1-permit matrix for todd solar llc todd solar llc... · exhibit 1. permit matrix for todd solar llc...
TRANSCRIPT
4545874.1 48885/129410 12/15/2015
Exhibit 1. Permit Matrix for Todd Solar LLC
Agency Permit / Approval1 Regulation Required for Status Comments State of Maryland Public
Service Commission (PSC) CPCN COMAR 20.79 Construction Application filed
PJM Interconnection, LLC Interconnection Condition for Issuance of CPCN Operation Studies
complete Facilities study completed August 2014
Maryland Department of the Environment (MDE)
Permit for Impact to Intermittent Stream
and Wetlands Buffer Not required NA Project avoids impacts to wetlands and
buffers.
US Army Corps of Engineers
Permit for Impact to Intermittent Stream
Section 404, Clean Water Act Not required NA Project avoids impacts to wetlands and
buffers.
Maryland Department of the Environment (MDE)
NPDES General Permit for
Construction Activity
COMAR 26.08, Clean Water Act (CWA), Section
401, 40 CFR 122 Construction Later
Dorchester County Forest Board2
Forest Conservation Act (FCA)
Natural Resources Article 5-1602(b)(5), 5-1603(f)
Not required - exempt NA
Does not apply provided CPCN incorporates Natural Resources Article 5-1603(f) and the cutting or clearing of the forest is conducted so as to minimize the loss of forest.
Dorchester County Planning Commission
Referral to BOA for Special Exception
Review
Dorchester County Zoning Code Construction Application in
progress Application and conceptual plan to be filed in December 2015
Dorchester County Board of Appeals Special Exception
Dorchester County Zoning Code, Table of Permitted
Uses Construction Later Expected to be reviewed at BOA public
meeting scheduled for January 2016.
Dorchester County Planning Commission Site Plan Approval Dorchester County Zoning
Code Construction Later
Site Plan Permit will be applied for after BOA approval. Target submission date is 1 weeks after BOA decision. Anticipate 60-90 days for approval.
Dorchester County Planning & Zoning Office Building Permit
Dorchester County Zoning Code Construction Later
Issued after approval of site plan and submittal of plans. To be requested by contractor
Dorchester County Planning & Zoning Office Electrical Permit
Dorchester County Zoning Code Construction Later
Issued after approval of site plan and submittal of plans. To be requested by contractor
Dorchester County Department of Public Works Grading Permit Dorchester County Zoning
Code Construction Later Department of Public Works will determine if this permit is required.
1 Abbreviations: CPCN = Certificate of Public Convenience and Necessity; NPDES = National Pollution Discharge Elimination System; BOA = Board of Appeals 2 While the FCA is ordinarily implemented at the county level, the exemption for projects subject to a CPCN under Natural Resources Article 5-1602(b)(5) and 5-1603(f) supersedes county-level implementation with the Commission’s “due consideration [of] the need to minimize the loss of forest and the provisions of afforestation and reforestation set forth in [the FCA] together with all applicable electrical safety codes.” Md. Natural Resources Article 5-1603(f).
G
ener
atio
n In
terc
onne
ctio
n
Fea
sibili
ty S
tudy
Rep
ort
Que
ue P
ositi
on X
3-00
8 Th
e In
terc
onne
ctio
n C
usto
mer
(IC
) has
pro
pose
d a
20 M
WE
(7.6
MW
C; 2
0 M
W M
FO) s
olar
po
wer
ed g
ener
atin
g fa
cilit
y to
be
loca
ted
in D
orch
este
r Cou
nty,
Mar
ylan
d. P
JM st
udie
d X
3-00
8 as
a
20 M
W in
ject
ion
into
the
Del
mar
va P
ower
and
Lig
ht (D
PL) s
yste
m a
nd e
valu
ated
the
proj
ect f
or
com
plia
nce
with
relia
bilit
y cr
iteria
for s
umm
er p
eak
cond
ition
s in
201
5. T
he p
lann
ed in
-ser
vice
dat
e,
as st
ated
in th
e A
ttach
men
t N, i
s Jun
e 01
, 201
7.
Poin
t(s) o
f Int
erco
nnec
tion
Th
e In
terc
onne
ctio
n C
usto
mer
requ
este
d a
Prim
ary
and
Seco
ndar
y Po
int o
f Int
erco
nnec
tion
(PO
I) be
ev
alua
ted
for t
he X
3-00
8 pr
ojec
t. T
he P
rimar
y PO
I sel
ecte
d w
as a
25k
V d
istrib
utio
n le
vel
inte
rcon
nect
ion
at th
e To
dd 2
5kV
subs
tatio
n. T
he S
econ
dary
PO
I sel
ecte
d w
as a
69k
V tr
ansm
issio
n le
vel i
nter
conn
ectio
n al
so a
t the
Tod
d su
bsta
tion.
The
stud
y re
sults
are
pro
vide
d in
the
Tran
smis
sion
Net
wor
k Im
pact
s sec
tion
belo
w.
Pr
imar
y PO
I Opt
ion
X3-
008
will
inte
rcon
nect
with
the
Del
mar
va P
ower
and
Lig
ht s
yste
m a
t the
Tod
d 69
/25k
V su
bsta
tion
as fo
llow
s.
10
MW
s will
con
nect
to th
e ex
istin
g T1
tran
sfor
mer
; 10
MW
s will
con
nect
to th
e ex
istin
g T2
tra
nsfo
rmer
.
Dir
ect C
onne
ctio
n R
equi
rem
ents
Tra
nsm
issio
n O
wne
r Sc
ope
of W
ork
The
scop
e of
wor
k an
d es
timat
ed c
osts
for t
he d
irect
con
nect
ion
faci
litie
s is
as fo
llow
s:
1.
Es
tabl
ish
two
(2) n
ew 2
5 kV
feed
ers w
ith 9
54 a
lum
inum
con
duct
or fr
om th
e To
dd S
ubst
atio
n to
the
PV si
te –
app
roxi
mat
ely
1.5
mile
s eac
h.
2.
A u
tility
ope
rate
d re
clos
er w
ill b
e re
quire
d on
the
cust
omer
tap
that
will
hav
e pr
oper
rela
ying
an
d co
mm
unic
atio
n.
3.
Util
ity g
rade
prim
ary
met
erin
g w
ill b
e re
quire
d.
4.
Gen
erat
ion
tele
met
ry a
nd re
mot
e tri
p ca
pabi
litie
s w
ill b
e pr
ovid
ed to
the
cont
rol c
ente
r. 5.
Pe
rform
a d
etai
led
time
base
d st
udy.
6.
Pr
otec
tion,
Pla
nnin
g, a
nd o
ther
eng
inee
ring
depa
rtmen
ts w
ill p
erfo
rm st
udie
s, de
sign
wor
k,
and
prep
are
engi
neer
ing
estim
ates
. 7.
Tr
ansf
er tr
ip m
ay b
e re
quire
d.
Th
e es
timat
ed c
ost t
o pe
rform
this
wor
k is
as fo
llow
s:
2
$450
,000
954
AA
C E
xpre
ss F
eede
rM
iles
$600
,000
Fibe
r Ins
talla
tion
Mile
s$7
5,00
0$5
0,00
0$2
0,00
0$1
0,00
0$3
0,00
0$2
0,00
0$1
,255
,000
$1,4
80,9
00$1
,703
,035
Var
ious
Dep
artm
ents
Wor
kSu
btot
al C
ost
Subt
otal
Cos
t with
18%
Ove
rhea
dsA
ppro
xim
ate
Tota
l Cos
t with
15%
Con
tinge
ncy
Rec
lose
r w/ R
elay
ing
and
Com
mun
icat
ions
Util
ity G
rade
Met
erin
gSC
AD
A In
tegr
atio
n in
to E
MS
Det
aile
d Ti
me
Bas
ed S
tudy
Est
imat
ed C
osts
Tod
d Su
bsta
tion
T1
New
Fee
der T
erm
inal
, Bre
aker
, and
Upg
rade
s 1.5
$300
,000
954
AA
C E
xpre
ss F
eede
rM
iles
$600
,000
Fibe
r Ins
talla
tion
Mile
s$7
5,00
0$5
0,00
0$2
0,00
0$1
0,00
0$1
,055
,000
$1,2
44,9
00$1
,431
,635
SCA
DA
Inte
grat
ion
into
EM
SSu
btot
al C
ost
Subt
otal
Cos
t with
18%
Ove
rhea
dsA
ppro
xim
ate
Tota
l Cos
t with
15%
Con
tinge
ncy
Est
imat
ed C
osts
Tod
d Su
bsta
tion
T2
New
Fee
der T
erm
inal
, Bre
aker
, and
Upg
rade
s 1.5
Rec
lose
r w/ R
elay
ing
and
Com
mun
icat
ions
Util
ity G
rade
Met
erin
g
App
roxi
mat
e To
tal C
ost f
or T
wo
Feed
ers:
$3,
134,
670
The
estim
ated
tim
e to
com
plet
e th
is w
ork
is 12
- 18
mon
ths a
fter r
ecei
pt o
f a fu
lly e
xecu
ted
inte
rcon
nect
ion
agre
emen
t. N
ote:
the
abo
ve c
ost d
oes n
ot in
clud
e th
e C
ontri
butio
n in
Aid
of C
onst
ruct
ion
(CIA
C) t
ax.
Spec
ial O
pera
ting
Req
uire
men
ts
1.
PH
I will
requ
ire th
e ca
pabi
lity
to re
mot
ely
trip
the
gene
rato
r fro
m it
s Sys
tem
Ope
ratio
ns
faci
lity.
Suc
h tri
ppin
g m
ay b
e fa
cilit
ated
by
eith
er a
gen
erat
or b
reak
er, i
nver
ter (
if so
eq
uipp
ed),
or a
line
recl
oser
, dep
endi
ng u
pon
the
spec
ific
circ
umst
ance
s and
the
eval
uatio
n by
PH
I.
3
2.
It is
the
Inte
rcon
nect
ion
Cus
tom
er’s
resp
onsi
bilit
y to
send
the
data
that
PJM
and
the
Com
pany
re
quire
s dire
ctly
to P
JM.
The
Inte
rcon
nect
ion
Cus
tom
er w
ill g
rant
per
mis
sion
for P
JM to
se
nd th
e C
ompa
ny th
e fo
llow
ing
tele
met
ry th
at th
e In
terc
onne
ctio
n C
usto
mer
send
s to
PJM
: re
al ti
me
MW
, MV
AR
, vol
ts, a
mpe
res,
gene
rato
r/sta
tus,
and
inte
rval
MW
H a
nd M
VA
RH
.
3.
The
Inte
rcon
nect
ion
Cus
tom
er w
ill b
e re
quire
d to
mak
e pr
ovis
ions
for a
voi
ce q
ualit
y ph
one
line
with
in a
ppro
xim
atel
y 3
feet
of e
ach
Com
pany
met
erin
g po
sitio
n to
faci
litat
e re
mot
e in
terr
ogat
ion
and
data
col
lect
ion.
4.
A m
utua
lly a
ccep
tabl
e m
eans
of i
nter
rupt
ing
and
disc
onne
ctin
g th
e ge
nera
tor w
ith a
vis
ible
br
eak,
abl
e to
be
tagg
ed a
nd lo
cked
out
, sha
ll be
wor
ked
out w
ith P
HI E
ngin
eerin
g.
Inte
rcon
nect
ion
Cus
tom
er S
cope
of W
ork
The
Inte
rcon
nect
ion
Cus
tom
er (I
C) i
s res
pons
ible
for a
ll de
sign
and
con
stru
ctio
n re
late
d to
act
iviti
es
on th
eir s
ide
of th
e Po
int o
f Int
erco
nnec
tion.
Site
pre
para
tion,
incl
udin
g gr
adin
g an
d an
acc
ess r
oad,
as
nec
essa
ry, i
s ass
umed
to b
e by
the
IC.
Rout
e se
lect
ion,
line
des
ign,
and
righ
t-of
-way
acq
uisit
ion
of
the
dire
ct c
onne
ct fa
cilit
ies
is no
t inc
lude
d in
this
repo
rt, a
nd is
the
resp
onsi
bilit
y of
the
IC.
Th
e IC
will
be
requ
ired
to in
stal
l met
erin
g an
d te
lem
etry
equ
ipm
ent t
o pr
ovid
e re
venu
e m
eter
ing
and
real
-tim
e te
lem
etry
dat
a to
PJM
. The
requ
irem
ents
for t
his e
quip
men
t are
list
ed in
App
endi
x 2,
Se
ctio
n 8
of A
ttach
men
t O to
the
PJM
Tar
iff, a
s wel
l as P
JM M
anua
ls 01
and
14D
. Pro
tect
ive
rela
ying
and
met
erin
g de
sign
and
inst
alla
tion
mus
t com
ply
with
PH
I’s A
pplic
able
Sta
ndar
ds.
The
Inte
rcon
nect
ion
Cus
tom
er w
ill p
urch
ase
and
inst
all a
ll m
eter
ing
inst
rum
ent t
rans
form
ers a
s wel
l as
con
stru
ct a
met
erin
g st
ruct
ure
per P
HI's
spe
cific
atio
ns. T
he se
cond
ary
wiri
ng c
onne
ctio
ns a
t the
in
stru
men
t tra
nsfo
rmer
s will
be
com
plet
ed b
y th
e In
terc
onne
ctio
n C
usto
mer
's co
ntra
ctor
s and
in
spec
ted
by P
HI,
whi
le th
e se
cond
ary
wiri
ng w
ork
at th
e m
eter
ing
encl
osur
e w
ill b
e co
mpl
eted
by
PHI's
met
er te
chni
cian
s. Th
e m
eter
ing
cont
rol c
able
and
met
er c
abin
ets w
ill b
e su
pplie
d by
PH
I and
in
stal
led
by th
e In
terc
onne
ctio
n C
usto
mer
's co
ntra
ctor
s. PH
I's m
eter
tech
nici
ans w
ill p
rogr
am a
nd
inst
all t
wo
solid
stat
e m
ulti
func
tion
met
ers (
Prim
ary
& B
acku
p) fo
r the
new
met
erin
g po
sitio
n.
Inve
rter R
equi
rem
ents
and
Cap
abili
ties
The
inve
rter a
t the
DG
loca
tion
shal
l hav
e th
e fo
llow
ing
capa
bilit
ies:
1.
V
olta
ge fl
icke
r red
uctio
n th
roug
h dy
nam
ic V
AR
resp
onse
2.
Ram
p ra
te c
ontro
l 3.
SC
AD
A c
omm
unic
atio
ns
4.
Cur
tailm
ent o
r oth
er m
itiga
tion
abili
ty if
hig
h vo
ltage
wer
e to
occ
ur
5.
Low
vol
tage
and
sys
tem
dist
urba
nce
ride
thro
ugh
6.
Abi
lity
to re
ceiv
e an
d re
spon
d to
a tr
ansf
er tr
ip o
r SC
AD
A s
igna
l
4
The
inve
rter s
hall
oper
ate
in a
ccor
danc
e w
ith th
e IE
EE 1
547
serie
s of s
tand
ards
that
hav
e be
en
appr
oved
. W
hile
inve
rters
shou
ld b
e ca
pabl
e of
vol
tage
stab
iliza
tion
thru
dyn
amic
VA
R re
spon
se
and
capa
ble
of lo
w v
olta
ge a
nd s
yste
m d
istur
banc
e rid
e th
roug
h, n
eith
er o
f the
se c
apab
ilitie
s sha
ll be
im
plem
ente
d un
til su
ch ti
me
that
the
IEEE
154
7 se
ries o
f sta
ndar
ds a
re re
vise
d an
d ap
prov
ed to
in
clud
e st
anda
rds
for t
hese
cap
abili
ties.
At s
uch
time
as th
ese
revi
sed
stan
dard
s bec
ome
avai
labl
e,
the
PV o
wne
r/ope
rato
r sha
ll co
oper
ate
with
the
Com
pany
(the
‘Com
pany
’ ref
errin
g to
AC
E, D
PL, o
r PE
PCO
) to
impl
emen
t the
se c
apab
ilitie
s with
setti
ngs a
ccep
tabl
e to
the
Com
pany
. U
ntil
such
tim
e,
the
inve
rters
shal
l ope
rate
with
a fi
xed
pow
er fa
ctor
sche
dule
as s
uppl
ied
by th
e C
ompa
ny.
Tra
nsm
issi
on N
etw
ork
Impa
cts
Pote
ntia
l tra
nsm
issio
n ne
twor
k im
pact
s are
as f
ollo
ws:
G
ener
ator
Del
iver
abili
ty
(Sin
gle
or N
-1 c
ontin
genc
ies f
or th
e Ca
paci
ty p
ortio
n on
ly o
f the
inte
rcon
nect
ion)
N
one
Mul
tiple
Fac
ility
Con
tinge
ncy
(D
oubl
e Ci
rcui
t Tow
er L
ine,
Lin
e wi
th F
aile
d Br
eake
r and
, Bus
Fau
lt co
ntin
genc
ies f
or th
e Fu
ll en
ergy
out
put.
N
one
Con
trib
utio
n to
Pre
viou
sly Id
entif
ied
Ove
rloa
ds
(Thi
s pro
ject
con
tribu
tes t
o th
e fo
llowi
ng c
ontin
genc
y ov
erlo
ads,
i.e. “
Netw
ork
Impa
cts”
, ide
ntifi
ed
for e
arlie
r gen
erat
ion
or tr
ansm
issio
n in
terc
onne
ctio
n pr
ojec
ts in
the
PJM
Que
ue)
Non
e Sh
ort C
ircu
it N
o iss
ues
iden
tifie
d.
Stab
ility
Ana
lysis
N
ot re
quire
d du
e to
pro
ject
size
. D
ynam
ic A
naly
sis
DPL
will
com
men
ce a
tim
e-ba
sed
dyna
mic
stud
y du
ring
the
Syst
em Im
pact
Stu
dy p
hase
to e
valu
ate
the
proj
ect’s
impa
ct o
n th
e D
PL d
istrib
utio
n sy
stem
. O
nce
com
plet
e, th
e re
sults
of t
he st
udy
will
be
revi
ewed
and
the
prop
osed
pro
ject
will
be
eval
uate
d fo
r pro
tect
ion
and
coor
dina
tion
issue
s. O
ther
re
quire
d up
grad
es m
ay b
e id
entif
ied
at th
at ti
me.
5
Syst
em P
rote
ctio
n Pr
otec
tive
rela
ying
and
met
erin
g de
sign
and
inst
alla
tion
mus
t com
ply
with
PH
I’s a
pplic
able
st
anda
rds.
Any
oth
er c
osts
det
erm
ined
by
syst
em p
rote
ctio
n as
a re
sult
of th
e sh
ort c
ircui
t stu
dies
will
be
supp
lied
in th
e ne
ar fu
ture
. O
ther
Cha
rges
PH
I res
erve
s the
righ
t to
char
ge th
e In
terc
onne
ctio
n C
usto
mer
Ope
ratio
n an
d M
aint
enan
ce e
xpen
ses
to m
aint
ain
the
Inte
rcon
nect
ion
Cus
tom
er’s
Atta
chm
ent F
acili
ties,
incl
udin
g m
eter
ing
and
tele
com
mun
icat
ions
faci
litie
s whi
ch a
re o
wne
d by
PH
I. N
ew S
yste
m R
einf
orce
men
ts
(Upg
rade
s req
uire
d to
miti
gate
relia
bilit
y cr
iteria
vio
latio
ns, i
.e. “
Netw
ork
Impa
cts,”
initi
ally
cau
sed
by th
e ad
ditio
n of
this
proj
ect’s
gen
erat
ion)
N
one
Con
trib
utio
n to
Pre
viou
sly Id
entif
ied
Syst
em R
einf
orce
men
ts
(Ove
rload
s ini
tially
cau
sed
by p
rior Q
ueue
pos
ition
s with
add
ition
al c
ontri
butio
n to
ove
rloa
ding
by
this
proj
ect.
