1 in-line inspection results evaluation and data integration olympic pipe line company ferndale to...
TRANSCRIPT
1
In-line Inspection Results Evaluation and Data Integration
Olympic Pipe Line CompanyFerndale to Renton 16” Project
OPS IMP WorkshopHouston, TX August 2001
2
Outline
• Background
• Project OverviewData AnalysisExcavation and Repair CriteriaRepair Plan and Execution
• Summary of Repairs
• Testing of Cut Outs
• Project Issues
3
Background
• Ferndale to Renton 16” ILI Project - a key element of Olympic’s Integrity Management Program
• Consistent with BP’s Business Values and HSE Goals of: No Accidents, No Harm to People, No Damage to the
Environment
• Unique when compared with other ILI Projects because Ferndale to Allen Segment Out-of-Service Schedule Driven Project High Staffing Levels Heavy Public and Municipal Involvement Three Types of ILI Tool Runs
4
System Description
Castle Rock
Tacoma
Renton
Woodinville
Allen
Bayview
FerndaleCherry Point
Anacortes
Sea-Tac
Washington
Oregon
System Data
- Petroleum Products
- 400 miles long
- Four source refineries
- Eight terminal points
- 16” and 14” Main Line
- 20” Loop Line
5
Project Overview
ILI Tool Runs
Project Execution
Repair Plan
Data Analysis
Repair Criteria
Data Integration
6
Data Analysis
• Used Deformation and High Resolution MFL tools from Ferndale to Renton
• Ran an Ultrasonic tool from Ferndale to Allen
• Data Logs: – Graded and Correlated by ILI Tool Vendors
– Data Reviewed and Validated by:• BP Consultants
• Office of Pipeline Safety
• Consultants of Various Municipalities
– Applied Negotiated Evaluation Criteria
– Repair Plan / Documentation Prepared by Consultants
7
Excavation and Repair Criteria
Dents B31.4 OPL 16”
Top Half of Pipe 6% 0.625% (0.100”)
Bottom Half 6% 4%
With Metal Loss Any Any
Locate at Welds Any Any
Ferndale to Renton 16”
8
Repair Plan
• Scope Definition – BP / Consultants / OPS
• Engineering, Procurement & Construction – OPL / BP
• Dig Sheets – ILI Tool Vendor and Consultants
• Permitting – OPL / BP
• Dig Locates – Chain Crew Contractor
• Excavations – Mechanical Contractor
• Field Evaluation – Visual Inspection – BP / Consultants / ILI Tool Vendor
– NDE – NDE Contractor
• Repair Decision – BP / Consultants / OPS
• Documentation – Consultants
9
Execution
• Office Staff Permitting Specialists Engineering & Procurement – OPL / BP Government & Public Affairs – BP
• Field Staff (full-time) ROW Access –Right-of-Way Agents Locates – Chain Crews by Consultant Construction Management – Coordinators by BP / OPL Digs – Mechanical Contractor crews Feature Evaluation
Tool Vendor Analysts NDE Crews Consultant
Others OPS and Consultants Various Municipalities
10
Summary of Repairs
Repair Type Deformation MFL / Ultrasonic Other
Comp. Sleeve 21 4 0
Cutout 73 7 3
Re-coat 14 6 0
Total 108 17 3
11
Testing of Cutouts
• To establish future criteria a select number of deformation cutouts were cycle tested.– ¼” or smaller
• Cyclic testing of 16” cut-outs – 30 yrs of service simulated
– No failures
• Hydrostatic testing of cutouts to be completed
12
Project Issues
• Recognize project drivers early
• Allow adequate lead time to secure permits
• Appraise and evaluate each dig site for ROW access
• Identify and Prepare for External Influences – these will impact the:– Project Schedule– Staffing Levels – Cost