. Asa result, we have no specific comments or requirements pertaining to protection measures at thistime. This statement should not be interpreted however as meaning that rare, threatened orendangered species are not in fact present. Ifappropriate habitat is available, certain speciescould be present without documentation because adequate surveys have not been conducted.

Thank you for allowing us the opportunity to review this project. If you should have any fuitherquestions regarding this information, please contact me at (410) 260-8573.

Sincerely,

o#o orLori A. Byrne,Environmental Review CoordinatorWildlife and Heritage ServiceMD Dept. of Natural Resources

ER# 2015.1351.do

Tawes State Office Building - 580 Taylor Avenue - Annapolis, Maryland2l40l410-260-8DNR or toll free in Maryland 877-620-8DNR - dnr.maryland.gov - TTY Users Call via the Maryland Relay

CONFIDENTIAL BUSINESS INFORMATION

1

Habitat Assessment

For the

Dorchester Solar Project

Prepared for:

Invenergy LLC One South Wacker Drive Suite 1800 Chicago, IL 60606 Prepared by: Davis & Associates Environmental Consulting LLC PO Box 733 Chestertown, MD 21620

CONFIDENTIAL BUSINESS INFORMATION

2

1. Introduction

A critical habitat assessment was conducted for a site in Dorchester County, Maryland. The assessment

followed Tier 1 and Tier 2 of the U.S. Fish and Wildlife Service Land-Based Wind Energy Guidelines

(USFWS 2012) because similar guidance for solar development has not yet been issued by the U.S. Fish

and Wildlife Service (USFWS).

2. Project Location and Setting

The site (project area) is located on the west side of Palmers Mill Road approximately 1.5 miles south of

its intersection with MD 382, southeast of Hurlock in Dorchester County, Maryland. The site is located

in the Coastal Plain Physiographic province and is in a predominantly agricultural area that also includes

residential uses. A wastewater treatment facility is located west of the site.

3. Methods

Database Review and Landscape Level Assessment (Tier 1 of USFWS Guidelines)

A preliminary site evaluation was conducted that consisted of a landscape level assessment of habitat

for species of concern and a review of databases and other available information at the county, state

and federal level for sensitive species including rare, threatened and endangered species. The following

databases and sources were reviewed:

U.S. Fish and Wildlife Information for Planning and Conservation (IPaC) tool

Maryland’s Environmental Resources and Land Information Network (MERLIN)

Maryland Amphibian and Reptile Atlas (MARA) Database

USGS Maryland/DC Breeding Bird Atlas Project (BBA)

Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare,

Threatened and Endangered Species of Dorchester County (April 2010)

Site Characterization and Analysis (Tier 2 of USFWS Guidelines)

A site characterization was completed to assess the potential presence of the species of concern

identified through the database review and landscape level assessment (Tier 1). For the site

characterization, the site was delineated into vegetative communities based on a review of leaf-off

aerial photography, soil maps, and topographic maps. A reconnaissance level site visit was conducted

on October 6, 2015 to field verify the delineation of the vegetative communities. In the mixed

hardwood forest community, a single transect was walked starting from the southeastern portion of the

site at Palmers Mill Road on the south side of Wrights Branch in a northwesterly direction. A transect

was then walked from the northwest in a southeasterly direction back toward Palmers Mill Road

through the wetland community. Dominant and codominant species were recorded as well as

observations regarding forest structure.

CONFIDENTIAL BUSINESS INFORMATION

3

4. Findings

Database Review and Landscape Level Assessment

U.S. Fish and Wildlife Information for Planning and Conservation (IPaC) tool

The U.S. Fish and Wildlife Information for Planning and Conservation (IPaC) tool identified only one

wildlife species, the Delmarva Peninsula Fox Squirrel, as protected by the Endangered Species Act with

the potential to occur on site. Shortly thereafter, the Delmarva Peninsula Fox Squirrel was delisted from

federal protection on November 16, 2015. A plant species, Swamp Pink, is also protected by the

Endangered Species Act, and has potential to grow in Maryland’s Coastal Plain.

The IPaC tool also identified numerous birds of conservation concern protected by the Migratory Bird

Treaty Act that could potentially occur in the project area. These species are listed in IPaC Trust

Resource Report in the Appendix. These are migratory birds that are protected by the Migratory Bird

Treaty Act, which requires analyzing potential impacts and implementing appropriate conservation

measures for all project activities.

Maryland’s Environmental Resources and Land Information Network (MERLIN)

MERLIN was reviewed and there were no records of any sensitive species occurring on the site.

Sensitive species considered by MERLIN include rare, threatened and endangered species both federally

and state listed species.