N
one
Pote
ntia
l Con
gest
ion
due
to L
ocal
Ene
rgy
Del
iver
abili
ty
(PJM
also
stud
ied
the
deliv
ery
of th
e en
ergy
por
tion
of th
e su
rrou
ndin
g ge
nera
tion.
Any
pot
entia
l pr
oble
ms i
dent
ified
bel
ow a
re li
kely
to re
sult
in o
pera
tiona
l res
trict
ions
to th
e pr
ojec
t und
er
study
. Th
e de
velo
per c
an p
roce
ed w
ith N
etwo
rk U
pgra
des t
o el
imin
ate
the
oper
atio
nal r
estr
ictio
n at
th
eir d
iscr
etio
n by
subm
ittin
g a
Tran
smiss
ion
Inte
rcon
nect
ion
Requ
est.
Not
e: O
nly
the
mos
t sev
erel
y ov
erlo
aded
con
ditio
ns a
re li
sted
belo
w. T
here
is n
o gu
aran
tee
of fu
ll de
liver
abili
ty fo
r thi
s pro
ject
by
fixin
g on
ly th
e co
nditi
ons l
isted
in th
is se
ctio
n. W
ith a
Tra
nsm
issio
n In
terc
onne
ctio
n Re
ques
t, a
subs
eque
nt a
naly
sis w
ill b
e pe
rfor
med
whi
ch a
naly
zes a
ll ov
erlo
ad c
ondi
tions
ass
ocia
ted
with
the
iden
tifie
d ov
erlo
aded
ele
men
t(s).
As a
resu
lt of
the
aggr
egat
e en
ergy
reso
urce
s in
the
area
, the
fo
llowi
ng v
iola
tions
wer
e id
entif
ied:
Th
ese
are
not r
equi
red
relia
bilit
y up
grad
es.
1.
The
(DP&
L/PE
CO
) Cla
ymon
t-Lin
woo
d 23
0 kV
line
(fro
m b
us 2
3100
0 to
bus
213
750
ckt 1
) lo
ads
from
100
.00%
to 1
00.0
7% (D
C p
ower
flow
) of i
ts e
mer
genc
y ra
ting
(805
MV
A) f
or th
e op
erat
iona
l con
tinge
ncy
'220
-85'
. Th
is pr
ojec
t con
tribu
tes a
ppro
xim
atel
y 3.
53 M
W to
the
ther
mal
vi
olat
ion.
6
Seco
ndar
y PO
I Opt
ion
PJM
stud
ied
X3-
008
as a
20
MW
inje
ctio
n at
the
Todd
69k
V su
bsta
tion.
T
rans
mis
sion
Net
wor
k Im
pact
s Po
tent
ial t
rans
mis
sion
netw
ork
impa
cts a
re a
s fol
low
s:
Gen
erat
or D
eliv
erab
ility
(S
ingl
e or
N-1
con
tinge
ncie
s for
the
Capa
city
por
tion
only
of t
he in
terc
onne
ctio
n)
Non
e M
ultip
le F
acili
ty C
ontin
genc
y
(Dou
ble
Circ
uit T
ower
Lin
e, L
ine
with
Fai
led
Brea
ker a
nd, B
us F
ault
cont
inge
ncie
s for
the
Full
ener
gy o
utpu
t.
Non
e C
ontr
ibut
ion
to P
revi
ously
Iden
tifie
d O
verl
oads
(T
his p
roje
ct c
ontri
bute
s to
the
follo
wing
con
tinge
ncy
over
load
s, i.e
. “Ne
twor
k Im
pact
s”, i
dent
ified
fo
r ear
lier g
ener
atio
n or
tran
smiss
ion
inte
rcon
nect
ion
proj
ects
in th
e PJ
M Q
ueue
) N
one
Shor
t Cir
cuit
No
issue
s id
entif
ied.
Po
tent
ial C
onge
stio
n du
e to
Loc
al E
nerg
y D
eliv
erab
ility
(P
JM a
lso st
udie
d th
e de
liver
y of
the
ener
gy p
ortio
n of
the
surr
ound
ing
gene
ratio
n. A
ny p
oten
tial
prob
lem
s ide
ntifi
ed b
elow
are
like
ly to
resu
lt in
ope
ratio
nal r
estri
ctio
ns to
the
proj
ect u
nder
stu
dy.
The
deve
lope
r can
pro
ceed
with
Net
work
Upg
rade
s to
elim
inat
e th
e op
erat
iona
l res
tric
tion
at
thei
r dis
cret
ion
by su
bmitt
ing
a Tr
ansm
issio
n In
terc
onne
ctio
n Re
ques
t. N
ote:
Onl
y th
e m
ost s
ever
ely
over
load
ed c
ondi
tions
are
liste
d be
low.
The
re is
no
guar
ante
e of
full
deliv
erab
ility
for t
his p
roje
ct b
y fix
ing
only
the
cond
ition
s list
ed in
this
sect
ion.
With
a T
rans
miss
ion
Inte
rcon
nect
ion
Requ
est,
a su
bseq
uent
ana
lysi
s will
be
perf
orm
ed w
hich
ana
lyze
s all
over
load
con
ditio
ns a
ssoc
iate
d wi
th th
e id
entif
ied
over
load
ed e
lem
ent(s
). A
s a re
sult
of th
e ag
greg
ate
ener
gy re
sour
ces i
n th
e ar
ea, t
he
follo
wing
vio
latio
ns w
ere
iden
tifie
d:
Thes
e ar
e no
t req
uire
d re
liabi
lity
upgr
ades
. 1.
Th
e (D
P&L/
PEC
O) C
laym
ont-L
inw
ood
230
kV li
ne (f
rom
bus
231
000
to b
us 2
1375
0 ck
t 1)
load
s fro
m 1
00.0
0% to
100
.07%
(DC
pow
er fl
ow) o
f its
em
erge
ncy
ratin
g (8
05 M
VA
) for
the
7
oper
atio
nal c
ontin
genc
y '2
20-8
5'.
This
proj
ect c
ontri
bute
s app
roxi
mat
ely
3.53
MW
to th
e th
erm
al
viol
atio
n.
Gen
erat
ion
Inte
rcon
nect
ion
Sy
stem
Impa
ct S
tudy
Rep
ort
Fo
r PJ
M G
ener
atio
n In
terc
onne
ctio
n Re
ques
t Q
ueue
Pos
ition
X3-
008
“T
odd
69kV
”
July
201
2
©
PJM
Inte
rcon
nect
ion
2012
. All
right
s res
erve
d.
PJM
DO
CS-
# 70
6907
-v1
X3-
008
Todd
69k
V
2
Pref
ace
The
inte
nt o
f the
Sys
tem
Impa
ct S
tudy
is to
det
erm
ine
a pl
an, w
ith a
ppro
xim
ate
cost
and
co
nstru
ctio
n tim
e es
timat
es, t
o co
nnec
t the
subj
ect g
ener
atio
n in
terc
onne
ctio
n pr
ojec
t to
the
PJM
ne
twor
k at
a lo
catio
n sp
ecifi
ed b
y th
e In
terc
onne
ctio
n C
usto
mer
. As a
requ
irem
ent f
or
inte
rcon
nect
ion,
the
Inte
rcon
nect
ion
Cus
tom
er m
ay b
e re
spon
sibl
e fo
r the
cos
t of c
onst
ruct
ing:
N
etw
ork
Upg
rade
s, w
hich
are
faci
lity
addi
tions
, or u
pgra
des t
o ex
istin
g fa
cilit
ies,
that
are
nee
ded
to
mai
ntai
n th
e re
liabi
lity
of th
e PJ
M sy
stem
. All
faci
litie
s req
uire
d fo
r int
erco
nnec
tion
of a
gen
erat
ion
inte
rcon
nect
ion
proj
ect m
ust b
e de
sign
ed to
mee
t the
tech
nica
l spe
cific
atio
ns (o
n PJ
M w
eb si
te) f
or
the
appr
opria
te tr
ansm
issi
on o
wne
r. In
som
e in
stan
ces a
n In
terc
onne
ctio
n C
usto
mer
may
not
be
resp
onsi
ble
for 1
00%
of t
he id
entif
ied
netw
ork
upgr
ade
cost
bec
ause
oth
er tr
ansm
issi
on n
etw
ork
uses
, e.g
. ano
ther
gen
erat
ion
inte
rcon
nect
ion
or m
erch
ant t
rans
mis
sion
upg
rade
, may
als
o co
ntrib
ute
to th
e ne
ed fo
r the
sam
e ne
twor
k re
info
rcem
ent.
The
poss
ibili
ty o
f sha
ring
the
rein
forc
emen
t cos
ts w
ith o
ther
pro
ject
s may
be
iden
tifie
d in
the
Feas
ibili
ty S
tudy
, but
the
actu
al a
lloca
tion
will
be
defe
rred
unt
il th
e Sy
stem
Impa
ct
Stud
y is
per
form
ed.
The
Syst
em Im
pact
Stu
dy e
stim
ates
do
not i
nclu
de th
e fe
asib
ility
, cos
t, or
tim
e re
quire
d to
obt
ain
prop
erty
righ
ts a
nd p
erm
its fo
r con
stru
ctio
n of
the
requ
ired
faci
litie
s. Ty
pica
lly, t
he p
roje
ct
deve
lope
r is r
espo
nsib
le fo
r rig
ht o
f way
, rea
l est
ate,
and
con
stru
ctio
n pe
rmit
issu
es.
For p
rope
rties
cu
rren
tly o
wne
d by
Tra
nsm
issi
on O
wne
rs, t
he c
osts
may
be
incl
uded
in th
e st
udy.
G
ener
al
Inve
nerg
y So
lar D
evel
opm
ent L
LC, t
he In
terc
onne
ctio
n C
usto
mer
(IC
), ha
s pro
pose
d a
20 M
WE
(7.6
MW
C; 2
0 M
W M
FO) s
olar
pow
ered
gen
erat
ing
faci
lity
to b
e lo
cate
d in
Dor
ches
ter C
ount
y,
Mar
ylan
d. P
JM st
udie
d X
3-00
8 as
a 2
0 M
W in
ject
ion
into
the
Del
mar
va P
ower
and
Lig
ht (D
PL)
dist
ribut
ion
syst
em a
t the
Tod
d 69
/25k
V su
bsta
tion
and
eval
uate
d th
e pr
ojec
t for
com
plia
nce
with
re
liabi
lity
crite
ria fo
r sum
mer
pea
k co
nditi
ons i
n 20
15.
The
plan
ned
in-s
ervi
ce d
ate,
as s
tate
d in
the
Atta
chm
ent N
, is J
une
01, 2
017.
Po
int o
f Int
erco
nnec
tion
X
3-00
8 w
ill in
terc
onne
ct w
ith th
e D
elm
arva
Pow
er a
nd L
ight
syst
em a
t the
Tod
d 69
/25k
V
subs
tatio
n as
follo
ws (
see
Atta
chm
ent 1
):
10
MW
s will
con
nect
to th
e ex
istin
g 69
/25k
V T
1 tra
nsfo
rmer
; 10
MW
s will
con
nect
to th
e ex
istin
g 69
/25k
V T
2 tra
nsfo
rmer
. D
irec
t Con
nect
ion
Req
uire
men
ts
Crit
eria
Lim
its fo
r Dis
tribu
ted
Ener
gy R
esou
rce
Con
nect
ions
to th
e D
PL D
istri
butio
n Sy
stem
s (le
ss
than
69k
V)
1. E
xist
ing
Dis
tribu
tion
Circ
uit C
apac
ity L
imits
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
3
The
aggr
egat
e lim
it of
larg
e (2
50 k
W a
nd o
ver)
gen
erat
or in
ject
ion
to a
sing
le, e
xist
ing
dist
ribut
ion
circ
uit i
s 0.5
MW
s on
the
4kV
, 3M
Ws o
n th
e 12
kV
, 6 M
Ws o
n th
e 25
kV
, and
10
MW
s on
the
34
kV.
2. E
xpre
ss C
ircui
t Cap
acity
Lim
its
Dis
tribu
ted
gene
ratio
n in
stal
latio
ns w
hich
exc
eed
the
limit
for a
n ex
istin
g ci
rcui
t req
uire
an
expr
ess
circ
uit.
The
max
imum
gen
erat
or si
ze fo
r exp
ress
circ
uits
shal
l be:
� 4
kV
0.
5 M
W
� 12
– 1
3.8
kV
10 M
Ws
� 23
– 2
5 kV
10 M
Ws
� 33
.26
– 34
.5 k
V
15 M
Ws
3. D
istri
butio
n Po
wer
Tra
nsfo
rmer
Lim
it Th
e ag
greg
ate
limit
of la
rge
(250
kW
and
ove
r) g
ener
ator
inje
ctio
n to
a si
ngle
dis
tribu
tion
trans
form
er o
f 22.
5 M
VA
nam
epla
te o
r lar
ger i
s 10
MW
s. Tr
ansf
orm
ers w
ith n
amep
late
ratin
gs
low
er th
an 2
2.5
MV
A w
ill b
e gi
ven
low
er ra
tings
on
an in
divi
dual
bas
is. I
f the
tran
sfor
mer
ratin
g is
si
gnifi
cant
ly g
reat
er th
an 4
0 M
VA
it m
ay b
e po
ssib
le to
con
side
r a g
reat
er a
mou
nt o
f inj
ectio
n.
Add
ing
a ne
w tr
ansf
orm
er w
ill b
e co
nsid
ered
if th
ere
is n
o av
aila
bilit
y on
any
of t
he e
xist
ing
trans
form
ers a
nd sp
ace
is a
vaila
ble
in a
n ex
istin
g su
bsta
tion.
Any
pro
pose
d tra
nsfo
rmer
s wou
ld b
e PH
I's st
anda
rd d
istri
butio
n tra
nsfo
rmer
(37
MV
A n
amep
late
ratin
g.)
4. E
xpre
ss C
ircui
t Len
gth
Lim
it If
ther
e is
no
mor
e in
ject
ion
capa
city
or s
pace
for a
n ad
ditio
nal t
rans
form
er a
t the
clo
sest
subs
tatio
n,
the
next
clo
sest
subs
tatio
n w
ill b
e co
nsid
ered
. The
leng
th o
f an
expr
ess c
ircui
t is l
imite
d to
5 m
iles,
or fo
r the
sake
of t
he fe
asib
ility
stud
y, 3
.8 st
raig
ht li
ne m
iles.
This
sim
plifi
catio
n is
use
d be
caus
e th
e fe
asib
ility
stud
y ph
ase
does
not
allo
w fo
r the
tim
e an
d re
sour
ces t
o ex
amin
e ro
utes
in d
etai
l (in
clud
ing
exis
ting
pole
line
s, ea
sem
ents
, RO
W, a
nd e
nviro
nmen
tal i
ssue
s etc
.)
5. W
hen
a N
ew S
ubst
atio
n is
Req
uire
d If
a d
istri
butio
n ex
pres
s circ
uit c
an’t
be b
uilt
from
an
exis
ting
subs
tatio
n fo
r a p
roje
ct, i
t will
be
nece
ssar
y to
con
stru
ct a
new
dis
tribu
tion
subs
tatio
n w
ith a
stan
dard
ring
bus
des
ign.
It w
ill b
e su
pplie
d by
ext
endi
ng e
xist
ing
trans
mis
sion
line
s. It
is th
e de
velo
per's
resp
onsi
bilit
y to
ver
ify
elig
ibili
ty o
f thi
s con
figur
atio
n fo
r sol
ar re
new
able
ene
rgy
certi
ficat
es w
ith N
ew Je
rsey
's C
lean
En
ergy
Pro
gram
if d
esire
d.
All
inje
ctio
n lim
its, g
iven
abo
ve in
MW
s, ar
e su
bjec
t to
mor
e de
taile
d st
udy
to e
nsur
e fe
asib
ility
. T
rans
mis
sion
Ow
ner
Scop
e of
Wor
k Th
e sc
ope
of w
ork
and
estim
ated
cos
t for
the
dire
ct c
onne
ctio
n fa
cilit
ies i
s as f
ollo
ws:
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
4
1.
Con
stru
ct tw
o (2
) new
25
kV fe
eder
s with
954
kcm
il A
ll A
lum
inum
Con
duct
or (A
AC
) fro
m
the
Todd
Sub
stat
ion
to th
e PV
site
– a
dis
tanc
e of
app
roxi
mat
ely
2.2
mile
s.
2.
Con
stru
ct tw
o (2
) new
25
kV fe
eder
term
inal
pos
ition
s at t
he T
odd
subs
tatio
n.
3.
A u
tility
ope
rate
d re
clos
er e
quip
ped
with
the
prop
er re
layi
ng a
nd c
omm
unic
atio
ns w
ill b
e in
stal
led
for e
ach
feed
er se
rvin
g th
e PV
gen
erat
or.
4.
Util
ity g
rade
prim
ary
met
erin
g w
ill b
e re
quire
d fo
r eac
h fe
eder
. 5.
Th
e in
verte
r sha
ll be
des
igne
d to
acc
omm
odat
e fu
ture
cap
abili
ty to
adj
ust o
utpu
t and
pow
er
fact
or if
nee
ded.
6.
A
det
aile
d, ti
me-
base
d st
udy
may
be
perf
orm
ed d
urin
g la
ter s
tudy
pha
ses.
7.
Pr
otec
tion,
Pla
nnin
g, a
nd o
ther
eng
inee
ring
depa
rtmen
ts w
ill p
erfo
rm st
udie
s, de
sign
wor
k,
and
prep
are
engi
neer
ing
estim
ates
. 8.
Tr
ansf
er tr
ip w
ill b
e re
quire
d. A
ppro
xim
atel
y 2.
2 m
iles o
f 48S
M A
DSS
fibe
r opt
ic c
able
was
es
timat
ed fo
r thi
s rep
ort t
o pr
ovid
e th
e co
mm
unic
atio
n ch
anne
l fro
m T
odd
Sub
to th
e PV
si
te.
Th
e es
timat
ed c
ost t
o pe
rfor
m th
is w
ork
is a
s fol
low
s:
$480
,000
954
AA
C E
xpre
ss F
eede
rM
iles
$455
,000
Fibe
r Ins
talla
tion
Mile
s$1
10,0
00$5
0,00
0$2
0,00
0$1
0,00
0$3
0,00
0$2
0,00
0$1
,175
,000
$1,3
86,5
00$1
,594
,475
Rec
lose
r w/ R
elay
ing
and
Com
mun
icat
ions
Util
ity G
rade
Met
erin
gSC
AD
A In
tegr
atio
n in
to E
MS
Det
aile
d Ti
me
Bas
ed S
tudy
Est
imat
ed C
osts
Tod
d Su
bsta
tion
T1
New
Fee
der T
erm
inal
, Bre
aker
, Upg
rade
s
2.2
Var
ious
Dep
artm
ents
Wor
kSu
btot
al C
ost
Subt
otal
Cos
t with
18%
Ove
rhea
dsA
ppro
xim
ate
Tot
al C
ost w
ith 1
5% C
ontin
genc
y
$330
,000
954
AA
C E
xpre
ss F
eede
r2.
2M
iles
$455
,000
$50,
000
$20,
000
$10,
000
$865
,000
$1,0
20,7
00$1
,173
,805
Est
imat
ed C
osts
Tod
d Su
bsta
tion
T2
New
Fee
der T
erm
inal
, Bre
aker
, Upg
rade
s
Subt
otal
Cos
tSu
btot
al C
ost w
ith 1
8% O
verh
eads
App
roxi
mat
e T
otal
Cos
t with
15%
Con
tinge
ncy
Rec
lose
r w/ R
elay
ing
and
Com
mun
icat
ions
Util
ity G
rade
Met
erin
gSC
AD
A In
tegr
atio
n in
to E
MS
A
ppro
xim
ate
tota
l cos
t for
bot
h fe
eder
s: $
2,76
8,28
0
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
5
Spec
ial O
pera
ting
Req
uire
men
ts
1.
