Example 1
FloSystem User Course
Well Model Building and Calibration
Naturally Flowing Oil Well
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
2/23
Overview
Data Entry
Well Deviation Data
Well Completion Data Reservoir Fluid Data
Reservoir Rock Data
Measured Data
Data Matching
Inflow / Outflow curves
Pressure-Depth profiles
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
3/23
Well Details Mid-perf depth - 8500 ft MD
4.5 OD, 4 ID, 11.6 ppf tubing to 3460 ft MD
3.5 OD, 3 ID, 9.2 ppf tubing to 5000 ft MD
2.875 OD, 2.441 ID, 6.4 ppf tubing to 7000 ft MD
7 OD, 6.3 ID, 23 ppf casing to 8500 ft MD
Oil 38 API Water Gravity: 1.1 Gas Gravity: 0.82 GOR : 400 scf/stb
Water-cut: 17% Res. Press.: 3800 psia
Pb : 1850 psia Res. Temp.: 187 oF
PI: 3.6 stb/day/psi Bo : 1.2 rb/stb
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
4/23
Dataprep General
Select File - NewSelect DataPrep - General
Report Labelling
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
5/23
Datum Double-click on Xmas Tree
Enter Datum details
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
6/23
Rotary Kelly Bushing
Wellhead Elevation
Mean Sea Level
Sea Bed
Datum
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
7/23
Deviation Data
Select Dataprep - Deviation Data - Well Data
Insert three lines, enter MD, TVD pairs - edit lastrow to 8500, 7500
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
8/23
Well Components
Select Dataprep - Equipment Data - Well Data
Enter data (node depth is BOTTOM of component)
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
9/23
Well Components
Select Config - PreferencesView Component name only
Try changing view from text to icons using View- Display as Text or Display as icons
In Config-Preferences, view MD, componentdata, etc.
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
10/23
Completion Editing Go Back to Deviation Data
Highlight 7000 - Insert Row Enter MD 6000 and TVD 5200
Note that a new node has been inserted in Tubing
3 Double-click on the lower section of Tubing 3
Re-label as Tubing 3b. Call the upper partTubing 3a.
Select Configure - Preferences and include all theoptions in the text display
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
11/23
PVT Data EntrySelect Dataprep - Reservoir Control - Fluid Parameters
EnterOil Gravity 38 APIGas Gravity 0.82Water Gravity 1.1GOR 400 scf/STBWater Cut 17 %
Select Check: Pressure 3800 psi, Temp 187 oF
Note Glasos correlation resultsPb =1715 psi, Bo = 1.20129
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
12/23
PVT Data Matching
Select Match, change temp to 187 oF, enter1850 psi beside temp and Calculate
Note Pb = 1715 psi. Press Best Fit
Note new Pb = 1850 PSI Select Form. Vol. Factor as Match Property
Change pressure to 3800 psi
Enter 1.20 as Bo beside 187o
F, 3800 psi field Calculate - Best Fitto tune Bo
Glasos correlation is now tuned for use
throughout the well model
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
13/23
IPR Data Entry
Select Manual Entry model and Edit Layer Enter layer pressure = 3800 psi, temp = 187
oF and PI = 3.6 STB/day / psi
Select Choose IPR and Vogel, then Plot Minimise graphing window
Select Norm. Pseudo Pressure and Plot
Select Straight Line and Plot Note that all three IPRs are plotted on the
same graph
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
14/23
IPR Data Entry(contd.)
Maximise graphing window
Double Click on Y axis, note that the Round option isselected
Note the other options
Click Edit , observe options of changing axes, titles,activate the coordinates and add a description of thegraph.
You can save the graph configuration as a template
(File - Save Template) and also print it. (File - Print) Close the graphing window and select Vogel model for
use in the rest of the exercise
Select OK until returned to the icon display
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
15/23
Measured Data
Use Notepad to view the file EX1.RVP (ASCII File)
This file contains one line - 5900 2200 - the firstnumber is observed surface flowrate in STB and thesecond is well flowing pressure at that rate - this is themeasured data to which we will match the model
Return to WellFlo
Select File - Load Measured Data -Flowrate versus Pressure
Load EX1.RVP - note one pair of values reported asread , it is possible to load multiple pairs.
Display on the Choose IPR plot.
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
16/23
Well Model Tuning
Select Analysis - Operating point Select Edit Rates Select Rate in lower left of screen / 1000 / 10,000 and
9 steps, select Fill and OK
Tatm. = 60oF Pwh = 200 psia (Top node Xmas Tree) Check Sensitivity Off (both)
Set Correlation to Duns and Ros (std)
Select Calculate and on completion of calculationResults and Plot .
Selecting Measured Data on then Plot to see theInflow /Outflowplot
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
17/23
Well Model Tuning
Note that the model represents a reasonablematch to observed data.
On Nodal Analysis screen select Sensitivities
Select Flow Correlation as sensitivity 1 and edit (1) Duns and Ros (std); (2) Beggs and Brill (std) (3) Hagedorn and Brown (std); (4) Orkizewski
Return to Nodal Analysis. Switch Sensitivity 1 on
and Calculate. On completion, select Results and Plot and All
Values for sensitivity 1 and Plot again
The four outflow curves are plotted with the IPR
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
18/23
Well Model Tuning
Zoom on the region of the plot where theintersections and observed data are.
Switching on Iterate To Exact Operating Pointwillgive a more accurate operating point. This option
should always be used. Note that Hagedorn & Brown (std) comes closest to
the observed data.
To get a better match, tune the correlation to themeasured data using the L- factor as a sensitivity.
L modifies the computed pressure gradients. Anacceptable range for L is 0.9 to 1.1.
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
19/23
Well Model Tuning
How should the productivity index be changed to
obtain a match on the inflow curve? What other reservoir parameter could be the cause
of the slight mismatch?
What else could be at fault?
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
20/23
Well Model Tuning Return to the Fluid Parameters section and re-tune
the formation volume factor to 1.3
Repeat the calculation with the same sensitivityvalues and note that the observed data now plotscloser to the Duns and Ros correlation outflow curve.
Return the Bo tuning to 1.2 and select the Hagedornand Brown (std) correlation.
Switch off sensitivity and calculate and plot theinflow/outflow curve.
Note the well flowrate reported on the graph Return to graphical editor.
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
21/23
Well Model Tuning Pressure vs Depth
Select File - Load Measured Data - Depth (MD) vs.Pressure (and Temp), & load EX1.DVP Select Analysis and Pressure Drop and enter the
operating rate you just obtained
start node is Xmas Tree at 200 psia solution node (end node) is Casing (mid-perfs)
Calculate and plot results as Pressure vs. MeasuredDepth, including measured data
Try Operating Pointcalculation mode with Iterate toexactswitched on. This will automatically provideyou with a pressure-depth plot at the appropriateoperating rate.
-
8/14/2019 1. Construccion de Un Modelo de Pozo - Corregido
22/23
Data MatchingPressure vs.Depth
Return to Pressure-Drop Calculation, switch onsensitivity 1 (flow correlations) and Calculate. Now plot pressure versus depth with All values set
in the sensitivity option.
The Hagedorn and Brown (std) correlation givesthe best match to the whole flowing gradientsurvey.
Switch off Sensitivity 1. Reverse the Pressure-Drop
calculation with start node as casing (whatpressure?), and solution node as Xmas tree. Compare the computed and measured data,
especially the THP.
-