1-33 retaining wall construction
TRANSCRIPT
![Page 1: 1-33 Retaining Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022082621/5695d3f21a28ab9b029fb8dc/html5/thumbnails/1.jpg)
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 15
TheStructuralEngineer42
Technical Guidance Note
Technical
October 2013
Note 33 Level 1
991290
Retaining walls can be grouped into three
categories gravity embedded and hybrid
They all perform the function of supporting
a material which is typically soil at an angle
that exceeds the angle of repose Each type
has unique properties making them ideally
suited to specific situations
Gravity retaining walls
A gravity retaining wall relies upon the
friction between it and the founding
material together with the wallrsquos self-weight
to resist sliding and overturning They can
be formed from masonry concrete or
reinforced soil and are typically used when
a shallower depth of excavation needs to be
retained They are normally between 1-3m
and are constructed to make way for level
ground such as a railway siding (Figure 1)
Retaining wall constructionIntroduction
Retaining walls have been used for thousands of years whether in the
construction of terraced fields on a steep slope or a railway cutting through
a hill side a retaining wall is used in some form or another
This Technical Guidance Note is a description to the various forms
of retaining walls that are currently used It is primarily concerned with
structures that retain soil although many of the aspects described can
be translated to retaining other materials such as grain sand and liquids
The water table will have design implications on the wall the pressure of
which can be alleviated by providing drainage and weep holes depending
on the soil conditions The aim of this note is to provide you with suffi cientfamiliarity of the various types of retaining wall so that when you encounter
them or are developing a retaining wall solution you will know what options
are available
983127 Retaining walls
983127 Applied practice
983127 Further reading
983127 Web resources
ICONLEGEND
Retaining wallsEmbedded retaining walls
Embedded retaining walls rely on being
installed into the soil to below the depth of
excavation Once the wall is in place within
the ground soil is excavated from its front
to a defined depth based on the bending
capacity of the retaining wall and the depth
of its embedment into the soil Embedded
retaining walls rely on the passive resistance
of the soil in front of them along with the
shear and bending capacity of the wall itself
to keep it in place They are most often
used for basements and other excavations
cut into previously level ground They are
suitable for very deep excavations ie in
excess of 10m andor where the site is
restricted eg adjacent site boundaries
or existing sub-structures (Figure 2)
For excavations in excess of 4-6m deep
propping to the embedded wall is usually
necessary to control wall deflections and
prevent excessive depths of embedment
Hybrid retaining walls
Hybrid retaining walls (Figure 3) combine
the features of both gravity and embedded
forms They rely on shear and bending
resistance of the wall and its base which
may or may not be fixed into position by
piles They are typically used where ground
levels need to be raised eg where there
are poor soil conditions to the extent that a
gravity retaining wall solution is not viable
Gravity retaining wallsGravity walls come in many different forms
all of which follow the principles described
in Fig 1 ie supporting lateral forces via
their resistance to sliding and overturning
They are often constructed using a backfill
method where the wall is built with the soil
it is to retain being placed against it Gravity
retaining walls can be split into three sub-
groups masonry reinforced concrete and
soil reinforcement
983123 Figure 1Concept
diagram of gravitybased retaining wall
983123 Figure 2Concept
diagram ofembedded retainingwall with pivot point
983123 Figure 3Concept
diagram of hybridretaining wall
Active
ActivePassive
Passive
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 25
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 35
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 45
wwwthestructuralengineerorg
45
Contiguous bored piled walls
Contiguous bored piled walls also referred
to as lsquocontigrsquo are dug and cast into the
ground with a small gap of 50-150mm
between each pile The presence of
this gap makes contiguous piled wallsunsuitable to retain granular soils like
sand and gravel as such soil types fall
through the gaps between the piles (Figure
10) Similarly they cannot retain water
and can only be placed in areas above
the water table or where de-watering is
being employed Where they are used
in permanent conditions a facing wall is
