1
Civil Systems PlanningBenefit/Cost Analysis
Paulina Jaramillo/Joe Marriott12-706/19-702 / 73-359Lecture 10
![Page 2: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/2.jpg)
12-706 and 73-359 2
Structuring Decisions
All about the objectives (what you want to achieve)
Decision context: setting for the decisionDecision: choice between options (there
is always an option, including status quo) Waiting for more information also an option
Uncertainty: as we’ve seen, always exists Outcomes: possible results of uncertain events Many uncertain events lead to complexity
![Page 3: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/3.jpg)
12-706 and 73-359 3
Structuring Decisions (2)
Can use: Fundamental objective hierarchy. Influence diagrams. Decision Trees
Risk Profiles
![Page 4: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/4.jpg)
12-706 and 73-359 4
Fundamental Objectives Hierarchy
Increase Lifetime Earnings
Increase Current Salary
Find New Job Get a Raise
Update Resume Network Do a Better Job
Marry Rich Go to School
Undergrad Grad School
![Page 5: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/5.jpg)
12-706 and 73-359 5
Influence Diagram/Decision Trees
Probably cause confusion. If one confuses you, do the other.
Important parts:
Decisions
Chance Events
Consequence/payoff
Calculation/constant
![Page 6: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/6.jpg)
12-706 and 73-359 6
Influence Diagram
Lifetime Earnings
Work
High Salary
Get a Raise
Find a Better Job
Marry Rich
Go to School
Undergrad
Grad School
![Page 7: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/7.jpg)
12-706 and 73-359 7
Other Notes
Chance node branches need to be mutually exclusive/exhaustive Only one can happen, all covered “One and only one can occur”
Timing of decisions along the way influences how trees are drawn (left to right)
As with NPV, sensitivity analysis, etc, should be able to do these by hand before resorting to software tools.
![Page 8: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/8.jpg)
12-706 and 73-359 8
Solving Decision Trees
We read/write them left to right, but “solve” them right to left.
Because we need to know expected values of options before choosing. Calculate values for chance nodes Picking best option at decision nodes
We typically make trees with “expected value” or NPV or profit as our consequence
Thus, as with BCA, we choose highest value.
![Page 9: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/9.jpg)
12-706 and 73-359 9
Texaco vs. Pennzoil
Counteroffer
$5 Billion
Texaco
Counteroffer
$3 Billion
Refuse
Settlement Amount ($ Billion)
Accept $2 Billion 2
Texaco Accept $5 Billion
5
Texaco Refuses
Counteroffer
Final Court
Decision
10.3
5
0
Final Court
Decision
10.3
5
0
Accept $3 Billion3
(0.17)
(0.5)
(0.33)
(0.2)
(0.5)
(0.3)
(0.2)
(0.5)
(0.3)
![Page 10: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/10.jpg)
12-706 and 73-359 10
To Solve the Tree
Solve from right to left:At chance node multiply monetary value
to probability and add them.At choice node choose highest value.
EMV for Simple Texaco vs. Pennzoil Tree:$4.63 Billion
![Page 11: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/11.jpg)
12-706 and 73-359 11
Risk Profiles
Risk profile shows a distribution of possible payoffs associated with particular strategies.
A strategy is what you plan to do going in to the decision. Holds your plans constant, allows chances to occur Only eliminate things YOU wouldn’t do, not things
“they” might not do.
Its not just finding the NPV of a branch.
![Page 12: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/12.jpg)
12-706 and 73-359 12
Risk Profiles (cont.)
Let’s think about the “subset” of the Texaco decision tree where we are only curious about the uncertainty/risk profile associated with various strategies to consider.
These represent the riskiness of each option There are only 3 “decision strategies” in the base
Texaco case:Accept the $2 billion offer (topmost branch of 1st dec.
node)Counteroffer $5 Billion, but plan to refuse counteroffer
(lower branch of 1st node, upper branch of second)Counteroffer $5B, but plan to accept counteroffer (lower
branch of both decision nodes)
![Page 13: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/13.jpg)
12-706 and 73-359 13
Texaco vs. Penzoil, Again
Risk Profile for "Accept to $2 Billion"
0%
100%
0% 0% 0% 0% 0% 0% 0% 0% 0%0%
20%
40%
60%
80%
100%
120%
0 1 2 3 4 5 6 7 8 9 10 11
x ($ Billion)
Chance that Settlement Equals X
Risk profile for “Accept $2 Billion” is obvious - get $2B with 100% chance.
![Page 14: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/14.jpg)
12-706 and 73-359 14
Risk Profile Texaco Counteroffer, accept $3 billion Below is just the part of original tree to consider when
calculating the risk profile:
Counteroffer
$5 Billion
Texaco
Counteroffer
$3 Billion
Texaco Accept $5 Billion
5
Texaco Refuses
Counteroffer
Final Court
Decision
10.3
5
0
Accept $3 Billion3
(0.17)
(0.5)
(0.33)
(0.2)
(0.5)
(0.3)
![Page 15: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/15.jpg)
12-706 and 73-359 15
Texaco vs. Pennzoil, continued
Risk Profile for "Counteroffer $5 Billion, Accept Texaco's $3 Billion Counteroffer"
15%
0%
33%
0%
42%
0% 0% 0% 0%
10%
0%0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
0 1 2 3 4 5 6 7 8 9 10 11
x ($ Billion)
Chance that Settlement Equals x
Risk Profile for "Counteroffer $5 Billion, Reject Texaco's $3 Billion Counteroffer"
25%
0% 0% 0% 0%
59%
0% 0% 0% 0%
17%
0%0%
10%
20%
30%
40%
50%
60%
70%
0 1 2 3 4 5 6 7 8 9 10 11
x ($ Billion)
Chance that Settlement Equals x
![Page 16: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/16.jpg)
12-706 and 73-359 16
Cumulative Risk Profiles
Graphs of cumulative distributions Percent chance that “payoff is less than
x”Cumulative Risk Profile for 3 Options in Texaco Case
0%
20%
40%
60%
80%
100%
120%
0 2 4 6 8 10 12
x ($billion)
Chance that payoff is less or equal to
x
Counteroffer $5 Billion, Accept Texaco's$3 Billion CounterofferAccept $2 Billion
Counteroffer $5 Billion, Refuse Texaco's$3 Billion Counteroffeer
![Page 17: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/17.jpg)
12-706 and 73-359 17
Dominance
To pick between strategies, it is useful to have rules by which to eliminate options
Let’s construct an example - assume minimum “court award” expected is $2.5B (instead of $0). Now there are no “zero endpoints” in the decision tree.
![Page 18: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/18.jpg)
12-706 and 73-359 18
Dominance Example
CRP below for 2 strategies shows “Accept $2 Billion” is dominated by the other.
0%
20%
40%
60%
80%
100%
120%
0 2 4 6 8 10 12
x ($billion)
Chance that payoff is less or equal to x
![Page 19: 1 Civil Systems Planning Benefit/Cost Analysis Paulina Jaramillo/Joe Marriott 12-706/19-702 / 73-359 Lecture 10](https://reader036.vdocuments.site/reader036/viewer/2022083005/56649f165503460f94c2c066/html5/thumbnails/19.jpg)
12-706 and 73-359 19
Next Class
Multi-Attribute Decision Making.Multi-Objective Programming.Value of Information.
Homework Due.