1 building const 1
TRANSCRIPT
-
8/3/2019 1 Building Const 1
1/38
BUILDING
CONSTRUCTIONl
PREPARATION FOR CONSTRUCTION
-
8/3/2019 1 Building Const 1
2/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
1. PREPARATION FOR CONSTRUCTION
1.1 STAKING-OUT THE BUILDING
1. Measure the required setback from the front cornermonuments and drive two stakes and stretch a linebetween them to represent the front building line.
2. Measure the required side setback from one of theside lot lines along the line established in (1) anddrive a stake A which will represent the first corner of
the building. Then from Stake A, measure the widthof the building and mark with a stake B to obtain theother front corner.
3. Estimate right angles from stakes A and B andmeasure the length of the building. In those twopoints, drive two temporary stakes C and D whichwill mark the rear corners of the building. C-D should
be equal to A-B.
4. Draw lines along the diagonals A-D and B-C andensure that these are equal.
5. Transfer the building lines to batter boards.
1.0
1.1
-
8/3/2019 1 Building Const 1
3/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
1.2 LAYING THE BATTERBOARDS
Batter boards are horizontal boards used to establish the height of the finish
foundation and to support the guidelines for the excavation of footing
trenches.
They should be carefully leveled because it is important that they are all at thesame elevation.
Leveling is done with a line level or carpenters level, or with a transit.
The height of the batter boards may be level with or a little higher that the topof the finished foundation.
1.0
1.2
-
8/3/2019 1 Building Const 1
4/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
1.3 FORMWORK AND SHORING
FORMS FOR CONCRETE
CONSTRUCTION. Materials used for
form construction are (1) Lumber, (2)Plywood, (3) Steel.
LUMBER FORMS. Lumber used in formconstruction should only be partially
seasoned.
PLYWOOD FORMS. These are usedwhere a smooth surface is required. The
plywood should be waterproof, Grade A
and at least thick.
STEEL FORMS. Steel forms may be in
the form of pans for concrete joist
construction or steel decking orcorrugated steel for concrete slabs andslab-and-joist construction.
1.0
1.3
-
8/3/2019 1 Building Const 1
5/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
Knee
BraceLedger
BlockingKicker
Sills
PLYWOOD FORMS
WOOD SHORING METAL SHORING
Braced T-and L-heads
Single PostWood Shore
Metal orWood Joists
Stringers
Jack
Adjustable
Metal Shores
Bracing
1.0
1.3
1. Lumber Forms and Shoring
-
8/3/2019 1 Building Const 1
6/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
1.0
1.3
COLUMN FORMS
WALL FORMS
WOOD FORMWORKSReusable forms may have asquare or rectangular crosssection
YOKES are clamping devicesfor keeping column forms andtops of wall forms fromspreading under the fluidpressure of newly placedconcrete
SPREADERS usually of wood,space and keep the wall orforms apart
FORM TIES
PLYWOOD SHEATHING
WOOD STUDS
HORIZONTAL WALERS
SILL PLATE
BRACING
-
8/3/2019 1 Building Const 1
7/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
1.0
1.3FORM TIES
SNAP TIES have notches or crimps thatallow their ends to be snapped off below theconcrete surface after stripping off the forms
small, truncated cones of wood, steel orplastic attached to form ties to space andspread wall forms, leave a neatly finisheddepression in the concrete surface to befilled or left exposed
SHE BOLTS consist of water rods that areinserted through the form and threaded ontothe ends of an inner rod. After striping thewater rods are removed for reuse while theinner rod remains in the concrete
a variety of wedges and slotted devicestighten the formwork and transfer the forcein a form tie to the walers
-
8/3/2019 1 Building Const 1
8/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
SCAFFOLDING COMPONENTS
Ledgers
Standards
Fixed Braces
AdjustableBraces
1.0
1.3
2. Steel Forms and Shoring
-
8/3/2019 1 Building Const 1
9/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site Investigation
Excavation & Earthworking
Slope Protection and
Retaining Structures
Rapidshor Heads
Base & Tilt Base
Adjustable Jacks
SCAFFOLDING COMPONENTS
1.0
1.3
-
8/3/2019 1 Building Const 1
10/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1. Ensure the ground and sleepers areadequately prepared, and the base, jacksand standards are in correct positions.
2. Assemble tower of 4 standardsand ledgers. Fix braces to stabilize.
3. Loosely fit the remainingcomponents until majority of first
level complete. Check standards forverticality and tighten ledgers.
