1 building const 1

Upload: marvelous-delgado

Post on 07-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 1 Building Const 1

    1/38

    BUILDING

    CONSTRUCTIONl

    PREPARATION FOR CONSTRUCTION

  • 8/3/2019 1 Building Const 1

    2/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    1. PREPARATION FOR CONSTRUCTION

    1.1 STAKING-OUT THE BUILDING

    1. Measure the required setback from the front cornermonuments and drive two stakes and stretch a linebetween them to represent the front building line.

    2. Measure the required side setback from one of theside lot lines along the line established in (1) anddrive a stake A which will represent the first corner of

    the building. Then from Stake A, measure the widthof the building and mark with a stake B to obtain theother front corner.

    3. Estimate right angles from stakes A and B andmeasure the length of the building. In those twopoints, drive two temporary stakes C and D whichwill mark the rear corners of the building. C-D should

    be equal to A-B.

    4. Draw lines along the diagonals A-D and B-C andensure that these are equal.

    5. Transfer the building lines to batter boards.

    1.0

    1.1

  • 8/3/2019 1 Building Const 1

    3/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.2 LAYING THE BATTERBOARDS

    Batter boards are horizontal boards used to establish the height of the finish

    foundation and to support the guidelines for the excavation of footing

    trenches.

    They should be carefully leveled because it is important that they are all at thesame elevation.

    Leveling is done with a line level or carpenters level, or with a transit.

    The height of the batter boards may be level with or a little higher that the topof the finished foundation.

    1.0

    1.2

  • 8/3/2019 1 Building Const 1

    4/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.3 FORMWORK AND SHORING

    FORMS FOR CONCRETE

    CONSTRUCTION. Materials used for

    form construction are (1) Lumber, (2)Plywood, (3) Steel.

    LUMBER FORMS. Lumber used in formconstruction should only be partially

    seasoned.

    PLYWOOD FORMS. These are usedwhere a smooth surface is required. The

    plywood should be waterproof, Grade A

    and at least thick.

    STEEL FORMS. Steel forms may be in

    the form of pans for concrete joist

    construction or steel decking orcorrugated steel for concrete slabs andslab-and-joist construction.

    1.0

    1.3

  • 8/3/2019 1 Building Const 1

    5/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    Knee

    BraceLedger

    BlockingKicker

    Sills

    PLYWOOD FORMS

    WOOD SHORING METAL SHORING

    Braced T-and L-heads

    Single PostWood Shore

    Metal orWood Joists

    Stringers

    Jack

    Adjustable

    Metal Shores

    Bracing

    1.0

    1.3

    1. Lumber Forms and Shoring

  • 8/3/2019 1 Building Const 1

    6/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.0

    1.3

    COLUMN FORMS

    WALL FORMS

    WOOD FORMWORKSReusable forms may have asquare or rectangular crosssection

    YOKES are clamping devicesfor keeping column forms andtops of wall forms fromspreading under the fluidpressure of newly placedconcrete

    SPREADERS usually of wood,space and keep the wall orforms apart

    FORM TIES

    PLYWOOD SHEATHING

    WOOD STUDS

    HORIZONTAL WALERS

    SILL PLATE

    BRACING

  • 8/3/2019 1 Building Const 1

    7/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.0

    1.3FORM TIES

    SNAP TIES have notches or crimps thatallow their ends to be snapped off below theconcrete surface after stripping off the forms

    small, truncated cones of wood, steel orplastic attached to form ties to space andspread wall forms, leave a neatly finisheddepression in the concrete surface to befilled or left exposed

    SHE BOLTS consist of water rods that areinserted through the form and threaded ontothe ends of an inner rod. After striping thewater rods are removed for reuse while theinner rod remains in the concrete

    a variety of wedges and slotted devicestighten the formwork and transfer the forcein a form tie to the walers

  • 8/3/2019 1 Building Const 1

    8/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    SCAFFOLDING COMPONENTS

    Ledgers

    Standards

    Fixed Braces

    AdjustableBraces

    1.0

    1.3

    2. Steel Forms and Shoring

  • 8/3/2019 1 Building Const 1

    9/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site Investigation

    Excavation & Earthworking

    Slope Protection and

    Retaining Structures

    Rapidshor Heads

    Base & Tilt Base

    Adjustable Jacks

    SCAFFOLDING COMPONENTS

    1.0

    1.3

  • 8/3/2019 1 Building Const 1

    10/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1. Ensure the ground and sleepers areadequately prepared, and the base, jacksand standards are in correct positions.