needed in front of contiguous piled walls
due to the gaps between each pile
Secant bored piled walls
Secant bored piled walls are a variant of
the contiguous piled wall with the majordifference being that there is no gap
between piles Instead the piles are divided
into primary and secondary (historically
referred to as female and male respectively)
The primary piles are installed first and the
bored secondary piles overlap their primary
neighbours (shown in green in Figure 11)
This creates a continuous wall that can resist
water penetration when carefully detailed
and executed Secant bored piled walls
come in three varieties that are dependent
on the characteristic compressive strength
of the primary bored pile (Table 1) Secant
bored piled walls can be installed into almost
any type of soil and can be placed where
there is a high water table
King postSoldier piled walls
King post or Soldier piled walls consist
of a series of steel posts that are either
driven into the ground or cast into place
within an excavated hole The posts are
installed 1-3m apart and the gap between
them is filled with spanning panels which
are typically precast concrete segments
(Figure 12) These are installed as the soil in
front of the retaining wall is removed They
are typically used in clay and granular soils
provided the water table is below the extent
of the excavation
Diaphragm walls
Diaphragm walls are a series of interlocking
reinforced concrete panels that have been
cast in situ by excavating a segment of
soil and replacing it with a fluid (typically
bentonite) A reinforcement cage is then
inserted and concrete is poured in via a
tremie pipe The concrete displaces the
bentonite as it is poured Diaphragm walls
can be 600-1500mm thick with each panel
being typically 22-8m wide They can retain
significantly more soil than most other wallswith a depth of 120m being possible due to
Table 1 Types of primary piles in secant bored piled wall
Secantprimarypile type
DescriptionCharacteristiccompression
strength (Nmm2)
Reinforcementpresent
Soft Bentonite cement 1-3 No
FirmConcrete with an admixture that
delays the development of strengthin the pile during drilling
10-20 No
HardFull strength concrete often with an
admixture that delays the developmentof strength in the pile during drilling
25-60Can be
installed inprimary pile
There is a risk of encountering any reinforcement in the primary pile when drilling
the secondary piles so it is preferable to avoid reinforcing primary piles
their ability to withstand very high lateral
loads They can be installed into almost any
type of soil and can resist water pressure
provided water bar seals are installed
across each segment (Figure 13)
Hybrid retaining wallsThe archetypal hybrid retaining wall is the
unpropped cantilever that is founded on pile
foundations Hybrid walls can be installed in
most soils and can retain water pressures
provided appropriate drainage and water
proofing measures are installed (Figure 14)
Criteria for retaining wall selectionThe primary criterion for the selection of
a retaining wall is the height required Of
secondary concern are space restrictions
as they will impact on the preferred
construction method and can preclude
certain types of walls As an example
a 2m high retaining wall adjacent to a
rural highway would likely be a gravity or
hybrid wall as it is not very high and space
restrictions are not likely to be a concern
A 4m deep basement construction within
a city centre however would most likely
require an embedded wall due to its height
and limited site access
Other criteria that should be considered
include stiffness of the wall to prevent
movement during its design life and
required water resistance which is
of particular relevance in basement
construction Water proofing construction
method and materials all have an impact on
cost and programme and should therefore
be taken into consideration
For further advice on selecting an
appropriate retaining wall solution see
Table 82 in the Manual for the geotechnical
design of structures to Eurocode 7
983123 Figure 13Diaphragm wall
983123 Figure 14Hybrid retaining wall
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 55
TheStructuralEngineer46
Technical Guidance Note
Technical
October 2013
Note 33 Level 1
991290
Eurocode 0
Web resources
The British Geotechnical Association
httpbgacityacuk
Eurocode 0
Applied practice
BS EN 1992-1-1 Eurocode 2 Design of
Concrete Structures - Part 1-1 GeneralRules for Buildings
BS EN 1992-1-1 UK National Annex to
Eurocode 2 Design of Concrete
Structures - Part 1-1 General Rules
for Buildings
BS EN 1997-1 Eurocode 7 Geotechnical
Design - Part 1-1 General Rules
BS EN 1997-1 UK National Annex to
Eurocode 7 Geotechnical Design - Part 1-1
General Rules
BS EN 15362010 - Execution of special
geotechnical work ndash bored piles