4. Position scaffold boards and ladders. 5. Additional ledgers and bracescan now be added, with additional
braces.
6. Once all levels are complete,jacks and heads can now be
positioned.
7. Jack head levels finalized and any jackbracing required is now fitted.
8. Primary beams can bepositioned, clamped and levels
checked.
9. Secondary beams can bepositioned and clamped to primarybeams, plywood decking to follow.
SCAFFOLDING ASSEMBLY INSTRUCTIONS1.0
1.3
-
8/3/2019 1 Building Const 1
11/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.4 CONSTRUCTION TOOLS & EQUIPMENT
Tools and equipment employed in construction are grouped into four:
1. Hand Toolsare the tools that use power delivered by man only.
2. Power Toolsare those that employ power supplied by forces otherthan that coming from humans.
3. Equipmentis a term that refers to large, complex tools and
machines that is designed to do a particular job.
4. Heavy Equipmentis equipment which is very large and verypowerful.
1.0
1.4
-
8/3/2019 1 Building Const 1
12/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1. Hand Tools
A pry bar is usedto force open
boards used informing concrete.
Measurement andlayout tools are the
following:
a. Folding rule andtape measure are
the most common
tools for measuringboards, pipe, wire,
etc.
b. Digital rule isused to measure
relatively longdistances such as
those in highway
construction.
c. Framing square
is a layout tool thatis used to
measure 90-degree angles at
the corners offramework and
joints. They can
also be employedto determine
cutting angles ondimension lumber.
d. Level is a long,
straight tool thatcontains one or
more vials of liquid
and used todetermine if the
horizontal orvertical is exact.
e. Chalk line or
chalk box is used
for marking lines.
1.0
1.4
-
8/3/2019 1 Building Const 1
13/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Types of hammers are the
following:
a. Claw hammer is anordinary hammer used to
drive or remove nails.
b. Sledgehammer is a heavy
hammer used to drive stakesinto the ground and to break
up concrete and stone.
Types of screwdrivers are:
a. Standard screwdriver has aflat tip and is designed to fit a
standard slotted screw.
b. Phillips screwdriver has an
X-shaped tip and is used to
turn Phillips-head screws only.
c. Spiral ratchet screwdriver isthat which relies on a pushing
force rather than a twisting
force.
1.0
1.4
P f
-
8/3/2019 1 Building Const 1
14/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Types of handsaws are the
following:
a. Ripsaw has chisel-liketeeth designed for ripping or
cutting with the grain ofwood.
b. Crosscut saw is used to
cut across the grain of wood.
c. Backsaw is a special
type of handsaw that has avery thin blade and makes
very straight cuts such asthose on trims and
mouldings.
d. Hacksaw is used to cutmetals.
1.0
1.4
P ti f
-
8/3/2019 1 Building Const 1
15/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Types of Chisels:
a. Wood chisel is used to trim
wood and clear away excessmaterial from wood joints.
b. Cold chisel is used to trim
metals.
Types of specialized hand tools
are the following:
a. Nail set is used to drive finishingnails below the surface of a
wooden trim or molding.
b. Pipe wrench is
used to turn roundobjects like pipes.
c. Brick trowel is
used to place andtrim mortar between
bricks or concreteblocks.
d. Bull float is usedto smoothen out the
surface of wet
concrete.
e. Blind riveter isused to fasten
pieces of sheet
metal together.
1.0
1.4
Preparation for
-
8/3/2019 1 Building Const 1
16/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Power drill.
Power screwdriver.
Radial arm saw.
Table saw.
Portable circular
saw.
Power miter saw.
Saber saw.
2. Power Tools
Power drill is used todrill holes in wood,
metal and concrete.
Power screwdriver or
screwgun is used toinstall and remove
screws.
Types of power sawsare the following:
a. Radial arm saw isused for crosscutting
wood and consists ofa motor-driven saw
blade that is hung onan arm over a table.
b. Table saw is used for
cutting large sheets ofwood and wood
composites and consistsof a blade mounted on an
electric motor beneath atable-like surface.
c. Portable circular saw isused for cutting materials
that are difficult to cutwith stationary tools.
d. Power miter saw is a
circular saw mountedover a small table used
to cut various angles in
wood.
e. Saber saw is used tocut curves or holes in
floors and roofs for pipesand has a small knife-
shaped blade that moves
up and down.
1.0
1.4
Preparation for
-
8/3/2019 1 Building Const 1
17/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Pneumatic hammer.
Rotary hammer.