D
PL w
ill re
quire
the
capa
bilit
y to
rem
otel
y tri
p th
e ge
nera
tor f
rom
its S
yste
m O
pera
tions
fa
cilit
y. S
uch
tripp
ing
may
be
faci
litat
ed b
y ei
ther
a g
ener
ator
bre
aker
, inv
erte
r (if
so
equi
pped
), or
a li
ne re
clos
er, d
epen
ding
upo
n th
e sp
ecifi
c ci
rcum
stan
ces a
nd th
e ev
alua
tion
by D
PL.
2.
It
is th
e In
terc
onne
ctio
n C
usto
mer
’s re
spon
sibi
lity
to se
nd th
e da
ta th
at P
JM a
nd D
PL
requ
ires d
irect
ly to
PJM
. Th
e In
terc
onne
ctio
n C
usto
mer
will
gra
nt p
erm
issi
on fo
r PJM
to
send
to D
PL th
e fo
llow
ing
tele
met
ry th
at th
e In
terc
onne
ctio
n C
usto
mer
send
s to
PJM
: rea
l tim
e M
W, M
VA
R, v
olts
, am
pere
s, ge
nera
tor/s
tatu
s, an
d in
terv
al M
WH
and
MV
AR
H.
3.
Th
e In
terc
onne
ctio
n C
usto
mer
will
be
requ
ired
to m
ake
prov
isio
ns fo
r a v
oice
qua
lity
phon
e lin
e w
ithin
app
roxi
mat
ely
3 fe
et o
f eac
h D
PL m
eter
ing
posi
tion
to fa
cilit
ate
rem
ote
inte
rrog
atio
n an
d da
ta c
olle
ctio
n.
4.
A
mut
ually
acc
epta
ble
mea
ns o
f int
erru
ptin
g an
d di
scon
nect
ing
the
gene
rato
r with
a v
isib
le
brea
k, a
ble
to b
e ta
gged
and
lock
ed o
ut, s
hall
be w
orke
d ou
t with
DPL
Dis
tribu
tion
Engi
neer
ing.
In
terc
onne
ctio
n C
usto
mer
Sco
pe o
f Dir
ect C
onne
ctio
n W
ork
The
Inte
rcon
nect
ion
Cus
tom
er (I
C) i
s res
pons
ible
for a
ll de
sign
and
con
stru
ctio
n re
late
d ac
tiviti
es o
n th
eir s
ide
of th
e Po
int o
f Int
erco
nnec
tion.
Site
pre
para
tion,
incl
udin
g gr
adin
g an
d an
acc
ess r
oad,
as
nece
ssar
y, is
ass
umed
to b
e by
the
IC.
Rou
te se
lect
ion,
line
des
ign,
and
righ
t-of-
way
acq
uisi
tion
of
the
dire
ct c
onne
ct fa
cilit
ies i
s not
incl
uded
in th
is re
port
and
is th
e re
spon
sibi
lity
of th
e IC
. Pr
otec
tive
rela
ying
and
met
erin
g de
sign
and
inst
alla
tion
mus
t com
ply
with
DPL
’s a
pplic
able
st
anda
rds.
The
IC is
als
o re
quire
d to
pro
vide
reve
nue
met
erin
g an
d re
al-ti
me
tele
met
erin
g da
ta to
PJ
M in
con
form
ance
with
the
requ
irem
ents
con
tain
ed in
PJM
Man
uals
M-0
1 an
d M
-14
and
the
PJM
Ta
riff.
Th
e in
verte
r at t
he D
G lo
catio
n sh
all h
ave
the
follo
win
g ca
pabi
litie
s:
� V
olta
ge fl
icke
r red
uctio
n th
roug
h dy
nam
ic V
AR
or f
ixed
PF
resp
onse
� R
amp
rate
con
trol
� SC
AD
A c
omm
unic
atio
ns
� C
urta
ilmen
t or o
ther
miti
gatio
n ab
ility
if h
igh
volta
ge w
ere
to o
ccur
� Lo
w v
olta
ge a
nd s
yste
m d
istu
rban
ce ri
de th
roug
h
� A
bilit
y to
rece
ive
and
resp
ond
to a
tran
sfer
trip
sign
al
� A
bilit
y to
adj
ust P
F or
VA
Rs b
ased
on
utili
ty si
gnal
� A
bilit
y to
Adj
ust R
eal P
ower
Out
put b
ased
on
utili
ty si
gnal
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
6
The
inve
rter s
hall
oper
ate
in a
ccor
danc
e w
ith th
e IE
EE 1
547
serie
s of s
tand
ards
that
hav
e be
en
appr
oved
. W
hile
inve
rters
shou
ld b
e ca
pabl
e of
vol
tage
stab
iliza
tion
thru
dyn
amic
VA
R re
spon
se
and
capa
ble
of lo
w v
olta
ge a
nd s
yste
m d
istu
rban
ce ri
de th
roug
h, n
eith
er o
f the
se c
apab
ilitie
s sha
ll be
im
plem
ente
d un
til su
ch ti
me
that
the
IEEE
154
7 se
ries o
f sta
ndar
ds a
re re
vise
d an
d ap
prov
ed to
in
clud
e st
anda
rds f
or th
ese
capa
bilit
ies.
At s
uch
time
as th
ese
revi
sed
stan
dard
s bec
ome
avai
labl
e,
the
PV o
wne
r/ope
rato
r sha
ll co
oper
ate
with
the
Com
pany
(the
‘Com
pany
’ ref
errin
g to
AC
E, D
PL, o
r PE
PCO
) to
impl
emen
t the
se c
apab
ilitie
s with
setti
ngs a
ccep
tabl
e to
the
Com
pany
. U
ntil
such
tim
e,
the
inve
rters
shal
l ope
rate
with
a fi
xed
pow
er fa
ctor
sche
dule
as s
uppl
ied
by th
e C
ompa
ny, a
nd b
e ab
le to
ope
rate
in th
e ra
nge
of 0
.95
lead
ing
to 0
.95
lagg
ing,
as s
peci
fied
by P
JM.
Tra
nsm
issi
on N
etw
ork
Impa
cts
Pote
ntia
l tra
nsm
issi
on n
etw
ork
impa
cts w
ere
as fo
llow
s:
Gen
erat
or D
eliv
erab
ility
(S
ingl
e or
N-1
con
tinge
ncie
s for
the
Capa
city
por
tion
only
of t
he in
terc
onne
ctio
n)
Non
e M
ultip
le F
acili
ty C
ontin
genc
y
(Dou
ble
Cir
cuit
Tow
er L
ine,
Lin
e w
ith F
aile
d Br
eake
r and
, Bus
Fau
lt co
ntin
genc
ies f
or th
e Fu
ll en
ergy
out
put.
N
one
Con
trib
utio
n to
Pre
viou
sly
Iden
tifie
d O
verl
oads
(T
his p
roje
ct c
ontr
ibut
es to
the
follo
win
g co
ntin
genc
y ov
erlo
ads,
i.e. “
Net
wor
k Im
pact
s”, i
dent
ified
fo
r ear
lier g
ener
atio
n or
tran
smis
sion
inte
rcon
nect
ion
proj
ects
in th
e PJ
M Q
ueue
) N
one
Shor
t Cir
cuit
Ana
lysi
s N
o pr
oble
ms i
dent
ified
. N
ew S
yste
m R
einf
orce
men
ts
(Upg
rade
s req
uire
d to
miti
gate
relia
bilit
y cr
iteri
a vi
olat
ions
, i.e
. “N
etw
ork
Impa
cts,”
initi
ally
ca
used
by
the
addi
tion
of th
is p
roje
ct’s
gen
erat
ion)
N
one
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
7
Con
trib
utio
n to
Pre
viou
sly
Iden
tifie
d Sy
stem
Rei
nfor
cem
ents
(O
verl
oads
initi
ally
cau
sed
by p
rior
Que
ue p
ositi
ons w
ith a
dditi
onal
con
tribu
tion
to o
verl
oadi
ng b
y th
is p
roje
ct.
This
pro
ject
may
hav
e a
% a
lloca
tion
cost
resp
onsi
bilit
y.
Non
e St
abili
ty A
naly
sis
Not
requ
ired.
O
ther
Cha
rges
D
PL re
serv
es th
e rig
ht to
cha
rge
the
Inte
rcon
nect
ion
Cus
tom
er o
pera
tion
and
mai
nten
ance
exp
ense
s to
mai
ntai
n th
e In
terc
onne
ctio
n C
usto
mer
’s A
ttach
men
t Fac
ilitie
s, in
clud
ing
met
erin
g an
d te
leco
mm
unic
atio
ns fa
cilit
ies t
hat a
re o
wne
d by
DPL
. D
eliv
ery
of E
nerg
y Po
rtio
n of
Inte
rcon
nect
ion
Req
uest
PJ
M a
lso
stud
ied
the
deliv
ery
of th
e en
ergy
por
tion
of th
is in
terc
onne
ctio
n re
ques
t. A
ny p
robl
ems
iden
tifie
d be
low
are
like
ly to
resu
lt in
ope
ratio
nal r
estri
ctio
ns to
the
proj
ect u
nder
stud
y. T
he
deve
lope
r can
pro
ceed
with
net
wor
k up
grad
es to
elim
inat
e th
e op
erat
iona
l res
trict
ion
at th
eir
disc
retio
n by
subm
ittin
g a
Mer
chan
t Tra
nsm
issi
on In
terc
onne
ctio
n re
ques
t. O
nly
the
mos
t sev
erel
y ov
erlo
aded
con
ditio
ns a
re li
sted
. The
re is
no
guar
ante
e of
full
deliv
ery
of
ener
gy fo
r thi
s pro
ject
by
fixin
g on
ly th
e co
nditi
ons l
iste
d in
this
sect
ion.
With
a T
rans
mis
sion
In
terc
onne
ctio
n R
eque
st, a
subs
eque
nt a
naly
sis w
ill b
e pe
rfor
med
, whi
ch w
ill st
udy
all o
verlo
ad
cond
ition
s ass
ocia
ted
with
the
over
load
ed e
lem
ent(s
) ide
ntifi
ed.
The
se a
re n
ot r
equi
red
relia
bilit
y up
grad
es.
1.
The
LIN
WO
OD
-CH
ICH
ST2
230
kV li
ne (f
rom
bus
213
750
to b
us 2
1349
0 ck
t 2) l
oads
from
10
3.92
% to
104
.03%
(AC
pow
er fl
ow) o
f its
nor
mal
ratin
g (8
31 M
VA
) for
non
-con
tinge
ncy
cond
ition
. Thi
s pro
ject
con
tribu
tes a
ppro
xim
atel
y 1.
98 M
W to
the
ther
mal
vio
latio
n.
2.
The
LIN
WO
OD
-CH
ICH
ST2
230
kV li
ne (f
rom
bus
213
750
to b
us 2
1349
0 ck
t 1) l
oads
from
12
6.16
% to
126
.33%
(AC
pow
er fl
ow) o
f its
em
erge
ncy
ratin
g (9
83 M
VA
) for
the
sing
le li
ne
cont
inge
ncy
outa
ge o
f CO
NTI
NG
ENC
Y D
ESC
RIP
TIO
N ('
220-
39').
Thi
s pro
ject
con
tribu
tes
appr
oxim
atel
y 3.
72 M
W to
the
ther
mal
vio
latio
n.
3.
The
LIN
WO
OD
-CH
ICH
ST2
230
kV li
ne (f
rom
bus
213
750
to b
us 2
1349
0 ck
t 2) l
oads
from
12
6.61
% to
126
.78%
(AC
pow
er fl
ow) o
f its
em
erge
ncy
ratin
g (9
83 M
VA
) for
the
sing
le li
ne
cont
inge
ncy
outa
ge o
f CO
NTI
NG
ENC
Y D
ESC
RIP
TIO
N ('
220-
43').
Thi
s pro
ject
con
tribu
tes
appr
oxim
atel
y 3.
73 M
W to
the
ther
mal
vio
latio
n.
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
8
4.
The
X2-
066
TAP-
SHA
RN
GTN
138
kV
line
(fro
m b
us 9
0934
0 to
bus
232
114
ckt 1
) loa
ds fr
om
138.
15%
to 1
38.3
8% (A
C p
ower
flow
) of i
ts n
orm
al ra
ting
(242
MV
A) f
or n
on-c
ontin
genc
y co
nditi
on. T
his p
roje
ct c
ontri
bute
s app
roxi
mat
ely
1.25
MW
to th
e th
erm
al v
iola
tion.
5.
Th
e X
2-06
6 TA
P-SH
AR
NG
TN 1
38 k
V li
ne (f
rom
bus
909
340
to b
us 2
3211
4 ck
t 1) l
oads
from
13
8.09
% to
138
.35%
(AC
pow
er fl
ow) o
f its
em
erge
ncy
ratin
g (2
57 M
VA
) for
the
sing
le li
ne
cont
inge
ncy
outa
ge o
f CO
NTI
NG
ENC
Y D
ESC
RIP
TIO
N ('
CK
T 67
37').
Thi
s pro
ject
con
tribu
tes
appr
oxim
atel
y 1.
48 M
W to
the
ther
mal
vio
latio
n.
© P
JM In
terc
onne
ctio
n 20
12. A
ll rig
hts r
eser
ved.
P
JMD
OC
S-#
7069
07-v
1
X
3-00
8 To
dd 6
9kV
9
Att
achm
ent 1
Tod
d69
/25
kVSu
bsta
tion
25K
VB
us
Tod
dSu
bsta
tion
T169
/25
kV25
MV
A
New
Feed
erM
Dxx
xx
Inve
nerg
ySo
lar
Dev
elop
men
tLL
C
Prop
osed
Gen
erat
or10
MW
Met
erow
ned
By
DPL
25K
VB
us
T269
/25
kV28
MV
AA
ppro
xim
atel
y2.
2m
ileso
fPA
CC
able
POI
M
VIP
ERR
eclo
ser
New
Feed
erM
Dxx
xxPr
opos
edG
ener
ator
10M
W
Met
erow
ned
By
DPL
App
roxi
mat
ely
2.2
mile
sof
PAC
Cab
le
VIP
ERR
eclo
ser
MD
2221
East
New
Mar
ket
69kV
Sour
ce
East
onPr
esto
n69
kVSo
urce
POI
M
MD
2267
12K
VB
usT3
69/1
2kV
10.5
MV
A
MD
0439
Alle
n69
kVSo
urce
Vie
nna
69kV
Sour
ce
Gen
erat
ion
Inte
rcon
nect
ion
Faci
litie
s Stu
dy
Repo
rt
For
PJM
Gen
erat
ion
Inte
rcon
nect
ion
Requ
est
Que
ue P
ositi
on X
3-00
8
“Tod
d 69
kV”
Au
gust
2014
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
2
A. T
rans
mis
sion
Ow
ner
Faci
litie
s Stu
dy S
umm
ary
1. D
escr
iptio
n of
Pro
ject
Inve
nerg
y So
lar D
evel
opm
ent,
LLC
, the
Inte
rcon
nect
ion
Cus
tom
er (I
C),
has p
ropo
sed
a 20
MW
E (7
.6 M
WC
; 20
MW
MFO
) sol
ar p
ower
ed g
ener
atin
g fa
cilit
y to
be
loca
ted
in
Dor
ches
ter C
ount
y, M
aryl
and.
PJM
stud
ied
X3-
008
as a
20
MW
inje
ctio
n in
to th
e D
elm
arva
Pow
er a
nd L
ight
(DPL
) sys
tem
at t
he T
odd
Subs
tatio
n an
d ev
alua
ted
it fo
r co
mpl
ianc
e w
ith re
liabi
lity
crite
ria fo
r sum
mer
pea
k co
nditi
ons i
n 20
15.
The
plan
ned
in-
serv
ice
date
, as s
tate
d in
the
Atta
chm
ent N
, is J
une
1, 2
017.
2.
Am
endm
ents
to th
e Sy
stem
Impa
ct S
tudy
or S
yste
m Im
pact
Stu
dy R
esul
ts
Th
is st
udy
is b
ased
on
the
Impa
ct S
tudy
dat
ed J
uly,
201
2 an
d is
bas
ed o
n co
nnec
ting
20
MW
of P
V to
Tod
d Su
bsta
tion
via
two
(2) n
ewly
con
stru
cted
25
kV fe
eder
s. A
dditi
onal
ly th
e sc
hedu
le h
as b
een
adju
sted
to m
eet a
stan
dard
con
stru
ctio
n sc
hedu
le.
The
DPL
por
tion
of th
e pr
ojec
t is p
roje
cted
to b
e co
mpl
eted
in a
ppro
xim
atel
y 18
-22
mon
ths f
ollo
win
g an
exe
cute
d In
terc
onne
ctio
n Se
rvic
e A
gree
men
t (IS
A) a
nd
Con
stru
ctio
n Se
rvic
e A
gree
men
t (C
SA).
3.
Inte
rcon
nect
ion
Cus
tom
er’s
Mile
ston
e Sc
hedu
le
Th
e pl
anne
d in
-ser
vice
dat
e, a
s ide
ntifi
ed in
Atta
chm
ent N
, was
June
1, 2
017.
Thi
s in-
serv
ice
date
can
be
met
pro
vide
d D
elm
arva
Pow
er is
giv
en 1
8-22
mon
ths t
o de
sign
, pr
ocur
e m
ater
ial a
nd c
onst
ruct
afte
r rec
eipt
of a
fully
exe
cute
d In
terc
onne
ctio
n Se
rvic
e A
gree
men
t (IS
A) a
nd In
terc
onne
ctio
n C
onst
ruct
ion
Serv
ice
Agr
eem
ent (
CSA
).
4. C
usto
mer
’s S
cope
of W
ork
Th
e IC
pro
pose
s the
con
stru
ctio
n of
one
pho
tovo
ltaic
syst
em w
ith a
max
imum
gen
erat
ion
capa
city
of 2
0 M
W.
X
3-00
8 w
ill in
terc
onne
ct to
the
Del
mar
va P
ower
and
Lig
ht d
istri
butio
n sy
stem
at t
he
Todd
69
kV su
bsta
tion
as fo
llow
s:
10 M
Ws w
ill c
onne
ct to
the
exis
ting
T1 tr
ansf
orm
er
via
a ne
w 2
5 kV
dis
tribu
tion
feed
er a
nd 1
0 M
W w
ill c
onne
ct to
the
exis
ting
T2
trans
form
er v
ia a
new
25
kV d
istri
butio
n fe
eder
. Ea
ch fe
eder
is n
ot p
erm
itted
to c
arry
m
ore
than
10
MW
. Th
e tw
o di
strib
utio
n fe
eder
s con
stru
cted
by
Del
mar
va P
ower
will
be
cons
truct
ed o
n on
e po
le li
ne.
The
IC a
ssum
es fu
ll re
spon
sibi
lity
for d
esig
n, p
erm
ittin
g an
d co
nstru
ctio
n of
all
faci
litie
s as
soci
ated
w
ith
the
X3-
008
gene
ratin
g st
atio
n on
th
eir
side
of
th
e Po
int
of
Inte
rcon
nect
ion
(PO
I.)
The
IC w
ill i
nter
conn
ect
X3-
008
with
the
DPL
sys
tem
via
the
tw
o ne
w d
istri
butio
n fe
eder
s.