    2. Assemble tower of 4 standardsand ledgers. Fix braces to stabilize.

    3. Loosely fit the remainingcomponents until majority of first

    level complete. Check standards forverticality and tighten ledgers.

    4. Position scaffold boards and ladders. 5. Additional ledgers and bracescan now be added, with additional

    braces.

    6. Once all levels are complete,jacks and heads can now be

    positioned.

    7. Jack head levels finalized and any jackbracing required is now fitted.

    8. Primary beams can bepositioned, clamped and levels

    checked.

    9. Secondary beams can bepositioned and clamped to primarybeams, plywood decking to follow.

    SCAFFOLDING ASSEMBLY INSTRUCTIONS1.0

    1.3

  • 8/3/2019 1 Building Const 1

    11/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.4 CONSTRUCTION TOOLS & EQUIPMENT

    Tools and equipment employed in construction are grouped into four:

    1. Hand Toolsare the tools that use power delivered by man only.

    2. Power Toolsare those that employ power supplied by forces otherthan that coming from humans.

    3. Equipmentis a term that refers to large, complex tools and

    machines that is designed to do a particular job.

    4. Heavy Equipmentis equipment which is very large and verypowerful.

    1.0

    1.4

  • 8/3/2019 1 Building Const 1

    12/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1. Hand Tools

    A pry bar is usedto force open

    boards used informing concrete.

    Measurement andlayout tools are the

    following:

    a. Folding rule andtape measure are

    the most common

    tools for measuringboards, pipe, wire,

    etc.

    b. Digital rule isused to measure

    relatively longdistances such as

    those in highway

    construction.

    c. Framing square

    is a layout tool thatis used to

    measure 90-degree angles at

    the corners offramework and

    joints. They can

    also be employedto determine

    cutting angles ondimension lumber.

    d. Level is a long,

    straight tool thatcontains one or

    more vials of liquid

    and used todetermine if the

    horizontal orvertical is exact.

    e. Chalk line or

    chalk box is used

    for marking lines.

    1.0

    1.4

  • 8/3/2019 1 Building Const 1

    13/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Types of hammers are the

    following:

    a. Claw hammer is anordinary hammer used to

    drive or remove nails.

    b. Sledgehammer is a heavy

    hammer used to drive stakesinto the ground and to break

    up concrete and stone.

    Types of screwdrivers are:

    a. Standard screwdriver has aflat tip and is designed to fit a

    standard slotted screw.

    b. Phillips screwdriver has an

    X-shaped tip and is used to

    turn Phillips-head screws only.

    c. Spiral ratchet screwdriver isthat which relies on a pushing

    force rather than a twisting

    force.

    1.0

    1.4

    P f

  • 8/3/2019 1 Building Const 1

    14/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Types of handsaws are the

    following:

    a. Ripsaw has chisel-liketeeth designed for ripping or

    cutting with the grain ofwood.

    b. Crosscut saw is used to

    cut across the grain of wood.

    c. Backsaw is a special

    type of handsaw that has avery thin blade and makes

    very straight cuts such asthose on trims and

    mouldings.

    d. Hacksaw is used to cutmetals.

    1.0

    1.4

    P ti f

  • 8/3/2019 1 Building Const 1

    15/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Types of Chisels:

    a. Wood chisel is used to trim

    wood and clear away excessmaterial from wood joints.

    b. Cold chisel is used to trim

    metals.