Pneumatic nailer
Powder-actuatedstud driver.
Stapler.
Type of power
hammers are:
a. Pneumatichammer or
jackhammer isused to break
up concrete or
asphalt paving.
Type of power
nailers and staplersare the following:
a. Nailers or nail
guns fastenmaterials together by
shooting nails into
the building material.
b. Powder-actuatedstud driver is a kind
of nailer that ispowered by
gunpowder and isused to drive long
pins into wood, steel
or concrete.
c. Staplers are likenailers but are
loaded with u-shaped staples
instead of nails for
fastening.
b. Rotary hammer is like an electric
drill that operates with both rotatingand reciprocating actions and is used
to drill holes in concrete.
1.0
1.4
Preparation for
-
8/3/2019 1 Building Const 1
18/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Conveyors are used for transportingmaterials unto large roofs.
Construction
laser.
Transit.
Surveyors level.
3. Equipment
Conveyor is an equipment whichmoves materials other than fluids.
Types of surveying
equipment:
a. Transit is anequipment used by
surveyors tomeasure horizontal
and vertical angles to
obtain land elevation.
b. Surveyors level isthat which is used to
determine anunidentified elevation
from a known one.
c. Construction laser
flashes a narrow,accurate beam of
light to make abaseline for
additionalmeasurements and
is used as a level or
as an alignment tool.
1.0
1.4
Preparation for
-
8/3/2019 1 Building Const 1
19/38
Preparation for
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Concrete pump.
Water pump.
Arc welding machine.
Weld made by a laser-powered welder.
Types of
pumps are:
a. Water pumpis used to
pump waterout of holes in
the ground so
thatconstruction
work cancommence.
Types of weldingmachines are
the following:
a. Arc weldingmachine is usedto weld materials
by meltingportions of the
metal.
b. Concrete pump is used to move
concrete from the concrete mixer tothe concrete form.
b. Laser-powered welder is used to
weld material by employing a laser toheat the metal.
1.0
1.4
Preparation for
1 0
-
8/3/2019 1 Building Const 1
20/38
p
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Bulldozer.
640-foot crane.
4. Heavy Equipment
Bulldozer is a tractor with a pushingblade which moves earth and clears
land of bushes and trees.
a. Crawler crane is a crane mounted
on metal treads so that it can moveover rough terrain.
b. Truck crane is mounted on a truck
frame so that it can be driven in the
site.
c. Tower crane or climbing crane isused in the construction of tall building
because it has a built-in jack thatraises the crane from floor to floor as
the building is constructed.
Cranes are
machines thatlift large and
heavy
materials. Thetypes ofcranes are:
1.0
1.4
Preparation for
1 0
-
8/3/2019 1 Building Const 1
21/38
p
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Excavator is a machine used for
digging or scooping earth from aplace and depositing it in another.
Types of excavators are:
a. Backhoe is used for general
digging which is usually mounted
on either a crawler or truck frame.
b. Trencher is a special kind which
digs trenches or long, narrowditches for pipelines or cables.
c. Front-end loader is a large
shoveling machine that can scoopor deposit a large amount of
material.
Trencher-excavator.
Backhoe.
Front-end loader.
1.0
1.4
Preparation for
1 0
-
8/3/2019 1 Building Const 1
22/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
Highway construction equipment
are:
a. Scraper is a machine that loads,hauls and dumps soil over medium
to long distances.
b. Grader is an earthworking
machine that grades or levels theground.
c. Compactor or roller is a machine
that compacts soil to prepare forroad paving.
d. Paver is a machine that places,
spreads and finishes concrete or
asphalt paving material
Scraper.
Grader.
1.0
1.4
Preparation for
1 0
-
8/3/2019 1 Building Const 1
23/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.5 FOUNDATION BED
The word foundation is applied to:
1. Construction below grade, such as footing courses, basementwalls, etc., forming the lower section of a structure;
2. The natural material, the particular part of the earths surface on
which the construction rests;
3. Special construction such as piling or piers used to transmit the loadsof the building to firm substrata.
Foundation bed is the natural material on which the construction rests.Walls, piers and columns below grade are called, in general, foundationwalls, piers and columns to distinguish them from similar construction
above grade. The lower portions of walls, piers or columns which arespread to provide a safe base are called footing courses.
