Page 1: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

1

MID FLORIDA P&DC

PARS READINESS ASSESSMENT

Mail Processing

Mid-FL P&DC

Orlando P&DC

Page 2: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

2

STAFFING AND SCHEDULING Hours of operation

09:00 to 01:00 CIOSS runs after 01:00 CIOSS for T-1 DPS

2 clerks for each machine NS-day employees

relief positions Mail processing and CFS clerks Trained New Bids have been posted

30 CFS (CIOSS relief) 10 CIOSS (CFS relief)

MID FLORIDA P&DC

Page 3: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

3

MID FLORIDA P&DC

Complement Impacts 10 CIOSS operator Bid positions will be needed

for PARS mail processing operations. 2 per machine (4) per day 2 tours (Tour-2 & Tour-3) 2 relief bids (days off, call-ins, etc)

CIOSS machine staffingDaily CIOSS staffing per Tour

Tour-2 1 7289183 1 1 1 1 18:00 2 7289184 1 1 1 1 1

PL-425 3 7289185 1 1 1 1 14 7289186 1 1 1 1 15 7289187 1 1 1 1 15 TOTAL 3 2 4 4 4 4 4

Tour-3 1 7289188 1 1 1 1 116:30 2 7289189 1 1 1 1 1

PL-435 3 7289190 1 1 1 1 14 7289191 1 1 1 1 15 7289192 1 1 1 1 15 TOTAL 3 2 4 4 4 4 4

ALL CIOSS CREWS 10 6 4 8 8 8 8 8

Page 4: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

4

MID FLORIDA P&DC

EAS Staffing Requirements 1 Mail Processing supervisor on Tour-2 will

need to cover CFS Manager position on Saturday and Sunday for CIOSS operations

Sat Sun Mon Tue Wed Thu FriManager XX XX 8:00-16:30SDO #1 X X 12:30-21:00SDO #2 X X 21:00-05:30SDO #3 X X 12:30 12:30 16:30 21:00 21:00 Relief *

Page 5: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

5

TRAINING All CIOSS/PARS operations Mail Processing and CFS employees will be

trained on proper operation of CIOSS machine and PARS mail flows

Waste mail procedures Current CFS waste mail procedure with

CIOSS volume verification CIOSS Downflows SDO’s, MDO’s and In-Plant will receive

training and assist craft training.

MID FLORIDA P&DC

Page 6: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

6

MID FLORIDA P&DC

PARS Train the Trainers In-Plant Support will assist in training the

trainers on the proper procedures in PARS Mailflows and Processing.

Each tour will have a minimum of two SDOs and one “lead” clerk who are trained by IPS.

Tour trainers will train all Automation Mail Processing Clerks on each tour.

PARS FAT operations Sept 15 - Nov 7

Page 7: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

7

Job Safety Analysis (JSAs)

DBCS JSA used for unmodified machine areas

Feeding Sweeping Jam Removals

New JSA for Loading Labelstock on CIOSS New CIOSS module’s mailpath, Pinchpoints,

Belts & Jams

MID FLORIDA P&DC

Page 8: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

8

Page 9: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

9

RBCS / PARS IMAGE MANAGEMENT All MP and CFS Supervisors and MDO’s Review and refresher training in RBCS /

PARS Image management Similar flows and container identification as

currently in place for RBCS operations. Training Handouts for Image flows Attachment-C Image projections Contingency and SOP for PARS operations.

MID FLORIDA P&DC

273/274/292273/274/292

Page 10: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

10

SYSTEM FAILURE CONTIGENCY REC IMAGES

CFS SDO will contact REC SREO for Image Handling coordination

Maintenance will contact REC ET TELECOMMUNICATIONS

Maintenance follow escalation procedures when there is a system failure/disconnection.

Help Desk ET-11

MID FLORIDA P&DC

Page 11: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

11

CIOSS FAILURE CONTIGENCY CIOSS #1 FAILURE:

All Forwards to CIOSS #2. Continue through Tour-1 window*

RTS volumes moved to MP operations, to be automated on ISSOCR with IJP endorsements*

Notify REC for Image flow adjustment

MID FLORIDA P&DC

Page 12: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

12

PARS SYSTEM FAILURE CONTIGENCY CIOSS Unavailable, LONG TERM FAILURE:

Forwards to CFS for FFT keying RTS volumes can be automated on

ISSOCR with IJP endorsements No-Record volumes can be 5-D sorted on

other MPE

Hold mail for 1 day until system is running, report as Delayed

MID FLORIDA P&DC

Page 13: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

13

MAIL PREP

PLANT OPERATIONS

Plant will place trays of PARS mail, without disturbing integrity of separator cards, into rolling stock for subsequent processing.

Intercept mail from DBCS and ISS/OSS operations will be PARS placarded as appropriate and flow to CIOSS operation.

MID FLORIDA P&DC

Page 14: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

14

MAIL PREP

Delivery Unit Operations

Delivery Units will place PARS mail into trays by Endorsement Reason for return with separator card at back of tray.

PARS delivery coordinator has instructed each D.U. on proper mail prep and containerization SOP.

