1 dr. r.p.singh cmd, powergrid. 2 rldc::brain generation ::heart sub-transmission:: sub arteries...
TRANSCRIPT
1
Dr. R.P.Singh
CMD, POWERGRID
22
RLDC::BrainGeneration ::Heart
Sub-Transmission:: Sub Arteries
Transmission:: Main Arteries
Distribution: Capillaries
Human Body vs. Power SystemHuman Body vs. Power System
Communication::Nervous System
USER
Voltage :: BP; Frequency:: Heart beat
3
1. Availability
3. Reliability
5. Affordability
2. Security
4. Quality
Objective of Power SystemObjective of Power System
44
Through :Through :
a) Generation Addition a) Generation Addition
b) Energy Conservationb) Energy Conservation
1. Availability of Power1. Availability of Power
55
GENERAGENERATIONTION
Generating CapacityGenerating Capacity
HydroHydro 32,335 MW (26%)32,335 MW (26%)
ThermalThermal 82,507 MW (66%)82,507 MW (66%)
CoalCoal 68,643 MW68,643 MW
GasGas 12,663 MW12,663 MW
NuclearNuclear 3,850 MW (3%)3,850 MW (3%)
RenewablesRenewables 6,158 MW (5%)6,158 MW (5%)
Installed capacity (Mar., 2006) Installed capacity (Mar., 2006)
8
Census ResultsCensus Results 1990-911990-91 2000-012000-01 2005-062005-06
Energy Shortage (%)Energy Shortage (%) 7.97.9 7.87.8 8.58.5
Peaking Shortage (%)Peaking Shortage (%) 16.716.7 12.312.3 12.512.5
Households Access to Electricity (%)Households Access to Electricity (%) 42.042.0 56.056.0 --
Rural Households Coverage (%)Rural Households Coverage (%) 31.031.0 43.843.8 --
Power Supply SituationPower Supply Situation
Source: Draft National Electricity Plan of Source: Draft National Electricity Plan of CEACEA
99
Peak Demand) Peak Demand) (MW)(MW)
Energy Energy Requirement Requirement
(BU)(BU)End of 10th Plan (2006 – 07)End of 10th Plan (2006 – 07) 1,15,7051,15,705 720720
End of 11th Plan (2011 – 12)End of 11th Plan (2011 – 12) 1,57,1071,57,107 975975
End of 12th Plan (2016 – 17)End of 12th Plan (2016 – 17) 2,12,7252,12,725 1,3201,320
End of 13th Plan (2021 – 22)End of 13th Plan (2021 – 22)
(Assuming 9% growth)(Assuming 9% growth)
2,88,9432,88,943 1,9001,900
Source: Draft National Electricity Source: Draft National Electricity Plan of CEAPlan of CEA
India’s Energy Requirement – Demand ForecastIndia’s Energy Requirement – Demand Forecast
1
10
YearYear HydroHydro ThermalThermal NuclearNuclear OthersOthers TotalTotalEnd of 9th PlanEnd of 9th Plan 26,26926,269 74,55074,550 2,7202,720 1,6281,628 105,167105,167End of 10th PlanEnd of 10th Plan 37,18437,184 101,035101,035 52405240 30003000 146,459146,459
End of 11th PlanEnd of 11th Plan 59,60459,604 134, 571134, 571 1018010180 76007600 211,955211,955
End of 12th PlanEnd of 12th Plan 333,000333,000
End of 13th PlanEnd of 13th Plan
(Assuming 9% (Assuming 9% growth)growth)
512,000512,000
GENERATION ADDITION ENVISAGED GENERATION ADDITION ENVISAGED figures in figures in MWMW
Source: Draft National Electricity Source: Draft National Electricity Plan of CEAPlan of CEA
1111
CoalCoal 246 billion tonnes (87% non coking 246 billion tonnes (87% non coking gr.)gr.)
HydroHydro 84,000 MW at 60% PLF, 84,000 MW at 60% PLF, Pumpstorage 96,000 MW & Micro Pumpstorage 96,000 MW & Micro 7,000 MW7,000 MW
Crude OilCrude Oil 728 million tonnes728 million tonnes
Natural gasNatural gas 660 billion Cu-m660 billion Cu-m
LignniteLignnite 5,060 million tonnes5,060 million tonnes
Renewables Renewables
- Biomass- Biomass
- Wind, solar etc.- Wind, solar etc.
6000 MWe6000 MWe
20,000 MWe20,000 MWe
UraniumUranium 78,000 tonnes78,000 tonnes
ThoriumThorium 5,18,000 tonnes – can sustain 5,18,000 tonnes – can sustain several hundred years requirementseveral hundred years requirementSource: Nuclear Power Corporation web Source: Nuclear Power Corporation web
sitesite
India’s available Energy ResourcesIndia’s available Energy Resources
1212
Advantages:-Advantages:-Availability of CoalAvailability of CoalShorter gestation period Shorter gestation period Low initial investment Low initial investment
Generation Addition - ThermalGeneration Addition - Thermal
Limitations:-Limitations:-
Long term sustenance questionable :Long term sustenance questionable :Limited resourceLimited resourceHighly pollutant Highly pollutant Disposal of ash : due to abrasive & high ash content Disposal of ash : due to abrasive & high ash content Dependence on imported fuel increasing Dependence on imported fuel increasing (about 100 MT by (about 100 MT by
2011-12)2011-12)Associated uncertainty in fuel cost- increases with Associated uncertainty in fuel cost- increases with
passage of time. passage of time.
Thus, coal has wider acceptability.Thus, coal has wider acceptability.
Thus, its prime position is threatened Thus, its prime position is threatened
1313
Advantages :-Advantages :-Renewable sourceRenewable sourceProgressively reducing TariffProgressively reducing TariffNon-pollutingNon-pollutingCarbon TradingCarbon TradingQuick start / stop for Grid controlQuick start / stop for Grid control
Generation Addition - HydroGeneration Addition - Hydro
Limitations :- Limitations :- Huge fund requirementHuge fund requirementLand Acquisition, Resettlement & Rehabilitation etc.Land Acquisition, Resettlement & Rehabilitation etc.Longer Gestation PeriodLonger Gestation PeriodGeological SurprisesGeological Surprises
Thus, Hydro development is a must. Thus, Hydro development is a must.
Thus, the growth is sluggish. Thus, the growth is sluggish.
