1-34 introduction to below ground drainage
DESCRIPTION
FreeTRANSCRIPT
![Page 1: 1-34 Introduction to Below Ground Drainage](https://reader036.vdocuments.site/reader036/viewer/2022082901/5695d3f11a28ab9b029fb76a/html5/thumbnails/1.jpg)
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 14
Note 34 Level 1
991290
February 2014
TheStructuralEngineer20
Technical Guidance Note
Technical
Below ground drainage is the primary
means by which all surface and foul water is
distributed from a structure into the public
network of sewers Drainage pipes that serve
a single structure are deemed
to be part of its drainage system while those
that are connected to multiple buildings are
classified as sewers This note covers only
drainage systems that connect into sewers
Most drainage systems require both surface
and foul water to remain separate for reasons
of hygiene and water treatment effi ciency A
combined system can result in a foul drainage
discharging into the surface water system
which is undesirable from a water treatment
perspective Note that surface water drainage
can and does overflow and while problematic
does not present a health hazard unlike an
overflow from a foul drainage system
Gravity based drainage systemsIt is preferable to have a gravity based system
of drainage that relies on relatively shallow
gradients to transport water into the sewer
system as described in BS EN 7522008
Drain and Sewer Systems Outside Buildings
Such systems require the least amount of
maintenance and energy to function There
are instances however where gravity based
systems are not possible and the use of
pumps and other alternatives are needed (Table 1)
Introduction to below
ground drainageIntroduction
The design and specification of below ground drainage often falls to a
structural engineer despite the subject typically not being the focus of their
training This apparently stems from the fact that in many instances below
ground drainage impacts upon the design of foundations which does fall within
the structural engineerrsquos design responsibilities Hence the design of drainage
and the substructure is typically grouped together in order to ensure that some
form of coordination is achievedThis Technical Guidance Note explains the basic principles of below ground
drainage for both surface and foul water Acting as an introduction it describes
the different types of drainage pipes that are available how they are installed
how they interface with structure their testing and maintenance
ICONLEGEND
Below ground drainage
Drainage design criteriaDrainage systems should be simply laid
out They should take the passage of least
resistance directly to the sewer system By
doing so the likelihood of blockages and
other defects is significantly reduced as the
required amount of pressure head is kept
to a minimum Abiding by the following rules
should ensure that simplicity is achieved
Change of direction gradient and pipe size
minimised ndash Whenever a drain pipersquos passage
is altered or its size is changed there is risk
of a blockage occurring It is for this reason
that a manhole must be installed when these
changes in the drain run occur These are
expensive to construct and their presence
must be kept to a reasonable minimum
Maintain the direction of flow into the
sewer ndash The outlet of drainage pipes shouldbe in line with the flow of the sewer they are
connecting to otherwise there is a risk of a
blockage forming within the sewer (Figure 1)
Limit excavation required to install drainage
ndash The amount of excavation works should
be kept to a minimum to reduce the risk
of damage to the pipes as the excavated
material is placed on top of them during
installation
Articulation at wallfoundation interfaces
ndash Pipes should be allowed to rotate as they
pass through substructure elements as the
soil they rest upon moves around the sub-
structure
Free air flow ndash Drainage systems should
allow for the free passage of air to prevent
build-up of gasses such as methane
Allow for soil movement ndash Drainage pipesare typically founded on the soil with no
983127
983127 Applied practice
983127 Further reading
983127 Web resources
Below grounddrainage
Table 1 Soil conditions and building types typically
requiring non-gravity based drainage
Soil conditions Building typeslocation
Contaminated
lsquoBrownfieldrsquo siteLarge retail units
High water table Adjacent tunnels
Mountainousand rolling hills
Sites bisected by riversStructures with basements
983123 Figure 1Direction of flow from
drainage outlet into sewer
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 24
wwwthestructuralengineerorg
21
additional means of support other than a
compacted granular fill therefore allowance
must be made for settlement and heave This
can be addressed by the judicious use of
rocker pipes (see lsquoDrainage pipe interactions
with structuresrsquo section)
Provision of access points ndash It is essential
that drainage systems have locations
included within them where the pipes can be
