1 BROOKHAVEN SCIENCE ASSOCIATES
Laboratory Office Building (LOB) Design
Ove DylingAssistant Director for Design Management
CFAC Review November 9 – 10, 2009
2 BROOKHAVEN SCIENCE ASSOCIATES
Outline
• Overview of LOB Design• Design Milestones and Schedules• LOB Design Features
• Prior Baseline Design• Optimized LOB Space Requirements• Current Design and Perspective views
• Review Process• Coordination with Ring Contractor• Cost Estimate• Conclusion
3 BROOKHAVEN SCIENCE ASSOCIATES
Overview of LOB Design (WBS 1.05.02.02) • Baseline Plan LOB Design Deferred to 2010
• Construction start limited by funding availability• Beamline support requirements can be better defined later• A/E can focus on Ring Building Design.
• LOB Design can now be Advanced using ARRA funding• Avoid inefficiencies in construction sequence• Determine likely conventional facilities costs sooner• DOE approved enlarged LOB concept in April 2009
• Experimental Facilities Division Programs the LOB• Meetings with HDR Lab Planners Feb - March 09• Town Hall Meeting with Users on 3-25-2009
4 BROOKHAVEN SCIENCE ASSOCIATES
Design Milestones and Schedule
• A/E scheduled milestones • Begin Title II LOB start April 21, 2009• Title II 50% Review Submittal July 15, 2009• Title II 100% Review Submittal September 25, 2009• Title II Construction Bid Issue November 18, 2009
• Schedule: Baseline Current Plan
• A/E Title II Construction Bid Issue 3/3/11 11/18/09• LOB Contract Award 10/3/11 3/15/10• LOB base scope construction start 12/13/11 7/1/10• LOB base scope construction complete 6/17/13 4/30/12
5 BROOKHAVEN SCIENCE ASSOCIATES
Lab-Office Building: Prior Baseline Design
Lab Office Building - each nominally has:
• 72 Offices
• 6 labs
• Machine shop
• 4 Conference Rooms
• Loading/storage area
Total = 23,800 gsf
Each Lab = 480 nsf
6 BROOKHAVEN SCIENCE ASSOCIATES
Optimized LOB Space Requirements
• Based on XFD detailed analysis and benchmarking with other facilities, an expanded LOB is required to satisfy the needs of the NSLS-II community
• In general, 8 laboratories and 2 electronic work areas plus a machine shop are needed to support user/staff activities at the beamlines:• 3 wet labs• 2 dry labs• 1 special purpose sample characterization lab• 1 mechanical assembly lab• 1 vacuum prep lab• 2 electronic work areas• 1 machine shop
• Adequate temporary storage space is needed for receiving and staging• 75 office spaces are needed to supports users & staff but 17 of these spaces
need to accommodate 2, 4, or 6 people sharing them – Total occupancy 124
7 BROOKHAVEN SCIENCE ASSOCIATES
57 One person Offices6Two people Offices7Six people Offices3Wet Laboratories7Dry Laboratories8Machine Shop9Conference Rooms1 Loading/Storage Area
LOB First Floor Plan
Total = 38,000 gsf
Each Lab = 480 nsf
8 BROOKHAVEN SCIENCE ASSOCIATES
Penthouse Floor Plan
Mechanical Penthouse
Clerestory - Open Plan and Lobby Corridor
Hi-bay over Shipping Receiving/Storage Area
9 BROOKHAVEN SCIENCE ASSOCIATES
Cross Sections
Office Area Lab Area
Mechanical Penthouse
10 BROOKHAVEN SCIENCE ASSOCIATES
Exterior Perspective
11 BROOKHAVEN SCIENCE ASSOCIATES
Exterior Perspective
12 BROOKHAVEN SCIENCE ASSOCIATES
Laboratory Floor Plans
13 BROOKHAVEN SCIENCE ASSOCIATES
Wet Lab
14 BROOKHAVEN SCIENCE ASSOCIATES
Dry Lab
15 BROOKHAVEN SCIENCE ASSOCIATES
Utilities and Services & ESH Considerations
16 BROOKHAVEN SCIENCE ASSOCIATES
Interior Perspectives
17 BROOKHAVEN SCIENCE ASSOCIATES
Interior Perspectives
18 BROOKHAVEN SCIENCE ASSOCIATES
Structure
• Foundation Plans• Foundations for columns are isolated spread footings• Exterior walls supported on concrete foundation wall and spread
footings• Footings designed for allowable bearing capacity of 5000 psf
• Penthouse Framing Plan• Floor is 2” composite steel deck with 3” lightweight concrete• Floor framing steel beams and girders composite action• Design Live Load 150 psf.