1414
Advantages :-Advantages :-Low capital costLow capital costClean fuelClean fuelEasy to handleEasy to handleShorter gestation period Shorter gestation period Can be set up close to load center, thus enhanced Can be set up close to load center, thus enhanced
grid stabilitygrid stabilityQuick start & stopQuick start & stop
Generation Addition - GasGeneration Addition - Gas
Limitations :-Limitations :-Limited Gas Availability – present/ futureLimited Gas Availability – present/ futureUncertain fuel costUncertain fuel cost
Needed for quick developmentNeeded for quick development
The purpose of quick availability challengedThe purpose of quick availability challenged
1515
Advantages :-Advantages :-Technologically provenTechnologically provenEconomically ViableEconomically ViableCompact sourceCompact sourceEnvironment FriendlyEnvironment FriendlyCan be set up close to load center, thus enhanced grid Can be set up close to load center, thus enhanced grid
stabilitystabilityLong term SustenanceLong term Sustenance
Generation Addition - NuclearGeneration Addition - Nuclear
Limitations :-Limitations :-High Capital costHigh Capital costSafetySafetyFuel availabilityFuel availabilityWaste management Waste management Social stigmaSocial stigma
Thus desirable to quicken our efforts Thus desirable to quicken our efforts
Continues to be under threat Continues to be under threat
1616
3595.00 MW3595.00 MW 1705.00 MW1705.00 MW 749.53 MW 749.53 MW 66.23 MW66.23 MW 41.98 MW41.98 MW
2.64 MW2.64 MW
6160.38 MW6160.38 MW
45000 MW45000 MW15000MW15000MW19500 MW19500 MW -------- --------2700 MW2700 MW
20MW PER 20MW PER SQ.KMSQ.KM
82,200MW82,200MW
WIND POWERWIND POWERSMALL HYDRO( up to 25 SMALL HYDRO( up to 25
MW)MW)BIOMASS POWERBIOMASS POWERBiomass based Power Biomass based Power Biomass GasifiersBiomass GasifiersENERGY RECOVERY FROM ENERGY RECOVERY FROM
URBAN & INDUSTRIAL URBAN & INDUSTRIAL WASTEWASTE
SOLAR PHOTOVOLTAIC SOLAR PHOTOVOLTAIC POWERPOWER
TOTAL TOTAL
ACHIEVEMENTACHIEVEMENT(AS ON 31.03.2005)(AS ON 31.03.2005)
POTENTIALPOTENTIALRESOURCE/SYSTEMRESOURCE/SYSTEM
Energy Potential from Non-Conventional Energy SourcesEnergy Potential from Non-Conventional Energy Sources
Yet to gather momentum Yet to gather momentum
1717
Advantages Advantages Nil fuel costNil fuel costNon pollutingNon pollutingSuitable for Distributed GenerationSuitable for Distributed Generation
Generation Addition - WindGeneration Addition - Wind
Limitations Limitations High Capital costHigh Capital costLow availability - about 20%Low availability - about 20%Grid un-stability Grid un-stability
Temptation to buildTemptation to build
Threatened due to risks involved Threatened due to risks involved
1818
Advantages Advantages Abundant sourceAbundant sourceSuitable for Distributed GenerationSuitable for Distributed GenerationNon pollutingNon polluting
Generation Addition - SolarGeneration Addition - Solar
Limitations Limitations High Capital costHigh Capital costTechnologyTechnology
Desire to exploreDesire to explore
Technological limitationTechnological limitation
1919
Advantages :- Advantages :- Solid, liquid or gaseous waste can be used as a fuel for Solid, liquid or gaseous waste can be used as a fuel for
the production of electric power the production of electric power Potential to greatly reduce greenhouse gas emissionsPotential to greatly reduce greenhouse gas emissionsReduced dependence on oil as biofuels are the only Reduced dependence on oil as biofuels are the only
liquid transportation fuels availableliquid transportation fuels availableSupport rural economiesSupport rural economies
Generation Addition - BiomassGeneration Addition - Biomass
Limitations :- Limitations :- Land requirements are enormousLand requirements are enormousTransport issues Transport issues
Talk of the townTalk of the town
Inertia to take risk/ Limited investorsInertia to take risk/ Limited investors
2020
Investment in Power sector is too huge to be sustained Investment in Power sector is too huge to be sustained by private players. It is, therefore, imperative that by private players. It is, therefore, imperative that Government continues to play major role in generation Government continues to play major role in generation addition programme.addition programme.
Capacity addition programme to be expedited through Capacity addition programme to be expedited through Public, Private & Public/Private Joint investments. Public, Private & Public/Private Joint investments.
Generation Addition - SuggestionsGeneration Addition - Suggestions
Government has to continue as major playerGovernment has to continue as major player
2121
Coal to remain mainstay to meet base load in near future Coal to remain mainstay to meet base load in near future as required experience & technical know how is as required experience & technical know how is available, however,available, however,We may have to share base load with Nuclear/ Hydro.We may have to share base load with Nuclear/ Hydro.Imported fuel including coal can only supplement that Imported fuel including coal can only supplement that
too, to a limited extent. It can not be a reliable source.too, to a limited extent. It can not be a reliable source.
Generation Addition - SuggestionsGeneration Addition - Suggestions
Coal based plants to be mainstay Coal based plants to be mainstay
2222
To bridge the demand supply gaps expeditiously, following is a To bridge the demand supply gaps expeditiously, following is a must .must .
Massive standardisation of equipment, Sub-systems & Plant Massive standardisation of equipment, Sub-systems & Plant layouts layouts
POWERGRID’s efforts in standardisation has led to reduced POWERGRID’s efforts in standardisation has led to reduced project cycle time by about 2 years and project project cycle time by about 2 years and project implementation without disputesimplementation without disputes
Reserve 50% of orders on BHEL planwise. Balance 50% to be Reserve 50% of orders on BHEL planwise. Balance 50% to be tendered on ICB basis. tendered on ICB basis.
BHEL necessarily to bid. The lowest gets the order. Further, BHEL necessarily to bid. The lowest gets the order. Further, this will establish the benchmark price.this will establish the benchmark price.
Cost based determination of tariff to continue with regulation Cost based determination of tariff to continue with regulation till a sustainable demand and supply balance is achieved.till a sustainable demand and supply balance is achieved.
It is important to build expeditiously coal based projects rather It is important to build expeditiously coal based projects rather than enter into endless debate of unit size, technology etc. than enter into endless debate of unit size, technology etc. These are necessary but not a must.These are necessary but not a must.
Generation Addition - SuggestionsGeneration Addition - Suggestions
Time is the essenceTime is the essence
2323
Hydro Projects, both macro and micro, need to be developed Hydro Projects, both macro and micro, need to be developed expeditiously preferably on war footing basis mainly for energy expeditiously preferably on war footing basis mainly for energy security and to achieve required thermal/ hydro mix of 60:40security and to achieve required thermal/ hydro mix of 60:40For development of hydro projects, set up an Authority with For development of hydro projects, set up an Authority with
following objectives:-following objectives:-Single source to clear projectsSingle source to clear projectsIts decision to be challenged only in the Hon’ble Its decision to be challenged only in the Hon’ble
Supreme Court that too with time limitSupreme Court that too with time limitTo be fully answerable for development and running of To be fully answerable for development and running of
Hydro projectsHydro projectsPreferably, the Authority may be apolitical else cutting Preferably, the Authority may be apolitical else cutting
across political boundariesacross political boundariesRun of the River Hydro Schemes to be run as base load – Run of the River Hydro Schemes to be run as base load –
Needs special attention.Needs special attention.Hydro storage plant to be built to address peak shortages – Hydro storage plant to be built to address peak shortages –
Would be more reliable & cheaper than D.G. sets.Would be more reliable & cheaper than D.G. sets.