Plant MHs will place trays of PARS mail from D.U. into rolling stock, placard, weigh-in and send to CIOSS staging area.

MID FLORIDA P&DC

Page 15: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

15

SIGNAGE Rigid-backed hanging signs developed for

PARS machines #s and staging areas. Installation of signage to be completed during

FAT installation of CIOSS mod. Signs for:

Staging areas

(010/MP/CFS/CFPS) Machine identification

(MP/CFPS) Next handling placards Plastic container headers

MID FLORIDA P&DC

Page 16: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

16

MAIL FLOWS CIOSS OPERATIONS MPE INTERCEPT

DBCS (to Image) ISS, OSS, AFC (to Label)

CIOSS IMAGE LIFT MODE Oper 091 - RTS Oper 093 - Carrier Identified Forwards Oper 095/096 - rescan/other

CIOSS LABEL MODE Oper 092 - Intercepted FWDs Oper 098 - Carrier Identified Forwards Oper 099 - RTS

MID FLORIDA P&DC

Page 17: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

17

MAIL FLOW CHANGES DUE TO PARS OGP operations

COA’s to CFPS (CFS) CIOSS INTERCEPT

FROM DBCS to image lift FROM ISS/OSS to label mode

AADC/SCF/DPS operations CIOSS INTERCEPT

FROM DBCS to image lift FROM ISS/OSS to label mode

Future new flows from other operations DDC DBCS Interception

MID FLORIDA P&DC

Page 18: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

18

MAIL FLOW CHANGES DUE TO PARS CIOSS (Close-out) Downflows

CIOSS Final Labeled mail to OGP - 891/894 CIOSS rejects to CFS FFTs No-Records to Delivery Units (via CFPS Pouches) Separator cards to SCF operations (3-digit sort) Separator cards to DBCS/DPS or ORL Dispatch

to 5-digit office Distribution to Postmaster/Station Mgr Holdout

MID FLORIDA P&DC

193/194/266/291193/194/266/291

Page 19: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

19

COA MAIL FLOW To CFPS periodically throughout OGP

operating window COA’S captured on OSS/DBCS Outgoing

Primary operations Placed into U-cart with placard identifying

COA to CFS

MID FLORIDA P&DC

CFS PARSTO: COA SCANNING

OPERATION 085

BCS/DBCS

COA CAPTURE

FROM:

Page 20: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

20

3982 LABEL DISPATCH 3982 Stickers printed in CFS will be

dispatched in Teal CFS Pouches to Delivery Office, by SCF print groups.

Mail processing / expediter must check with CFS to insure SCF DOV clearance before truck departure.

CFS must adhere to predetermined DOV schedules for all offices.

Orlando offices dispatched 0125, 0215, 0330, 0435 and 0555

327 offices dispatched at 0500 (B/C) or @ 0700 (A) DPS HCRs

MID FLORIDA P&DC

Page 21: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

21

SEPARATOR CARDS SOP

Verify RTS volumes have a separator card at back of each tray to identify endorsement messaging

Replace damaged cards with plant contingency cards, notify PM/Station Mgr.

Collect cards after CIOSS run and stage for subsequent SCF processing.

Run cards on SCF sort plan to separate into 5-digit zone

Send to Delivery Units, running with DPS

MID FLORIDA P&DC

Page 22: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

22

PARS REJECTS Placards developed to flow mail to FFT

terminals in CFS Operations Separated by 5 digit zone

MID FLORIDA P&DC

PARSTO: CFS

PARS REJECTS

CIOSS REJECTS

5 DIGIT ZONE

FROM:

Page 23: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

23

MID FLORIDA P&DC

Local Waste mail Procedures An SOP has been developed for the flow of waste

mail from CIOSS operations for waste verification. NO MAIL will be “wasted” on the CIOSS. Must be verified before disposal

CFS PARSTO: WASTE MAIL

VERIFICATION

FROM:

CIOSS WASTE MAIL BIN

OPER-083

Current waste mail procedures in place will take verified waste mail to the proper disposal point.

Waste bin Errors will be photo copied

Page 24: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

24

Local Waste mail Procedures, cont. Verified waste bin error sample of the “Waste

Mail Error Tracking Sheet”

Error sheet requires a Date, copy of the Letter, the yellow Label, and Reason for waste error

Page 25: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

25

DAMAGED MAIL SOP

SOP has been developed for both RTS and Forwarded mail damaged mail volumes, coming from the CIOSS machine operations

MID FLORIDA P&DC

Page 26: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

26

DAMAGED MAIL SOP, cont. SOP’s goal is to return all possible mail to

automated mail stream.

RTS Damaged mail will be processed to retain reason for return and returned to automated mail stream if possible.

Non-Machinable sent to Hand Endorsement Unit and then to Manual RTS Cases

Forwarded mail will be processed and and placed back into the automated mail stream

Non-Machinable sent to CFS FFTs

MID FLORIDA P&DC

Page 27: 1 MID FLORIDA P&DC PARS READINESS ASSESSMENT Mail Processing Mid-FL P&DC Orlando P&DC

27