• Low & Mid Roof Framing Plan• Low roof supported on steel beam and girders• Mid roof supported on long span open web steel bowstring joists• Roof decking: 1 ½” x 20 GA.• Roof designed for 30 psf. live load plus snow drifts.
19 BROOKHAVEN SCIENCE ASSOCIATES
LOB Utilities• Fire Protection
• 100% wet piped sprinkler system• Multi-zone alarmed sprinkler system zones
• Mechanical• 3 Air Handlers Units • Intake louver on left side of Penthouse• Exhaust louver on right side of Penthouse• Air supplied through air terminal units w/reheat coils for
temperature control• Perimeter heating with fin tube radiation below windows• Wet labs with hoods totally exhausted• General lab exhaust and return air as required by lab function
20 BROOKHAVEN SCIENCE ASSOCIATES
LOB Utilities (Cont)• Electrical Lighting
• Recessed 2 x 4 in enclosed offices• Linear pendants in open high bay• Recessed 1 x 4 in labs• Decorative refractor pendants in lobby
• Electrical Controls• Perimeter offices motion and photocell• Interior offices motion• Open high bay photo cell• Labs motion• Corridors, toilets, support motion
21 BROOKHAVEN SCIENCE ASSOCIATES
LOB Utilities (Cont)• Telecommunication
• Lab spaces one telephone/data outlet every 6’-0”• Offices two communication outlets• Conference rooms wall telephone and floor trench data • Interaction area wall mounted telephone/data
• Security• First Floor Proxi card reader control
• Exterior doors, Laboratories, Offices, Conference rooms, Tech areas, and Staging/Receiving
• Penthouse • Proxi card reader + Keypad control for Comm. rooms• Proxi card at stairs
22 BROOKHAVEN SCIENCE ASSOCIATES
LOB Utilities (Cont)• Fire Alarm
• Speakers for Emergency Voice Evacuation and general announcements
• American with Disabilities Act Guidelines Applied• Visual Alarms in Common areas, corridors, labs, meeting
rooms, toilet rooms• Manual pull stations at exits and exterior doors• Visual alarm provided on Penthouse level• Duct mounted smoke detectors for fan shutdown
23 BROOKHAVEN SCIENCE ASSOCIATES
LOB shelled space
Fit out of corridor and bathrooms• Insulated exterior walls• Basic HVAC (one AHU)• Basic Lighting & Fire Protection
24 BROOKHAVEN SCIENCE ASSOCIATES
Bathroom if LOB not Built
Bathroom Required by Code if LOB not built• Single person Mens & Womens • ADA Compliant
25 BROOKHAVEN SCIENCE ASSOCIATES
LOB Design Review Process
• In Preparation for Title II LOB Design Review Submittals• Various Design Coordination Meetings with BNL/HDR
• HDR submitted Title II LOB Design at 50% and 100% • Each submittal distributed for design review to:
• BNL ES&H group, BNL Fire Protection group, BNL Plant Engineering, Commissioning agent and NSLS II Project team
• HDR conducts design presentation/review mtg at BNL• NSLS II collects comments from stakeholders - transmits to HDR
• 50% comments not incorporated repeated on 100% comments• 100% comments posted on share point and tracked until resolved• NSLS II project team goes to HDR to discuss/plan comment resolution
26 BROOKHAVEN SCIENCE ASSOCIATES
LOB Design Review Process (Cont)
• Finalizing design for LOB Bid Issue Set• HDR committed to provide advance copies of drawings with revisions
prior to issuing the Bid Set• NSLS II reviews these advance copies and return comments if any
prior to issue of Bid Set
27 BROOKHAVEN SCIENCE ASSOCIATES
Coordination with Ring Contractor
• LOB RFP and Bid Package structured so that LOB can be built by contractor other than Ring Bldg contractor
• Held numerous planning meetings to determine coordination requirements for two contractors to work on the site
• Coordination affected:• Schedule of when construction of LOBs could begin adjacent the Ring bldg• Site access and laydown/staging areas• Movement of materials within the site• Contractor insurance and liability considerations
28 BROOKHAVEN SCIENCE ASSOCIATES
Conclusion
• Extensive Lab and Office programming provides confidence that design will meet needs
• Conducted 50% review August 15, 2009• Conducted 100% review October 13, 2009• Bid set scheduled for submittal on November 18, 2009• Confident Bid Set will be well coordinated and complete• Market conditions support favorable pricing • Looking forward to a successful procurement process