Generation Addition - SuggestionsGeneration Addition - Suggestions
Potential for Hydro Generation to be unleashedPotential for Hydro Generation to be unleashed
2424
Gas & oil based Power Plants to be set up Gas & oil based Power Plants to be set up With assured fuel linkages & with long term With assured fuel linkages & with long term
sustainable pricing mechanism sustainable pricing mechanism To be generally used for peaking purpose & as To be generally used for peaking purpose & as
base load for major load centresbase load for major load centres
Nuclear power is technically proven, however, fuel Nuclear power is technically proven, however, fuel availability needs to be addressed. Target should availability needs to be addressed. Target should be to establish about 15-20 % of installed be to establish about 15-20 % of installed capacity in a period of 20 years.capacity in a period of 20 years.
Generally located near load centres, of course Generally located near load centres, of course taking into account safety issues on account of taking into account safety issues on account of militancy, war etc. militancy, war etc.
Generation Addition - SuggestionsGeneration Addition - Suggestions
2525
For commercial sustenance, grid design, operability & For commercial sustenance, grid design, operability & safety, it is desirable to set up power plants with 85 to safety, it is desirable to set up power plants with 85 to 90% of generation capacity on long term contract basis. 90% of generation capacity on long term contract basis. The remaining 10 to 15 % to cater to market. This would The remaining 10 to 15 % to cater to market. This would enable :enable :Avoid gamingAvoid gamingAct as a catalyst to peg the prices for long term Act as a catalyst to peg the prices for long term
contractscontractsGenerate competitionGenerate competitionTo cater to seasonal & day to day variationsTo cater to seasonal & day to day variationsThis would also serve the same purpose as 15% This would also serve the same purpose as 15%
unallocated quota from central generating unitsunallocated quota from central generating unitsLoad centre generation plants to the extent of 50 % for Load centre generation plants to the extent of 50 % for
major & important cities - a must for quick start & stop to major & important cities - a must for quick start & stop to meet exigencies, grid stability etc.meet exigencies, grid stability etc.
With increased population of major cities it is even With increased population of major cities it is even important to set up power plants at several locations to important to set up power plants at several locations to cater to exigenciescater to exigencies
Generation Addition - SuggestionsGeneration Addition - Suggestions
2626
ENERGY ENERGY CONSERVATIONCONSERVATION
2828
Shall mitigate the gap between demand and Shall mitigate the gap between demand and supply as well as reduce environmental emissionssupply as well as reduce environmental emissions
Saving potential Saving potential additional 5000 MW at end of X planadditional 5000 MW at end of X planadditional 4000 MW at end of XI planadditional 4000 MW at end of XI planadditional 5500 MW at end of XII planadditional 5500 MW at end of XII plan
Regulatory & promotional rolesRegulatory & promotional rolesSystematic & urgent action plan to make it a Systematic & urgent action plan to make it a
national movementnational movement
b. Energy Conservationb. Energy Conservation
2929
Through :Through :
a) Transmission & Sub-transmission Networka) Transmission & Sub-transmission Network
b) Grid Managementb) Grid ManagementLoad Despatch & dedicated Communication Load Despatch & dedicated Communication
facilitiesfacilities
c) Distribution Networkc) Distribution Network
Security & ReliabilitySecurity & Reliability
3030
TRANSMISSITRANSMISSIONON&&
SUB-SUB-TRANSMISSITRANSMISSI
ONONNETWORKSNETWORKS
3232
Investment in the Sector Investment in the Sector
Electricity outlook 2003 published by International Electricity outlook 2003 published by International Energy Association (IEA) envisages an Energy Association (IEA) envisages an investment of about US $ 16 Trillion in Energy investment of about US $ 16 Trillion in Energy sector from 2003-30 or US $ 568 billion / year. sector from 2003-30 or US $ 568 billion / year. Out of thisOut of this
US $ 10 Trillion in Power Sector (60%), out of US $ 10 Trillion in Power Sector (60%), out of this, this,
US $ 5.5 Trillion in Transmission & US $ 5.5 Trillion in Transmission & Distribution (T&D) which is 55% of total Distribution (T&D) which is 55% of total investment in power sectorinvestment in power sector
TRANSMISSION & SUB-TRANSMISSION & SUB-TRANSMISSION NETWORKSTRANSMISSION NETWORKS
3333
Priority to generation Priority to generation 50:50 investment in generation and T&D 50:50 investment in generation and T&D
recommended, however, at present 72:28recommended, however, at present 72:28Popular belief that T&D will automatically develop Popular belief that T&D will automatically develop
if generation is establishedif generation is establishedAlmost similar thought process exists in Almost similar thought process exists in
developed and developing countriesdeveloped and developing countries
Present StatusPresent Status
34
Energy Resource MapEnergy Resource MapHydro potential in Hydro potential in
NER and upper NER and upper part of NRpart of NR
Coal reserves Coal reserves mainly in ERmainly in ER
For optimal For optimal utilisation of utilisation of resources – strong resources – strong National GridNational Grid
3535
Started Commercial operation in 1992-93 with the Started Commercial operation in 1992-93 with the mission of Establishment and operation of mission of Establishment and operation of Regional & National Power GridRegional & National Power Grid
Carries 45% of Country’s generated electricity Carries 45% of Country’s generated electricity Transmission Network - 56,317 Ckt. Kms. of EHV Transmission Network - 56,317 Ckt. Kms. of EHV Sub-Stations – 95Sub-Stations – 95Network availability - above 99.7%Network availability - above 99.7%
POWERGRID – The Central Transmission UtilityPOWERGRID – The Central Transmission Utility
3636
Right of Way, Conservation of Right of Way, Conservation of forests, flora & faunaforests, flora & fauna
Resettlement & RehabilitationResettlement & Rehabilitation Integrated Transmission System Integrated Transmission System
planning and selection of proper planning and selection of proper technology to mitigate above technology to mitigate above issuesissues
Challenges in setting up Transmission NetworksChallenges in setting up Transmission Networksand National Gridand National Grid
3737
Hybrid system comprising of HVDC & EHVAC Hybrid system comprising of HVDC & EHVAC Transmission System upto 800 kV with Transmission System upto 800 kV with multi Ckts. Or moremulti Ckts. Or more
Upgrading & Uprating of existing Upgrading & Uprating of existing transmission corridorstransmission corridors
Extra High Towers with multi circuits to Extra High Towers with multi circuits to avoid deforestation and protection of wild avoid deforestation and protection of wild lifelife
Compact Towers to reduce Right Of WayCompact Towers to reduce Right Of Way Use of fixed & variable Series Compensator Use of fixed & variable Series Compensator
(FACTS)(FACTS) High Temperature Conductors for increased High Temperature Conductors for increased
LoadingLoading
Addressing the Right of Way Issues etcAddressing the Right of Way Issues etc
38
Chicken Neck AreaChicken Neck Area
39
1
DOUBLE CIRCUIT TOWER
( 45 Mtr. High)
MULTI CIRCUIT TOWER
( 70 Mtr. High)
4
2
312
40
220 KV S/C Chukha-Birpara line upgraded 220 KV S/C Chukha-Birpara line upgraded with 400/220 KV multi-circuit line in with 400/220 KV multi-circuit line in
Jaldapara Sanctuary without felling of single Jaldapara Sanctuary without felling of single treetree
4141
9-25mtrs.