Maryland Amphibian and Reptile Atlas (MARA) Database

The Maryland Amphibian and Reptile Atlas is a five-year joint project of the Natural History Society of

Maryland and the Maryland Department of Natural Resources. The goal of the project is to document

the current distributions of Maryland’s amphibian and reptile species. The MARA database was

reviewed to determine what species have the potential to occur on the site. The list of species reported

in the Rhodesdale quadrangle (the quadrangle of the project site) is included in the Appendix. None of

the species on the MARA list with potential to occur on the site is listed as state or federally threatened

or endangered.

USGS Maryland/DC Breeding Bird Atlas Project (BBA)

The results of the Maryland and DC Breeding Bird Atlas Project for 2002-2006 were reviewed for the

project site. The site is located in the northwest quadrant of the Rhodesdale quadrangle. A list of the

species is provided in the Appendix. No federally or state listed bird species appear on the list.

However, the prairie warbler and the wood thrush do appear on the list and these birds are listed as

birds on conservation concern by the USFWS as part of the Migratory Bird Treaty Act.

CONFIDENTIAL BUSINESS INFORMATION

4

Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare, Threatened and

Endangered Species of Dorchester County (April 2010)

The Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare, Threatened

and Endangered Species of Dorchester County (April 2010) is included in the Appendix. A review of the

MERLIN database does not show any records for any of these species on the project site.

Site Characterization and Analysis (Tier 2 of USFWS Guidelines)

The entire site consists of 143.3 acres. Approximately 124 (87%) acres are in use as tilled agricultural

fields for corn and soybeans and approximately 19 (13%) acres are in natural vegetation along Wrights

Branch, a tributary of Marshyhope Creek.

The natural vegetation on the site consists of two vegetative communities. One community is an

uneven-aged, mature mixed hardwood forest that slopes down to Wrights Branch. Dominant trees are

approximately 16 inches in diameter. Dominant species include sweetgum, southern red oak, and

mockernut hickory. Understory and shrub layer species include American holly, mountain laurel,

greenbrier and poison ivy. The understory and shrub layer are moderately dense. The second

community is a wetland area that occurs at the base of the slope immediately adjacent to Wrights

Branch. Dominant tree species include red maple, sweetgum, blackgum, American holly, and sweetbay.

Shrub and perennial species include sensitive fern, royal fern, cinnamon fern, sweet pepperbush, lizard

tail, and clearweed.

FEDERALLY LISTED SPECIES

Based on the site characterization and review of the database information, the following species listed

as federally threatened or endangered have the potential to occur in Dorchester County:

Swamp Pink (Helonias bullata)

Description and Habitat

Swamp pink is a perennial of the lily family. It occurs in acidic wetlands from New Jersey south to

Georgia. The swamp pink can grow only in wetlands with perennially saturated – but not flooded – soils.

This dependence on an uncommon habitat type restricts the plant to small, scattered populations

throughout its range. The swamp pink grows in forested wetlands of Maryland’s coastal plain. In April,

its bright pink flowers bloom among the emerging skunk cabbage leaves. Four populations are currently

known, two in Cecil County and two in Anne Arundel County. It was classified as an Endangered Species

by the State of Maryland in 1987. (MD DNR 2015).

Analysis

The soils in the wetlands on site are frequently flooded and therefore suitable habitat for swamp pink

does not occur on the project site. Furthermore, the MERLIN database does not show any sensitive

habitats occurring on the project site.

CONFIDENTIAL BUSINESS INFORMATION

5

Other Federally Listed Species

Two other species listed as federally endangered appear on Maryland Department of Natural Resources

Wildlife and Heritage Service List of Rare, Threatened and Endangered Species of Dorchester County

(April 2010). These two species are the American Burying Beetle (Nicrophorus americanus) and the Red-

cockaded Woodpecker (Picoides borealis). However, both of these species are noted as Endangered

Extirpated in Maryland, which means that it was once a viable component of the flora or fauna of the

state but for which no naturally occurring populations are known to exist in the state.

MIGRATORY BIRD TREATY ACT

The following birds are listed as birds of conservation concern and appear on the USGS Maryland/DC

Breeding Bird Atlas Project (BBA) for the northwest quadrant of the Rhodesdale quadrangle where the

project site is located.

Prairie Warbler (Dendroica discolor): The prairie warbler occurs in brushy slashings, bushy pastures,

and low pines. It breeds in dry, old clearings, edges of forest, and sandy pine barrens with undergrowth

of scrub oaks, especially on ends of slopes and ridges. The prairie warbler likes thick second-growth of

hickory, dogwood, hazel, or laurel with blackberry vines.