cleaned of debris to avoid blockages forming
Pipe sizes and typesDrainage systems can have pipe sizes
ranging from 75-1200mm In the UK the
minimum diameter is 100mm when foul waste
is likely to travel through it Pipes are split into
three categories rigid semi-rigid and flexible
(Table 2)
The terms lsquorigidrsquo lsquosemi-rigidrsquo and lsquoflexiblersquo
concern the material the pipes are made from
and not how much the overall system moves
All drainage systems must have joints that
can articulate to allow them to shift as the soil
in which it rests heaves and settles
The key difference between flexible and
semirigid pipes is how the soil around them
sheds forces that are applied to the pipes due
to a surcharge such as road traffi c Flexible
pipes react by deforming and the soil around
them sheds forces away from the pipe The
opposite is true for semirigid pipes as they
are a point of stiffness that tends to attract
forces (Figure 2) This is further explained in
Clause 42 of BS EN 92952010 Guide to the
structural design of buried pipelines
Pipe gradients and jointsPipes are laid to falls that are dictated by
the amount of water and waste they are to
transport The shallowest gradient is 180 for
pipes smaller than 150mm diameter For all
other drainage systems that have peak flows
of more than 1Ls the gradient can be no less
than 1150 For systems with flows of less than
1Ls a gradient of at least 140 is required This
is further explained in Table 6 of Approved
Document H12010 Drainage and Waste
Disposal in the Building Regulations for England
Joints in pipes must be water-tight and
flexible enough to allow the pipes to move
with respect to soil heave and settlement
Bedding of drainage pipesAll founding material for drain pipes must
allow for soil movement and surcharge
forces placed above the pipe Diagram 10 of
Approved Document H1 provides guidanceon the type of bedding material that should
Table 2 Examples of flexible semi-rigid and rigid drainage pipes
Flexible Semi-rigid Rigid
PVC-u and polypropylene Ductile iron Vitrified clay
Thin walled steel Thick walled steel Concrete
Glass reinforced plastics - Reinforced concrete
be used when installing drainage depending
on its rigidsemi-rigid and flexible forms
(summarised in Figure 3)
Where drainage pipes have less than 600-
1200mm of backfill cover and depending on
the type of surface (wearing course) of the
soil provision should be made to protect the
pipe due to movement of the surface This
can be done by installing a concrete slab
over the top of the bedding to the pipe with
a 75mm thick layer of flexible filler material
between its soffi t and the granular fill thatsurrounds the drain pipe (Figure 4)
S e m i - r i g i d a
n d r i g i d p i p e s
F l e
x i b l e p i p e s
Selected fill with no timber
frozen material vegetation
lumps of clay gt100mm
and stones gt40mm
Granular material with
5-40mm sized aggregate
depending on pipe size
Selected or granular fill
with no stones gt40mm
lt600-1200mm of backfill
75mm thick
compressible material
Granular fill surround
Class descriptions
B Used for all conditions
D Can only be used if
trench is made by hand
trimming by shovel
F Used for all conditions
The joints must have 45deg of
spread in the granular fill
N Used when hand
trimming by shovel
is not possible
983123 Figure 2Flexible and rigid drainage pipe
behaviour when subjected to surcharge
983123 Figure 3Bedding details for drainage pipes
Drain pipe
300mm bearing to slab
on original ground
Concrete slab
983123 Figure 4Section through shallow
drain pipe protection detail
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 34
Note 34 Level 1
991290
February 2014
TheStructuralEngineer22
Technical Guidance Note
Technical
Anti-vermin
infiltration sheets
Lintels over opening
in structure
Compressible
sealant to prevent
entry of gas
It is also possible to cast drainage within raft
foundations with the aim of simplifying their
installation and integrating them into the sub-
structure
The precise amount of cover required todrainage pipes is provided in Tables 8-10 of
Approved Document H1
The material contained in the backfill must
be free of large stones and bricks in order
to minimise the risk of these large objects
impacting the drainage pipe and damaging it
as the backfill is laid on top of the pipe
Drainage pipe interactions with str ucturesTypically structures are relatively rigidstiff
when compared to the soil they are founded
on Clearly this is not the case for rock anddense gravels However where the soil
can move relative to the structure so do
the drain pipes within it Where such pipes
interface with the structure of a building care
needs to be taken to ensure that flexibility
of the drainage system is maintained This
is typically achieved through two different
methods
The first is the use of rocker pipes These are
short length unique pipes typically 600mm
long that allow connecting drainage pipes
to rotate around the structural penetration
without breaking their seal and thus maintain
their integrity (Figure 5)