50mtrs
Forest & Wild Life ProtectionForest & Wild Life Protection
4242
140 meter tall tower140 meter tall tower
4343
800 kV Compact Tower800 kV Compact Tower800 kV Normal Tower800 kV Normal Tower
ROW – 85 mtrsROW – 85 mtrsROW – 64 mtrsROW – 64 mtrs
44
Proposed 400 Proposed 400 kV Compact kV Compact Single pole Single pole
tower tower at Delhi & at Delhi &
NoidaNoida
45
Benefits of Series CompensationBenefits of Series Compensation
Direct benefits Direct benefits Saving in Saving in
investment investment Increase in Increase in
capacity capacity
Indirect Indirect benefits benefits
No No additional additional corridorcorridor
46
Transmission Projects - Environmentally clean Transmission Projects - Environmentally clean and non Pollutingand non Polluting
Not covered under Environment (Protection) act, Not covered under Environment (Protection) act, 1986 except in two Districts i.e. Gurgaon and 1986 except in two Districts i.e. Gurgaon and AlwarAlwar
YetYet POWERGRID is the first PSU to develop POWERGRID is the first PSU to develop
Environmental and Social Policy & Procedures Environmental and Social Policy & Procedures (ESPP) in 1998 and upgraded it in line with (ESPP) in 1998 and upgraded it in line with changes and International best practices in 2005 changes and International best practices in 2005 to pre-empt all possible Environment & Social to pre-empt all possible Environment & Social issues through proper & timely managementissues through proper & timely management
Addressing resettlement & Addressing resettlement & Rehabilitation IssuesRehabilitation Issues
47
EnvironmentalEnvironmental Avoidance, minimisation & mitigation of (Forest, Avoidance, minimisation & mitigation of (Forest,
National parks & Sanctuaries, Monuments etc.)National parks & Sanctuaries, Monuments etc.) Conservation & protection of natural resourcesConservation & protection of natural resources Efficient & safe technology practicesEfficient & safe technology practices
PRINCIPLES OF ESPPPRINCIPLES OF ESPP
SocialSocial Avoidance, minimisation & mitigation in Avoidance, minimisation & mitigation in
habituated area, tribal area through land habituated area, tribal area through land management.management.
Public consultationPublic consultation Health & safetyHealth & safety Progressive entitlements to Project Affected Progressive entitlements to Project Affected
PersonPerson
4848
Total Forest involvement reduced from 6% to 2% Total Forest involvement reduced from 6% to 2% after implementation of ESPP since 1998after implementation of ESPP since 1998
Timely project implementation without any Timely project implementation without any rehabilitation and resettlement disputes.rehabilitation and resettlement disputes.
Land use pattern traversed in
27000 Ckt. Km (till 1998)
6%
64%
28%
2%Forest
Agricultural land
Revenue land
Others
Benefits of ESPPBenefits of ESPP
4949
PlanningPlanning It needs a paradigm shift from our existing It needs a paradigm shift from our existing
approach of approach of ““N-1” redundancy criteria for the system N-1” redundancy criteria for the system
to feed major cities, cluster of industries etc., to feed major cities, cluster of industries etc., to -to -““N-2” where same voltage level N-2” where same voltage level
exists/plannedexists/planned““N-1” criteria for each voltage level where N-1” criteria for each voltage level where
different voltage level exist / planneddifferent voltage level exist / planned For HVDC system, “N-1” criteria may continue For HVDC system, “N-1” criteria may continue
to follow with redundancy in parallel AC to follow with redundancy in parallel AC networknetwork
Integrated Transmission System Integrated Transmission System Development - SuggestionsDevelopment - Suggestions
5050
Laying of high capacity EHV multi-circuit Laying of high capacity EHV multi-circuit towers near major load centres, forest areas towers near major load centres, forest areas and near cluster of generating stations (e.g and near cluster of generating stations (e.g Singrauli, Korba, Arunachal Pradesh etc.) to Singrauli, Korba, Arunachal Pradesh etc.) to address sustainable Right-of-Way issue address sustainable Right-of-Way issue
It is desirable to undertake It is desirable to undertake upgradation/uprating of existing transmission upgradation/uprating of existing transmission lines through Hot line erection to utilise ROWlines through Hot line erection to utilise ROW
Establishment of GIS in cities, near major load Establishment of GIS in cities, near major load centres/cluster of generating stations and/or centres/cluster of generating stations and/or replace existing S/s with GIS to address replace existing S/s with GIS to address soaring prices of landsoaring prices of land
Integrated Transmission System Integrated Transmission System Development - SuggestionsDevelopment - Suggestions
5151
Operation & MaintenanceOperation & Maintenance
Patrolling of transmission line through Patrolling of transmission line through Helicopter and thermovision scaning Helicopter and thermovision scaning
Hot line washing through HelicopterHot line washing through Helicopter
Design review of transformer Design review of transformer
Integrated Transmission System Integrated Transmission System Development - SuggestionsDevelopment - Suggestions
5252
Development of National Grid on continual basis with sufficient Development of National Grid on continual basis with sufficient inter regional power transfer capacity is critical for long term inter regional power transfer capacity is critical for long term sustenance of the sectorsustenance of the sector
Inter regional (National Grid) power transfer capacity could be Inter regional (National Grid) power transfer capacity could be achieved on following criteria :achieved on following criteria :To cater to unallocated power (10-15% of Central Sector To cater to unallocated power (10-15% of Central Sector
Generation) and also 15% merchant share from Generation) and also 15% merchant share from IPPs/other generatorsIPPs/other generators
To cater to 10% of Captive Power Projects surpluses To cater to 10% of Captive Power Projects surpluses which is equivalent to 2% of installed capacitywhich is equivalent to 2% of installed capacity
5% extra capacity to take care of extreme seasonal 5% extra capacity to take care of extreme seasonal variation viz. very cold/hot, heavy rains or natural variation viz. very cold/hot, heavy rains or natural calamities like flood, earthquake etc.calamities like flood, earthquake etc.