The forested areas and the edge of the forested areas on the site provide suitable habitat for the prairie

warbler for breeding. This species was also identified on the breeding bird atlas in this quadrant of the

Rhodesdale quadrangle as being observed with probable breeding evidence of territorial behavior. The

species is considered a Bird of Conservation Concern by the US Fish and Wildlife Service. The prairie

warbler is not listed on the current list of rare, threatened and endangered species in Maryland.

Wood Thrush (Hylocichla mustelina): The Wood Thrush breeds in deciduous and mixed forests in the

eastern U.S. where there are large trees, moderate understory, shade, and abundant leaf litter for

foraging. They winter in lowland tropical forests in Central America. Suitable habitat for the wood

thrush occurs on the project site in the forested areas along Wrights Branch. The species is considered a

Bird of Conservation Concern by the US Fish and Wildlife Service. The wood thrush is not listed on the

current list of rare, threatened and endangered species in Maryland.

STATE LISTED SPECIES

Delmarva Peninsula Fox Squirrel (Sciurus niger cinereus):

Description, Habitat and Behavior

The largest of all the tree squirrels, the Delmarva Peninsula fox squirrel has silver to whitish-gray slate

hair and an unusually full, fluffy tail and white belly. The squirrel’s coat varies in color from frosty silver-

gray to almost black. The Delmarva fox squirrel lives in mature forests of mixed hardwoods and pines

with a closed canopy and open understory. A habitat suitability model indicated that sites were fox

squirrels were present had a higher percentage of large trees (>12 inches in diameter), a lower

percentage of shrub groundcover, and a slightly lower understory density than did sites where squirrels

CONFIDENTIAL BUSINESS INFORMATION

6

were not found. Although it is a forest animal, the squirrel spends considerable time on the ground

foraging for food, typically in woodlots of mixed loblolly pine and hardwoods such as oak, maple,

hickory, walnut, and beech— trees that provide food including nuts and seeds. The squirrel will also

take food from farm fields. Feeding on tree buds and flowers during the spring, the squirrel will also eat

fungi, insects, fruit, and seeds. In the summer and early fall, the squirrel forages on mature, green pine

cones. The animal generally lives in woodlands associated with farmland areas—not typically in

suburban settings. Less agile than the common gray squirrel, the Delmarva fox squirrel often ambles

along the forest floor rather than leaping from branch to branch. The animal usually avoids

confrontations by running away rather than climbing a tree but will do so to avoid a predator. The fox

squirrel is also quieter than the gray squirrel. The home range of the fox squirrel varies, but averages

about 40 acres. The Delmarva fox squirrel prefers to nest in tree cavities but will also nest on a tree

crotch, in tangles of vines in tree trunks or at the end of large tree branches. Squirrels mate in late

winter and early spring. About 44 days later in February and March as many as four young are born.

Females may give birth to two litters per year. They raise the young by themselves for about three

months (USFWS, 2008).

On November 16, 2015, the U.S. Fish and Wildlife Service issued a final rule removing the Delmarva fox

squirrel from the list of endangered and threatened species. Following its 2012 review of the species,

the USFWS concluded that the best available scientific and commercial data indicate the Delmarva fox

squirrel is no longer in danger of extinction or likely to become endangered within the foreseeable

future. However, the Maryland Department of Natural Resources Wildlife and Heritage Service will

continue to protect the Delmarva fox squirrel and its habitat as a state threatened species (Lori, Byrne,

MD DNR WHS, personal communication to Noreen Davis, Nov 2015).

Analysis

The project site contains 19 acres of hardwood forest. There is a fairly dense shrub layer and dense

understory making the site unsuitable for the Delmarva fox squirrel. This is consistent with the MERLIN

database, which does not show that the site contains habitat for the Delmarva fox squirrel.

CONFIDENTIAL BUSINESS INFORMATION

7

Literature Cited

U.S. Fish and Wildlife Service. (2012). U.S. Fish and Wildlife Service Land-Based Wind Energy Guidelines.

Washington, D.C.

U.S. Fish and Wildlife Service (2008). Delmarva Peninsula Fox Squirrel Sciurus niger cinereus.

Washington, D.C.

MD Department of Natural Resources (October 2015). Endangered Plant Fact Sheet Swamp pink,

Helonias bullata. Retrieved from

http://dnr2.maryland.gov/wildlife/Pages/plants_wildlife/rte/rteplantfacts.aspx?PID=Swamp%20

Pink.