The second form of detail isolates the
structure away from the drainage pipe
by creating a void within the structure to
allow passage of the pipe If this solution
is adopted provision must be made to seal
the structure around the pipe to avoid the
passage of gasses into the structure (Figure
6)
983123 Figure 5Rocker pipe detail 983123 Figure 6
Section through structuralisolation from drain pipe detail
When pipes are passing through basement
walls a puddle-flange is required to prevent
water ingress into the basement due to the
penetration through it
Most drainage interface solutions with suband super-structure elements are expensive
and diffi cult to construct It is therefore
advisable to avoid the need to have such
details by planning the development of the
below ground drainage system so that it is
sympathetic to the structure and vice-versa
TestingOnce a drainage system has been installed
it needs to be tested BS 80001989
Workmanship on building sites mdashPart 14
Code of practice for below ground drainage
provides guidance on the extent and
methodology of testing that is required ofall newly installed below ground drainage
systems in the UK There are two forms of
test air based and water based
Clause 5143 of BS 8000 Part 14 describes
how the water base test is applied It explains
the eight elements of the test that must
be adhered to in order for it to be valid In
summary the test pushes water through the
drainage system with a 15m head of pressure
The drains are left in this state for two hours
whereupon the head of water is monitored
to see if there has been any leakage Some
leakage the calculation of which is based on
the diameter of the pipe and its overall length
is allowed
Clause 5144 of BS 8000 Part 14 explains
the air based test procedure for below
ground drainage This testing system
requires the use of a manometer to provide
air pressure to the drainage system that has
been temporarily plugged The air pressure
is measured over a period of five minutes to
determine how much leakage there is within
the system
Maintenance of drainsThe primary method of access to drains is
via manholes deep chambers usually madeof precast concrete or masonry (Figure 7)
These are installed where there are junctions
changes in direction andor gradient and
increases in pipe size
There are other less intrusive methods of
providing access to drainage A lsquorodding
eyersquo is a pipe that extends to the surface
that allows the drain to be cleaned using a
specialist tool Access fittings and inspection
chambers are small surface mounted units
that allow easy maintenance of the drainage
pipes they are fixed into
Pest controlVermin infestation is a continual problem with
drainage systems but it can be managed
by adopting simple details that reduce the
risk of it occurring The sealing of inspection
chambers is one method that prevents vermin
from entering the drainage system These are
chambers that have access covers within them
rather than over an open channel Anti-climbing
devices within the drain pipes also prevent the
passage of vermin These can be fins or one-
way valves that are placed into the direction of
the flow of waterwaste within the drain
Drains that are no longer required should
either be removed or filledplugged with
concrete to ensure they do not provide a
means of access for vermin into the new
drainage system
Plastic or metal gratings should also be
installed where there are gullies connecting
to the drainage system for surface water
drainage to prevent vermin gaining access
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 44
wwwthestructuralengineerorg
23
Applied practice
BS EN 7522008 Drain and Sewer Systems
Outside Buildings
BS 80001989 Workmanship on building
sites - Part 14 Code of practice for below
ground drainage
BS EN 92952010 Guide to the structural
design of buried pipelines
Approved Document H12010 Drainage and
Waste Disposal in the Building Regulations
for England
Glossary and
further reading
Adopted drainage ndash a system that is
connected to a public sewer
Bedding ndash material that is laid under and
around the drain pipe as a founding material
Benching ndash open channels formed within
This year the Kenneth Severn Award question has been set by 2014 Institution PresidentNick Russell Those aged 28 years or under are invited to answer the following
TRAINING ENGINEERS IS A PARTNERSHIP BETWEEN ACADEMIA AND INDUSTRY HOW COULD LINKS BETWEEN THESE BESTRENGTHENED FOR THE BENEFIT OF THE PROFESSION
To enter please submit your answer in the form of
a written paper entitled ldquoTraining engineers is a
partnership between academia and industry How
could links between these be strengthened for the
editorialistructeorg
Your paper should be a maximum of 1500 words
and may include relevant imagery that supplementsyour answer
The judges will be looking for originality value to
the structural engineering profession and clarity
of presentation
Closing date for entries is Friday 28 February 2014
The winning author will receive
The prestigious Kenneth Severn Diploma