BS EN 15382010 - Execution of special
geotechnical work ndash diaphragm walls
BS EN 120631999 - Execution of special
geotechnical work ndash sheet pile walls
Glossary andfurther reading
Angle of repose -The deepest angle
of slope relative to a horizontal surface agranular material such as soil is
resting upon
Bentonite - A form of absorbent clay that
is used during the construction of some
forms of retaining wall
Caisson - A water-tight retaining sub-
structure typically used for the construction
of marine engineering works such as piers
Tremie pipe - Method of placing concrete
within a liquid or highly viscous material that
relies on the delivery pipe remaining in thefreshly placed concrete so that it displaces
the liquid
Unsupported height - The extent of a
retaining wall that has no propping
Water table - The depth at which ground
water is located
Technical Lecture SeriesConferences amp Seminars Annual Institution Events Special Interest Series A series of lectures organised in partnership by
the Institution and other leading organisations
Registration is required in advance by visiting the events section of the Institution website wwwistructeorg and following the
instructions provided Registration will close Friday 11 October Space is limited and latecomers will only be admitted to the
eventsistructeorg
Pai Lin Li Lecture
Institution members wishing to spend 4 ndash 6
weeks outside their own country studying
unrivalled opportunity to sample the technical
economic social and political conditions in
another country and to examine how these
various factors affect the practise of structural
engineering
winners John Orr and Katie Symons who will
Form an adventure in concrete
and brick
Form active design can facilitate architecturally
construction
John Orr
PhD MEng(Hons)
John Orr is a lecturer in
sustainable construction at
the University of Bath UK He
degrees from the same institution in 2009 and 2012
respectively His research interests include the design
of concrete structures using fabric formwork and
the shear behaviour and computational modelling of
concrete
International perspectives on Life Cycle
Assessment of structural materialsparticularly timber lessons to be learned
from Australasia
Australia and New Zealand in 2013 examining the
materials particularly with respect to embodied
materials particularly timber is also explored
Katie Symons MEng MA
(Cantab) MIStructE MICE CEng
Katie Symons has a keen
interest in the sustainability of
the built environment especially
the embodied energy andcarbon of buildings She presented her research
undertaken during a secondment to the University of
Society conference in Sydney in July 2012 She
has had journal papers published on the subject of
evaluating embodied energy and carbon
Thursday 17 October
Registration from 1730
Lecture at 1800
International HQ
Further ReadingThe Institution of Structural Engineers
(2013) Manual for the geotechnical design
of structures to Eurocode 7 London The
Institution of Structural Engineers
The Institution of Civil Engineers (2012) ICE
manual of geotechnical engineering London
Thomas Telford
The Institution of Structural Engineers
(2004) Design and construction of deep
basements including cut and cover structures
London The Institution of Structural Engineers
CIRIA (2000) Publication C516 Modular
gravity retaining walls design guidance
London CIRIA
CIRIA (2003) Publication C580 EmbeddedRetaining Walls London CIRIA
![Page 2: 1-33 Retaining Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022082621/5695d3f21a28ab9b029fb8dc/html5/thumbnails/2.jpg)
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 25
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 35
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 45
wwwthestructuralengineerorg
45
Contiguous bored piled walls
Contiguous bored piled walls also referred
to as lsquocontigrsquo are dug and cast into the
ground with a small gap of 50-150mm
between each pile The presence of
this gap makes contiguous piled wallsunsuitable to retain granular soils like
sand and gravel as such soil types fall
through the gaps between the piles (Figure
10) Similarly they cannot retain water
and can only be placed in areas above
the water table or where de-watering is
being employed Where they are used
in permanent conditions a facing wall is
needed in front of contiguous piled walls
due to the gaps between each pile
Secant bored piled walls
Secant bored piled walls are a variant of
the contiguous piled wall with the majordifference being that there is no gap
between piles Instead the piles are divided
into primary and secondary (historically
referred to as female and male respectively)
The primary piles are installed first and the
bored secondary piles overlap their primary
neighbours (shown in green in Figure 11)