CONFIDENTIAL BUSINESS INFORMATION

8

APPENDIX

1. IPaC Trust Resource Report

2. Maryland Amphibian and Reptile Atlas (MARA) Species for Rhodesdale quadrangle

3. USGS Maryland/DC Breeding Bird Atlas Project (BBA) for Rhodesdale NW

4. Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare,

Threatened and Endangered Species of Dorchester County (April 2010)

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:52 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6170213548 -75.8372604847 25.15 10.0 35.15

2 38.6196702758 -75.8341276646 27.27 10.0 37.27

3 38.6156800917 -75.8306515217 25.74 10.0 35.74

4 38.6140873091 -75.8332693577 22.34 10.0 32.34

Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

1 38.6158728998 -75.8285754919 23.4 6.0

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

©1997-2014 Sandia Corporation

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:54 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6170213548 -75.8372604847 25.15 10.0 35.15

2 38.6196702758 -75.8341276646 27.27 10.0 37.27

3 38.6156800917 -75.8306515217 25.74 10.0 35.74

4 38.6140873091 -75.8332693577 22.34 10.0 32.34

Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

2 38.6152441757 -75.8304838836 26.36 6.0

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

©1997-2014 Sandia Corporation

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:54 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6170213548 -75.8372604847 25.15 10.0 35.15

2 38.6196702758 -75.8341276646 27.27 10.0 37.27

3 38.6156800917 -75.8306515217 25.74 10.0 35.74

4 38.6140873091 -75.8332693577 22.34 10.0 32.34

Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

3 38.6147663418 -75.8308003843 25.49 6.0

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

©1997-2014 Sandia Corporation

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:54 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6170213548 -75.8372604847 25.15 10.0 35.15

2 38.6196702758 -75.8341276646 27.27 10.0 37.27

3 38.6156800917 -75.8306515217 25.74 10.0 35.74

4 38.6140873091 -75.8332693577 22.34 10.0 32.34

Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

4 38.6142507805 -75.8311061561 23.46 6.0

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

©1997-2014 Sandia Corporation

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:55 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6170213548 -75.8372604847 25.15 10.0 35.15

2 38.6196702758 -75.8341276646 27.27 10.0 37.27

3 38.6156800917 -75.8306515217 25.74 10.0 35.74

4 38.6140873091 -75.8332693577 22.34 10.0 32.34

Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

5 38.6139049752 -75.8314602077 23.37 6.0

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

©1997-2014 Sandia Corporation

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:55 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6150765151 -75.837110281 28.97 6.0 34.97

2 38.6093255168 -75.8400285244 31.99 6.0 37.99

3 38.6094428887 -75.8339989185 23.88 6.0 29.88

4 38.6105327616 -75.8326900005 25.18 6.0 31.18

5 38.6121423899 -75.8328402042 24.88 6.0 30.88

6 38.6131651557 -75.8335053921 9.8 6.0 15.8

Observation Points

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

Latitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

6 38.609002743 -75.834183991 25.61 6.0

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

©1997-2014 Sandia Corporation

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:55 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6150765151 -75.837110281 28.97 6.0 34.97

2 38.6093255168 -75.8400285244 31.99 6.0 37.99

3 38.6094428887 -75.8339989185 23.88 6.0 29.88

4 38.6105327616 -75.8326900005 25.18 6.0 31.18

5 38.6121423899 -75.8328402042 24.88 6.0 30.88

6 38.6131651557 -75.8335053921 9.8 6.0 15.8

Observation Points

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

Latitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

7 38.6090949642 -75.8383145928 31.64 6.0

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

©1997-2014 Sandia Corporation

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/4

Solar Glare Hazard Analysis Report

Generated Oct. 29, 2015, 2:56 p.m.

Inputs

Glare found

Print

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/4

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6150765151 -75.837110281 28.97 6.0 34.97

2 38.6093255168 -75.8400285244 31.99 6.0 37.99

3 38.6094428887 -75.8339989185 23.88 6.0 29.88

4 38.6105327616 -75.8326900005 25.18 6.0 31.18

5 38.6121423899 -75.8328402042 24.88 6.0 30.88

6 38.6131651557 -75.8335053921 9.8 6.0 15.8

Observation Points

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/4

Latitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)

8 38.6090907723 -75.839741528 32.49 6.0

Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/4

©1997-2014 Sandia Corporation

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/14

Solar Glare Hazard Analysis Flight Path Report

Generated Oct. 29, 2015, 2:51 p.m.

Flight path: Private Air StripGrass Runway for crop dusting

Glare found

Print

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/14

Analysis & PV array parameters

Flight path parameters

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

Direction (deg) 326.55

Glide slope (deg) 3.0

Consider pilot visibility from cockpit False

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/14

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/14

Glare occurrence plotsAll times are in standard time. For Daylight Savings Time add one hour.