A cash prize of pound500
The winning paper will be
Considered for publication in The Structural
Engineer
Entrants must be 28 years of age or under on
1 January 2014
Entry is NOT restricted to members of the Institution
Please ensure that you include your name date of
birth and full contact details with your submission
Registered with the Charity Commission for England and Wales No 233392 and in Scotland No SC038263
2014Nick Russell
BSc(Hons) CEng FIStructE FICE MCMI
Institution President 2014
CMIICE
Eurocode 0
Web resources
The Institution of Structural Engineers library
wwwistructeorgresources-centrelibrary
joints that allow for large amounts of
articulation at its ends to ensure flexibility of
the drainage pipe system
Rodding eye ndash surface mounted
cleaning point for below ground drainagesystems
Further ReadingPitman P (2001) External Works Roads and
Drainage A practical guide Boca Raton FL
CRC Press (Taylor amp Francis)
Butler D and Davies J (2010) Urban Drainage
(3rd ed) Boca Raton FL CRC Press (Taylor
amp Francis)
Scottish Water (2011) Sewers for Scotland
Consultation Report (2nd ed) [Online]
Available at wwwscottishpowercouk(Accessed January 2014)
inspection chambers and manholes to
maintain the flow of water and waste
Private drainage ndash a system that is not
connected to a public sewer
Rocker pipe ndash a short pipe with unique
983118 Figure 7Section through a typical precast
concrete manhole
Rodding
eye inlet
Benching
Precast
concretering
manhole
shaft
Drain
pipe
![Page 2: 1-34 Introduction to Below Ground Drainage](https://reader036.vdocuments.site/reader036/viewer/2022082901/5695d3f11a28ab9b029fb76a/html5/thumbnails/2.jpg)
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 24
wwwthestructuralengineerorg
21
additional means of support other than a
compacted granular fill therefore allowance
must be made for settlement and heave This
can be addressed by the judicious use of
rocker pipes (see lsquoDrainage pipe interactions
with structuresrsquo section)
Provision of access points ndash It is essential
that drainage systems have locations
included within them where the pipes can be
cleaned of debris to avoid blockages forming
Pipe sizes and typesDrainage systems can have pipe sizes
ranging from 75-1200mm In the UK the
minimum diameter is 100mm when foul waste
is likely to travel through it Pipes are split into
three categories rigid semi-rigid and flexible
(Table 2)
The terms lsquorigidrsquo lsquosemi-rigidrsquo and lsquoflexiblersquo
concern the material the pipes are made from
and not how much the overall system moves
All drainage systems must have joints that
can articulate to allow them to shift as the soil
in which it rests heaves and settles
The key difference between flexible and
semirigid pipes is how the soil around them
sheds forces that are applied to the pipes due
to a surcharge such as road traffi c Flexible
pipes react by deforming and the soil around
them sheds forces away from the pipe The
opposite is true for semirigid pipes as they
are a point of stiffness that tends to attract
forces (Figure 2) This is further explained in
Clause 42 of BS EN 92952010 Guide to the
structural design of buried pipelines
Pipe gradients and jointsPipes are laid to falls that are dictated by
the amount of water and waste they are to
transport The shallowest gradient is 180 for
pipes smaller than 150mm diameter For all
other drainage systems that have peak flows
of more than 1Ls the gradient can be no less
than 1150 For systems with flows of less than
1Ls a gradient of at least 140 is required This
is further explained in Table 6 of Approved
Document H12010 Drainage and Waste
Disposal in the Building Regulations for England
Joints in pipes must be water-tight and
flexible enough to allow the pipes to move
with respect to soil heave and settlement
Bedding of drainage pipesAll founding material for drain pipes must
allow for soil movement and surcharge
forces placed above the pipe Diagram 10 of
Approved Document H1 provides guidanceon the type of bedding material that should
Table 2 Examples of flexible semi-rigid and rigid drainage pipes
Flexible Semi-rigid Rigid
PVC-u and polypropylene Ductile iron Vitrified clay
Thin walled steel Thick walled steel Concrete
Glass reinforced plastics - Reinforced concrete
be used when installing drainage depending
on its rigidsemi-rigid and flexible forms
(summarised in Figure 3)
Where drainage pipes have less than 600-
1200mm of backfill cover and depending on
the type of surface (wearing course) of the
soil provision should be made to protect the
pipe due to movement of the surface This
can be done by installing a concrete slab
over the top of the bedding to the pipe with
a 75mm thick layer of flexible filler material
between its soffi t and the granular fill thatsurrounds the drain pipe (Figure 4)
S e m i - r i g i d a
n d r i g i d p i p e s
F l e
x i b l e p i p e s
Selected fill with no timber
frozen material vegetation
lumps of clay gt100mm
and stones gt40mm
Granular material with