    Types of specialized hand tools

    are the following:

    a. Nail set is used to drive finishingnails below the surface of a

    wooden trim or molding.

    b. Pipe wrench is

    used to turn roundobjects like pipes.

    c. Brick trowel is

    used to place andtrim mortar between

    bricks or concreteblocks.

    d. Bull float is usedto smoothen out the

    surface of wet

    concrete.

    e. Blind riveter isused to fasten

    pieces of sheet

    metal together.

    1.0

    1.4

    Preparation for

  • 8/3/2019 1 Building Const 1

    16/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Power drill.

    Power screwdriver.

    Radial arm saw.

    Table saw.

    Portable circular

    saw.

    Power miter saw.

    Saber saw.

    2. Power Tools

    Power drill is used todrill holes in wood,

    metal and concrete.

    Power screwdriver or

    screwgun is used toinstall and remove

    screws.

    Types of power sawsare the following:

    a. Radial arm saw isused for crosscutting

    wood and consists ofa motor-driven saw

    blade that is hung onan arm over a table.

    b. Table saw is used for

    cutting large sheets ofwood and wood

    composites and consistsof a blade mounted on an

    electric motor beneath atable-like surface.

    c. Portable circular saw isused for cutting materials

    that are difficult to cutwith stationary tools.

    d. Power miter saw is a

    circular saw mountedover a small table used

    to cut various angles in

    wood.

    e. Saber saw is used tocut curves or holes in

    floors and roofs for pipesand has a small knife-

    shaped blade that moves

    up and down.

    1.0

    1.4

    Preparation for

  • 8/3/2019 1 Building Const 1

    17/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Pneumatic hammer.

    Rotary hammer.

    Pneumatic nailer

    Powder-actuatedstud driver.

    Stapler.

    Type of power

    hammers are:

    a. Pneumatichammer or

    jackhammer isused to break

    up concrete or

    asphalt paving.

    Type of power

    nailers and staplersare the following:

    a. Nailers or nail

    guns fastenmaterials together by

    shooting nails into

    the building material.

    b. Powder-actuatedstud driver is a kind

    of nailer that ispowered by

    gunpowder and isused to drive long

    pins into wood, steel

    or concrete.

    c. Staplers are likenailers but are

    loaded with u-shaped staples

    instead of nails for

    fastening.

    b. Rotary hammer is like an electric

    drill that operates with both rotatingand reciprocating actions and is used

    to drill holes in concrete.

    1.0

    1.4

    Preparation for

  • 8/3/2019 1 Building Const 1

    18/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Conveyors are used for transportingmaterials unto large roofs.

    Construction

    laser.

    Transit.

    Surveyors level.

    3. Equipment

    Conveyor is an equipment whichmoves materials other than fluids.

    Types of surveying

    equipment:

    a. Transit is anequipment used by

    surveyors tomeasure horizontal

    and vertical angles to

    obtain land elevation.

    b. Surveyors level isthat which is used to

    determine anunidentified elevation

    from a known one.

    c. Construction laser

    flashes a narrow,accurate beam of

    light to make abaseline for

    additionalmeasurements and

    is used as a level or

    as an alignment tool.

    1.0

    1.4

    Preparation for

  • 8/3/2019 1 Building Const 1

    19/38

    Preparation for

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Concrete pump.

    Water pump.

    Arc welding machine.

    Weld made by a laser-powered welder.

    Types of

    pumps are:

    a. Water pumpis used to

    pump waterout of holes in

    the ground so

    thatconstruction

    work cancommence.

    Types of weldingmachines are

    the following:

    a. Arc weldingmachine is usedto weld materials

    by meltingportions of the

    metal.

    b. Concrete pump is used to move

    concrete from the concrete mixer tothe concrete form.

    b. Laser-powered welder is used to

    weld material by employing a laser toheat the metal.

    1.0

    1.4

    Preparation for

    1 0

  • 8/3/2019 1 Building Const 1

    20/38

    p

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Bulldozer.

    640-foot crane.