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6170213548 -75.8372604847 25.15 10.0 35.15

2 38.6196702758 -75.8341276646 27.27 10.0 37.27

3 38.6156800917 -75.8306515217 25.74 10.0 35.74

4 38.6140873091 -75.8332693577 22.34 10.0 32.34

Flight Path Observation Points

Latitude (deg)Longitude(deg)

GroundElevation (ft)

Eye-level height aboveground (ft) Glare?

Threshold 38.621028229 -75.8410477638 29.21 50.0 No

1/4 mi 38.61801304 -75.8384952486 25.78 122.6 Yes

1/2 mi 38.6149978511 -75.8359427333 7.96 209.6 Yes

3/4 mi 38.6119826622 -75.8333902181 25.17 261.57 No

1 mi 38.6089674732 -75.8308377028 25.22 330.69 No

1 1/4 mi 38.6059522843 -75.8282851876 23.45 401.65 No

1 1/2 mi 38.6029370953 -75.8257326723 22.33 471.94 No

1 3/4 mi 38.5999219064 -75.823180157 20.17 543.29 No

2 mi 38.5969067175 -75.8206276418 0.52 632.11 No

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 5/14

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 6/14

ThresholdNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 7/14

1/4 mi

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 8/14

1/2 mi

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 9/14

3/4 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 10/14

1 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 11/14

1 1/4 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 12/14

1 1/2 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 13/14

1 3/4 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 14/14

©1997-2014 Sandia Corporation

2 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 1/14

Solar Glare Hazard Analysis Flight Path Report

Generated Oct. 29, 2015, 2:50 p.m.

Flight path: Private Air StripGrass Runway for crop dusting

Glare found

Print

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 2/14

Analysis & PV array parameters

Flight path parameters

Analysis name Todd-MD_Fixed

PV array axis tracking none

Orientation of array (deg) 180.0

Tilt of solar panels (deg) 25.0

Rated power (kW) 0.0

Vary reflectivity True

PV surface material Light textured glass with ARC

Timezone offset -5.0

Subtended angle of sun (mrad) 9.3

Peak DNI (W/m^2) 1000.0

Ocular transmission coefficient 0.5

Pupil diameter (m) 0.002

Eye focal length (m) 0.017

Time interval (min) 1

Correlate slope error with material False

Slope error (mrad) 10.0

Direction (deg) 326.55

Glide slope (deg) 3.0

Consider pilot visibility from cockpit False

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 3/14

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 4/14

PV array vertices

id Latitude (deg)Longitude(deg)

GroundElevation (ft)

Height of panels aboveground (ft)

Totalelevation (ft)

1 38.6150765151 -75.837110281 28.97 6.0 34.97

2 38.6093255168 -75.8400285244 31.99 6.0 37.99

3 38.6094428887 -75.8339989185 23.88 6.0 29.88

4 38.6105327616 -75.8326900005 25.18 6.0 31.18

5 38.6121423899 -75.8328402042 24.88 6.0 30.88

6 38.6131651557 -75.8335053921 9.8 6.0 15.8

Flight Path Observation Points

Latitude (deg)Longitude(deg)

GroundElevation (ft)

Eye-level height aboveground (ft) Glare?

Threshold 38.621028229 -75.8410477638 29.21 50.0 No

1/4 mi 38.61801304 -75.8384952486 25.78 122.6 No

1/2 mi 38.6149978511 -75.8359427333 7.96 209.6 Yes

3/4 mi 38.6119826622 -75.8333902181 25.17 261.57 Yes

1 mi 38.6089674732 -75.8308377028 25.22 330.69 Yes

1 1/4 mi 38.6059522843 -75.8282851876 23.45 401.65 Yes

1 1/2 mi 38.6029370953 -75.8257326723 22.33 471.94 No

1 3/4 mi 38.5999219064 -75.823180157 20.17 543.29 No

2 mi 38.5969067175 -75.8206276418 0.52 632.11 No

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 5/14

Glare occurrence plotsAll times are in standard time. For Daylight Savings Time add one hour.

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 6/14

ThresholdNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 7/14

1/4 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 8/14

1/2 mi

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 9/14

3/4 mi

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 10/14

1 mi

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 11/14

1 1/4 mi

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 12/14

1 1/2 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 13/14

1 3/4 miNo glare

10/29/2015 Solar Glare Hazard Analysis Tool Report

https://share.sandia.gov/phlux/sghat/ 14/14

©1997-2014 Sandia Corporation

2 miNo glare