5-40mm sized aggregate
depending on pipe size
Selected or granular fill
with no stones gt40mm
lt600-1200mm of backfill
75mm thick
compressible material
Granular fill surround
Class descriptions
B Used for all conditions
D Can only be used if
trench is made by hand
trimming by shovel
F Used for all conditions
The joints must have 45deg of
spread in the granular fill
N Used when hand
trimming by shovel
is not possible
983123 Figure 2Flexible and rigid drainage pipe
behaviour when subjected to surcharge
983123 Figure 3Bedding details for drainage pipes
Drain pipe
300mm bearing to slab
on original ground
Concrete slab
983123 Figure 4Section through shallow
drain pipe protection detail
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 34
Note 34 Level 1
991290
February 2014
TheStructuralEngineer22
Technical Guidance Note
Technical
Anti-vermin
infiltration sheets
Lintels over opening
in structure
Compressible
sealant to prevent
entry of gas
It is also possible to cast drainage within raft
foundations with the aim of simplifying their
installation and integrating them into the sub-
structure
The precise amount of cover required todrainage pipes is provided in Tables 8-10 of
Approved Document H1
The material contained in the backfill must
be free of large stones and bricks in order
to minimise the risk of these large objects
impacting the drainage pipe and damaging it
as the backfill is laid on top of the pipe
Drainage pipe interactions with str ucturesTypically structures are relatively rigidstiff
when compared to the soil they are founded
on Clearly this is not the case for rock anddense gravels However where the soil
can move relative to the structure so do
the drain pipes within it Where such pipes
interface with the structure of a building care
needs to be taken to ensure that flexibility
of the drainage system is maintained This
is typically achieved through two different
methods
The first is the use of rocker pipes These are
short length unique pipes typically 600mm
long that allow connecting drainage pipes
to rotate around the structural penetration
without breaking their seal and thus maintain
their integrity (Figure 5)
The second form of detail isolates the
structure away from the drainage pipe
by creating a void within the structure to
allow passage of the pipe If this solution
is adopted provision must be made to seal
the structure around the pipe to avoid the
passage of gasses into the structure (Figure
6)
983123 Figure 5Rocker pipe detail 983123 Figure 6
Section through structuralisolation from drain pipe detail
When pipes are passing through basement
walls a puddle-flange is required to prevent
water ingress into the basement due to the
penetration through it
Most drainage interface solutions with suband super-structure elements are expensive
and diffi cult to construct It is therefore
advisable to avoid the need to have such
details by planning the development of the
below ground drainage system so that it is
sympathetic to the structure and vice-versa
TestingOnce a drainage system has been installed
it needs to be tested BS 80001989
Workmanship on building sites mdashPart 14
Code of practice for below ground drainage
provides guidance on the extent and
methodology of testing that is required ofall newly installed below ground drainage
systems in the UK There are two forms of
test air based and water based
Clause 5143 of BS 8000 Part 14 describes
how the water base test is applied It explains
the eight elements of the test that must
be adhered to in order for it to be valid In
summary the test pushes water through the
drainage system with a 15m head of pressure
The drains are left in this state for two hours
whereupon the head of water is monitored
to see if there has been any leakage Some
leakage the calculation of which is based on
the diameter of the pipe and its overall length
is allowed
Clause 5144 of BS 8000 Part 14 explains
the air based test procedure for below
ground drainage This testing system
requires the use of a manometer to provide
air pressure to the drainage system that has
been temporarily plugged The air pressure
is measured over a period of five minutes to
determine how much leakage there is within
the system
Maintenance of drainsThe primary method of access to drains is
via manholes deep chambers usually madeof precast concrete or masonry (Figure 7)
These are installed where there are junctions
changes in direction andor gradient and
increases in pipe size
There are other less intrusive methods of
providing access to drainage A lsquorodding
eyersquo is a pipe that extends to the surface
that allows the drain to be cleaned using a
specialist tool Access fittings and inspection
chambers are small surface mounted units
that allow easy maintenance of the drainage
pipes they are fixed into
Pest controlVermin infestation is a continual problem with
drainage systems but it can be managed
by adopting simple details that reduce the
risk of it occurring The sealing of inspection
chambers is one method that prevents vermin