    4. Heavy Equipment

    Bulldozer is a tractor with a pushingblade which moves earth and clears

    land of bushes and trees.

    a. Crawler crane is a crane mounted

    on metal treads so that it can moveover rough terrain.

    b. Truck crane is mounted on a truck

    frame so that it can be driven in the

    site.

    c. Tower crane or climbing crane isused in the construction of tall building

    because it has a built-in jack thatraises the crane from floor to floor as

    the building is constructed.

    Cranes are

    machines thatlift large and

    heavy

    materials. Thetypes ofcranes are:

    1.0

    1.4

    Preparation for

    1 0

  • 8/3/2019 1 Building Const 1

    21/38

    p

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Excavator is a machine used for

    digging or scooping earth from aplace and depositing it in another.

    Types of excavators are:

    a. Backhoe is used for general

    digging which is usually mounted

    on either a crawler or truck frame.

    b. Trencher is a special kind which

    digs trenches or long, narrowditches for pipelines or cables.

    c. Front-end loader is a large

    shoveling machine that can scoopor deposit a large amount of

    material.

    Trencher-excavator.

    Backhoe.

    Front-end loader.

    1.0

    1.4

    Preparation for

    1 0

  • 8/3/2019 1 Building Const 1

    22/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    Highway construction equipment

    are:

    a. Scraper is a machine that loads,hauls and dumps soil over medium

    to long distances.

    b. Grader is an earthworking

    machine that grades or levels theground.

    c. Compactor or roller is a machine

    that compacts soil to prepare forroad paving.

    d. Paver is a machine that places,

    spreads and finishes concrete or

    asphalt paving material

    Scraper.

    Grader.

    1.0

    1.4

    Preparation for

    1 0

  • 8/3/2019 1 Building Const 1

    23/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.5 FOUNDATION BED

    The word foundation is applied to:

    1. Construction below grade, such as footing courses, basementwalls, etc., forming the lower section of a structure;

    2. The natural material, the particular part of the earths surface on

    which the construction rests;

    3. Special construction such as piling or piers used to transmit the loadsof the building to firm substrata.

    Foundation bed is the natural material on which the construction rests.Walls, piers and columns below grade are called, in general, foundationwalls, piers and columns to distinguish them from similar construction

    above grade. The lower portions of walls, piers or columns which arespread to provide a safe base are called footing courses.

    1.0

    1.5

    Preparation for

    C t ti

    1 0

  • 8/3/2019 1 Building Const 1

    24/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.5.1 TYPES OF FOUNDATION BEDS

    Foundation beds may be classified as follows:

    1. Rock (solid rock, bedrock or ledge). Undisturbed rock masses forming an

    undisturbed part of the original rock-formation. Some examples of harder rocks

    are granite, slate, sandstone, and limestone which are all capable of carrying theload of any ordinary structure. Examples of softer rocks are shale, shaley slates

    and certain marley limestone and clay stones.

    2. Decayed rock (rotten rock). Sand, clays and other materials resulting from the

    disintegration of rock masses, lacking the coherent qualities but occupying thespace formerly occupied by the original rock.

    3. Loose rock. Rock masses detached from the ledge of which they originally

    formed a part.

    4. Gravel. Detached rock particles, generally water-worn, rounded and

    intermediate in size between sand particles and boulders.

    5. Boulders. Detached rock masses larger than gravel, generally rounded andworn as a result of having been transported by water a considerable distance

    from the ledges of which they originally formed a part.

    1.0

    1.5

    Preparation for

    C t ti

    1.0

  • 8/3/2019 1 Building Const 1

    25/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    6. Sand. Non-coherent rock particles smaller than in maximum dimension.

    7. Clay. A plastic material resulting from the decomposition and hydration of

    feldspathic rocks, being hydrated silicate of alumina, generally mixed withpowdered feldspar, quartz and other materials.

    8. Hard-pan. Any strong coherent mixture of clay or other cementing material

    with sand, gravel and boulders.

    9. Silt. A finely divided earthy material deposited from running water.

    10. Mud. Finely divided earthy material generally containing vegetable matter

    and deposited from still or slowly moving water.