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
3
This
pro
pose
d in
terc
onne
ctio
n w
ill b
e re
quire
d to
satis
fy th
e re
quire
men
ts o
utlin
ed in
IE
EE15
47 in
clud
ing
but n
ot li
mite
d to
ove
r/und
er v
olta
ge, o
ver/u
nder
freq
uenc
y an
d an
ti-is
land
ing
requ
irem
ents
. D
PL’s
syst
em p
rote
ctio
n gr
oup
will
nee
d to
rece
ive
the
prop
osed
se
tting
s for
revi
ew to
ens
ure
com
plia
nce
with
this
stan
dard
.
This
pro
pose
d in
terc
onne
ctio
n w
ill b
e re
quire
d to
satis
fy th
e re
quire
men
ts o
utlin
ed in
D
PL’s
“Te
chni
cal C
onsi
dera
tions
Cov
erin
g Pa
ralle
l Ope
ratio
ns o
f Cus
tom
er O
wne
d G
ener
atio
n” d
ocum
ent f
or u
nits
gre
ater
than
1 M
W.
DPL
’s sy
stem
pro
tect
ion
grou
p w
ill
need
to re
ceiv
e th
e pr
opos
ed se
tting
s and
ass
ocia
ted
sche
mes
for r
evie
w to
ens
ure
com
plia
nce
with
this
stan
dard
. If
the
IC e
lect
s to
use
a st
ep u
p tra
nsfo
rmer
with
a d
elta
hig
h si
de w
indi
ng, a
dditi
onal
m
easu
res a
re re
quire
d in
ord
er to
pre
vent
Tem
pora
ry-O
ver-
Vol
tage
(TO
V) d
urin
g ab
norm
al c
ondi
tions
. Th
ree
phas
e vo
ltage
sens
ing
mus
t be
inst
alle
d at
the
25 k
V si
de o
f th
e ge
nera
tor's
tran
sfor
mer
. PT’
s can
not b
e in
stal
led
on lo
wer
vol
tage
bus
. Thi
s re
quire
men
t can
be
avoi
ded
by u
sing
a g
roun
ded-
wye
/gro
unde
d-w
ye st
ep u
p tra
nsfo
rmer
.
Inve
rter R
equi
rem
ents
This
sect
ion
cont
ains
setti
ng re
quire
men
ts fo
r the
ope
ratio
n of
the
IC’s
pro
pose
d eq
uipm
ent.
The
inve
rter
at t
he D
G lo
catio
n sh
all h
ave
the
follo
win
g ca
pabi
litie
s:
� V
olta
ge fl
icke
r red
uctio
n th
roug
h dy
nam
ic V
AR
resp
onse
� R
amp
rate
con
trol
� SC
AD
A c
omm
unic
atio
ns
� C
urta
ilmen
t or o
ther
miti
gatio
n ab
ility
if h
igh
volta
ge w
ere
to o
ccur
� Lo
w v
olta
ge a
nd s
yste
m d
istu
rban
ce ri
de th
roug
h
� A
bilit
y to
rece
ive
and
resp
ond
to a
tran
sfer
trip
or S
CA
DA
sign
al
The
inve
rter s
hall
oper
ate
in a
ccor
danc
e w
ith th
e IE
EE 1
547
serie
s of s
tand
ards
that
hav
e be
en a
ppro
ved.
Whi
le in
verte
rs sh
ould
be
capa
ble
of v
olta
ge st
abili
zatio
n th
ru d
ynam
ic
VA
R re
spon
se a
nd c
apab
le o
f low
vol
tage
and
sys
tem
dis
turb
ance
ride
thro
ugh,
nei
ther
of
thes
e ca
pabi
litie
s sha
ll be
impl
emen
ted
until
such
tim
e th
at th
e IE
EE 1
547
serie
s of
stan
dard
s are
revi
sed
and
appr
oved
to in
clud
e st
anda
rds f
or th
ese
capa
bilit
ies.
At s
uch
time
as th
ese
revi
sed
stan
dard
s bec
ome
avai
labl
e, th
e PV
ow
ner/o
pera
tor s
hall
coop
erat
e w
ith th
e C
ompa
ny to
impl
emen
t the
se c
apab
ilitie
s with
setti
ngs a
ccep
tabl
e to
the
Com
pany
. U
ntil
such
tim
e, th
e in
verte
rs sh
all b
e ca
pabl
e of
ope
ratin
g at
a fi
xed
pow
er
fact
or v
alue
bet
wee
n 0.
95 le
ad a
nd 0
.95
lag
as sp
ecifi
ed b
y th
e C
ompa
ny. T
he v
alue
is
supp
lied
belo
w:
1.
Ope
rate
inve
rters
at u
nity
pow
er fa
ctor
(“PF
”)
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
4
Not
e: In
the
futu
re, t
he c
ompa
ny re
serv
es th
e ri
ght t
o is
sue
new
fixe
d po
wer
fact
or se
tting
re
quir
emen
ts (0
.95
lead
to 0
.95
lag)
if n
eces
sary
.
It
is th
e re
spon
sibi
lity
of th
e ow
ner
to s
ecur
e th
e in
verte
r fr
om a
ny u
naut
horiz
ed a
cces
s (in
clud
ing
phys
ical
and
rem
ote
acce
ss) w
hich
cou
ld a
lter s
ettin
gs o
r adv
erse
ly a
ffec
t the
in
verte
r’s a
bilit
y to
ope
rate
as
requ
ired.
Sec
urity
mea
sure
s sh
ould
incl
ude
utili
zing
sec
ure
pass
wor
d se
tting
s and
/or p
hysi
cal l
ocks
on
cabi
net d
oors
.
A m
utua
lly a
ccep
tabl
e m
eans
of
inte
rrup
ting
and
disc
onne
ctin
g th
e ge
nera
tor
with
a
visi
ble
brea
k, a
ble
to b
e ta
gged
and
loc
ked
out,
shal
l be
wor
ked
out
with
Com
pany
D
istri
butio
n En
gine
erin
g pe
rson
nel.
5. D
escr
iptio
n of
Fac
ilitie
s Inc
lude
d in
the
Faci
litie
s Stu
dy (D
PL S
cope
of W
ork)
� C
omm
unic
atio
ns –
Fib
er o
ptic
cab
le w
ill c
onne
ct T
odd
Subs
tatio
n to
the
IC’s
de
mar
catio
n ca
bine
t at t
he so
lar s
ite to
faci
litat
e D
PL’s
requ
irem
ents
for t
rans
fer t
rip a
nd
rem
ote
trip.
App
roxi
mat
ely
1.42
mile
s of 4
8SM
AD
SS a
eria
l cab
le a
nd 2
00 fe
et o
f un
derg
roun
d fib
er w
ill b
e us
ed.
Con
stru
ctio
n w
ill b
e on
the
new
ly in
stal
led
pole
s int
o th
e su
bsta
tion.
�
One
new
25
kV fe
eder
term
inal
will
be
inst
alle
d on
the
T1 tr
ansf
orm
er a
t Tod
d Su
bsta
tion
to c
onne
ct o
ne 1
0 M
W e
xpre
ss d
istri
butio
n ci
rcui
t.
�
One
new
25
kV fe
eder
term
inal
will
be
inst
alle
d on
the
T2 tr
ansf
orm
er a
t Tod
d Su
bsta
tion
to c
onne
ct o
ne 1
0 M
W e
xpre
ss d
istri
butio
n ci
rcui
t.
�
Esta
blis
h tw
o (2
) new
25
kV fe
eder
s with
954
AA
C p
rimar
y co
nduc
tors
from
the
Todd
Su
bsta
tion
to th
e ge
nera
ting
site
alo
ng S
keet
Clu
b R
oad
and
Har
per R
oad,
a d
ista
nce
of
appr
oxim
atel
y 1.
42 m
iles.
The
feed
ers w
ill b
e co
nstru
cted
on
the
sam
e po
le li
ne e
xcep
t th
ey w
ill se
para
te a
t the
sola
r site
and
at t
he su
bsta
tion.
The
T1
feed
er m
ust b
e co
nstru
cted
in o
rder
to c
ompl
ete
the
T2 fe
eder
. Th
is w
ork
will
incl
ude:
� In
stal
ling
appr
oxim
atel
y fo
rty-tw
o (4
2) n
ew 5
5’ w
ood
dist
ribut
ion
pole
s al
ong
Skee
t Clu
b an
d H
arpe
r Roa
ds in
Sta
te H
ighw
ay ri
ght o
f way
to
acco
mm
odat
e th
e ne
w 2
5kV
feed
ers
� In
stal
ling
appr
oxim
atel
y 8,
300
feet
of d
oubl
e ci
rcui
t 3 p
hase
954
AA
C
prim
ary
and
8,30
0 fe
et o
f 1-4
/0 A
AA
C n
eutra
l �
Perf
orm
ing
any
nece
ssar
y tre
e tri
mm
ing
and
rem
oval
alo
ng th
e pu
blic
ro
adw
ays
� In
stal
ling
one
(1) a
utom
atic
circ
uit r
eclo
ser a
t the
sola
r site
on
each
circ
uit
for a
tota
l of t
wo
(2) r
eclo
sers
�
Inst
allin
g on
e (1
) aer
ial p
rimar
y m
eter
clu
ster
at t
he so
lar s
ite o
n ea
ch
circ
uit f
or a
tota
l of t
wo
(2) m
eter
ing
clus
ters
DPL
will
inst
all a
min
imum
of t
hree
pol
es o
n th
e IC
sola
r site
for e
ach
feed
er.
One
pol
e w
ill b
e to
acc
omm
odat
e th
e pr
imar
y m
eter
clu
ster
, one
will
be
to a
ccom
mod
ate
the
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
5
auto
mat
ic c
ircui
t rec
lose
r and
the
final
pol
e w
ill b
e th
e se
para
tion
poin
t bet
wee
n D
PL
owne
d fa
cilit
ies a
nd IC
ow
ned
faci
litie
s for
the
circ
uit.
The
IC is
resp
onsi
ble
to ta
ke th
e ov
erhe
ad p
rimar
y 25
kV fe
ed fr
om th
at p
oint
on.
D
PL w
ill re
quire
the
capa
bilit
y to
rem
otel
y di
scon
nect
the
gene
rato
r fro
m th
e gr
id b
y co
mm
unic
atio
n fr
om it
s Sys
tem
Ope
ratio
ns fa
cilit
y. S
uch
disc
onne
ctio
n m
ay b
e fa
cilit
ated
by
eith
er a
gen
erat
or b
reak
er, a
line
recl
oser
, or o
ther
met
hod
depe
ndin
g up
on
the
spec
ific
circ
umst
ance
s and
the
eval
uatio
n of
the
Com
pany
. 6.
Tot
al C
ost o
f Dis
tribu
tion
Ow
ner F
acili
ties I
nclu
ded
in th
e Fa
cilit
ies S
tudy
A
ttach
men
t Fac
ilitie
s
$2,6
61,9
01
A
ttach
men
t Fac
ilitie
s with
15%
Con
tinge
ncy
$3,0
61,1
87
7. S
umm
ary
of th
e Sc
hedu
le fo
r Com
plet
ion
of W
ork
for t
he F
acili
ties S
tudy
Th
e ov
eral
l est
imat
ed ti
mel
ine
for t
his p
roje
ct is
app
roxi
mat
ely
18-2
2 m
onth
s fro
m th
e da
te o
f the
PJM
rele
ase
for d
esig
n/co
nstru
ctio
n. T
his t
imel
ine
may
be
able
to b
e im
prov
ed w
ith p
refe
rred
sys
tem
out
ages
. Th
e sc
hedu
le p
rovi
ded
is a
n es
timat
e of
the
nece
ssar
y tim
efra
mes
to c
ompl
ete
the
wor
k.
Subs
tatio
n D
esig
n, P
rocu
rem
ent a
nd C
onst
ruct
ion
18-
22 m
onth
s D
istri
butio
n Li
ne D
esig
n, P
rocu
rem
ent a
nd C
onst
ruct
ion
1
6-18
mon
ths
Out
side
Pla
nt C
omm
. Des
ign,
Pro
cure
men
t and
Con
stru
ctio
n 1
0-12
mon
ths
DPL
will
be
able
to m
eet t
he sc
hedu
le su
pplie
d by
the
IC fo
r thi
s PJM
que
ue p
roje
ct
prov
ided
that
the
IC e
xecu
tes t
he in
terc
onne
ctio
n ag
reem
ents
in th
e pr
oper
tim
efra
me
to
allo
w th
e de
sign
and
con
stru
ctio
n pe
riod
outli
ned
in th
is re
port.
B
. Tra
nsm
issi
on O
wne
r Fa
cilit
ies S
tudy
Res
ults
This
sect
ion
desc
ribes
faci
litie
s ide
ntifi
ed to
be
inst
alle
d, re
plac
ed, a
nd/o
r upg
rade
d by
D
PL to
acc
omm
odat
e th
e pr
ojec
t. D
urin
g de
taile
d de
sign
and
ana
lysi
s oth
er c
ompo
nent
s m
ay b
e in
dent
ified
for i
nsta
llatio
n or
repl
acem
ent d
ue to
this
inte
rcon
nect
ion.
1.
Tra
nsm
issi
on L
ines
- N
ew
Not
app
licab
le
2. T
rans
mis
sion
Lin
e –
Upg
rade
s N
ot a
pplic
able
3.
New
Sub
stat
ion/
Switc
hyar
d Fa
cilit
ies
Not
app
licab
le
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
6
4. U
pgra
des t
o Su
bsta
tion/
Switc
hyar
d Fa
cilit
ies
Wor
k ac
tiviti
es in
clud
e th
e in
stal
latio
n, re
plac
emen
t and
exp
ansi
on o
f exi
stin
g eq
uipm
ent a
nd
prot
ectiv
e re
layi
ng a
t Tod
d Su
bsta
tion
to c
reat
e an
add
ition
al fe
eder
pos
ition
on
both
the
T1 a
nd
T2 tr
ansf
orm
ers.
This
wor
k co
nsis
ts o
f the
follo
win
g:
Th
e ne
w T
1 fe
eder
will
con
sist
of t
he fo
llow
ing:
one
new
25
kV, 1
200A
, 20
kA p
ower
circ
uit
brea
ker,
with
rela
ted
disc
onne
ct sw
itche
s, an
d fo
unda
tion;
one
new
feed
er b
ay w
ith d
isco
nnec
t sw
itche
s, su
rge
arre
ster
s, st
ruct
ure
and
foun
datio
ns;
one
thre
e-ph
ase
set o
f 69k
V c
apac
itor
volta
ge tr
ansf
orm
ers,
stru
ctur
e an
d fo
unda
tion;
a p
re-f
abric
ated
con
trol h
ouse
with
rela
y, c
ontro
l an
d co
mm
unic
atio
n pa
nels
, AC
and
DC
supp
ly s
yste
ms,
and
foun
datio
ns;
grou
ndin
g, c
ondu
it,
cabl
e tro
ugh,
and
ston
ing;
con
trol c
able
s and
all
mis
cella
neou
s ite
ms f
or a
com
plet
e in
stal
latio
n.
The
prot
ectiv
e re
layi
ng w
ill c
onsi
st o
f new
fron
t-lin
e an
d ba
ck-u
p fe
eder
rela
ys a
nd o
ne se
t of
bus d
iffer
entia
l rel
ays.
A n
ew O
rion
LX- b
ased
rem
ote
term
inal
uni
t will
pro
vide
in
terc
onne
ctio
n to
all
prot
ectiv
e an
d co
ntro
l rel
ays.
Fo
r the
T1
feed
er, t
he w
ork
incl
udes
the
inst
alla
tion
of th
e fo
llow
ing
new
equ
ipm
ent:
� O
ne (1
) 25
kV, 1
200
A, 2
0 kA
circ
uit b
reak
er
� Si
x (6
) 25
kV, 1
200
A si
ngle
-pol
e ho
okst
ick
disc
onne
ct sw
itche
s �
Thre
e (3
) 25
kV st
atio
n cl
ass s
urge
arr
este
rs
� Th
ree
(3) 6
9 kV
CV
T’s
� O
ne (1
) fro
nt-li
ne &
bac
k-up
feed
er re
layi
ng p
rote
ctio
n pa
nel
� O
ne (1
) bus
diff
eren
tial r
elay
ing
prot
ectio
n pa
nel
� O
ne (1
) sup
ervi
sory
pan
el (O
rion
LX a
nd e
ther
net s
witc
h)
� O
ne (1
) gal
vani
zed
stee
l thr
ee-p
hase
CV
T st
and
� O
ne (1
) pre
-fab
ricat
ed c
ontro
l hou
se w
ith A
C a
nd D
C a
uxili
ary
syst
ems
� O
ne (1
) 25k
V b
ox st
ruct
ure
bay
� Lo
t of c
ondu
ctor
s, co
nnec
tors
, and
insu
lato
rs fo
r the
bus
syst
ems
� Lo
t of s
tatio
n gr
ound
con
duct
ors a
nd c
onne
ctor
s �
Lot o
f con
trol c
able
s �
Lot o
f cab
le tr
ench
and
con
duit
for n
ew ra
cew
ay sy
stem
s �
Lot o
f fou
ndat
ions
for a
bove
list
ed e
quip
men
t
The
new
T2
feed
er w
ill c
onsi
st o
f the
follo
win
g: o
ne n
ew 2
5 kV
, 120
0A, 2
0 kA
pow
er c
ircui
t br
eake
r, w
ith re
late
d di
scon
nect
switc
hes,
and
foun
datio
n; o
ne th
ree-
phas
e se
t of 6
9kV
cap
acito
r vo
ltage
tran
sfor
mer
s, st
ruct
ure
and
foun
datio
n; g
roun
ding
, con
duit,
cab
le tr
ough
, and
ston
ing;
co
ntro
l cab
les a
nd a
ll m
isce
llane
ous i
tem
s for
a c
ompl
ete
inst
alla
tion.
The
pro
tect
ive
rela
ying
w
ill c
onsi
st o
f new
fron
t-lin
e an
d ba
ck-u
p fe
eder
rela
ys a
nd o
ne se
t of b
us d
iffer
entia
l rel
ays.
For t
he T
2 fe
eder
, the
wor
k in
clud
es th
e in
stal
latio
n of
the
follo
win
g ne
w e
quip
men
t: �
One
(1) 2
5 kV
, 120
0 A
, 20
kA c
ircui
t bre
aker
�
Six
(6) 2
5 kV
, 120
0 A
sing
le-p
ole
hook
stic
k di
scon
nect
switc
hes
� Th
ree
(3) 2
5 kV
stat
ion
clas
s sur
ge a
rres
ters
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
7
� Th
ree
(3) 6
9 kV
CV
T’s
� O
ne (1
) set
of f
ront
-line
& b
ack-
up fe
eder
rela
ys
� O
ne (1
) bus
diff
eren
tial r
elay
ing
prot
ectio
n pa
nel
� O
ne (1
) gal
vani
zed
stee
l thr
ee-p
hase
CV
T st
and
� Lo
t of c
ondu
ctor
s, co
nnec
tors
, and
insu
lato
rs fo
r the
bus
syst
ems
� Lo
t of s
tatio
n gr
ound
con
duct
ors a
nd c
onne
ctor
s �
Lot o
f con
trol c
able
s �
Lot o
f cab
le tr
ench
and
con
duit
for n
ew ra
cew
ay sy
stem
s �
Lot o
f fou
ndat
ions
for a
bove
list
ed e
quip
men
t
Any
nec
essa
ry v
aria
nces
and
per
mits
to p
erfo
rm th
e ab
ove
wor
k w
ill b
e ob
tain
ed.
Out
ages
are
ava
ilabl
e fr
om fa
ll to
sprin
g.