from entering the drainage system These are
chambers that have access covers within them
rather than over an open channel Anti-climbing
devices within the drain pipes also prevent the
passage of vermin These can be fins or one-
way valves that are placed into the direction of
the flow of waterwaste within the drain
Drains that are no longer required should
either be removed or filledplugged with
concrete to ensure they do not provide a
means of access for vermin into the new
drainage system
Plastic or metal gratings should also be
installed where there are gullies connecting
to the drainage system for surface water
drainage to prevent vermin gaining access
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 44
wwwthestructuralengineerorg
23
Applied practice
BS EN 7522008 Drain and Sewer Systems
Outside Buildings
BS 80001989 Workmanship on building
sites - Part 14 Code of practice for below
ground drainage
BS EN 92952010 Guide to the structural
design of buried pipelines
Approved Document H12010 Drainage and
Waste Disposal in the Building Regulations
for England
Glossary and
further reading
Adopted drainage ndash a system that is
connected to a public sewer
Bedding ndash material that is laid under and
around the drain pipe as a founding material
Benching ndash open channels formed within
This year the Kenneth Severn Award question has been set by 2014 Institution PresidentNick Russell Those aged 28 years or under are invited to answer the following
TRAINING ENGINEERS IS A PARTNERSHIP BETWEEN ACADEMIA AND INDUSTRY HOW COULD LINKS BETWEEN THESE BESTRENGTHENED FOR THE BENEFIT OF THE PROFESSION
To enter please submit your answer in the form of
a written paper entitled ldquoTraining engineers is a
partnership between academia and industry How
could links between these be strengthened for the
editorialistructeorg
Your paper should be a maximum of 1500 words
and may include relevant imagery that supplementsyour answer
The judges will be looking for originality value to
the structural engineering profession and clarity
of presentation
Closing date for entries is Friday 28 February 2014
The winning author will receive
The prestigious Kenneth Severn Diploma
A cash prize of pound500
The winning paper will be
Considered for publication in The Structural
Engineer
Entrants must be 28 years of age or under on
1 January 2014
Entry is NOT restricted to members of the Institution
Please ensure that you include your name date of
birth and full contact details with your submission
Registered with the Charity Commission for England and Wales No 233392 and in Scotland No SC038263
2014Nick Russell
BSc(Hons) CEng FIStructE FICE MCMI
Institution President 2014
CMIICE
Eurocode 0
Web resources
The Institution of Structural Engineers library
wwwistructeorgresources-centrelibrary
joints that allow for large amounts of
articulation at its ends to ensure flexibility of
the drainage pipe system
Rodding eye ndash surface mounted
cleaning point for below ground drainagesystems
Further ReadingPitman P (2001) External Works Roads and
Drainage A practical guide Boca Raton FL
CRC Press (Taylor amp Francis)
Butler D and Davies J (2010) Urban Drainage
(3rd ed) Boca Raton FL CRC Press (Taylor
amp Francis)
Scottish Water (2011) Sewers for Scotland
Consultation Report (2nd ed) [Online]
Available at wwwscottishpowercouk(Accessed January 2014)
inspection chambers and manholes to
maintain the flow of water and waste
Private drainage ndash a system that is not
connected to a public sewer
Rocker pipe ndash a short pipe with unique
983118 Figure 7Section through a typical precast
concrete manhole
Rodding
eye inlet
Benching
Precast
concretering
manhole
shaft
Drain
pipe
![Page 3: 1-34 Introduction to Below Ground Drainage](https://reader036.vdocuments.site/reader036/viewer/2022082901/5695d3f11a28ab9b029fb76a/html5/thumbnails/3.jpg)
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 34
Note 34 Level 1
991290
February 2014
TheStructuralEngineer22
Technical Guidance Note
Technical
Anti-vermin
infiltration sheets
Lintels over opening
in structure
Compressible
sealant to prevent
entry of gas
It is also possible to cast drainage within raft
foundations with the aim of simplifying their
installation and integrating them into the sub-
structure
The precise amount of cover required todrainage pipes is provided in Tables 8-10 of
Approved Document H1
The material contained in the backfill must
be free of large stones and bricks in order
to minimise the risk of these large objects
impacting the drainage pipe and damaging it
as the backfill is laid on top of the pipe
Drainage pipe interactions with str ucturesTypically structures are relatively rigidstiff
when compared to the soil they are founded
on Clearly this is not the case for rock anddense gravels However where the soil
can move relative to the structure so do
the drain pipes within it Where such pipes
interface with the structure of a building care
needs to be taken to ensure that flexibility
of the drainage system is maintained This
is typically achieved through two different