    11. Mould. Earthy material containing a large proportion of humus or vegetablematter.

    12. Loam. Earthy material containing a proportion of vegetable matter.

    13. Peat. Compressed and partially carbonized vegetable matter.

    14. Filled Ground. All artificial fills and some natural fills are liable to a more orless uniform but continuous settlement or shrinkage due to the gradual

    consolidation of the material of which the fill is composed

    1.0

    1.5

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    26/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.5.2 ALLOWABLE LOADS ON FOUNDATION BEDS

    Because there are variations in the materials and conditions affectingsuch materials, thorough investigation is required before one can

    determine the allowable unit load on the foundation bed. In caseswherein the material and conditions are uniform over the entire site ofthe building, a uniform unit load may be used. In cases wherein entirelydifferent conditions exist under different portions of the same building,the unit load on the foundation bed must be reduced as much aspossible so as to reduce the differences in settlements between the twosections of the building to a minimum.

    0

    1.5

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    27/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.6 SITE INVESTIGATION

    Before any design is made, the architect is required to get as muchvaluable data about site excavation and building erection at the project

    site in order to determine the character of the materials which will beencountered at the level of a foundation bed.

    1.6.1 METHODS OFEXPLORATION

    1. Test pits. For shallow work, an openpit is the most suitable method since itcalls for an actual inspection of theundisturbed material over aconsiderable area.

    2. Test borings. For excavations thatare carried no deeper than theproposed level, the underlying material

    may be investigated by test boring.

    1.6.2 LOADING TESTS

    Loading tests of the materials formingthe foundation bed are made to assistin determining its safe bearingcapacity.

    Soil Boring Rig. SPT Sample.

    1.6

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    28/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.7 EXCAVATION AND EARTHWORKING

    These processes entail the following:

    1. Excavating is the process of digging

    the earth to provide a place for thefoundation of the building.

    2. Leveling and Grading are processes

    that change land elevation and slope byfilling in low spots and shaving off high

    spots.

    3. Stabilizing the Soil is the process of

    compacting the soil on which thestructure will rest.

    4. The protection of adjoining structure is

    a law that provides that any person

    making an excavation is responsible forresulting damage to adjoining property.

    1.7

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    29/38

    Construction

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    5. Shoring is a process of

    transferring a portion of the

    load of the wall to temporaryfootings and done when theexcavation does not go much

    below the adjoining footingsand when the material is fairly

    solid.

    1.7

    It consists of the following members:a) sheet piles, which are timber, steel, or pre-cast planks driven side by side to retain earth and

    prevent water from seeping into the exaction and

    b) wales or continuous horizontal beams which tie the sheet piles in place or

    c) soldier piles, which are steel H-sections driven vertically into the ground to support

    d) lagging or heavy timber planks joined together horizontally to retain the face of an excavation.

    e) crossbracing or rakers are diagonalswhich supportthe wales and soldier piles bearing onheel blocks or footings.

    f) tiebacks secured torock or soil anchors are resorted to when crossbracing or rakers wouldinterfere with the excavation procedure.

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    30/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.7

    STEEL

    TIMBER

    PRECAST

    SOLDIER PILES/BEAMS(STEEL H-SECTIONS)

    LAGGING refers to the heavytimber planks joined togetherside by side to retain the face ofan excavation

    TIEBACKS

    SHEET PILING AND SOLDIERBEAMS WITH LAGGING

    SHEET PILING

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    31/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    6. Needling and underpinning is a

    process where needles or girders

    are used in cases where part orall of the weight of the wall has to

    be carried, as when the oldfooting is removed and the wall

    underpinned or carried down to a

    new footing at a greater depth.