This creates a continuous wall that can resist
water penetration when carefully detailed
and executed Secant bored piled walls
come in three varieties that are dependent
on the characteristic compressive strength
of the primary bored pile (Table 1) Secant
bored piled walls can be installed into almost
any type of soil and can be placed where
there is a high water table
King postSoldier piled walls
King post or Soldier piled walls consist
of a series of steel posts that are either
driven into the ground or cast into place
within an excavated hole The posts are
installed 1-3m apart and the gap between
them is filled with spanning panels which
are typically precast concrete segments
(Figure 12) These are installed as the soil in
front of the retaining wall is removed They
are typically used in clay and granular soils
provided the water table is below the extent
of the excavation
Diaphragm walls
Diaphragm walls are a series of interlocking
reinforced concrete panels that have been
cast in situ by excavating a segment of
soil and replacing it with a fluid (typically
bentonite) A reinforcement cage is then
inserted and concrete is poured in via a
tremie pipe The concrete displaces the
bentonite as it is poured Diaphragm walls
can be 600-1500mm thick with each panel
being typically 22-8m wide They can retain
significantly more soil than most other wallswith a depth of 120m being possible due to
Table 1 Types of primary piles in secant bored piled wall
Secantprimarypile type
DescriptionCharacteristiccompression
strength (Nmm2)
Reinforcementpresent
Soft Bentonite cement 1-3 No
FirmConcrete with an admixture that
delays the development of strengthin the pile during drilling
10-20 No
HardFull strength concrete often with an
admixture that delays the developmentof strength in the pile during drilling
25-60Can be
installed inprimary pile
There is a risk of encountering any reinforcement in the primary pile when drilling
the secondary piles so it is preferable to avoid reinforcing primary piles
their ability to withstand very high lateral
loads They can be installed into almost any
type of soil and can resist water pressure
provided water bar seals are installed
across each segment (Figure 13)
Hybrid retaining wallsThe archetypal hybrid retaining wall is the
unpropped cantilever that is founded on pile
foundations Hybrid walls can be installed in
most soils and can retain water pressures
provided appropriate drainage and water
proofing measures are installed (Figure 14)
Criteria for retaining wall selectionThe primary criterion for the selection of
a retaining wall is the height required Of
secondary concern are space restrictions
as they will impact on the preferred
construction method and can preclude
certain types of walls As an example
a 2m high retaining wall adjacent to a
rural highway would likely be a gravity or
hybrid wall as it is not very high and space
restrictions are not likely to be a concern
A 4m deep basement construction within
a city centre however would most likely
require an embedded wall due to its height
and limited site access
Other criteria that should be considered
include stiffness of the wall to prevent
movement during its design life and
required water resistance which is
of particular relevance in basement
construction Water proofing construction
method and materials all have an impact on
cost and programme and should therefore
be taken into consideration
For further advice on selecting an
appropriate retaining wall solution see
Table 82 in the Manual for the geotechnical
design of structures to Eurocode 7
983123 Figure 13Diaphragm wall
983123 Figure 14Hybrid retaining wall
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 55
TheStructuralEngineer46
Technical Guidance Note
Technical
October 2013
Note 33 Level 1
991290
Eurocode 0
Web resources
The British Geotechnical Association
httpbgacityacuk
Eurocode 0
Applied practice
BS EN 1992-1-1 Eurocode 2 Design of
Concrete Structures - Part 1-1 GeneralRules for Buildings
BS EN 1992-1-1 UK National Annex to
Eurocode 2 Design of Concrete
Structures - Part 1-1 General Rules
for Buildings
BS EN 1997-1 Eurocode 7 Geotechnical
Design - Part 1-1 General Rules
BS EN 1997-1 UK National Annex to
Eurocode 7 Geotechnical Design - Part 1-1
General Rules
BS EN 15362010 - Execution of special
geotechnical work ndash bored piles
BS EN 15382010 - Execution of special
geotechnical work ndash diaphragm walls
BS EN 120631999 - Execution of special
geotechnical work ndash sheet pile walls
Glossary andfurther reading
Angle of repose -The deepest angle
of slope relative to a horizontal surface agranular material such as soil is
resting upon
Bentonite - A form of absorbent clay that
is used during the construction of some
forms of retaining wall
Caisson - A water-tight retaining sub-