It
is D
PL p
ract
ice
to u
se se
para
te c
ontra
ctor
s for
: �
Inst
alla
tion
of fo
unda
tions
�
All
prim
ary
and
rela
ying
wor
k
� Te
stin
g an
d co
mm
issi
onin
g
D
PL w
ill re
view
the
IPR
cab
inet
dra
win
g PR
IOR
TO
TH
E PU
RC
HA
SE O
F EQ
UIP
MEN
T th
en te
st fo
r pro
per r
elay
ope
ratio
n af
ter i
nsta
llatio
n of
the
requ
ired
prot
ectio
n eq
uipm
ent a
t the
sola
r site
. 5.
Met
erin
g &
Com
mun
icat
ions
DPL
’s M
eter
Dep
artm
ent w
ill c
onst
ruct
two
(2) 2
5kV
thre
e ph
ase
prim
ary
met
erin
g cl
uste
r mou
nt a
ssem
blie
s with
inst
alle
d m
eter
ing
devi
ce e
quip
ped
with
load
pro
file,
te
lem
etry
, and
I/O
s, in
clud
ing
DN
P ou
tput
s. A
con
tract
or o
r a D
PL o
verh
ead
line
crew
w
ill b
e re
quire
d to
put
the
clus
ter m
ount
ass
embl
ies i
nto
serv
ice,
and
Met
er D
epar
tmen
t te
chni
cian
s will
com
plet
e th
e se
cond
ary
wiri
ng a
nd re
late
d m
eter
wor
k at
the
base
of t
he
met
erin
g po
les.
A m
eter
tech
nici
an w
ill a
ssis
t the
con
tract
or o
r DPL
ove
rhea
d lin
e cr
ew
in e
nerg
izin
g th
is e
quip
men
t. Th
e m
eter
tech
nici
an w
ill a
lso
prog
ram
and
inst
all t
wo
solid
st
ate
mul
ti fu
nctio
n m
eter
s (Pr
imar
y &
Bac
kup)
for e
ach
new
met
erin
g po
sitio
n.
The
IC w
ill b
e re
quire
d to
mak
e pr
ovis
ions
for a
voi
ce q
ualit
y ph
one
lines
with
in
appr
oxim
atel
y 3
feet
of e
ach
met
erin
g po
sitio
n to
faci
litat
e re
mot
e in
terr
ogat
ion
and
data
co
llect
ion
by D
PL.
Tele
met
ry
It is
the
IC’s
resp
onsi
bilit
y to
send
the
data
, tha
t PJM
and
the
Com
pany
requ
ires,
dire
ctly
to
PJM
. Th
e IC
will
gra
nt it
s per
mis
sion
to P
JM fo
r PJM
to se
nd th
e C
ompa
ny th
e fo
llow
ing
tele
met
ry d
ata
that
the
IC se
nds t
o PJ
M: r
eal t
ime
meg
awat
ts, m
egav
ars,
volts
, am
pere
s, ge
nera
tor s
tatu
s, an
d in
terv
al m
egaw
att-h
ours
, and
meg
avar
-hou
rs.
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
8
6. E
nviro
nmen
tal,
Rea
l Est
ate
and
Perm
ittin
g Is
sues
Rea
l Est
ate
Rea
l Est
ate
invo
lvem
ent w
ill b
e a
curs
ory
chec
k of
exi
stin
g pr
oper
ty ri
ghts
alo
ng th
e pr
opos
ed d
istri
butio
n ro
ute
and
ther
e m
ay a
lso
be th
e ne
ed to
acq
uire
righ
ts fo
r pol
e an
chor
s and
guy
wire
s in
a fe
w lo
catio
ns.
Als
o, R
eal E
stat
e m
ay b
e in
volv
ed in
obt
aini
ng
the
nece
ssar
y St
ate
Hig
hway
per
mits
. En
viro
nmen
tal
The
Envi
ronm
enta
l Dep
artm
ent w
ill p
rovi
de a
che
ck o
f ava
ilabl
e pu
blic
dat
a as
far a
s w
etla
nds a
nd th
reat
ened
and
end
ange
red
spec
ies a
re c
once
rned
. Th
ey w
ill p
rovi
de in
put
to m
inim
ize
any
impa
cts d
urin
g th
e de
sign
pha
se o
f the
pro
ject
. Th
ey w
ill p
rovi
de a
ny
addi
tiona
l pro
ject
revi
ew, a
vian
des
ign
revi
ew a
nd fi
nal p
roje
ct p
erm
ittin
g th
at is
ne
cess
ary.
Thi
s est
imat
e as
sum
es th
e ne
ed fo
r per
mits
and
revi
ews m
ay b
e re
duce
d by
pl
acin
g th
e po
le li
ne a
long
the
Stat
e H
ighw
ays.
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
9
7.
Sum
mar
y of
Res
ults
of S
tudy
T1
Fee
der
Pr
ojec
t Nam
e: X
3-00
8 To
dd 6
9 kV
In
dire
ct
Dire
ct
TOTA
L ($
) 10
MW
T1
Tran
sfor
mer
and
New
Fee
der
Mat
eria
l La
bor
Mat
eria
l La
bor
Rea
l Est
ate
1
,400
8,6
00
10
,000
S
yste
m P
lann
ing
400
2,60
0 3,
000
Dis
tribu
tion
Ove
rhea
d C
onst
ruct
ion
74,7
65
1
16,6
32
250,
050
390,
383
831,
830
Proj
ect M
anag
emen
t & S
peci
al B
illin
g
5
00
3,
500
4,00
0 O
utsi
de P
lant
Com
mun
icat
ions
2
,400
17
,000
13
,867
10
5,45
5 13
8,72
2 S
yste
m P
rote
ctio
n
5
00
3,
500
4,00
0 In
terc
onne
ctio
n A
rrang
emen
ts
400
2,60
0 3,
000
Sys
tem
Ope
ratio
ns
400
2,60
0 3,
000
Met
erin
g
1
,141
196
15
,159
2,
604
19,1
00
Env
ironm
enta
l
900
6,
600
7,50
0 S
ubst
atio
n E
ngin
eerin
g &
Con
stru
ctio
n
30
,000
25
,000
34
1,00
0 29
4,00
0 69
0,00
0 TO
TAL
CO
ST
108,
306
163,
328
620,
076
822,
442
1,71
4,15
2 15
% C
ontin
genc
y 16
,246
24
,499
93
,011
12
3,36
7 25
7,12
3
GR
AN
D T
OTA
L
124,
552
187,
827
713,
087
945,
809
1,97
1,27
5 T2
Fee
der
Proj
ect N
ame:
X3-
008
Todd
69
kV
Indi
rect
D
irect
TOTA
L ($
) 10
MW
T2
Tran
sfor
mer
and
New
Fee
der
Mat
eria
l La
bor
Mat
eria
l La
bor
Rea
l Est
ate
S
yste
m P
lann
ing
D
istri
butio
n O
verh
ead
Con
stru
ctio
n
50
,200
60
,164
16
0,52
9 23
0,76
1 50
1,65
4 Pr
ojec
t Man
agem
ent &
Spe
cial
Bill
ing
Out
side
Pla
nt C
omm
unic
atio
ns
2
25
9
48
1,50
0 6,
322
8,99
5 S
yste
m P
rote
ctio
n
Inte
rcon
nect
ion
Arra
ngem
ents
Sys
tem
Ope
ratio
ns
210
2,79
0 3,
000
Met
erin
g
1
,141
196
15
,159
2,
604
19,1
00
Env
ironm
enta
l
Sub
stat
ion
Eng
inee
ring
& C
onst
ruct
ion
11,0
00
17,0
00
149,
000
238,
000
415,
000
TOTA
L C
OST
62
,566
78
,518
32
6,18
8 48
0,47
7 94
7,74
9 15
% C
ontin
genc
y 9,
385
11,7
78
48,9
28
72,0
72
142,
163
GR
AN
D T
OTA
L
71,9
51
90,2
96
375,
116
552,
549
1,08
9,91
2
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
10
Gen
erat
ion
proj
ects
mee
ting
IRS
"Saf
e H
arbo
r" p
rovi
sion
s gen
eral
ly d
o no
t inc
ur "C
IAC
" (C
ontri
butio
n in
Aid
to C
onst
ruct
ion)
, a ta
x co
llect
ed b
y th
e ut
ility
for t
he st
ate
or fe
dera
l go
vern
men
t. If
for a
ny re
ason
, "C
IAC
" wou
ld b
e re
quire
d fo
r thi
s pro
ject
, it w
ould
be
the
resp
onsi
bilit
y of
the
party
ow
ning
the
gene
rato
r to
pay
this
cos
t.
DPL
rese
rves
the
right
to c
harg
e th
e IC
ope
ratio
n an
d m
aint
enan
ce e
xpen
ses t
o m
aint
ain
the
IC’s
at
tach
men
t fac
ilitie
s, in
clud
ing
met
erin
g an
d te
leco
mm
unic
atio
ns fa
cilit
ies,
owne
d by
DPL
. Sc
hedu
les a
nd A
ssum
ptio
ns
This
pro
ject
con
stru
ctio
n sc
hedu
le o
f 18-
22 m
onth
s was
com
plet
ed w
ith th
e as
sum
ptio
n th
at it
w
ould
not
be
impa
cted
by
stor
m d
amag
e an
d re
stor
atio
n, ti
me
of y
ear l
imita
tions
, per
mitt
ing
issu
es, o
utag
e sc
hedu
ling,
syst
em e
mer
genc
ies,
and
cont
ract
or a
nd e
quip
men
t ava
ilabi
lity.
It
is im
porta
nt to
not
e th
at th
is p
roje
ct w
ill b
e in
corp
orat
ed in
to th
e ex
istin
g pr
ojec
t wor
k lo
ad a
t D
PL a
t the
tim
e of
con
tract
exe
cutio
n. I
f the
wor
kloa
d of
exi
stin
g pr
ojec
ts is
ext
ensi
ve, r
esou
rce
cons
train
ts m
ay c
ause
this
pro
ject
to b
e de
laye
d be
yond
the
proj
ecte
d in
-ser
vice
dat
e.
© P
JM In
terc
onne
ctio
n 20
14. A
ll rig
hts r
eser
ved.
X
3-00
8 To
dd 6
9 kV
11
Atta
chm
ent #
1
Todd
69/2
5kV
Subs
tatio
n
25K
VBu
s
Todd
Subs
tatio
n
T169
/25
kV25
MV
A
New
Feed
erM
Dxx
xx
Inve
nerg
ySo
lar
Dev
elop
men
tLLC
Prop
osed
Gen
erat
or10
MW
Met
erow
ned
ByD
PL25
KV
Bus
T269
/25
kV28
MV
AA
ppro
xim
atel
y1.
42m
ileso
f95
4A
AC
POI
M
VIP
ERRe
clos
er
New
Feed
erM
Dxx
xxPr
opos
edG
ener
ator
10M
W
Met
erow
ned
ByD
PL
App
roxi
mat
ely
1.42
mile
sof
954
AA
C
VIP
ERRe
clos
er
MD
2221
East
New
Mar
ket
69kV
Sour
ce
Easto
nPr
esto
n69
kVSo
urce
POI
M
MD
2267
12K
VBu
sT3
69/1
2kV
10.5
MV
A
MD
0439
Alle
n69
kVSo
urce
Vie
nna
69kV
Sour
ce
POI
Poin
tofI
nter
conn
ectio
n
'alo) qleg :ot lleut ^q
1o (dor palu;rd llulqns
S t lZ't, 1o-l :aleo
NollvwuoJNl ]vNoIttoov irslnOru rHw E seluadord ruolsrr.l uo lflJlr lsuinov oN aneq lltr pafo.ra ",n E
salyedord rgolslq uo Sl)llll ISUIAOV ereq ;;rm pafolA ,qf Esaruadord )r.rols!r.l uo rllltl oN a^eq ;1rm paford aqr flSNOIIIONO) HII/IA l)llJl ISuIAOV ON eneq ;;rrvr pafo.ta aq.l f] peJle lp[uatod Jo eare aql ut s]tIuIdOUd )tUOlStH ON are aJerll
,c
?
:uollPu!uralao IHUII
'()la ,sasn ;ern1;nt1r6e'pado;anap'paulu 'papoo/$) eare t>aford ul sasn puel luasard pue lsed;o uot1d1::sa6 B
'saJnpn4s pue s6ugp;1nq ;;e;o sa6eu.r; 6ulpnpu1 alrs lrafo.td aql Eu;rrroqs 1lelt6tR ro 1u;rd) sqdel6oloq6 X's6urnnerq uorDnrlsuoJ.lo\pue'ueld alts !IolAlo ado>5 'uo11d1rlsaq nafold ffi
'palteu rlrea;: na[ord ]o sauepunoq pue uor]p)ol rlllM uolpas deyrl pen6 sgsn Io qder6oloqd lertay E]'luaLuutof ]noqlli\^ peurnlar aq ro sr(e1ap u! llnsal ,(eu sleiltuqns alalduorul 'patlnbat ale sluaurq)Plle llV
:sluauq)el}V
au e51 uodag\pulslc\/q.radord
suorle6rlsaru g 1e:16o1oaqrre ol pa[qns r(lsnotAeld
luauuureno6 lero; e r(q lt.lolstq paleu6rsaq I seruadord )!.lo]s!H ]o,Oo]uanul pue1,fuey1 aq] ul papnl)ul flIHhl
^q plaq lueuresee ue o1 lrafqns f] ralsg6ag leuor]eN aq] ul patsl"l I :(elqerlldde lle llaq)) saruado.rd se^lo^ur paford s1q1
'atueqtn$!p punorb leu!ulru qtlrvr pauueld rtg;1re; re;os a;ers {r11;tn aq plnom stql:uo1ld;r>sa6 leuotltppv\.laqlO
spu e;tapys(eMrateg/au! laloqS nuorlelrpqeilauT6ullapouag f]
a)uPqlnlsrcl punoig/uollene:q [}uorlrlotuag f, uorpnrlsuoJ /vlaN
sllpar) xel uorlpllllqpLlau lp.rapel ro a1e15 f:(alqerldde lle l)aql) sapry)ulpa[ord stql tr
o8_r.uorssrruuro) a)r^ras )!lqnd cw'('r1a llrurad l9f/l6N 19SOl
lonu:* raldeql 'EIoz loueol lllE puo6 't'a) asuelslsse
JaLllo Jo 'slured 'tu1pun1losaf,Jnos alels pue leJapaj ls!'l
EUltpar) xPI luaulsa^ul
(alqEr!ldde r!)raqtunN 6up;re,r1t1urra67pe[or6
aueN l!urrad7urer6o167l(:ua6yadl(1l(>ua6y
:uopdyrsa6 pa[or6
>1aar1 adoqr(qsreylIenruateMEt8'SLapnr16uo1LL9'8€apnllel :(uMou)| l) saleutproo)
ow lrot,0tutrlfurt!fpeog radre;1ssarppv
:uo!le)o-I pafor6
€rr9-0r9 (roE) r+raqurnN euoqdtuor':1;(6raua^uI@Jal IIttlalleuJl
II)
sserppV 6u11;e61
eueN peluo)
9bozzdtzerur6rylalelsq)rnLl) sllel
laaJls ael 'N 0z I
,(rua6y/ueduo3lalllw )ul
:pe1uo1 l(rerup6
Jalsaq)roo,0uno)retue) relos ppolatueN t:aford
TSNUJ i 1:e,!:l;1.:*
.l
"t\'.)tll( ).l sll I(l\\'l.tuvt\
1C,;# r,l,r/olaqunp 6o1 I
:pa^tareu
A]NO lsn lHl,ll
s6uDleuapun lerepal pue alels uo OdHSOW
Asnll le)ltolslH puel^Jew aq] txolj sluaululo) lo, ]senbeu ,S'Iufuol l,l]nlu l)Iroud
Cultural Resource Assessment for the
Todd Solar Center Site
Hurlock, Dorchester County, Maryland
Prepared for
Invenergy, LLC
One South Wacker Drive
Suite 1800
Chicago, Illinois 60606
Prepared by
Mechelle Kerns, PhD, RPA
Kerns CRM Consultants, LLC
94 West Earleigh Heights Road 410-409-5187
Severna Park, Maryland 21146 www.KernsCRMConsultants.com
October 15, 2015
Cultural Resource Assessment for the Todd Solar Center Site,
Hurlock, Dorchester County, Maryland
Table of Contents
Figures............................................................................................................................................. 1
Introduction ..................................................................................................................................... 2
Property Description ....................................................................................................................... 5
Cultural Context .............................................................................................................................. 6
Regional Prehistory ..................................................................................................................... 6
Paleo-Indian Period ................................................................................................................ 6
Archaic Period ........................................................................................................................ 6
Woodland Period .................................................................................................................... 6
Prehistoric Occupation in the Immediate Area ....................................................................... 7
Historical Context ....................................................................................................................... 8
Site Conditions .............................................................................................................................. 10
Local Environmental Setting .................................................................................................... 10
Topography ............................................................................................................................... 10
Soils........................................................................................................................................... 11
Surface Conditions and Signs of Disturbance .......................................................................... 12
Historic Resources ........................................................................................................................ 14
Archaeological Resources ............................................................................................................. 15
Planned Alterations ....................................................................................................................... 16
Findings and Recommendations ................................................................................................... 18
Bibliography ................................................................................................................................. 19
Appendix I: Qualifications ............................................................................................................ 21
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
Figures
Figure 1: Project Location in Maryland .......................................................................................... 2
Figure 2: Maryland Archaeological Research Units Map .............................................................. 3
Figure 3: Maryland Watershed Map ............................................................................................... 3
Figure 4: Project Location 1988 Rhodesdale USGS Topo Map ..................................................... 4
Figure 5: Proposed Project Property ............................................................................................... 5
Figure 6: Project Area Topography .............................................................................................. 11
Figure 7: Project Area Typical Soil Profile .................................................................................. 11
Figure 8: Project Area, Wright’s Branch ...................................................................................... 12
Figure 9: Project Area, After Harvest ........................................................................................... 13
Figure 10: Project Area, Under Cultivation .................................................................................. 13
Figure 11: Recorded Sites in the Immediate Area ........................................................................ 15
Figure 12: Typical Solar Panel Facility ........................................................................................ 16
Figure 13: Planned Alterations to the Property............................................................................. 17
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
2
Introduction
Invenergy, a developer of solar power collection and transmission utility sites, is considering a
location for the installation of a new facility. This report addresses the potential for historical
and cultural resources (Phase Ia archaeological and historic structures survey) within the project
area and the Area of Proposed Effect (APE). The proposed site for the Todd Solar Center is
located on the near the town of Hurlock, on Harper Road, on the Eastern Shore of Maryland in
Dorchester County, approximately 14 miles southwest of the county seat of Cambridge (Figure
1). The site is located within the Coastal Plain Province, Maryland Archaeological Research Unit
3 - Nanticoke-Wicomico-Manokin-Big Annemessex Drainage (Figure 2).
Figure 1: Project Location in Maryland
The project property is located approximately 1.5 miles southwest of Hurlock, Maryland, a small
town of 2.88 square miles at the intersection of MD Routes 331 and 392. The project area is not
within the town boundaries. The immediate area is rural and agricultural.
The site is located within the Nanticoke River watershed (Figure 3). The property consists of a
143.3-acre parcel of agriculture land currently under cultivation with soybeans and potatoes. The
parcel is bisected by Wright’s Branch that runs into Marshyhope Creek, a tributary of the
Nanticoke River. The property’s eastern boundary is approximately one-quarter mile from
Marshyhope Creek.
The property is bounded by Harper Road to the east, Ennals Rd to the south, Skeet Club Road to
the north, and the Hurlock Sewage Treatment Plant (on Jones Villa Drive) to the west: large
wastewater treatment ponds abut the project property (Figure 4).