Say Total 25 %Say Total 25 %
National Grid capacity envisaged as –National Grid capacity envisaged as –
By 11th Plan (2012) :By 11th Plan (2012) : 37,000 MW37,000 MW
By 12th Plan (2017) : By 12th Plan (2017) : 50,000 MW50,000 MW
National Grid – A Continuing ProcessNational Grid – A Continuing Process
53
National Grid
National Grid’s Growth matching with Generation & Demand
PresentInter-regional
Capacity- 9,500 MW
By 2012Inter-regional
Capacity>37,150MW
Generation Growth (GW)
Inter-regional capacity
Investment Requirement Investment Requirement
during 11during 11thth Plan : US$1000 Plan : US$1000
BillionBillion
Generation:US$50 BillionGeneration:US$50 Billion
Trans, Distr & RE : US$50 Trans, Distr & RE : US$50
BillionBillion
Inter-regional exchange
• Invest Defd : USD 6 Bn
1
54
SUB TRANSMISSIONSUB TRANSMISSION
1
55
Commensurate development of Sub-Commensurate development of Sub-transmission at 220kV/132kV/66/33kV transmission at 220kV/132kV/66/33kV networks is a must networks is a must
However, Sub-transmission sector is a However, Sub-transmission sector is a small entity –small entity –Not having enough fund as well as Not having enough fund as well as
trained manpowertrained manpowerLimited growth prospect and difficulty Limited growth prospect and difficulty
in commercial sustainabilityin commercial sustainabilityLeast priority on O&M of system due to Least priority on O&M of system due to
lack of fund etclack of fund etc
SUB TRANSMISSIONSUB TRANSMISSION
5656
Development of HVDC/ 800kV/400kV network with CTUDevelopment of HVDC/ 800kV/400kV network with CTU 1000 kV lines to supplement 765 kV network to 1000 kV lines to supplement 765 kV network to
economise on Right of Way for long term sustenanceeconomise on Right of Way for long term sustenance Uprate and upgrade existing transmission corridors to Uprate and upgrade existing transmission corridors to
enhance their capacity in a big wayenhance their capacity in a big way Regional level Sub-transmission entities may be Regional level Sub-transmission entities may be
formed clubbing all the respective State’s sub-formed clubbing all the respective State’s sub-transmission assets (220kV/132kV/110/66/33kV) transmission assets (220kV/132kV/110/66/33kV)
They would be responsible for network development They would be responsible for network development and its O&M and its O&M
Chairman of each Regional Sub-transmission entity Chairman of each Regional Sub-transmission entity shall be on rotation basis from the participating States shall be on rotation basis from the participating States
Central Govt. agencies to monitor the development Central Govt. agencies to monitor the development and performance of these entitiesand performance of these entities
Transmission & Sub-Transmission Transmission & Sub-Transmission Development - SuggestionsDevelopment - Suggestions
5757
Load Despatch & Load Despatch & Communication FacilitiesCommunication Facilities
Grid ManagementGrid Management
5858
Crucial for effective management of the Grid
RTU RTU RTU
SUB LDC SUB LDC SUB LDC
SLDC SLDC SLDC
ERLDC WRLDC NRLDC SRLDC NERLDC
NLDC
Hierarchical Diagram of Communication SystemHierarchical Diagram of Communication System
Grid ManagementGrid Management
5959
NLDC : Being set up by POWERGRIDNLDC : Being set up by POWERGRID
RLDCs already set up and being managed RLDCs already set up and being managed by POWERGRIDby POWERGRID
State Load Despatch Centre (SLDC) State Load Despatch Centre (SLDC) backed up by sub state Load Despatch backed up by sub state Load Despatch Centres already set upCentres already set up
Grid ManagementGrid Management
6060
Transparent communication exists between Transparent communication exists between RLDCs and SLDCs/ Sub SLDCsRLDCs and SLDCs/ Sub SLDCs
Similar transparency needed between Similar transparency needed between SLDC, distributors and consumersSLDC, distributors and consumers
Transparency and effective communication Transparency and effective communication leads to leads to Increased awarenessIncreased awarenessCommercialisationCommercialisationEconomyEconomy
Grid ManagementGrid Management
6161
Grid DisturbanceGrid DisturbanceNo major Grid Disturbance in last 3½ yearsNo major Grid Disturbance in last 3½ yearsNo. of Partial Grid disturbances reduced from No. of Partial Grid disturbances reduced from
sixties / seventies to single digitsixties / seventies to single digit Frequency Frequency
Frequency excursions mostly in the operating Frequency excursions mostly in the operating band as specified in GRID CODE band as specified in GRID CODE
VoltageVoltageImprovement in voltage profileImprovement in voltage profile
Inter-regional exchangesInter-regional exchangesIncreased from 8,145 MUs (2000-01) to 34,800 Increased from 8,145 MUs (2000-01) to 34,800
MUs(2005-06)MUs(2005-06)Higher peak / comsumer Demand met from Higher peak / comsumer Demand met from
existing generating capacityexisting generating capacity
Grid PerformanceGrid Performance
62
Grid Disturbances (Nos)Grid Disturbances (Nos)
63
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
1995-961996-971997-981998-991999-002000-012001-022002-032003-042004-052005-06
YEAR
% O
F T
IME
NorthernRegion Western Region Southern Region Eastern Region
POST ABT / ULDC
PRE ABT / ULDC
64
300
320
340
360
380
400
420
0:0
1
1:0
1
2:0
1
3:0
1
4:0
1
5:0
1
6:0
1
7:0
1
8:0
1
9:0
1
10:0
1
11:0
1
12:0
1
13:0
1
14:0
1
15:0
1
16:0
1
17:0
1
18:0
1
19:0
1
20:0
1
21:0
1
22:0
1
23:0
1
TIME IN HRS --->
VO
LTA
GE I
N K
V -
-->
2005
2002
2004
2003
COMPARISION OF BANGALORE VOLTAGE ON TYPICAL DAYS IN LAST FOUR YEARS
65Year --
MU
s -
-Inter Regional ExchangeInter Regional Exchange
6666
In FY 2005-06, energy exchange of 34800 MU worth In FY 2005-06, energy exchange of 34800 MU worth Rs. 7000 Crore took place, which broadly translates Rs. 7000 Crore took place, which broadly translates to deferred investment of Rs. 27000 Crore, to deferred investment of Rs. 27000 Crore, equivalent to setting up of 6800MW power equivalent to setting up of 6800MW power generation capacity. generation capacity.