1.0
1.5
Preparation for
C t ti
1 0
-
8/3/2019 1 Building Const 1
24/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.5.1 TYPES OF FOUNDATION BEDS
Foundation beds may be classified as follows:
1. Rock (solid rock, bedrock or ledge). Undisturbed rock masses forming an
undisturbed part of the original rock-formation. Some examples of harder rocks
are granite, slate, sandstone, and limestone which are all capable of carrying theload of any ordinary structure. Examples of softer rocks are shale, shaley slates
and certain marley limestone and clay stones.
2. Decayed rock (rotten rock). Sand, clays and other materials resulting from the
disintegration of rock masses, lacking the coherent qualities but occupying thespace formerly occupied by the original rock.
3. Loose rock. Rock masses detached from the ledge of which they originally
formed a part.
4. Gravel. Detached rock particles, generally water-worn, rounded and
intermediate in size between sand particles and boulders.
5. Boulders. Detached rock masses larger than gravel, generally rounded andworn as a result of having been transported by water a considerable distance
from the ledges of which they originally formed a part.
1.0
1.5
Preparation for
C t ti
1.0
-
8/3/2019 1 Building Const 1
25/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
6. Sand. Non-coherent rock particles smaller than in maximum dimension.
7. Clay. A plastic material resulting from the decomposition and hydration of
feldspathic rocks, being hydrated silicate of alumina, generally mixed withpowdered feldspar, quartz and other materials.
8. Hard-pan. Any strong coherent mixture of clay or other cementing material
with sand, gravel and boulders.
9. Silt. A finely divided earthy material deposited from running water.
10. Mud. Finely divided earthy material generally containing vegetable matter
and deposited from still or slowly moving water.
11. Mould. Earthy material containing a large proportion of humus or vegetablematter.
12. Loam. Earthy material containing a proportion of vegetable matter.
13. Peat. Compressed and partially carbonized vegetable matter.
14. Filled Ground. All artificial fills and some natural fills are liable to a more orless uniform but continuous settlement or shrinkage due to the gradual
consolidation of the material of which the fill is composed
1.0
1.5
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
26/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.5.2 ALLOWABLE LOADS ON FOUNDATION BEDS
Because there are variations in the materials and conditions affectingsuch materials, thorough investigation is required before one can
determine the allowable unit load on the foundation bed. In caseswherein the material and conditions are uniform over the entire site ofthe building, a uniform unit load may be used. In cases wherein entirelydifferent conditions exist under different portions of the same building,the unit load on the foundation bed must be reduced as much aspossible so as to reduce the differences in settlements between the twosections of the building to a minimum.
0
1.5
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
27/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.6 SITE INVESTIGATION
Before any design is made, the architect is required to get as muchvaluable data about site excavation and building erection at the project
site in order to determine the character of the materials which will beencountered at the level of a foundation bed.
1.6.1 METHODS OFEXPLORATION
1. Test pits. For shallow work, an openpit is the most suitable method since itcalls for an actual inspection of theundisturbed material over aconsiderable area.
2. Test borings. For excavations thatare carried no deeper than theproposed level, the underlying material
may be investigated by test boring.
1.6.2 LOADING TESTS
Loading tests of the materials formingthe foundation bed are made to assistin determining its safe bearingcapacity.
Soil Boring Rig. SPT Sample.
1.6
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
28/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.7 EXCAVATION AND EARTHWORKING
These processes entail the following:
1. Excavating is the process of digging
the earth to provide a place for thefoundation of the building.
2. Leveling and Grading are processes
that change land elevation and slope byfilling in low spots and shaving off high
spots.
3. Stabilizing the Soil is the process of
compacting the soil on which thestructure will rest.
4. The protection of adjoining structure is
a law that provides that any person
making an excavation is responsible forresulting damage to adjoining property.
1.7
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
29/38
Construction
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
5. Shoring is a process of
transferring a portion of the
load of the wall to temporaryfootings and done when theexcavation does not go much
below the adjoining footingsand when the material is fairly
solid.
1.7
It consists of the following members:a) sheet piles, which are timber, steel, or pre-cast planks driven side by side to retain earth and
prevent water from seeping into the exaction and
b) wales or continuous horizontal beams which tie the sheet piles in place or
c) soldier piles, which are steel H-sections driven vertically into the ground to support
d) lagging or heavy timber planks joined together horizontally to retain the face of an excavation.
e) crossbracing or rakers are diagonalswhich supportthe wales and soldier piles bearing onheel blocks or footings.
f) tiebacks secured torock or soil anchors are resorted to when crossbracing or rakers wouldinterfere with the excavation procedure.