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
3
Figure 2: Maryland Archaeological Research Units Map
Figure 3: Maryland Watershed Map
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
4
Figure 4: Project Location 1988 Rhodesdale USGS Topo Map
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
5
Property Description
The proposed project area is situated in a rural setting abutting a wastewater treatment plant and
levied management ponds. The 143.8-acre site has been cleared of vegetation, save a buffer of
trees that bisects the property, following a creek that runs through the parcel (Figure 5). The
land is flat with virtually no variation in elevation. It is currently utilized a farmland and has
been such for the last century. There is very little residential development in the immediate area
with the largest concentration of housing located 1.5 miles to the northwest.
Figure 5: Proposed Project Property
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
6
Cultural Context
Regional Prehistory
The following summaries of regional prehistory of the Potomac River Valley and the Mid-
Atlantic Region have been taken from the works of LeeDecker, Martin, and Friedlander (1988)
and Weinberg, Lawrence and Schopp (2007). The prehistory of the Potomac River Valley and
Mid-Atlantic region has been traditionally divided into three major periods, the Paleo-Indian,
Archaic, and Woodland. A fourth time period, the Contact Period, marks the final phase of
occupation by Native American groups in the Mid-Atlantic region.
Paleo-Indian Period (circa 11,000 to 8,000 B.C.) is characterized by a hunting and gathering
subsistence pattern, followed by small kin-base bands who hunted cold-adapted animals such as
caribou, mastodon, and woodland bison (Weinberg, Lawrence and Schopp 2007). Fish and
foraging for plant resources were also presumably important in their diet. Paleo-Indian finds in
Maryland are poorly represented, with only a few intact sites including the Higgins Site and over
a hundred isolated stone tools found (Dent 1995 and Ebright 1992).
Archaic Period (circa 8,000 to 1000 B.C.) lifeways are characterized by hunting and gathering
of a variety of food resources within a relatively well-defined territorial area, while continuing
the traditions from the Paleo-Indian Period. Settlements expanded into more diverse
environments, gathering a wide variety of shellfish, fish, game and plant food resources such as
nuts, berries, and roots (Dent 1995). The appearance of the Corner-Notched Tradition (7,500-
6000) and the Bifurcate Tradition (6,800 to 6,000) represent tool style changes characteristic of
the Early Archaic Period.
While the Middle Archaic tool kits continued to resemble those of previous periods, several
types of ground-stone tools were added for processing an expanded resource base. A variety of
grinding tools, such as mortars and pestles, indicate the increased reliance on plants in their diet.
The Late Archaic Period (circa 4,000 to 1000 B.C.) is marked by a greater emphasis on local
resource exploitation. Settlement patterns are found more along interior drainages, with larger
social groupings and increased sedentism (Mouer 1991 and Steponaistis 1980). Regionally,
evidence for permanent housing began to appear at this time (Griffin 1978). The establishment
of extensive trade networks and the introduction of complex mortuary practices are characteristic
of this period (Thomas 1973). Carved, lug-handled steatite bowls are one of the most noted
types of artifacts to be introduced to the Chesapeake Bay Region, indicating a more sedentary
pattern of existence (Dent 1995 and Tuck 1978).
Woodland Period (circa 1,000 B.C. to A.D. 1600) is better known than the Paleo-Indian and
Archaic Periods. The Early Woodland Period (1,000 - 300 B.C.) represents an increased
sedentary lifestyle for the native population, with larger, long-term sites being serviced by
outlying extraction sites (Mouer 1991). Domesticated cultigens, such as corn, beans, and squash,
together with wild glasses, such as amaranth and chenopodium, where gradually incorporated
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
7
into the daily diet. The flaked tool industry reflects Late Archaic technology with small bifaces,
drills, scrapers, and utilized flakes. Antler and bone tools have been recovered as well (Dent
1995). A rapid rise in ceramic technology flourished during the Early Woodland Period. The
earliest ceramics, Marcey Creek wares, were tempered with crushed steatite and formed in a
similar fashion as steatite bowls of the previous period (Mouer 1991). Other types of ceramics,
including Selden Island, Bushnell, and Croaker Landing wares, are possibly distinctive forms for
the Chesapeake Bay area (Custer 1989). Accokeek wares, featuring sand and quartz temper and
coil construction, eventually replaced Marcey Creek ceramics (Steponaitis 1980 and Wright
1973).
The Middle Woodland Period (300 B.C. to A.D. 900) witnessed the continued elaboration of
mortuary practices, including burial mounds and elaborate, exotic ceremonial grave goods
related to the Adena culture (Griffin 1967). These grave practices and goods indicate a shift
from a band level of social organization to complex rank societies, along with the emergence of
extensive trade associations beyond the immediate interior of Maryland. Pottery styles
continued to shift. Popes Creek, a thick-walled, and sand-tempered, net-impressed ware, and
Mockley, a shell-tempered cord-and net-impressed ware, are two dominant styles (Custer 1989,
Dent 1995, Steponaitis 1980 and Wright 1973).
In the Late Woodland Period (A.D. 900 to 1607), settlement patterns begin to reflect permanent
towns with a subsistence base focused on cultivated foodstuffs, such as corn, beans, and squash.
Floodplain locales are the favored locations for villages, based on the availability of fertile
bottomland soils for agricultural practices. Smaller base camps and procurement sites tend to
serve as specialized function sites with periods of multiple re-use. Ceramic diversity continues,
with a variety of motifs likely associated with the borrowing of designs from other societies
through established trade networks. Food sources were diverse and plentiful, including shellfish
and anadromous fish, nuts, starchy tubers, amaranth and goosefoot (Dent 1995).
Prehistoric Occupation in the Immediate Area
During the contact period (post 1607) and throughout the 17th century, the colony of Maryland
generally had good relations with the native inhabitants through a number of treaties. Some
persistent issues that caused strife were due to inter-tribal relations that arose when groups
traveled into or out of competing territories. The names of native groups on the Eastern Shore of
Maryland are memorialized in the names of the rivers that flow into the Chesapeake Bay and the
Atlantic Ocean; Wicomiss, Choptank, Nanticoke, Assteague, Pocomoke and Accomac (Dent
1995). The Choptank and Nanticoke groups are associated with Dorchester County, Maryland
and the adjacent area of what is now Delaware. The territories they occupied are related to the
watersheds that share their name. The proposed project area is located between the Choptank (to
the west) and Nanticoke (to the west) Rivers.
The Nanticoke Indians, and other groups on the Eastern Shore present during the initial contact
period (early 17th
century), do not appear to have the numbers or political groupings as those on
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
8
the Western Shore such as the Powhatan and Susquehannocks (Dent 1955). Of the groups
occupying the mid-shore (in sections of modern Maryland and Delaware) region during the Late
Woodland, the Nanticoke consisted of approximately 650 people (Dent 1995; after Feest 1978).
They were considered a distinct group that occupied the “… territory bounding the drainage
system of the Nanticoke River.” (Porter 1979: 326). As with many of the Algonquin associated
tribal groups in Tidewater Region, the Nanticoke began to leave the Maryland and Delaware
region in the mid-eighteenth century after agreements with colonial governments failed and after
white settlers did not honor Indian-land boundaries (Porter 1979). Many groups moved north into
the Pennsylvania but some remained on the Eastern Shore up to the period of the American
Revolution (Porter 1979).
Historical Context
Dorchester County, Maryland was formed by 1669 from sections of Somerset (1666) and Talbot
(1662) Counties. The countryseat of Cambridge was established by 1684. As with most colonial
settlement in the Chesapeake region, the navigable rivers and adjacent areas were settled first,
with interior settlement by subsequent generations. By 1790, Dorchester County had nearly
16,000 residents with 30% percent of the population consisting of slaves but the majority of the
population was concentrated near Cambridge, the seat of government and the court, and along
the Choptank River (US Census 1996).
The Town of Hurlock was not part of the colonial period development but was one of the towns
established along the railways in Maryland during the railroad build-out after the US Civil War
(mid 19th
century). The town is located at a crossroads and was not incorporated until 1892. It
was first settled in 1869 after to the construction of the Dorchester and Delaware Railroad. The
first resident and businessman in the area was John M. Hurlock. His storehouse was constructed
the year the rail line was complete in 1869 and he built a house in 1872: the town is named for
him (Jones 1902). By 1902, the town had 450 residents (Jones 1902). The most significant
period of growth was from 1890 to 1930. Currently, Hurlock is the second largest town in
Dorchester County and has a large historic district (D-653) (MHT 2008).
The subject property is currently owned by W & J McWilliams Farms, LLC and they have held
the property since 2009. The previous owner, Warren M. Saunders purchased in the land,
(consisting of three tracks) in 1979 from Ruth Ann Gadekar who inherited the land from her
father Samuel Harold Phillips in 1971 (Dorchester County 1971). Previous to 1971, the subject
property was owned by Olin P Conway (1925), George Hertzog (1907) and John L. and Charles
M Scott (1905). The Scotts purchased the land from John P. and Sarah R. Harper (1882) and it
was combined with a track from D W Davis (1899). In 1882, a 74-acre section of the parcel was
conveyed from Thomas Hubbert to the Harpers and is referred to as “being part of a track of land
called Airey’s Chance” (Dorchester County 1882). Thomas Hubbert purchased the land from
Robert W. and Mary Randall in 1879 and property the was also referred to as part of “Airey’s
Chance.” The Randalls had held it prior to 1872: they purchased it from Lewis Ross and Caleb
Shepherd (Dorchester County 1879). Prior to 1872, the land records did not provide chain-of-
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
9
title information. However, the track of Airey’s Chance was patented by John Pitt Airey in 1766
and was made up of parts of three previously patented parcels; Govert’s Chance (1704), Brooms
Chance (1704) and True Dealing (1686) consisting of 563 ½ acres (Dorchester County 1766).
The numerous conveyances in the 19th
century appear to be related to investments in the land
surrounding Hurlock and the development related to the railroad. A number of the owners lived
outside of the state. Land records indicate that it has historically been part of larger parcels and
used and/or leased for farming not residential occupation.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
10
Site Conditions
Local Environmental Setting
As with much of the Eastern Shore, Dorchester County is sparsely populated with little
development. The majority of land use is agricultural or recreational due to the many waterways
and nature areas. “Dorchester County’s primary economies are agriculture and forestry-based.
Seafood processing from catching, cleaning, packing, and shipping, to the preparation of
seafood- is the primary economy in many of the village areas” (Cole 2008: 4). According to the
Maryland Department of the Environment,
Dorchester County covers approximately 354,870 land acres. Forty-eight percent (48%)
or 170,338 acres are zoned agricultural. Agricultural land dominates most of the
northeast portion of the county. Approximately 4% of Dorchester’s total land area is
developed. The remaining area is comprised of resource lands including forests,
agricultural lands, and wetlands. Tidal wetlands account for roughly 25% of the county’s
land area. Dorchester County’s wetlands account for approximately 39% of the entire
state’s wetlands (MDNR 2000).
As of 2005, “…woodland is a dominant feature of Dorchester County and… commercial
woodland consists of good quality loblolly pine as well as upland oaks, sweetgum, blackgum,
Virginia pine, holly, beech, or red maple, depending on soil wetness” (DSCD 2000:6).
The proposed project site in Hurlock is located between the Choptank and Nanticoke Rivers with
many feeder streams in the area. The two nearest bodies of water are Wrights Branch (which
bisects the project property) and Marshyhope Creek, a tributary of the the Nanticoke River. The
intersection of the Marshyhope Creek and the Nanticoke is approximately 7.5 miles downstream
from the project area. According to the Maryland Department of the Environment, “Marshyhope
Creek is existing stream valley greenways. This corridor is undeveloped and consists of
wetlands, marsh, and wooded banks that provide valuable habitat and stream protection”
(MDNR 2000).
Topography
Generally, the Eastern Shore of Maryland is flat with very little vibration in elevation. The
highest point in Dorchester County is at 57 feet AMLS between the upper reaches of the
Choptank and Nanticoke Rivers (MGS 2008). The proposed project area is nearly level at 25
AMSL and slopes to the southeast as it approaches the Marshyhope Creek.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
11
Figure 6: Project Area Topography
Soils
The USDA, Natural Resources Conservation Service, classifies the dominate soil within the APE
as Galestown loamy sand (GaA) with 0 to 2 percent slopes. The setting consists of flats and
fluviomarine terraces with linear down- and across-slopes and the project area is nearly level.
The soils are somewhat excessively drained with the water table at 80 inches.
Horizon Depth Soil Texture
Ap 0 to 11 inches Loamy Sand
Bt 11 to 40 inches Loamy Sand
BC 40 to 51 inches Sand
C 51 to 80 inches Sand
Figure 7: Project Area Typical Soil Profile
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
12
Surface Conditions and Signs of Disturbance
The portion of the project area considered for development consists of previously disturbed land
characterized by agricultural fields with a plow zone (Ap-the top most layer of the soil disturbed
to depth that a plow will penetrate, 12 to 25 cm, resulting in homogenizes soil layer), irrigation
well sites, drainage swales (some with culverts), and access roads. Wright’s Branch Creek
bisects the parcel and both sides of the creek are lined with a buffer of trees (Figure 8).
Figure 8: Project Area, Wright’s Branch
A review of historic topographic maps dating to 1905 indicates the northern section of the
proposed project site has been under cultivation since in early 20th
century: this was likely the
case in the 19th
century (based on the land records and land use patterned in the area). The
southern section of the parcel (below the creek) was mostly wooded until the mid-20th
century
but cleared converted to farmland by 1975. There is no domestic structure associated with the
current property configuration and only agricultural buildings and water-pumping infrastructure
are present. A review of aerial photographs dating to the 1960s, illustrate only farm-related
buildings. At the time of survey and reporting part of the property had recently been harvested
and the remainder cultivated with soybeans (Figures 9 and 10).
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
13
Figure 9: Project Area, After Harvest
Figure 10: Project Area, Under Cultivation
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
14
Historic Resources
There is no dwelling structure associated with the property and it’s current configuration.
According to the files and the GIS system at the Maryland Historical Trust/MD-SHPO, there are
no recorded historic structures extant within the APE (within a half of a mile) of the proposed
project area. However, there is a location with a MIHP number on the abutting parcel directly to
the north on Harper Road: the structure was town down ca. 2000. The Andrew Phillips Farm (D-
123) was recorded in 1975 and was noted as “a two-part frame dwelling, the earliest part being
one and one-half story, three bay long with a lean to on one gable and a two story, two bay long
structure on the other” (Bourne 1975). It was recorded as a 19th
century vernacular domestic
structure in deteriorated condition: it was not determined eligible for listing on the National
Register. The Phillips family owned the property from 1925 until 1979.
The housing abutting the property on the eastern boundary (near the intersection of Harper Road
and Palmer Mill Road) consists of trailer homes and small manufactured one level “ranch style”
houses. Similar types of housing are present on Ennall Road on the southern boundary of the
property near the water treatment plant facility.
The Hurlock Historic District (D-653) is located over 1.5 miles from the proposed project area
(to the northwest) and is outside the APE for direct effect. The Petersburg Survey District (D-
766) is located 0.60 miles from the proposed project area and it is outside the APE for direct
effect. The survey district and has not been formally evaluated for listing on the National
Register. Located at the southeastern most boundary of the survey district is the Zorah ME
Church, which dates to 1898, and although the Maryland Historical Trust in 1975 recorded it in
and in 2008 it has not been evaluated or determined eligible for the National Register.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
15
Archaeological Resources
According to the files at the Maryland Historical Trust/MD-SHPO, there are six recorded
archaeology sites within 2 miles (the APE) of the proposed Todd Solar Center project area. All
are located east of the project site and east of Palmers Mill Road adjacent to Marshyhope Creek.
No Phase I surveys have been conducted on the subject property on or adjacent properties: there
are no recorded archaeological sites on the subject property.
Site # Site Name Type Recorded
18DO08 Orchard Woodland short-term procurement camp and
historic field scatter 1954
18DO09 Blanchard Archaic and Late Woodland short-term resource
procurement camp 1954
18DO14 Waddell River Farm Late Archaic and Early & Late Woodland short-
term procurement camp 1953
18DO15 Unk Harper Woodland lithics and ceramics 1954
18DO26 Tub Island Late Woodland and possible Archaic base camp 1955
18DO29 G. Coventry / Ennal's Wharf Middle and Late Woodland short-term resource
procurement camp 1955
Figure 11: Recorded Sites in the Immediate Area
The sites date from the Archaic (8,000 to 6,000 BCE) to through the historic period. The
environmental context falls within the generally accepted type for prehistoric settlement as
established by predictive models for the region. Land areas within 200 meters (656 feet) of
stream terraces, stream confluences, and water features generally have a moderate to high
probability for evidence of prehistoric occupation and settlement (A.D. Marble & Company
2006: 37-44). The subject property is located in an area with documented archaeological sites
and the environmental setting (proximity to Wright’s Branch) is one associated with prehistoric
occupation and settlement.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
16
Planned Alterations
The proposed development of the subject property calls for minimal ground disturbance and
some limited excavation related to the installation of infrastructure for a solar energy collection
and distribution facility. As planned, the project would consist of photovoltaic (PV) panels and
steel racks installed in rows in the agricultural fields (Figure 12).
Figure 12: Typical Solar Panel Facility
Ground disturbance would be related to buried electric transmit cables, the installation of
approximately nine electricity inverters, and a small switchyard to be built on the site. An
electric circuit connecting the two fields of panels would be installed by underground directional
bore or overhead circuit. An eight-foot fence will surround the facility and a gravel road is
expected to be installed around the perimeter of the panel arrays. As the site is largely flat, little
to no grading is expected. The PV racks will be mounted on piles that can be installed without
excavation via boring. The area of the stream and wooded buffers would not be developed as
part of the project and appropriate setbacks will be established based on state/local regulations
(Figure 13).
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
17
Figure 13: Planned Alterations to the Property
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
18
Findings and Recommendations
There are no recorded historic resources, nor were any discovered during this survey, that
suggest that this planned undertaking would have a direct effect on historic resources. Moreover,
the abutting water treatment plant and related water treatment ponds have previously altered the
view shed of the property. No further study related to historic resources is warranted.
The subject property is located near an area with documented archaeological sites and the
environmental setting is one associated with prehistoric occupation and settlement therefore
there is a high to moderate likelihood that prehistoric or historic archaeological resources maybe
located within the APE and could be disturbed or destroyed by this planned undertaking. Phase I
archaeological testing is warranted to establish the presence or absence within the proposed APE
to determine the impact of development on archaeological resources.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
19
Bibliography
A.D. Marble & Company
2006 U.S. 301 Project Development, Archaeological Predictive Model. Prepared for the
Delaware Department of Transportation in association with Rummel, Klepper, & Kahl
Bourne, Michael
1975 Maryland Historical Trust Worksheet. Nomination Form for the National Register of
Historic Places, National Park Service. “Andres Phillips Farm (D-123).” On File at the
Maryland Historical Trust, Crownsville, MD.
Cadzow, Donald A.
1939 “Archaeological Studies of the Susquehannock Indians of Pennsylvania.” Safe Harbor
Report, No. 2, Harrisburg, PA: Pennsylvania Historical Commission.
Cole, Wanda Diane
2008 Sea Level Rise: Technical Guidance for Dorchester County. Maryland Eastern Shore
Resource Conservation & Development Council. Maryland Department of Natural
Resources Coastal Zone Management Division. Annapolis, Maryland.
Dent, Richard J.
1995 Chesapeake Prehistory: Old Traditions, New Directions. Plenum Press, New York.
Dorchester County Maryland
1971 Dorchester County Circuit Court (Land Records) PLC 169, p. 0546. MSA CE 47-220.
1929 Dorchester County Circuit Court (Land Records) JFD 25, p. 0110. MSA CE 47-79.
1907 Dorchester County Circuit Court (Land Records) CL 32, p. 0647. MSA CE 47-44.
1905 Dorchester County Circuit Court (Land Records) CL 31, p. 0229. MSA CE 47-4.
1882 Dorchester County Circuit Court (Land Records) CL 4, p. 0696. MSA CE 47-16.
1878 Dorchester County Circuit Court (Land Records). FJH 13 & CL 1, p. 0105. MSA CE 47-
13.