methods
The first is the use of rocker pipes These are
short length unique pipes typically 600mm
long that allow connecting drainage pipes
to rotate around the structural penetration
without breaking their seal and thus maintain
their integrity (Figure 5)
The second form of detail isolates the
structure away from the drainage pipe
by creating a void within the structure to
allow passage of the pipe If this solution
is adopted provision must be made to seal
the structure around the pipe to avoid the
passage of gasses into the structure (Figure
6)
983123 Figure 5Rocker pipe detail 983123 Figure 6
Section through structuralisolation from drain pipe detail
When pipes are passing through basement
walls a puddle-flange is required to prevent
water ingress into the basement due to the
penetration through it
Most drainage interface solutions with suband super-structure elements are expensive
and diffi cult to construct It is therefore
advisable to avoid the need to have such
details by planning the development of the
below ground drainage system so that it is
sympathetic to the structure and vice-versa
TestingOnce a drainage system has been installed
it needs to be tested BS 80001989
Workmanship on building sites mdashPart 14
Code of practice for below ground drainage
provides guidance on the extent and
methodology of testing that is required ofall newly installed below ground drainage
systems in the UK There are two forms of
test air based and water based
Clause 5143 of BS 8000 Part 14 describes
how the water base test is applied It explains
the eight elements of the test that must
be adhered to in order for it to be valid In
summary the test pushes water through the
drainage system with a 15m head of pressure
The drains are left in this state for two hours
whereupon the head of water is monitored
to see if there has been any leakage Some
leakage the calculation of which is based on
the diameter of the pipe and its overall length
is allowed
Clause 5144 of BS 8000 Part 14 explains
the air based test procedure for below
ground drainage This testing system
requires the use of a manometer to provide
air pressure to the drainage system that has
been temporarily plugged The air pressure
is measured over a period of five minutes to
determine how much leakage there is within
the system
Maintenance of drainsThe primary method of access to drains is
via manholes deep chambers usually madeof precast concrete or masonry (Figure 7)
These are installed where there are junctions
changes in direction andor gradient and
increases in pipe size
There are other less intrusive methods of
providing access to drainage A lsquorodding
eyersquo is a pipe that extends to the surface
that allows the drain to be cleaned using a
specialist tool Access fittings and inspection
chambers are small surface mounted units
that allow easy maintenance of the drainage
pipes they are fixed into
Pest controlVermin infestation is a continual problem with
drainage systems but it can be managed
by adopting simple details that reduce the
risk of it occurring The sealing of inspection
chambers is one method that prevents vermin
from entering the drainage system These are
chambers that have access covers within them
rather than over an open channel Anti-climbing
devices within the drain pipes also prevent the
passage of vermin These can be fins or one-
way valves that are placed into the direction of
the flow of waterwaste within the drain
Drains that are no longer required should
either be removed or filledplugged with
concrete to ensure they do not provide a
means of access for vermin into the new
drainage system
Plastic or metal gratings should also be
installed where there are gullies connecting
to the drainage system for surface water
drainage to prevent vermin gaining access
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 44
wwwthestructuralengineerorg
23
Applied practice
BS EN 7522008 Drain and Sewer Systems
Outside Buildings
BS 80001989 Workmanship on building
sites - Part 14 Code of practice for below
ground drainage
BS EN 92952010 Guide to the structural
design of buried pipelines
Approved Document H12010 Drainage and
Waste Disposal in the Building Regulations
for England
Glossary and
further reading
Adopted drainage ndash a system that is
connected to a public sewer
Bedding ndash material that is laid under and
around the drain pipe as a founding material
Benching ndash open channels formed within
This year the Kenneth Severn Award question has been set by 2014 Institution PresidentNick Russell Those aged 28 years or under are invited to answer the following
TRAINING ENGINEERS IS A PARTNERSHIP BETWEEN ACADEMIA AND INDUSTRY HOW COULD LINKS BETWEEN THESE BESTRENGTHENED FOR THE BENEFIT OF THE PROFESSION
To enter please submit your answer in the form of
a written paper entitled ldquoTraining engineers is a
partnership between academia and industry How
could links between these be strengthened for the
editorialistructeorg
Your paper should be a maximum of 1500 words
