1 march 2001 cms hcal rbx production readiness review1 h c a l rbx safety issues rbx production...

14
1 March 2001 CMS HCAL RBX Production Readiness Review 1 H C A L RBX SAFETY ISSUES RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E. Elias HCAL Electronics Coordinator

Post on 19-Dec-2015

222 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 1

H

C

A

L

RBX SAFETY ISSUESRBX SAFETY ISSUESRBX SAFETY ISSUESRBX SAFETY ISSUES

RBX Production Readiness Review

Safety Issues and Mitigations

John E. Elias

HCAL Electronics Coordinator

Page 2: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 2

H

C

A

L

RBX HAZARDSRBX HAZARDSRBX HAZARDSRBX HAZARDS

Low Voltage and Fire• Each box requires

• 18 amps at 6.5 volts

• 26 amps at 4.5 volts

High Voltage• HV System is capable of 15 kV

Optical Data Link Lasers• VCSELs operate at 850 nm

• not visible light

• but focused well by the eye

Page 3: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 3

H

C

A

L

Low Voltage and Fire - 1Low Voltage and Fire - 1Low Voltage and Fire - 1Low Voltage and Fire - 1

Wires from LV supply to the RBX (20m)• Sized for ~1 Volt drop under normal conditions

• Can carry worst case fault current indefinitely without overheating

• Example: 20 amps at 1 volt drop nominal

• RBX ground fault at LV supply max. current gives power = VxI = 7.5Vx26A = 195 W which is only10 W per meter of wire

• Current limiting features built into the LV supply are adequate to mitigate the hazard

Page 4: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 4

H

C

A

L

Low Voltage and Fire - 2Low Voltage and Fire - 2Low Voltage and Fire - 2Low Voltage and Fire - 2

Readout Cards• Each card has access to the full power supply

current via the backplane in event of a fault

• Mitigations

• Current limiting feature in voltage regulators

• PolyFuse protection at point of entry

Polymeric positive temperature coefficient device for overcurrent and overtemperature protection

Resettable – power down

Page 5: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 5

H

C

A

L

Low Voltage and Fire - 3Low Voltage and Fire - 3Low Voltage and Fire - 3Low Voltage and Fire - 3

Sample Draw System Planned• Continuously monitors air sampling system

for fumes and aerosols, “sniffers”

• Break detector into many monitor zones

• Multi-level alarming

• Off normal – check into it

• Seriously off normal – do something now

• Corroboration by other system – fire alarm

• Provision for automatic shutdown of the low voltage system

• Individual RBX basis

• Entire half-barrel, end cap or HO basis

Page 6: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 6

H

C

A

L

High Voltage - 1High Voltage - 1High Voltage - 1High Voltage - 1

  Power

Supply

BV (5)

Return Current

Bleeder Box

Safety resistor

RBX HV Unit

HV Filter resistor

HPD

HV (5)

Bleeder resistor

Safety resistor

Z

Return Current

HV Back plane

Readout Module

HV Cable, 150 m long (5 HV & 5 BV conductors)

Page 7: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 7

H

C

A

L

High Voltage - 2High Voltage - 2High Voltage - 2High Voltage - 2

RBX HV Module

Page 8: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 8

H

C

A

L

High Voltage - 3High Voltage - 3High Voltage - 3High Voltage - 3

RBX High Voltage Distributor (Backplane)

Page 9: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 9

H

C

A

L

High Voltage - 4High Voltage - 4High Voltage - 4High Voltage - 4

BINDER WRAP & BRAIDED SHIELD

PROTECTIVE JACKET 0.05”/1.2 mm

O.D. = 0.484” / 12.3 mm

5 SINGLE WIRES 26 AWG,

8 / 12 kV (AC/DC) O.D.= 0.118”/ 3.0 mm

3 & 4 CONDUCTOR SUB-CABLES 26 AWG,

2 / 3 kV (AC/DC) SINGLE WIRE O.D.= 0.051”/ 1.3 mm

Page 10: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 10

H

C

A

L

High Voltage - 5High Voltage - 5High Voltage - 5High Voltage - 5

Energy Stored in the KERPEN HV Cable.5 HV wires, 150 m, 51 pf/m, total of 40 nf and 25 nf

of the power supply output capacitance.

0

1

2

3

4

5

6

7

8

9

10

0 2 4 6 8 10 12 14 16 18 20

Voltage (kV)

En

erg

y (J

)

Far End Energy(Power S. + Cable)

Near End Energy(Power Supply)

CERN safety limit for a capacitive discharge is 10 J (TIS, IS 28)

Page 11: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 11

H

C

A

L

High Voltage - 6High Voltage - 6High Voltage - 6High Voltage - 6

High Voltage Summary• Connectors have deeply recessed contacts

and are rated for 30 kV

• Safety resistor potted in series at RBX end of the cable limits maximum discharge current to 1 mamp per wire at 10 kV

• Stored energy in the cable (all five wires) is 6 Joules at the maximum supply voltage

• Maximum power supply current capability is 40 microamps

• A 250 meter length of cable has been held at 20 kV for one year (accelerated testing) with the leakage current unchanged at < 10 pamp

Page 12: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 12

H

C

A

L

Laser Diode - 1Laser Diode - 1Laser Diode - 1Laser Diode - 1

VCSELs drive the optical data links• Optical power is 1.8 mW typ.

• But the 850 nm light is not visible and this overrides the power consideration and makes it hazard class 3b “can cause eye injury in less than 0.25 sec”

3 mm long

1 mm dia.

• Glued to ~15 cm long connectorized fiber

Page 13: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 13

H

C

A

L

Laser Diode - 2Laser Diode - 2Laser Diode - 2Laser Diode - 2

Intrinsically eye-safe Strategy 1• Glue a permanent attenuator in fiber pigtail to make the

link intrinsically eye-safe at the front panel connector of the Readout Module

• Unkown – whether the light level at the receiver is adequate for good link performance

• Known – the TTC optical links are intrinsically eye-safe and perform very well

Intrinsically eye-safe Strategy 2• Use a spring loaded shutter on the front panel

connector of the Readout Module

• Unknown – whether shutters exist for ribbon connectors or a custom add-on is needed

• Known – it will be costly

Page 14: 1 March 2001 CMS HCAL RBX Production Readiness Review1 H C A L RBX SAFETY ISSUES RBX Production Readiness Review Safety Issues and Mitigations John E

1 March 2001 CMS HCAL RBX Production Readiness Review 14

H

C

A

L

Laser Diode - 3Laser Diode - 3Laser Diode - 3Laser Diode - 3

Eye-Safety on the workbench• The laser and fiber pigtail are removable from

the printed circuit board with two fasteners

Work to be Done• Detailed power density analysis using the

beam power profile versus angle

• Determination of the minimum safe distance between the fiber end and the eye surface

Commitment – intrinsically safe system• Administrative procedures may still be needed

but they are not the principal mitigation