1766 Patented Certificates 350. Aireys Chance, John Pitt Airey, 563 1/2 Acres.
Dorchester Soil Conservation District (DSCD)
2000 Dorchester Soil Conservation District Strategic Plan. Maryland Association of Soil
Conservation Districts. Cambridge, MD. Accessed 10/15/2015
http://mascd.net/districts/dorchester/Dorchester%20Strategic%20Plan.pdf.
Ebright, Carol A.
1992 “Early Native American Prehistory on the Maryland Western Shore: Archaeological
Investigations at the Higgins Site.” Vols. 1 – 3, Baltimore, Maryland State Highway
Administration and Department of Natural Resources.
Griffin, James B.
1967 “Eastern North American Archaeology: A summary.” Science 156:175-191.
1978 “Eastern United States.” In: Chronologies in New World Archaeology edited by R. E.
Taylor and C. W. Meighan. Academic Press, New York.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
20
Jones, Elias
1902 History of Dorchester County, Maryland. Williams & Wilkins Company Press:
Baltimore, MD.
LeeDecker, Charles H. and John W. Martin, Amy Friedlander
1988 Archaeological Evaluation of the Greenbelt Storage Yard, WMATA Construction
Segment E-11, Prince George's County, Maryland. (tDAR ID: 166875)
Maryland Department of Natural Resources
2000 Maryland Atlas of Greenways, Water Trails, and Green Infrastructure. Maryland
Greenways Commission. Accesses October 14, 2015.
http://www.dnr.state.md.us/greenways/introduction.html
Maryland Geological Survey (MSG)
2008 Highest and Lowest Elevations in Maryland's Counties. Maryland Geology. Accessed
October 14, 2015. http://www.mgs.md.gov/geology/highest_and_lowest_elevations.html
Maryland Historical Trust
2008 Maryland Historical Trust. Determination of Eligibility Form for the Hurlock Historic
District (D-653). Multiple forms; Bourne 1975, Reinhart 2001 and Tourat 2008.
Porter III, Frank W.
1979 "Strategies for Survival: The Nanticoke Indians in a Hostile World.” Ethnohistory 26,
no. 4: 325.
State of Maryland, Department of Natural Resources
2014 “MERLIN- Maryland Environmental Resource and Land Information Network.”
http://geodata.md.gov/imaptemplate/?appid=a8ec7e2ff4c34a31bc1e9411ed8e7a7e
Steponaitis, Laurie C.
1980 A Survey of Artifact Collections from the Patuxent River Drainage, Maryland. (TDAR
ID: 116845)
Wright, Henry T.
1973 An Archeological Sequence in the Middle Chesapeake Region, Maryland. Baltimore:
Maryland Geological Survey.
US Census Bureau
1996 Population of States and Counties of the United States: 1790 to 1990. Washington, DC:
GPO.
USDA Natural Resources Conservation Service
1997 "Web Soil Survey.” National Resources Inventory.
http://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm (accessed April 8, 2015).
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
21
Appendix I: Qualifications
MECHELLE KERNS, PHD, RPA
Principal Archaeologist & Historian
Kerns CRM Consultants, LLC
94 West Earleigh Heights Rd
Severna Park, MD 21146
410-409-5187
EDUCATION
Doctor of Philosophy
Maritime History & Archaeology
University of St Andrews, Scotland, UK, 2003
Master of Arts
Historical Studies & Public History
University of Maryland Baltimore County,
1999
Bachelor of Arts
Ancient Studies
University of Maryland Baltimore County,
1996
EXPERIENCE AND QUALIFICATIONS:
Dr. Kerns has over seventeen years of experience with historical research, archeology, maritime
history, and cultural resource management in 11 states throughout the United States. She
exceeds the Secretary of the Interior’s standards for Archeology and History and is certified by
the Register of Professional Archaeologists (RPA). She has extensive experience with all phases
of archaeological field work (terrestrial and underwater) as well as research design development,
data analysis, report writing, public outreach and education programs and has directed
reconnaissance, intensive surveys, and data recovery investigations on both historic and
prehistoric sites. Clients have included the Federal government (FEMA, USACE, US BOP, and
VAMC), state and local infrastructure authorities; state governments; non-profit organizations;
and the private sector.
Representative projects include:
2013 Clifton Mansion (18BC178) Phase I Archaeological Testing: Geothermal Field, Porch
Foundation and Elevator Installation Project Areas. Clifton Mansion & Civic Works,
Baltimore, MD.
2013 Cambridge Solar Project: Phase I Archaeological Investigation of the Adams Farm at
4919 Bucktown Road, Cambridge, Dorchester County, Maryland. OneEnergy
Renewables, Seattle, WA.
2011 Survey Report: Staff Housing at the United State Penitentiary, Atlantic, Georgia. Federal
Bureau of Prisons.
2011 Cultural/Historical Research for Environmental Assessments (EA) for Five New England
Veteran Administration Medical Centers, US Veterans Administration.
Cultural Resource Assessment for the Todd Solar Center Site, Hurlock, Dorchester County, Maryland
2009 Hudson River Sediment Remediation Phase I Project Archeological Resources
Assessment Underwater Resource U-2. U.S. EPA, New York Department of
Environmental Quality, and General Electric.
2009 National Aeronautics and Space Administration, Wallops Flight Facility Shore Line
Restoration Environmental Impact Statement. NASA, Wallops Flight Facility.
2009 Phase II Archaeological Evaluation of Site 47BA199 (Forest Service Site 09-02-05-009)
Chequamegon-Nicolet National Forest Bayfield County, Wisconsin. DuPont Corporate
Remediation.
2009 Phase I Archaeological Survey of Locations 21 and 31, Dover Air Force Base, Dover DE.
DOD, US Air Force.
2009 Phase I Archaeological Survey of The Beauvoir Property (22HR1012) Harrison County,
Mississippi. Department of Homeland Security, FEMA.
2008 Iron Forge (18AN1386) Discovery Cultural Resources Documentation for the Maryland
Aviation Administration, Anne Arundel County, Maryland.
2008 Report of Investigations: Archival Research Concerning Center Hill Lake, Tennessee.
Department of the Army Nashville District, US Army Corps of Engineers.
2008 Phase I Archaeological Survey of the Black and White Inn (18MO669) Montgomery
County, Maryland. Montgomery County Department of Public Works and
Transportation.
2008 Phase I Archaeological Survey of Area I & Area J Trails at the Lorton Prison Facility.
Fairfax County Park Authority, Cultural Resource Management and Protection Section,
Fairfax, VA.
2007 Phase I Archaeological Survey of Area G & Area H Trails at the Lorton Prison Facility.
Fairfax County Park Authority, Cultural Resource Management and Protection Section,
Fairfax, VA.
2007 Phase II Archaeological Survey of the Homeland Property (18PR867 and 18PR868).
Prince George’s County, MD. Pulte Homes Corporation, 2007.
2006 Phase I Archaeological Survey Demiray Property (18FR857) 104-106 North Market
Street Frederick, Maryland. David Demiray, on file at the City of Frederick Office of
Planning and the MHT.
2006 Fountain Rock Park Phase II Archaeological Survey (18FR835 & 18FR836). Public
Works Division Frederick County Office of Project Management Frederick, MD.
2002 The Santa Rosa Island Shipwreck (Phase III) Project (8ES1905). Archaeology Institute,
The University of West Florida, Pensacola, FL.
1997-2005 Phase III Excavations at London Town (18AN48), Edgewater, Maryland. Anne
Arundel County’s Office of Environmental and Cultural Resources, Annapolis, MD.
U.S. Fish & Wildlife Service
Todd SolarIPaC Trust Resource ReportGenerated September 01, 2015 04:01 PM MDT
UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report
09/01/2015 04:01 Page 2 Information for Planning and ConservationIPaCVersion 2.2.3
US Fish & Wildlife Service
IPaC Trust Resource Report
Project DescriptionNAME
Todd Solar
PROJECT CODE
UFINC-DENQ5-HJXES-PBCI7-4H3CYQ
LOCATION
Dorchester County, Maryland
DESCRIPTION
20 MW solar energy project targetingconstruction in 3q and 4q 2016
U.S. Fish & Wildlife Contact InformationSpecies in this report are managed by:
Chesapeake Bay Ecological Services Field Office177 Admiral Cochrane DriveAnnapolis, MD 21401-7307 (410) 573-4599
UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report
09/01/2015 04:01 Page 3 Information for Planning and ConservationIPaCVersion 2.2.3
Endangered
Endangered SpeciesProposed, candidate, threatened, and endangered species that are managed by the
and should be considered as part of an effect analysisEndangered Species Programfor this project.
This unofficial species list is for informational purposes only and does not fulfill therequirements under of the Endangered Species Act, which states that FederalSection 7agencies are required to "request of the Secretary of Interior information whether anyspecies which is listed or proposed to be listed may be present in the area of aproposed action." This requirement applies to projects which are conducted, permittedor licensed by any Federal agency.
A letter from the local office and a species list which fulfills this requirement can beobtained by returning to this project on the IPaC website and requesting an OfficialSpecies List from the regulatory documents section.
Mammals Delmarva Peninsula Fox Squirrel Sciurus niger cinereus
CRITICAL HABITAT
has been designated for this species.No critical habitat
https://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=A00B
Critical HabitatsPotential effects to critical habitat(s) within the project area must be analyzed along withthe endangered species themselves.
There is no critical habitat within this project area
UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report
09/01/2015 04:01 Page 4 Information for Planning and ConservationIPaCVersion 2.2.3
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Migratory BirdsBirds are protected by the and the Bald and Golden EagleMigratory Bird Treaty ActProtection Act.
Any activity which results in the of migratory birds or eagles is prohibited unlesstakeauthorized by the U.S. Fish and Wildlife Service ( ). There are no provisions for1allowing the take of migratory birds that are unintentionally killed or injured.
You are responsible for complying with the appropriate regulations for the protection ofbirds as part of this project. This involves analyzing potential impacts and implementingappropriate conservation measures for all project activities.
American Oystercatcher Haematopus palliatus
Year-roundhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0G8
American Bittern Botaurus lentiginosus
Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0F3
Bald Eagle Haliaeetus leucocephalus
Year-roundhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B008
Black-billed Cuckoo Coccyzus erythropthalmus
Season: Breedinghttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0HI
Fox Sparrow Passerella iliaca
Season: Wintering
Gull-billed Tern Gelochelidon nilotica
Season: Breeding
Kentucky Warbler Oporornis formosus
Season: Breeding
Least Bittern Ixobrychus exilis
Season: Breeding
Least Tern Sterna antillarum
Season: Breeding
Lesser Yellowlegs Tringa flavipes
Season: Wintering
Marbled Godwit Limosa fedoa
Season: Wintering
Nelson's Sparrow Ammodramus nelsoni
Season: Wintering
Peregrine Falcon Falco peregrinus
Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0FU
Pied-billed Grebe Podilymbus podiceps
Year-round
UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report
09/01/2015 04:01 Page 5 Information for Planning and ConservationIPaCVersion 2.2.3
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern
Bird of conservation concern Prairie Warbler Dendroica discolor
Season: Breeding
Prothonotary Warbler Protonotaria citrea
Season: Breeding
Purple Sandpiper Calidris maritima
Season: Wintering
Red Knot Calidris canutus rufa
Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0DM
Red-headed Woodpecker Melanerpes erythrocephalus
Year-round
Rusty Blackbird Euphagus carolinus
Season: Wintering
Saltmarsh Sparrow Ammodramus caudacutus
Year-round
Seaside Sparrow Ammodramus maritimus
Year-round
Short-billed Dowitcher Limnodromus griseus
Season: Wintering
Short-eared Owl Asio flammeus
Season: Winteringhttps://ecos.fws.gov/speciesProfile/profile/speciesProfile.action?spcode=B0HD
Snowy Egret Egretta thula
Season: Breeding
Wood Thrush Hylocichla mustelina
Season: Breeding
Worm Eating Warbler Helmitheros vermivorum
Season: Breeding
UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report
09/01/2015 04:01 Page 6 Information for Planning and ConservationIPaCVersion 2.2.3
RefugesAny activity proposed on lands must undergo a 'CompatibilityNational Wildlife RefugeDetermination' conducted by the Refuge. If your project overlaps or otherwise impacts aRefuge, please contact that Refuge to discuss the authorization process.
There are no refuges within this project area
UFINC-DENQ5-HJXES-PBCI7-4H3CYQIPaC Trust Resource Report
09/01/2015 04:01 Page 7 Information for Planning and ConservationIPaCVersion 2.2.3
WetlandsImpacts to and other aquatic habitats from your project may be subject toNWI wetlandsregulation under Section 404 of the Clean Water Act, or other State/Federal Statutes.
Project proponents should discuss the relationship of these requirements to their projectwith the Regulatory Program of the appropriate .U.S. Army Corps of Engineers District
DATA LIMITATIONS
The Service's objective of mapping wetlands and deepwater habitats is to produce reconnaissance level informationon the location, type and size of these resources. The maps are prepared from the analysis of high altitude imagery.Wetlands are identified based on vegetation, visible hydrology and geography. A margin of error is inherent in the useof imagery; thus, detailed on-the-ground inspection of any particular site may result in revision of the wetlandboundaries or classification established through image analysis.
The accuracy of image interpretation depends on the quality of the imagery, the experience of the image analysts,the amount and quality of the collateral data and the amount of ground truth verification work conducted. Metadatashould be consulted to determine the date of the source imagery used and any mapping problems.
Wetlands or other mapped features may have changed since the date of the imagery or field work. There may beoccasional differences in polygon boundaries or classifications between the information depicted on the map and theactual conditions on site.
DATA EXCLUSIONS
Certain wetland habitats are excluded from the National mapping program because of the limitations of aerialimagery as the primary data source used to detect wetlands. These habitats include seagrasses or submergedaquatic vegetation that are found in the intertidal and subtidal zones of estuaries and nearshore coastal waters.Some deepwater reef communities (coral or tuberficid worm reefs) have also been excluded from the inventory.These habitats, because of their depth, go undetected by aerial imagery.
DATA PRECAUTIONS
Federal, state, and local regulatory agencies with jurisdiction over wetlands may define and describe wetlands in adifferent manner than that used in this inventory. There is no attempt, in either the design or products of thisinventory, to define the limits of proprietary jurisdiction of any Federal, state, or local government or to establish thegeographical scope of the regulatory programs of government agencies. Persons intending to engage in activitiesinvolving modifications within or adjacent to wetland areas should seek the advice of appropriate federal, state, orlocal agencies concerning specified agency regulatory programs and proprietary jurisdictions that may affect suchactivities.
Wetland data is unavailable at this time.
Inv* gvSeptember 4,2015
Lori ByrneDNR Wildlife &580 Taylor Ave.Tawes Office BuiAnnapolis, MD 21
Tel: 410-260-8573
Subject:Envi
Dear Ms. Byrne:
Invenergy Solaragricultural parcelMap 0023, Parcelwater treatment p ow
The attached sk
:ntage
ing E-101
for Todd Solar in Dorchester County, MD
LLC, is developing a 20 MW solar project on a 143-acreDo County, MD. The parcel is identified in the tax records as
1 and is located southeast of the Town of Hurlock, MD, adjacent to aby the Town of Hurlock.
Note that as part oshows
the projpreliminary project boundaries on a USGS 24,000 scale map.
, the local utility will be installing overhead electric linesbetween the solaryellow and black
ilities the Todd Substation which is represented on the sketch as a
Todd Solarreview of pspecles, rare specr
Please providelisted below.
Sincerel
J. MillerDirector, ProjectInvenergy LLC120 N. Lee Street,Falls Church, VA(301) 610-6413
i\\'l iNl ill( ;\' I J,(l One South Wacker
ectthe
proji. or
land Wildlife & Heritage Service perform an environmentalto identifr any potential impacts of the project to protectedhabitat.
environmental review to me at the Falls Church, VA address
l0uite,.046
, Suite 1800 Chicago, \L 60606 "l 31,2.224.1,4tJ0 F 312.224.7444 invenergSrllc.com
)^Cof) !-t{ ;gCJ.:;EH i:^r o 5l
-1tl-.t e
:)oo
-IUooL
oo
3r,
oaao.Euoo
P.E-r-E
*=UUFEflEIJiFEEfIi9lo olC rffi EIEERS i PI I
O i,.i-4o
IIItII
I"rI
1.*t-j
IMnRYLANDDEPARTMENT OF
NRruRnI RTSOURCES
Lorry Hogan, Governor
Boyd K. Ruthefiord, Lt. Governor
Mark J. Belton, Secretary
Mqrk L. Hoffman, Acting Deputy Secretory
September 24,2015
Eric MillerInvenergy, LLCOne South Wacker Dr., Suite 1800Chicago, IL 60606
RE: Environmental Review for Todd Solar, 20 MW solar project, TM 23 P l, Town ofHurlock, Dorchester County, MD.
Dear Mr. Miller:
The Wildlife and Heritage Service has determined that there are no State or Federal records forrare, threatened or endangered species within the boundaries of the project site as delineated. Asa result, we have no specific comments or requirements pertaining to protection measures at thistime. This statement should not be interpreted however as meaning that rare, threatened orendangered species are not in fact present. Ifappropriate habitat is available, certain speciescould be present without documentation because adequate surveys have not been conducted.
Thank you for allowing us the opportunity to review this project. If you should have any fuitherquestions regarding this information, please contact me at (410) 260-8573.
Sincerely,
o#o orLori A. Byrne,Environmental Review CoordinatorWildlife and Heritage ServiceMD Dept. of Natural Resources
ER# 2015.1351.do
Tawes State Office Building - 580 Taylor Avenue - Annapolis, Maryland2l40l410-260-8DNR or toll free in Maryland 877-620-8DNR - dnr.maryland.gov - TTY Users Call via the Maryland Relay
CONFIDENTIAL BUSINESS INFORMATION
1
Habitat Assessment
For the
Dorchester Solar Project
Prepared for:
Invenergy LLC One South Wacker Drive Suite 1800 Chicago, IL 60606 Prepared by: Davis & Associates Environmental Consulting LLC PO Box 733 Chestertown, MD 21620
CONFIDENTIAL BUSINESS INFORMATION
2
1. Introduction
A critical habitat assessment was conducted for a site in Dorchester County, Maryland. The assessment
followed Tier 1 and Tier 2 of the U.S. Fish and Wildlife Service Land-Based Wind Energy Guidelines
(USFWS 2012) because similar guidance for solar development has not yet been issued by the U.S. Fish
and Wildlife Service (USFWS).
2. Project Location and Setting
The site (project area) is located on the west side of Palmers Mill Road approximately 1.5 miles south of
its intersection with MD 382, southeast of Hurlock in Dorchester County, Maryland. The site is located
in the Coastal Plain Physiographic province and is in a predominantly agricultural area that also includes
residential uses. A wastewater treatment facility is located west of the site.
3. Methods
Database Review and Landscape Level Assessment (Tier 1 of USFWS Guidelines)
A preliminary site evaluation was conducted that consisted of a landscape level assessment of habitat
for species of concern and a review of databases and other available information at the county, state
and federal level for sensitive species including rare, threatened and endangered species. The following
databases and sources were reviewed:
U.S. Fish and Wildlife Information for Planning and Conservation (IPaC) tool
Maryland’s Environmental Resources and Land Information Network (MERLIN)
Maryland Amphibian and Reptile Atlas (MARA) Database
USGS Maryland/DC Breeding Bird Atlas Project (BBA)
Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare,
Threatened and Endangered Species of Dorchester County (April 2010)
Site Characterization and Analysis (Tier 2 of USFWS Guidelines)
A site characterization was completed to assess the potential presence of the species of concern
identified through the database review and landscape level assessment (Tier 1). For the site
characterization, the site was delineated into vegetative communities based on a review of leaf-off
aerial photography, soil maps, and topographic maps. A reconnaissance level site visit was conducted
on October 6, 2015 to field verify the delineation of the vegetative communities. In the mixed
hardwood forest community, a single transect was walked starting from the southeastern portion of the
site at Palmers Mill Road on the south side of Wrights Branch in a northwesterly direction. A transect
was then walked from the northwest in a southeasterly direction back toward Palmers Mill Road
through the wetland community. Dominant and codominant species were recorded as well as
observations regarding forest structure.