Enhanced utilization of un-harnessed capacityEnhanced utilization of un-harnessed capacityRs. 13000 Crore worth of energy transacted Rs. 13000 Crore worth of energy transacted
through open market mechanism in 2005-06.through open market mechanism in 2005-06.Saving of Rs. 1750 Crore achieved by backing Saving of Rs. 1750 Crore achieved by backing
down expensive liquid fuel generationdown expensive liquid fuel generationSouthern Region started conserving water to Southern Region started conserving water to
meet peak demandmeet peak demandKadamparai & Srisailam Hydro Power Plants Kadamparai & Srisailam Hydro Power Plants
started operation in pumped storage mode to started operation in pumped storage mode to meet peak demand meet peak demand
Economy achieved through Inter Economy achieved through Inter Regional Exchange & effective Grid Regional Exchange & effective Grid
ManagementManagement
6767
Development of intelligent Grid with State-Development of intelligent Grid with State-of-the-Art features likeof-the-Art features likeWide Area ManagementWide Area ManagementAdoptive islandingAdoptive islandingSelf healing GridsSelf healing GridsProbabilistic Assessment, Dynamic Probabilistic Assessment, Dynamic
Stability Assessment and Voltage Stability Assessment and Voltage Stability Assessment (VSA) technique Stability Assessment (VSA) technique etc.etc.
SLDCs to be managed by POWERGRIDSLDCs to be managed by POWERGRID
Grid Management – Future Grid Management – Future PerspectivePerspective
6868
Inter-National Inter-National ExchangesExchanges
6969
Economy in generationEconomy in generationAdvantage from time diversityAdvantage from time diversityReduction in operation cost through Reduction in operation cost through
improved resource managementimproved resource management Reduction in investment for spinning Reduction in investment for spinning
reservesreserves Improved reliability, stability and efficiencyImproved reliability, stability and efficiency Reduced length of transmission lineReduced length of transmission line
Reduction in capital costReduction in capital costReduction in lossesReduction in losses
Facilitate clean development - reduced GHG Facilitate clean development - reduced GHG emissionemission
Better hydro-thermal mixBetter hydro-thermal mix
International Grid Interconnections - International Grid Interconnections - BenefitsBenefits
70
South Asian Countries Around IndiaSouth Asian Countries Around India
ChinaChinaChina
India
Nepal
Bangladesh
Bhutan
7171
Chukha HEP (4x84 MW), Chukha HEP (4x84 MW), Bhutan connected with Bhutan connected with Indian systemIndian system
Kurichu HEP (4x15 MW) Kurichu HEP (4x15 MW) of Bhutan connected to of Bhutan connected to Indian Grid Indian Grid 132kV Geylegphug -132kV Geylegphug -
SalakatiSalakati Tala HEP(1020MW) to be Tala HEP(1020MW) to be
interconnected with interconnected with Indian grid by 2006Indian grid by 2006
India – Bhutan Grid Interconnection India – Bhutan Grid Interconnection – An Experience– An Experience
7272
Bhutan Bhutan Economic benefit - about US$ 58 million Economic benefit - about US$ 58 million
annually through exchange of Chukha & annually through exchange of Chukha & Kurichu PowerKurichu Power
IndiaIndiaAccess to clean powerAccess to clean powerImproved grid controllability and Improved grid controllability and
stabilitystability
Advantages of India – Bhutan Grid Advantages of India – Bhutan Grid InterconnectionInterconnection
7373
Presently 16 nos. links at 132/33/11 kV voltage levelPresently 16 nos. links at 132/33/11 kV voltage level About 50 MW power being exchangedAbout 50 MW power being exchanged Net export to Nepal (about 10% of demand of Nepal Net export to Nepal (about 10% of demand of Nepal
met through imports from India)met through imports from India) Supply of 70MU/annum from Tanakpur (India) to Supply of 70MU/annum from Tanakpur (India) to
NepalNepal
India – Nepal Grid InterconnectionIndia – Nepal Grid Interconnection
7474
More hydro projects envisaged to come up in More hydro projects envisaged to come up in BhutanBhutanPunatsangechu - IPunatsangechu - I : 1000 MW: 1000 MWPunatsangechu - IIPunatsangechu - II : 1000 MW: 1000 MWMangdechuMangdechu : 600 MW: 600 MWSankoshSankosh : 4060 MW: 4060 MW
High Capacity HVDC Transmission System High Capacity HVDC Transmission System envisagedenvisaged
Interconnection – Future ScopeInterconnection – Future Scope
7575
India - NepalIndia - Nepal Indo-Nepal Power Exchange Committee Indo-Nepal Power Exchange Committee
recommended for construction additional 132kV lines recommended for construction additional 132kV lines Anandnagar (IndiaAnandnagar (India) - ) - Butwal (NepalButwal (Nepal) ) Motihari (IndiaMotihari (India)) - Birganj Nepal- Birganj Nepal Sitamarhi (India) – Dhalkebar (NepalSitamarhi (India) – Dhalkebar (Nepal))
Large potential projects being considered for Large potential projects being considered for development and export of power to Indiadevelopment and export of power to India West Seti HEPWest Seti HEP 750 MW750 MW Arun HEPArun HEP 685 MW685 MW Pancheshwar HEP Pancheshwar HEP 6,500 MW6,500 MW
India – Sri LankaIndia – Sri LankaProposal for interconnection of Sri Lanka with Proposal for interconnection of Sri Lanka with
Southern Regional Grid of India has been under Southern Regional Grid of India has been under discussiondiscussion
Interconnection – Future Scope .. Interconnection – Future Scope .. ContdContd
7676
India – MyanmarIndia – MyanmarTamanthi HEP in Myanmar –2300 MWTamanthi HEP in Myanmar –2300 MW
India BangladeshIndia BangladeshEast Zone of Bangladesh (generation dominated) East Zone of Bangladesh (generation dominated)
shares border with the NER of Indiashares border with the NER of IndiaBangladesh can supply power to NER IndiaBangladesh can supply power to NER India
West Zone of Bangladesh (load dominated) West Zone of Bangladesh (load dominated) shares border with the Eastern Region of Indiashares border with the Eastern Region of India India can supply power to Western BangladeshIndia can supply power to Western Bangladesh
India may consider expeditious solutions to expedite such exchanges
Interconnection – Future Scope .. Interconnection – Future Scope .. ContdContd
7777
DISTRIBUTDISTRIBUTION ION
NETWORKNETWORKSS
7878
Issues ailing the distribution system are:Issues ailing the distribution system are:Inadequate infrastructureInadequate infrastructureAge old distribution system, both in cities and Age old distribution system, both in cities and
villagesvillagesAlmost nonexistent system of maintenance of Almost nonexistent system of maintenance of
infrastructureinfrastructureNon recovery of full tariffNon recovery of full tariffReal time monitoring and communication with Real time monitoring and communication with
consumers missingconsumers missingLeast priority to Rural AreasLeast priority to Rural Areas
Even though 75% of the economy is rural Even though 75% of the economy is rural based – based –
so as the political massso as the political mass
Distribution & Rural ElectrificationDistribution & Rural Electrification
7979
To improve the same, GoI has taken following To improve the same, GoI has taken following steps : steps : For towns, Accelerated Power development & For towns, Accelerated Power development &
Reforms Programme (APDRP) Reforms Programme (APDRP) For rural areas, Rajiv Gandhi Grameen Vikas For rural areas, Rajiv Gandhi Grameen Vikas
Yojana (RGGVY)Yojana (RGGVY) APDRP: works worth Rs.17,612 Cr. undertakenAPDRP: works worth Rs.17,612 Cr. undertaken RGGVY: works worth Rs.16,000 Cr. undertakenRGGVY: works worth Rs.16,000 Cr. undertaken These schemes are being implemented by : These schemes are being implemented by :
State Electricity BoardsState Electricity BoardsState Electricity Boards and Central PSUsState Electricity Boards and Central PSUsCPSUs on behalf of State Electricity BoardsCPSUs on behalf of State Electricity Boards
Distribution & Rural ElectrificationDistribution & Rural Electrification
8080
To address all the above issues, following To address all the above issues, following are suggested :are suggested :
A. Segregate Rural from Urban A. Segregate Rural from Urban Distribution SystemDistribution System
B. Separation of Wire from SupplyB. Separation of Wire from Supply
Distribution & Rural ElectrificationDistribution & Rural Electrification
81
Central / State Transmission800/400 KV
Urban Electricity Infrastructure- Privatise/State Govt. 33/11 KV
State / Central Rural Electrification agency 33/11 KV
State Sub- Transmission / PrivateDistribution220/132 / 66 KV
A. Segregation of Urban and Rural A. Segregation of Urban and Rural Distribution SystemDistribution System
8282
A1. URBAN AREASA1. URBAN AREAS These areas become commercially These areas become commercially
attractive due to attractive due to Limited coverage area Limited coverage area Less capital requirementLess capital requirementManageable wire infrastructure both during Manageable wire infrastructure both during
installation and operation installation and operation Fair control on theft Fair control on theft
Almost ‘Nil’ subsidies involvedAlmost ‘Nil’ subsidies involved Much higher consumption (70 – 75%)Much higher consumption (70 – 75%) Therefore, private investment could be Therefore, private investment could be
successfully brought in urban areas.successfully brought in urban areas.
