1MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

DEEPWATER DRILLING CHALLENGES

BENJAMIN CHOO

GM, DRILLING – MURPHY MALAYSIA

2MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Introduction

► In search for oil and gas, operators have moved further offshore and into deeper waters.

► Deepwater is generally described as water depths > 1000 ft or 300 m.

► Deepwater is the ‘final frontier’ of oil and gas exploration.

► Deepwater fields have large commercial upside, hence justifying the technical and financial risks.

3MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Offshore Sabah Water Depths

DeepwaterBlock K:1,320m

PetronasTowers: 452m

Kinabalu Field: 55m

4MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Deepwater Drilling Challenges

► Deepwater drilling provides the greatest challenges in scope and opportunity.

► Drilling costs typically make up 50% to 60% of deepwater development costs.

► Overcoming deepwater drilling challenges is key to unlocking deepwater oil and gas fields as they represent the majority of the development risks and costs.

► Key aspects of deepwater drilling are the deepwater drilling rig, support vessels, shore base, specialized well planning, well control equipment and emergency response.

5MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Deepwater Drilling Rig

► Deepwater drilling rigs are floating rigs.

► Semi-submersible or drill ship design.

► They are either moored or anchored at location or are dynamically positioned (DP).

► High load capacity, large storage capability and capable of handling high wellbore pressures (15,000 psi).

► High day rates (>$500k/day).

6MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Deepwater Drilling Support Vessels

► Large support vessels for deepwater drilling rigs function as: Towing and anchor

handlers for moored rigs. Supplies fuel, tools,

material and equipment to the drill rig.

Remotely Operated Underwater Vehicle (ROV) support.

7MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Subsea Well Control Equipment

► Deepwater drilling rigs utilize subsea blowout preventers (BOPs) located at the sea floor.

► Subsea BOPs are designed to operate in high external pressures caused by water depth and up to 15,000 psi internal pressure.

► Operated by electro-hydraulic multiplex (MUX) systems to achieve fast response.

8MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Deepwater Well Construction

► Deepwater wells construction is unique as it is based on a subsea wellhead system.

► Deepwater wells are challenging due to the narrow window between the formation pressure and the rock strength.

► Other challenges include gas hydrates and cold seabed temperature.

9MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Shorebase Support for Deepwater Drilling

► Good setup of a shore base helps to efficiently support deepwater drilling operations and prevent expensive shutdown of the drilling rig

► The shore base needs to have good infrastructure access, ample yard space and sufficient water depth at the quay for large deepwater drilling support vessels to berth.

10MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Deepwater Emergency Response

► Emergency well control and blowout response plan need to be developed.

► Emergency response based on ICS structure.

► Access to subsea well containment package. Subsea capping stack. Subsea dispersant

system and dispersants. Debris removal.

► Ability to drill relief well.

11MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Other Challenges

► Escalating costs, i.e. rigs, vessels, third party services, etc.

► Finding and retaining competent key personnel.► Increasingly stringent regulatory requirements for

deepwater drilling post Macondo.► Long lead times for tools and equipment.

12MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Murphy’s Deepwater Operations in Malaysia ► Drilled over 120 deepwater wells in

Malaysia since 2002.► Global top quartile deepwater

drilling performance.► Held world record for deepest water

depth for mooring a semi-submersible rig for Ocean Rover in 8,430 ft (2,570m) of water depth.

► Developed and producing from Kikeh since Aug 2007 which is the first deepwater field in Malaysia.

► Production from subsea tieback of Gumusut Kakap deepwater field.

► First oil achieved from Siakap North Petai deepwater project in Feb 2014.

Ocean Rover

SKD Menang, Kikeh DTU and Kikeh FPSO

13MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

Deepwater Drilling Performance – Murphy Malaysia vs Global

1.982.13

2.70

3.84

4.204.41 4.46

4.59

5.60 5.68

6.27

6.60

7.24

7.898.02

0

1

2

3

4

5

6

7

8

9

Murphy Malaysia v Global - Sub Sea DBML (1000ft) - 2011 to 2013

107 New Development Wells, Drilled between 2011 and 2013, using a Semi Submersible, or Drill Ship in water depths of between 503m and 1807m with 3 or 4 casing strings, using Rotary Top Drive, Mud Motor and Rotary Steerable drilling methods

Murphy

14MURPHY OIL CORPORATION www.murphyoilcorp.com NYSE: MUR

QUESTIONS?