structure typically used for the construction
of marine engineering works such as piers
Tremie pipe - Method of placing concrete
within a liquid or highly viscous material that
relies on the delivery pipe remaining in thefreshly placed concrete so that it displaces
the liquid
Unsupported height - The extent of a
retaining wall that has no propping
Water table - The depth at which ground
water is located
Technical Lecture SeriesConferences amp Seminars Annual Institution Events Special Interest Series A series of lectures organised in partnership by
the Institution and other leading organisations
Registration is required in advance by visiting the events section of the Institution website wwwistructeorg and following the
instructions provided Registration will close Friday 11 October Space is limited and latecomers will only be admitted to the
eventsistructeorg
Pai Lin Li Lecture
Institution members wishing to spend 4 ndash 6
weeks outside their own country studying
unrivalled opportunity to sample the technical
economic social and political conditions in
another country and to examine how these
various factors affect the practise of structural
engineering
winners John Orr and Katie Symons who will
Form an adventure in concrete
and brick
Form active design can facilitate architecturally
construction
John Orr
PhD MEng(Hons)
John Orr is a lecturer in
sustainable construction at
the University of Bath UK He
degrees from the same institution in 2009 and 2012
respectively His research interests include the design
of concrete structures using fabric formwork and
the shear behaviour and computational modelling of
concrete
International perspectives on Life Cycle
Assessment of structural materialsparticularly timber lessons to be learned
from Australasia
Australia and New Zealand in 2013 examining the
materials particularly with respect to embodied
materials particularly timber is also explored
Katie Symons MEng MA
(Cantab) MIStructE MICE CEng
Katie Symons has a keen
interest in the sustainability of
the built environment especially
the embodied energy andcarbon of buildings She presented her research
undertaken during a secondment to the University of
Society conference in Sydney in July 2012 She
has had journal papers published on the subject of
evaluating embodied energy and carbon
Thursday 17 October
Registration from 1730
Lecture at 1800
International HQ
Further ReadingThe Institution of Structural Engineers
(2013) Manual for the geotechnical design
of structures to Eurocode 7 London The
Institution of Structural Engineers
The Institution of Civil Engineers (2012) ICE
manual of geotechnical engineering London
Thomas Telford
The Institution of Structural Engineers
(2004) Design and construction of deep
basements including cut and cover structures
London The Institution of Structural Engineers
CIRIA (2000) Publication C516 Modular
gravity retaining walls design guidance
London CIRIA
CIRIA (2003) Publication C580 EmbeddedRetaining Walls London CIRIA
![Page 3: 1-33 Retaining Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022082621/5695d3f21a28ab9b029fb8dc/html5/thumbnails/3.jpg)
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 35
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 45
wwwthestructuralengineerorg
45
Contiguous bored piled walls
Contiguous bored piled walls also referred
to as lsquocontigrsquo are dug and cast into the
ground with a small gap of 50-150mm
between each pile The presence of
this gap makes contiguous piled wallsunsuitable to retain granular soils like
sand and gravel as such soil types fall
through the gaps between the piles (Figure
10) Similarly they cannot retain water
and can only be placed in areas above
the water table or where de-watering is
being employed Where they are used
in permanent conditions a facing wall is
needed in front of contiguous piled walls
due to the gaps between each pile
Secant bored piled walls
Secant bored piled walls are a variant of
the contiguous piled wall with the majordifference being that there is no gap
between piles Instead the piles are divided
into primary and secondary (historically
referred to as female and male respectively)
The primary piles are installed first and the
bored secondary piles overlap their primary
neighbours (shown in green in Figure 11)
This creates a continuous wall that can resist
water penetration when carefully detailed
and executed Secant bored piled walls
come in three varieties that are dependent
on the characteristic compressive strength
of the primary bored pile (Table 1) Secant
bored piled walls can be installed into almost
any type of soil and can be placed where
there is a high water table
King postSoldier piled walls
King post or Soldier piled walls consist
of a series of steel posts that are either
driven into the ground or cast into place