CONFIDENTIAL BUSINESS INFORMATION
3
4. Findings
Database Review and Landscape Level Assessment
U.S. Fish and Wildlife Information for Planning and Conservation (IPaC) tool
The U.S. Fish and Wildlife Information for Planning and Conservation (IPaC) tool identified only one
wildlife species, the Delmarva Peninsula Fox Squirrel, as protected by the Endangered Species Act with
the potential to occur on site. Shortly thereafter, the Delmarva Peninsula Fox Squirrel was delisted from
federal protection on November 16, 2015. A plant species, Swamp Pink, is also protected by the
Endangered Species Act, and has potential to grow in Maryland’s Coastal Plain.
The IPaC tool also identified numerous birds of conservation concern protected by the Migratory Bird
Treaty Act that could potentially occur in the project area. These species are listed in IPaC Trust
Resource Report in the Appendix. These are migratory birds that are protected by the Migratory Bird
Treaty Act, which requires analyzing potential impacts and implementing appropriate conservation
measures for all project activities.
Maryland’s Environmental Resources and Land Information Network (MERLIN)
MERLIN was reviewed and there were no records of any sensitive species occurring on the site.
Sensitive species considered by MERLIN include rare, threatened and endangered species both federally
and state listed species.
Maryland Amphibian and Reptile Atlas (MARA) Database
The Maryland Amphibian and Reptile Atlas is a five-year joint project of the Natural History Society of
Maryland and the Maryland Department of Natural Resources. The goal of the project is to document
the current distributions of Maryland’s amphibian and reptile species. The MARA database was
reviewed to determine what species have the potential to occur on the site. The list of species reported
in the Rhodesdale quadrangle (the quadrangle of the project site) is included in the Appendix. None of
the species on the MARA list with potential to occur on the site is listed as state or federally threatened
or endangered.
USGS Maryland/DC Breeding Bird Atlas Project (BBA)
The results of the Maryland and DC Breeding Bird Atlas Project for 2002-2006 were reviewed for the
project site. The site is located in the northwest quadrant of the Rhodesdale quadrangle. A list of the
species is provided in the Appendix. No federally or state listed bird species appear on the list.
However, the prairie warbler and the wood thrush do appear on the list and these birds are listed as
birds on conservation concern by the USFWS as part of the Migratory Bird Treaty Act.
CONFIDENTIAL BUSINESS INFORMATION
4
Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare, Threatened and
Endangered Species of Dorchester County (April 2010)
The Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare, Threatened
and Endangered Species of Dorchester County (April 2010) is included in the Appendix. A review of the
MERLIN database does not show any records for any of these species on the project site.
Site Characterization and Analysis (Tier 2 of USFWS Guidelines)
The entire site consists of 143.3 acres. Approximately 124 (87%) acres are in use as tilled agricultural
fields for corn and soybeans and approximately 19 (13%) acres are in natural vegetation along Wrights
Branch, a tributary of Marshyhope Creek.
The natural vegetation on the site consists of two vegetative communities. One community is an
uneven-aged, mature mixed hardwood forest that slopes down to Wrights Branch. Dominant trees are
approximately 16 inches in diameter. Dominant species include sweetgum, southern red oak, and
mockernut hickory. Understory and shrub layer species include American holly, mountain laurel,
greenbrier and poison ivy. The understory and shrub layer are moderately dense. The second
community is a wetland area that occurs at the base of the slope immediately adjacent to Wrights
Branch. Dominant tree species include red maple, sweetgum, blackgum, American holly, and sweetbay.
Shrub and perennial species include sensitive fern, royal fern, cinnamon fern, sweet pepperbush, lizard
tail, and clearweed.
FEDERALLY LISTED SPECIES
Based on the site characterization and review of the database information, the following species listed
as federally threatened or endangered have the potential to occur in Dorchester County:
Swamp Pink (Helonias bullata)
Description and Habitat
Swamp pink is a perennial of the lily family. It occurs in acidic wetlands from New Jersey south to
Georgia. The swamp pink can grow only in wetlands with perennially saturated – but not flooded – soils.
This dependence on an uncommon habitat type restricts the plant to small, scattered populations
throughout its range. The swamp pink grows in forested wetlands of Maryland’s coastal plain. In April,
its bright pink flowers bloom among the emerging skunk cabbage leaves. Four populations are currently
known, two in Cecil County and two in Anne Arundel County. It was classified as an Endangered Species
by the State of Maryland in 1987. (MD DNR 2015).
Analysis
The soils in the wetlands on site are frequently flooded and therefore suitable habitat for swamp pink
does not occur on the project site. Furthermore, the MERLIN database does not show any sensitive
habitats occurring on the project site.
CONFIDENTIAL BUSINESS INFORMATION
5
Other Federally Listed Species
Two other species listed as federally endangered appear on Maryland Department of Natural Resources
Wildlife and Heritage Service List of Rare, Threatened and Endangered Species of Dorchester County
(April 2010). These two species are the American Burying Beetle (Nicrophorus americanus) and the Red-
cockaded Woodpecker (Picoides borealis). However, both of these species are noted as Endangered
Extirpated in Maryland, which means that it was once a viable component of the flora or fauna of the
state but for which no naturally occurring populations are known to exist in the state.
MIGRATORY BIRD TREATY ACT
The following birds are listed as birds of conservation concern and appear on the USGS Maryland/DC
Breeding Bird Atlas Project (BBA) for the northwest quadrant of the Rhodesdale quadrangle where the
project site is located.
Prairie Warbler (Dendroica discolor): The prairie warbler occurs in brushy slashings, bushy pastures,
and low pines. It breeds in dry, old clearings, edges of forest, and sandy pine barrens with undergrowth
of scrub oaks, especially on ends of slopes and ridges. The prairie warbler likes thick second-growth of
hickory, dogwood, hazel, or laurel with blackberry vines.
The forested areas and the edge of the forested areas on the site provide suitable habitat for the prairie
warbler for breeding. This species was also identified on the breeding bird atlas in this quadrant of the
Rhodesdale quadrangle as being observed with probable breeding evidence of territorial behavior. The
species is considered a Bird of Conservation Concern by the US Fish and Wildlife Service. The prairie
warbler is not listed on the current list of rare, threatened and endangered species in Maryland.
Wood Thrush (Hylocichla mustelina): The Wood Thrush breeds in deciduous and mixed forests in the
eastern U.S. where there are large trees, moderate understory, shade, and abundant leaf litter for
foraging. They winter in lowland tropical forests in Central America. Suitable habitat for the wood
thrush occurs on the project site in the forested areas along Wrights Branch. The species is considered a
Bird of Conservation Concern by the US Fish and Wildlife Service. The wood thrush is not listed on the
current list of rare, threatened and endangered species in Maryland.
STATE LISTED SPECIES
Delmarva Peninsula Fox Squirrel (Sciurus niger cinereus):
Description, Habitat and Behavior
The largest of all the tree squirrels, the Delmarva Peninsula fox squirrel has silver to whitish-gray slate
hair and an unusually full, fluffy tail and white belly. The squirrel’s coat varies in color from frosty silver-
gray to almost black. The Delmarva fox squirrel lives in mature forests of mixed hardwoods and pines
with a closed canopy and open understory. A habitat suitability model indicated that sites were fox
squirrels were present had a higher percentage of large trees (>12 inches in diameter), a lower
percentage of shrub groundcover, and a slightly lower understory density than did sites where squirrels
CONFIDENTIAL BUSINESS INFORMATION
6
were not found. Although it is a forest animal, the squirrel spends considerable time on the ground
foraging for food, typically in woodlots of mixed loblolly pine and hardwoods such as oak, maple,
hickory, walnut, and beech— trees that provide food including nuts and seeds. The squirrel will also
take food from farm fields. Feeding on tree buds and flowers during the spring, the squirrel will also eat
fungi, insects, fruit, and seeds. In the summer and early fall, the squirrel forages on mature, green pine
cones. The animal generally lives in woodlands associated with farmland areas—not typically in
suburban settings. Less agile than the common gray squirrel, the Delmarva fox squirrel often ambles
along the forest floor rather than leaping from branch to branch. The animal usually avoids
confrontations by running away rather than climbing a tree but will do so to avoid a predator. The fox
squirrel is also quieter than the gray squirrel. The home range of the fox squirrel varies, but averages
about 40 acres. The Delmarva fox squirrel prefers to nest in tree cavities but will also nest on a tree
crotch, in tangles of vines in tree trunks or at the end of large tree branches. Squirrels mate in late
winter and early spring. About 44 days later in February and March as many as four young are born.
Females may give birth to two litters per year. They raise the young by themselves for about three
months (USFWS, 2008).
On November 16, 2015, the U.S. Fish and Wildlife Service issued a final rule removing the Delmarva fox
squirrel from the list of endangered and threatened species. Following its 2012 review of the species,
the USFWS concluded that the best available scientific and commercial data indicate the Delmarva fox
squirrel is no longer in danger of extinction or likely to become endangered within the foreseeable
future. However, the Maryland Department of Natural Resources Wildlife and Heritage Service will
continue to protect the Delmarva fox squirrel and its habitat as a state threatened species (Lori, Byrne,
MD DNR WHS, personal communication to Noreen Davis, Nov 2015).
Analysis
The project site contains 19 acres of hardwood forest. There is a fairly dense shrub layer and dense
understory making the site unsuitable for the Delmarva fox squirrel. This is consistent with the MERLIN
database, which does not show that the site contains habitat for the Delmarva fox squirrel.
CONFIDENTIAL BUSINESS INFORMATION
7
Literature Cited
U.S. Fish and Wildlife Service. (2012). U.S. Fish and Wildlife Service Land-Based Wind Energy Guidelines.
Washington, D.C.
U.S. Fish and Wildlife Service (2008). Delmarva Peninsula Fox Squirrel Sciurus niger cinereus.
Washington, D.C.
MD Department of Natural Resources (October 2015). Endangered Plant Fact Sheet Swamp pink,
Helonias bullata. Retrieved from
http://dnr2.maryland.gov/wildlife/Pages/plants_wildlife/rte/rteplantfacts.aspx?PID=Swamp%20
Pink.
CONFIDENTIAL BUSINESS INFORMATION
8
APPENDIX
1. IPaC Trust Resource Report
2. Maryland Amphibian and Reptile Atlas (MARA) Species for Rhodesdale quadrangle
3. USGS Maryland/DC Breeding Bird Atlas Project (BBA) for Rhodesdale NW
4. Maryland Department of Natural Resources Wildlife and Heritage Service List of Rare,
Threatened and Endangered Species of Dorchester County (April 2010)
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:52 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6170213548 -75.8372604847 25.15 10.0 35.15
2 38.6196702758 -75.8341276646 27.27 10.0 37.27
3 38.6156800917 -75.8306515217 25.74 10.0 35.74
4 38.6140873091 -75.8332693577 22.34 10.0 32.34
Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
1 38.6158728998 -75.8285754919 23.4 6.0
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
©1997-2014 Sandia Corporation
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:54 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6170213548 -75.8372604847 25.15 10.0 35.15
2 38.6196702758 -75.8341276646 27.27 10.0 37.27
3 38.6156800917 -75.8306515217 25.74 10.0 35.74
4 38.6140873091 -75.8332693577 22.34 10.0 32.34
Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
2 38.6152441757 -75.8304838836 26.36 6.0
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
©1997-2014 Sandia Corporation
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:54 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6170213548 -75.8372604847 25.15 10.0 35.15
2 38.6196702758 -75.8341276646 27.27 10.0 37.27
3 38.6156800917 -75.8306515217 25.74 10.0 35.74
4 38.6140873091 -75.8332693577 22.34 10.0 32.34
Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
3 38.6147663418 -75.8308003843 25.49 6.0
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
©1997-2014 Sandia Corporation
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:54 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6170213548 -75.8372604847 25.15 10.0 35.15
2 38.6196702758 -75.8341276646 27.27 10.0 37.27
3 38.6156800917 -75.8306515217 25.74 10.0 35.74
4 38.6140873091 -75.8332693577 22.34 10.0 32.34
Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
4 38.6142507805 -75.8311061561 23.46 6.0
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
©1997-2014 Sandia Corporation
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:55 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6170213548 -75.8372604847 25.15 10.0 35.15
2 38.6196702758 -75.8341276646 27.27 10.0 37.27
3 38.6156800917 -75.8306515217 25.74 10.0 35.74
4 38.6140873091 -75.8332693577 22.34 10.0 32.34
Observation PointsLatitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
5 38.6139049752 -75.8314602077 23.37 6.0
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
©1997-2014 Sandia Corporation
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:55 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6150765151 -75.837110281 28.97 6.0 34.97
2 38.6093255168 -75.8400285244 31.99 6.0 37.99
3 38.6094428887 -75.8339989185 23.88 6.0 29.88
4 38.6105327616 -75.8326900005 25.18 6.0 31.18
5 38.6121423899 -75.8328402042 24.88 6.0 30.88
6 38.6131651557 -75.8335053921 9.8 6.0 15.8
Observation Points
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
Latitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
6 38.609002743 -75.834183991 25.61 6.0
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
©1997-2014 Sandia Corporation
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:55 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6150765151 -75.837110281 28.97 6.0 34.97
2 38.6093255168 -75.8400285244 31.99 6.0 37.99
3 38.6094428887 -75.8339989185 23.88 6.0 29.88
4 38.6105327616 -75.8326900005 25.18 6.0 31.18
5 38.6121423899 -75.8328402042 24.88 6.0 30.88
6 38.6131651557 -75.8335053921 9.8 6.0 15.8
Observation Points
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
Latitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
7 38.6090949642 -75.8383145928 31.64 6.0
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
©1997-2014 Sandia Corporation
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/4
Solar Glare Hazard Analysis Report
Generated Oct. 29, 2015, 2:56 p.m.
Inputs
Glare found
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/4
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6150765151 -75.837110281 28.97 6.0 34.97
2 38.6093255168 -75.8400285244 31.99 6.0 37.99
3 38.6094428887 -75.8339989185 23.88 6.0 29.88
4 38.6105327616 -75.8326900005 25.18 6.0 31.18
5 38.6121423899 -75.8328402042 24.88 6.0 30.88
6 38.6131651557 -75.8335053921 9.8 6.0 15.8
Observation Points
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/4
Latitude (deg) Longitude (deg) Ground Elevation (ft) Eye-level height above ground (ft)
8 38.6090907723 -75.839741528 32.49 6.0
Glare Occurrence PlotAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/4
©1997-2014 Sandia Corporation
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/14
Solar Glare Hazard Analysis Flight Path Report
Generated Oct. 29, 2015, 2:51 p.m.
Flight path: Private Air StripGrass Runway for crop dusting
Glare found
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/14
Analysis & PV array parameters
Flight path parameters
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
Direction (deg) 326.55
Glide slope (deg) 3.0
Consider pilot visibility from cockpit False
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/14
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/14
Glare occurrence plotsAll times are in standard time. For Daylight Savings Time add one hour.
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6170213548 -75.8372604847 25.15 10.0 35.15
2 38.6196702758 -75.8341276646 27.27 10.0 37.27
3 38.6156800917 -75.8306515217 25.74 10.0 35.74
4 38.6140873091 -75.8332693577 22.34 10.0 32.34
Flight Path Observation Points
Latitude (deg)Longitude(deg)
GroundElevation (ft)
Eye-level height aboveground (ft) Glare?
Threshold 38.621028229 -75.8410477638 29.21 50.0 No
1/4 mi 38.61801304 -75.8384952486 25.78 122.6 Yes
1/2 mi 38.6149978511 -75.8359427333 7.96 209.6 Yes
3/4 mi 38.6119826622 -75.8333902181 25.17 261.57 No
1 mi 38.6089674732 -75.8308377028 25.22 330.69 No
1 1/4 mi 38.6059522843 -75.8282851876 23.45 401.65 No
1 1/2 mi 38.6029370953 -75.8257326723 22.33 471.94 No
1 3/4 mi 38.5999219064 -75.823180157 20.17 543.29 No
2 mi 38.5969067175 -75.8206276418 0.52 632.11 No
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 5/14
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 6/14
ThresholdNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 7/14
1/4 mi
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 8/14
1/2 mi
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 9/14
3/4 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 10/14
1 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 11/14
1 1/4 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 12/14
1 1/2 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 13/14
1 3/4 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 14/14
©1997-2014 Sandia Corporation
2 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 1/14
Solar Glare Hazard Analysis Flight Path Report
Generated Oct. 29, 2015, 2:50 p.m.
Flight path: Private Air StripGrass Runway for crop dusting
Glare found
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 2/14
Analysis & PV array parameters
Flight path parameters
Analysis name Todd-MD_Fixed
PV array axis tracking none
Orientation of array (deg) 180.0
Tilt of solar panels (deg) 25.0
Rated power (kW) 0.0
Vary reflectivity True
PV surface material Light textured glass with ARC
Timezone offset -5.0
Subtended angle of sun (mrad) 9.3
Peak DNI (W/m^2) 1000.0
Ocular transmission coefficient 0.5
Pupil diameter (m) 0.002
Eye focal length (m) 0.017
Time interval (min) 1
Correlate slope error with material False
Slope error (mrad) 10.0
Direction (deg) 326.55
Glide slope (deg) 3.0
Consider pilot visibility from cockpit False
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 3/14
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 4/14
PV array vertices
id Latitude (deg)Longitude(deg)
GroundElevation (ft)
Height of panels aboveground (ft)
Totalelevation (ft)
1 38.6150765151 -75.837110281 28.97 6.0 34.97
2 38.6093255168 -75.8400285244 31.99 6.0 37.99
3 38.6094428887 -75.8339989185 23.88 6.0 29.88
4 38.6105327616 -75.8326900005 25.18 6.0 31.18
5 38.6121423899 -75.8328402042 24.88 6.0 30.88
6 38.6131651557 -75.8335053921 9.8 6.0 15.8
Flight Path Observation Points
Latitude (deg)Longitude(deg)
GroundElevation (ft)
Eye-level height aboveground (ft) Glare?
Threshold 38.621028229 -75.8410477638 29.21 50.0 No
1/4 mi 38.61801304 -75.8384952486 25.78 122.6 No
1/2 mi 38.6149978511 -75.8359427333 7.96 209.6 Yes
3/4 mi 38.6119826622 -75.8333902181 25.17 261.57 Yes
1 mi 38.6089674732 -75.8308377028 25.22 330.69 Yes
1 1/4 mi 38.6059522843 -75.8282851876 23.45 401.65 Yes
1 1/2 mi 38.6029370953 -75.8257326723 22.33 471.94 No
1 3/4 mi 38.5999219064 -75.823180157 20.17 543.29 No
2 mi 38.5969067175 -75.8206276418 0.52 632.11 No
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 5/14
Glare occurrence plotsAll times are in standard time. For Daylight Savings Time add one hour.
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 6/14
ThresholdNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 7/14
1/4 miNo glare
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 8/14
1/2 mi
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 9/14
3/4 mi
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 10/14
1 mi
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 11/14
1 1/4 mi
10/29/2015 Solar Glare Hazard Analysis Tool Report
https://share.sandia.gov/phlux/sghat/ 12/14
1 1/2 miNo glare