A. Segregation of Urban and Rural Distribution A. Segregation of Urban and Rural Distribution System - AdvantagesSystem - Advantages
8383
A2. RURAL AREASA2. RURAL AREAS Rural Area gets due priorityRural Area gets due priority Following issues associated with Rural Areas Following issues associated with Rural Areas
get focused attentionget focused attentionRemote locationRemote locationMeager consumption thus low returnsMeager consumption thus low returnsWide spread area resulting in high installation Wide spread area resulting in high installation
costcostHigh subsidiesHigh subsidies
Thus, Infrastructure Development in rural Thus, Infrastructure Development in rural areas may have to continue with the areas may have to continue with the Government.Government.
A. Segregation of Urban and Rural Distribution A. Segregation of Urban and Rural Distribution System - AdvantagesSystem - Advantages
8484
X. Wire Business - Setting up of X. Wire Business - Setting up of infrastructure up to Distribution Transformer infrastructure up to Distribution Transformer (33/11/0.4 kV) and its O&M May be (33/11/0.4 kV) and its O&M May be Privatised/continued with State GovernmentPrivatised/continued with State Government
Y. Supply Business – Supply to end Y. Supply Business – Supply to end consumers from Distribution Transformers consumers from Distribution Transformers (11/0.4 kV) including Metering, Billing and (11/0.4 kV) including Metering, Billing and CollectionCollectionIt is a fit case to be offered to Private It is a fit case to be offered to Private
entity(s)/ local bodies / Franchisees etc.entity(s)/ local bodies / Franchisees etc.
B. Separation of Wire Business & B. Separation of Wire Business & Supply - UrbanSupply - Urban
85
Distribution Transformer33/11/0.4 KV
Domestic
Commercial & Industry
Wire business ends here
Supply business begins here
Wire business begins here
Block level132/66 KV
Metering Collection
Billing
STATE / PRIVATE
PRIVATE
B. Separation of Wire Business & B. Separation of Wire Business & Supply - UrbanSupply - Urban
8686
WIRE BUSINESS: Two models are suggestedWIRE BUSINESS: Two models are suggestedModel I - Development of Rural electricity Model I - Development of Rural electricity
infrastructure and O&M by the Stateinfrastructure and O&M by the State90% grant to be provided for developing 90% grant to be provided for developing
infrastructureinfrastructureO&M cost to be borne by the StateO&M cost to be borne by the StateA central agency to oversee the A central agency to oversee the
establishment of wire from concept to establishment of wire from concept to commissioning, its O&M and future expansion.commissioning, its O&M and future expansion.
Model II – A Central Agency for establishment Model II – A Central Agency for establishment and O&M of Rural electricity infrastructureand O&M of Rural electricity infrastructure100% grant by GoI for establishing wire100% grant by GoI for establishing wireO&M of wires, about 2.5-3% of establishment O&M of wires, about 2.5-3% of establishment
cost, may be given as grant by GoIcost, may be given as grant by GoI
B. Separation of Wire Business & B. Separation of Wire Business & Supply - RuralSupply - Rural
8787
SUPPLY BUSINESS-SUPPLY BUSINESS-Setting up of supply network from Setting up of supply network from
Distribution Transformer (11/0.4kV) of a Distribution Transformer (11/0.4kV) of a village to end consumersvillage to end consumers
Installation of Meters, Billing and Installation of Meters, Billing and CollectionCollection
May be offered to Local bodies / May be offered to Local bodies / Panchayats / Franchaisess etc.Panchayats / Franchaisess etc.
BPL consumers to be clubbed into a BPL consumers to be clubbed into a number of clusters with single meter number of clusters with single meter feeding to each clusterfeeding to each cluster
B. Separation of Wire Business & B. Separation of Wire Business & Supply - RuralSupply - Rural
8888
Distribution Transformer33/11/0.4 KV
BPL Domestic
Agriculture
Industry
Single Phase
Wire business ends here
Supply businessbegins here
Three Phase
Wire businessbegins here
Block level132/66 KV
Metering Billing Collection
STATE / Central Agency
PRIVATE
B. Separation of Wire Business & B. Separation of Wire Business & Supply - UrbanSupply - Urban
8989
Single agency for development of wire network from Single agency for development of wire network from concept to commissioning, its operation & concept to commissioning, its operation & maintenance and future expansionmaintenance and future expansion
Reliability and availability of “wire system” assuredReliability and availability of “wire system” assured Open access at the lowest level feasibleOpen access at the lowest level feasible Economic viability of the wire agencyEconomic viability of the wire agency Supply agency not burdened with infrastructure Supply agency not burdened with infrastructure
development and its O&Mdevelopment and its O&M Supply agency can disconnect nonpaying customersSupply agency can disconnect nonpaying customers Self monitored theft control as Consumer becomes Self monitored theft control as Consumer becomes
custodian of the local facilitiescustodian of the local facilities Enable clear visibility of GoI grant through the Enable clear visibility of GoI grant through the
pricing of cost to serve various categories of pricing of cost to serve various categories of consumersconsumers
Advantages of Separation of Wire Advantages of Separation of Wire & Supply& Supply
9090
Money, being one of the important motivating Money, being one of the important motivating factor, Government & Private Companies factor, Government & Private Companies have been making earnest attempt to have been making earnest attempt to address the sameaddress the same
SuggestionSuggestionTo bring in efficiency in Power Sector, which is To bring in efficiency in Power Sector, which is
presently experiencing shortage of suitable presently experiencing shortage of suitable manpower, we may consider to form Joint manpower, we may consider to form Joint Venture companies with the employees Venture companies with the employees
To begin with, small projects may be taken upTo begin with, small projects may be taken upSuch a joint Venture company be managed by Such a joint Venture company be managed by
an Independent Board of Directors for an Independent Board of Directors for transparency.transparency.