within an excavated hole The posts are
installed 1-3m apart and the gap between
them is filled with spanning panels which
are typically precast concrete segments
(Figure 12) These are installed as the soil in
front of the retaining wall is removed They
are typically used in clay and granular soils
provided the water table is below the extent
of the excavation
Diaphragm walls
Diaphragm walls are a series of interlocking
reinforced concrete panels that have been
cast in situ by excavating a segment of
soil and replacing it with a fluid (typically
bentonite) A reinforcement cage is then
inserted and concrete is poured in via a
tremie pipe The concrete displaces the
bentonite as it is poured Diaphragm walls
can be 600-1500mm thick with each panel
being typically 22-8m wide They can retain
significantly more soil than most other wallswith a depth of 120m being possible due to
Table 1 Types of primary piles in secant bored piled wall
Secantprimarypile type
DescriptionCharacteristiccompression
strength (Nmm2)
Reinforcementpresent
Soft Bentonite cement 1-3 No
FirmConcrete with an admixture that
delays the development of strengthin the pile during drilling
10-20 No
HardFull strength concrete often with an
admixture that delays the developmentof strength in the pile during drilling
25-60Can be
installed inprimary pile
There is a risk of encountering any reinforcement in the primary pile when drilling
the secondary piles so it is preferable to avoid reinforcing primary piles
their ability to withstand very high lateral
loads They can be installed into almost any
type of soil and can resist water pressure
provided water bar seals are installed
across each segment (Figure 13)
Hybrid retaining wallsThe archetypal hybrid retaining wall is the
unpropped cantilever that is founded on pile
foundations Hybrid walls can be installed in
most soils and can retain water pressures
provided appropriate drainage and water
proofing measures are installed (Figure 14)
Criteria for retaining wall selectionThe primary criterion for the selection of
a retaining wall is the height required Of
secondary concern are space restrictions
as they will impact on the preferred
construction method and can preclude
certain types of walls As an example
a 2m high retaining wall adjacent to a
rural highway would likely be a gravity or
hybrid wall as it is not very high and space
restrictions are not likely to be a concern
A 4m deep basement construction within
a city centre however would most likely
require an embedded wall due to its height
and limited site access
Other criteria that should be considered
include stiffness of the wall to prevent
movement during its design life and
required water resistance which is
of particular relevance in basement
construction Water proofing construction
method and materials all have an impact on
cost and programme and should therefore
be taken into consideration
For further advice on selecting an
appropriate retaining wall solution see
Table 82 in the Manual for the geotechnical
design of structures to Eurocode 7
983123 Figure 13Diaphragm wall
983123 Figure 14Hybrid retaining wall
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 55
TheStructuralEngineer46
Technical Guidance Note
Technical
October 2013
Note 33 Level 1
991290
Eurocode 0
Web resources
The British Geotechnical Association
httpbgacityacuk
Eurocode 0
Applied practice
BS EN 1992-1-1 Eurocode 2 Design of
Concrete Structures - Part 1-1 GeneralRules for Buildings
BS EN 1992-1-1 UK National Annex to
Eurocode 2 Design of Concrete
Structures - Part 1-1 General Rules
for Buildings
BS EN 1997-1 Eurocode 7 Geotechnical
Design - Part 1-1 General Rules
BS EN 1997-1 UK National Annex to
Eurocode 7 Geotechnical Design - Part 1-1
General Rules
BS EN 15362010 - Execution of special
geotechnical work ndash bored piles
BS EN 15382010 - Execution of special
geotechnical work ndash diaphragm walls
BS EN 120631999 - Execution of special
geotechnical work ndash sheet pile walls
Glossary andfurther reading
Angle of repose -The deepest angle
of slope relative to a horizontal surface agranular material such as soil is
resting upon
Bentonite - A form of absorbent clay that
is used during the construction of some
forms of retaining wall
Caisson - A water-tight retaining sub-
structure typically used for the construction
of marine engineering works such as piers
Tremie pipe - Method of placing concrete
within a liquid or highly viscous material that
relies on the delivery pipe remaining in thefreshly placed concrete so that it displaces
the liquid
Unsupported height - The extent of a
retaining wall that has no propping
Water table - The depth at which ground
water is located
Technical Lecture SeriesConferences amp Seminars Annual Institution Events Special Interest Series A series of lectures organised in partnership by