    1.7

    NEEDLE; a short beam passedthrough a wall as a temporarysupport while the foundation orpart beneath is repaired, alteredor strengthened

    DEAD SHORE; an upright timberfor supporting a dead load duringthe structural alteration of abuilding, esp. one of two supportsfor a needle

    NEEDLING

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    32/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures

    1.7

    EXISTINGWATER TABLE

    WATER TABLEAFTER PUMPING

    DEWATERING

    7. Dewatering refers to the process of lowering a water table

    or preventing an excavation from filling with groundwater. It is

    accomplished by driving perforated tubes called wellpointsinto the ground to collect water from the surrounding area so

    it can be pumped away.

    Preparation for

    Construction

    1.0

    1 8 SLOPE PROTECTION AND RETAINING

  • 8/3/2019 1 Building Const 1

    33/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures 1.8

    1.8 SLOPE PROTECTION AND RETAINING

    STRUCTURES

    1. The need for stabilizing a sloping

    ground can be reduced bydiverting the runoff at the top of

    the slope or by creating a seriesof terraces to reduce the velocity

    of the runoff.

    2. Natural means of stabilization

    include soil binders --- plantmaterials that inhibit or prevent

    erosion by providing a groundcover and forming a densenetwork of roots that bind the soil.

    Preparation for

    Construction

    1.0

    3 Ri i l f i l l b k

  • 8/3/2019 1 Building Const 1

    34/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures 1.8

    RIPRAPDepth of layer should be greaterthan the maximum size of stone

    FILTER FABRIC or GRADEDSAND and GRAVEL for drainage

    3. Riprap is a layer of irregularly brokenand random-sized stones placed on the

    slope of an embankment.

    4. Cribbing is a cellular framework of squared steel,

    concrete, or timber members, assembled in layers atright angles, and filled with earth or stones.

    5. A Bin Wall is a type of gravity retaining wallformed by stacking modular, interlocking pre-

    cast concrete units and filling the voids withcrushed stone or gravel.

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    35/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures 1.8

    GABIONS

    Filter fabric or gradedsand and gravel fordrainage

    6. Gabions are galvanized or PVC coated wire

    baskets filled with stones and stacked to form

    an abutment or retaining structure.

    7. Retaining Structures. When a desired change inground elevation exceeds the angle of repose of the

    soil, a retaining wall becomes necessary to hold themass of earth on the uphill side of the grade change.

    The types of RC retaining walls are as follows:10 (255)

    0.5 H

    a) Gravity Retaining Wall - resistsoverturning and sliding by thesheer weight and volume of its

    mass.

    Preparation for

    Construction

    1.0

    b) T type Cantilevered Retaining Wall limited to a height of 20

  • 8/3/2019 1 Building Const 1

    36/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures 1.8

    8 (205)

    0.6H(0.9H w/ surcharge)

    Batter refers to backwardsloping face of a wall as it

    rises to offset illusion of faceleaning forward

    Temperature steel for wallsmore than 10 (255) thick

    Structural Steel

    reinforcement

    Drainage mat w/ filter fabricor porous gravel backfill

    2 (51 mm) o weepholes @

    4-6 (1220-1830mm) o.c. orperforated drainpipe slopedto outlet away from wall

    Footing should extendbelow the frostline or2 (610mm) below the

    grade level,whichever is higher

    2 (51) min

    3 (75) min

    b) T-type Cantilevered Retaining Walllimited to a height of 20

    (6 M); beyond this height a counterfort wall is employed.

    Preparation for

    Construction

    1.0

  • 8/3/2019 1 Building Const 1

    37/38

    Staking-Out the Building

    Laying the Batterboards

    Formwork & Shoring

    Construction Tools &

    Equipment

    Foundation Bed

    Site InvestigationExcavation & Earthworking

    Slope Protection and

    Retaining Structures 1.8

    c) Counterfort Retaining Wall utilizestriangular-shaped cross walls to stiffen the

    vertical slab and add weight to the base. Thecounterforts are spaced at equal intervals

    equal to one-half the wall height.

    0.7H(1.25 w/ surcharge)

    0.6H(1.0 w/ surcharge)

    d) L-type Cantilevered Retaining Wall

    usedwhen the wall abuts a property line or otherobstruction.

  • 8/3/2019 1 Building Const 1

    38/38

    END