and may include relevant imagery that supplementsyour answer
The judges will be looking for originality value to
the structural engineering profession and clarity
of presentation
Closing date for entries is Friday 28 February 2014
The winning author will receive
The prestigious Kenneth Severn Diploma
A cash prize of pound500
The winning paper will be
Considered for publication in The Structural
Engineer
Entrants must be 28 years of age or under on
1 January 2014
Entry is NOT restricted to members of the Institution
Please ensure that you include your name date of
birth and full contact details with your submission
Registered with the Charity Commission for England and Wales No 233392 and in Scotland No SC038263
2014Nick Russell
BSc(Hons) CEng FIStructE FICE MCMI
Institution President 2014
CMIICE
Eurocode 0
Web resources
The Institution of Structural Engineers library
wwwistructeorgresources-centrelibrary
joints that allow for large amounts of
articulation at its ends to ensure flexibility of
the drainage pipe system
Rodding eye ndash surface mounted
cleaning point for below ground drainagesystems
Further ReadingPitman P (2001) External Works Roads and
Drainage A practical guide Boca Raton FL
CRC Press (Taylor amp Francis)
Butler D and Davies J (2010) Urban Drainage
(3rd ed) Boca Raton FL CRC Press (Taylor
amp Francis)
Scottish Water (2011) Sewers for Scotland
Consultation Report (2nd ed) [Online]
Available at wwwscottishpowercouk(Accessed January 2014)
inspection chambers and manholes to
maintain the flow of water and waste
Private drainage ndash a system that is not
connected to a public sewer
Rocker pipe ndash a short pipe with unique
983118 Figure 7Section through a typical precast
concrete manhole
Rodding
eye inlet
Benching
Precast
concretering
manhole
shaft
Drain
pipe
![Page 4: 1-34 Introduction to Below Ground Drainage](https://reader036.vdocuments.site/reader036/viewer/2022082901/5695d3f11a28ab9b029fb76a/html5/thumbnails/4.jpg)
7212019 1-34 Introduction to Below Ground Drainage
httpslidepdfcomreaderfull1-34-introduction-to-below-ground-drainage 44
wwwthestructuralengineerorg
23
Applied practice
BS EN 7522008 Drain and Sewer Systems
Outside Buildings
BS 80001989 Workmanship on building
sites - Part 14 Code of practice for below
ground drainage
BS EN 92952010 Guide to the structural
design of buried pipelines
Approved Document H12010 Drainage and
Waste Disposal in the Building Regulations
for England
Glossary and
further reading
Adopted drainage ndash a system that is
connected to a public sewer
Bedding ndash material that is laid under and
around the drain pipe as a founding material
Benching ndash open channels formed within
This year the Kenneth Severn Award question has been set by 2014 Institution PresidentNick Russell Those aged 28 years or under are invited to answer the following
TRAINING ENGINEERS IS A PARTNERSHIP BETWEEN ACADEMIA AND INDUSTRY HOW COULD LINKS BETWEEN THESE BESTRENGTHENED FOR THE BENEFIT OF THE PROFESSION
To enter please submit your answer in the form of
a written paper entitled ldquoTraining engineers is a
partnership between academia and industry How
could links between these be strengthened for the
editorialistructeorg
Your paper should be a maximum of 1500 words
and may include relevant imagery that supplementsyour answer
The judges will be looking for originality value to
the structural engineering profession and clarity
of presentation
Closing date for entries is Friday 28 February 2014
The winning author will receive
The prestigious Kenneth Severn Diploma
A cash prize of pound500
The winning paper will be
Considered for publication in The Structural
Engineer
Entrants must be 28 years of age or under on
1 January 2014
Entry is NOT restricted to members of the Institution
Please ensure that you include your name date of
birth and full contact details with your submission
Registered with the Charity Commission for England and Wales No 233392 and in Scotland No SC038263
2014Nick Russell
BSc(Hons) CEng FIStructE FICE MCMI
Institution President 2014
CMIICE
Eurocode 0
Web resources
The Institution of Structural Engineers library
wwwistructeorgresources-centrelibrary
joints that allow for large amounts of
articulation at its ends to ensure flexibility of
the drainage pipe system
Rodding eye ndash surface mounted
cleaning point for below ground drainagesystems
Further ReadingPitman P (2001) External Works Roads and
Drainage A practical guide Boca Raton FL
CRC Press (Taylor amp Francis)
Butler D and Davies J (2010) Urban Drainage
(3rd ed) Boca Raton FL CRC Press (Taylor
amp Francis)
Scottish Water (2011) Sewers for Scotland
Consultation Report (2nd ed) [Online]
Available at wwwscottishpowercouk(Accessed January 2014)
inspection chambers and manholes to
maintain the flow of water and waste
Private drainage ndash a system that is not
connected to a public sewer
Rocker pipe ndash a short pipe with unique
983118 Figure 7Section through a typical precast
concrete manhole
Rodding
eye inlet
Benching
Precast
concretering
manhole
shaft
Drain
pipe