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
30/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.7
STEEL
TIMBER
PRECAST
SOLDIER PILES/BEAMS(STEEL H-SECTIONS)
LAGGING refers to the heavytimber planks joined togetherside by side to retain the face ofan excavation
TIEBACKS
SHEET PILING AND SOLDIERBEAMS WITH LAGGING
SHEET PILING
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
31/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
6. Needling and underpinning is a
process where needles or girders
are used in cases where part orall of the weight of the wall has to
be carried, as when the oldfooting is removed and the wall
underpinned or carried down to a
new footing at a greater depth.
1.7
NEEDLE; a short beam passedthrough a wall as a temporarysupport while the foundation orpart beneath is repaired, alteredor strengthened
DEAD SHORE; an upright timberfor supporting a dead load duringthe structural alteration of abuilding, esp. one of two supportsfor a needle
NEEDLING
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
32/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures
1.7
EXISTINGWATER TABLE
WATER TABLEAFTER PUMPING
DEWATERING
7. Dewatering refers to the process of lowering a water table
or preventing an excavation from filling with groundwater. It is
accomplished by driving perforated tubes called wellpointsinto the ground to collect water from the surrounding area so
it can be pumped away.
Preparation for
Construction
1.0
1 8 SLOPE PROTECTION AND RETAINING
-
8/3/2019 1 Building Const 1
33/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures 1.8
1.8 SLOPE PROTECTION AND RETAINING
STRUCTURES
1. The need for stabilizing a sloping
ground can be reduced bydiverting the runoff at the top of
the slope or by creating a seriesof terraces to reduce the velocity
of the runoff.
2. Natural means of stabilization
include soil binders --- plantmaterials that inhibit or prevent
erosion by providing a groundcover and forming a densenetwork of roots that bind the soil.
Preparation for
Construction
1.0
3 Ri i l f i l l b k
-
8/3/2019 1 Building Const 1
34/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures 1.8
RIPRAPDepth of layer should be greaterthan the maximum size of stone
FILTER FABRIC or GRADEDSAND and GRAVEL for drainage
3. Riprap is a layer of irregularly brokenand random-sized stones placed on the
slope of an embankment.
4. Cribbing is a cellular framework of squared steel,
concrete, or timber members, assembled in layers atright angles, and filled with earth or stones.
5. A Bin Wall is a type of gravity retaining wallformed by stacking modular, interlocking pre-
cast concrete units and filling the voids withcrushed stone or gravel.
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
35/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures 1.8
GABIONS
Filter fabric or gradedsand and gravel fordrainage
6. Gabions are galvanized or PVC coated wire
baskets filled with stones and stacked to form
an abutment or retaining structure.
7. Retaining Structures. When a desired change inground elevation exceeds the angle of repose of the
soil, a retaining wall becomes necessary to hold themass of earth on the uphill side of the grade change.
The types of RC retaining walls are as follows:10 (255)
0.5 H
a) Gravity Retaining Wall - resistsoverturning and sliding by thesheer weight and volume of its
mass.
Preparation for
Construction
1.0
b) T type Cantilevered Retaining Wall limited to a height of 20
-
8/3/2019 1 Building Const 1
36/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures 1.8
8 (205)
0.6H(0.9H w/ surcharge)
Batter refers to backwardsloping face of a wall as it
rises to offset illusion of faceleaning forward
Temperature steel for wallsmore than 10 (255) thick
Structural Steel
reinforcement
Drainage mat w/ filter fabricor porous gravel backfill
2 (51 mm) o weepholes @
4-6 (1220-1830mm) o.c. orperforated drainpipe slopedto outlet away from wall
Footing should extendbelow the frostline or2 (610mm) below the
grade level,whichever is higher
2 (51) min
3 (75) min
b) T-type Cantilevered Retaining Walllimited to a height of 20
(6 M); beyond this height a counterfort wall is employed.
Preparation for
Construction
1.0
-
8/3/2019 1 Building Const 1
37/38
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring
Construction Tools &
Equipment
Foundation Bed
Site InvestigationExcavation & Earthworking
Slope Protection and
Retaining Structures 1.8
c) Counterfort Retaining Wall utilizestriangular-shaped cross walls to stiffen the
vertical slab and add weight to the base. Thecounterforts are spaced at equal intervals
equal to one-half the wall height.
0.7H(1.25 w/ surcharge)
0.6H(1.0 w/ surcharge)
d) L-type Cantilevered Retaining Wall
usedwhen the wall abuts a property line or otherobstruction.
-
8/3/2019 1 Building Const 1
38/38
END