Employees – A Stake HolderEmployees – A Stake Holder
9191
Increase in Generation – more reliance on Nuclear & Increase in Generation – more reliance on Nuclear & HydroHydro
Imported fuel to meet limited requirementsImported fuel to meet limited requirements Hydro Authority with full responsibilityHydro Authority with full responsibility Expeditious Harnessing of non-conventional energy Expeditious Harnessing of non-conventional energy
resources resources Development of strong National Grid to continueDevelopment of strong National Grid to continue Development of HVDC / 800kV / 400 kV network with Development of HVDC / 800kV / 400 kV network with
CTUCTU Formation of Regional level Sub-transmission entities Formation of Regional level Sub-transmission entities
clubbing all the respective State’s sub-transmission clubbing all the respective State’s sub-transmission assets (220kV/132kV/110/66/33kV)assets (220kV/132kV/110/66/33kV)
Isolation of Rural Electrification Infrastructure from Isolation of Rural Electrification Infrastructure from Urban areas and separation of wire business from Urban areas and separation of wire business from supply to shield the wire business from the risk of supply to shield the wire business from the risk of collection, making it a viable entitycollection, making it a viable entity
SummarisingSummarising
9292
Formation of a central agency for establishment / Formation of a central agency for establishment / oversee and O&M of Rural electricity oversee and O&M of Rural electricity infrastructureinfrastructure
Sustenance through people --Right people at the Sustenance through people --Right people at the right placeright place
Start dialogue with neighbouring countries for Start dialogue with neighbouring countries for power exchangepower exchange
Needs paradigm shift from present Trans. Needs paradigm shift from present Trans. planning approach especially for system feeding planning approach especially for system feeding to major cities, cluster of major industries to to major cities, cluster of major industries to ““N-2” where same voltage level exists/plannedN-2” where same voltage level exists/planned““N-1” criteria for each voltage level where N-1” criteria for each voltage level where
different voltage level exists/planneddifferent voltage level exists/planned
SummarisingSummarising
93
Thank Thank YouYou
9494
Security & ReliabilityThrough :Through :
a) a) Transmission & Sub-transmission Transmission & Sub-transmission NetworkNetwork
b) b) Grid ManagementGrid Management Load Despatch & dedicated Communication facilitiesLoad Despatch & dedicated Communication facilities
c) Distribution Networkc) Distribution Network
9595
TRANSMISSION & SUB-TRANSMISSION
NETWORKS
9696
A. Segregation of Urban & A. Segregation of Urban & Rural Distribution - Rural Distribution -
AdvantagesAdvantages
A2. RURAL AREAS Rural Area gets due priority Following issues associated with Rural Areas get
focused attention Remote location Meager consumption thus low returns Wide spread area resulting in high installation cost High subsidies
Thus, Infrastructure Development in rural areas may have to continue with the Government.
9797
98
A. Generation
B. Central / state
Transmission,
800/400/220/132/66 KV
Urban Electricity Infrastructure- Privatise/State Govt.
Rural Electricity Infrastructure-
Rs. 1.75
Rs. 1.75+0.26=Rs. 2.01
B = Rs. 0.26
9999
Village level11/0.4 KV
BPL Domestic
Agriculture
Commercial & Industry
Single Phase
Wire business ends here
Supply businessbegins here
Three Phase
Cost to Serve
C = Rs. 1.09
D = Rs. 0.53
A+B+C+D= A+B+C+D= Rs. 2.01+1.09+0.53=3.63Rs. 2.01+1.09+0.53=3.63
Actual Actual CostCost
100100
Village level11/0.4 KV
BPL Domestic
Agriculture
Commercial & Industry
Single Phase
Wire business ends here
Supply businessbegins here
Three Phase
Cost to Serve
C = Rs. 0.28
D = Rs. 0.25
A+B+C+D= A+B+C+D= Rs. 2.01+0.28+0.25=2.54Rs. 2.01+0.28+0.25=2.54
Through Through RGGVYRGGVY
101101
Rural Electricity Infrastructure
Su
pp
ly
arr
an
gem
en
t
Agriculture
Below Poverty Level (BPL)
Industrial+ CommercialPrice = Actual Cost, Say Rs. 3.63 per Unit
Price = Say Rs. 1.3 per Unit – does not include cost of rural infrastructure (Rs. 1.09 per unit) – a visible subsidy by GoI grant
• Single meter for cluster of houses with Rationing of supply (limited energy)
• Cross subsidy from Industrial consumers
DomesticPrice = Subsidsed Cost, Say Rs. 2.54 per Unit
102102
Security & ReliabilityThrough :Through :
a) a) Transmission & Sub-transmission Transmission & Sub-transmission NetworkNetwork
b) b) Grid ManagementGrid Management Load Despatch & dedicated Communication facilitiesLoad Despatch & dedicated Communication facilities
c) Distribution Networkc) Distribution Network
103103
TRANSMISSION & SUB-TRANSMISSION
NETWORKS
104104
A. Segregation of Urban & A. Segregation of Urban & Rural Distribution - Rural Distribution -
AdvantagesAdvantages
A2. RURAL AREAS Rural Area gets due priority Following issues associated with Rural Areas get
focused attention Remote location Meager consumption thus low returns Wide spread area resulting in high installation cost High subsidies
Thus, Infrastructure Development in rural areas may have to continue with the Government.
105105
India – Dominated by Coal
Bangladesh – Dominated by natural gas
Bhutan – High dependence on hydro
Nepal – High dependence on hydro
Pakistan – Largely petroleum and natural gas
Sri Lanka – Dependence on petroleum
106106
Evolving Open Electricity market
Countries with limited resources would be benefited, e.g. Sri Lanka
Thermal resources – cheaper to transport in electricity form; Hydro resources – can only be transported in electricity form
Huge hydro Resources of Bhutan can be effectively utilised
Export countries benefited economically, Import countries benefited by deferring investment towards setting up power plants
Opportunities for Opportunities for InterconnectionInterconnection
107107
Efficiency Gain A large portion of losses beyond DT is taken
care by supplier/trader Reduction in manpower of the “wire”
company as metering at 11 KV level only Metering, Billing and Collection by
supplier/trader A cluster of BPL consumers shall be provided
supply from a single meter