the Institution and other leading organisations
Registration is required in advance by visiting the events section of the Institution website wwwistructeorg and following the
instructions provided Registration will close Friday 11 October Space is limited and latecomers will only be admitted to the
eventsistructeorg
Pai Lin Li Lecture
Institution members wishing to spend 4 ndash 6
weeks outside their own country studying
unrivalled opportunity to sample the technical
economic social and political conditions in
another country and to examine how these
various factors affect the practise of structural
engineering
winners John Orr and Katie Symons who will
Form an adventure in concrete
and brick
Form active design can facilitate architecturally
construction
John Orr
PhD MEng(Hons)
John Orr is a lecturer in
sustainable construction at
the University of Bath UK He
degrees from the same institution in 2009 and 2012
respectively His research interests include the design
of concrete structures using fabric formwork and
the shear behaviour and computational modelling of
concrete
International perspectives on Life Cycle
Assessment of structural materialsparticularly timber lessons to be learned
from Australasia
Australia and New Zealand in 2013 examining the
materials particularly with respect to embodied
materials particularly timber is also explored
Katie Symons MEng MA
(Cantab) MIStructE MICE CEng
Katie Symons has a keen
interest in the sustainability of
the built environment especially
the embodied energy andcarbon of buildings She presented her research
undertaken during a secondment to the University of
Society conference in Sydney in July 2012 She
has had journal papers published on the subject of
evaluating embodied energy and carbon
Thursday 17 October
Registration from 1730
Lecture at 1800
International HQ
Further ReadingThe Institution of Structural Engineers
(2013) Manual for the geotechnical design
of structures to Eurocode 7 London The
Institution of Structural Engineers
The Institution of Civil Engineers (2012) ICE
manual of geotechnical engineering London
Thomas Telford
The Institution of Structural Engineers
(2004) Design and construction of deep
basements including cut and cover structures
London The Institution of Structural Engineers
CIRIA (2000) Publication C516 Modular
gravity retaining walls design guidance
London CIRIA
CIRIA (2003) Publication C580 EmbeddedRetaining Walls London CIRIA
![Page 4: 1-33 Retaining Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022082621/5695d3f21a28ab9b029fb8dc/html5/thumbnails/4.jpg)
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 45
wwwthestructuralengineerorg
45
Contiguous bored piled walls
Contiguous bored piled walls also referred
to as lsquocontigrsquo are dug and cast into the
ground with a small gap of 50-150mm
between each pile The presence of
this gap makes contiguous piled wallsunsuitable to retain granular soils like
sand and gravel as such soil types fall
through the gaps between the piles (Figure
10) Similarly they cannot retain water
and can only be placed in areas above
the water table or where de-watering is
being employed Where they are used
in permanent conditions a facing wall is
needed in front of contiguous piled walls
due to the gaps between each pile
Secant bored piled walls
Secant bored piled walls are a variant of
the contiguous piled wall with the majordifference being that there is no gap
between piles Instead the piles are divided
into primary and secondary (historically
referred to as female and male respectively)
The primary piles are installed first and the
bored secondary piles overlap their primary
neighbours (shown in green in Figure 11)
This creates a continuous wall that can resist
water penetration when carefully detailed
and executed Secant bored piled walls
come in three varieties that are dependent
on the characteristic compressive strength
of the primary bored pile (Table 1) Secant
bored piled walls can be installed into almost
any type of soil and can be placed where
there is a high water table
King postSoldier piled walls
King post or Soldier piled walls consist
of a series of steel posts that are either
driven into the ground or cast into place
within an excavated hole The posts are
installed 1-3m apart and the gap between
them is filled with spanning panels which
are typically precast concrete segments
(Figure 12) These are installed as the soil in
front of the retaining wall is removed They
are typically used in clay and granular soils
provided the water table is below the extent
of the excavation
Diaphragm walls
Diaphragm walls are a series of interlocking
reinforced concrete panels that have been
cast in situ by excavating a segment of
soil and replacing it with a fluid (typically
bentonite) A reinforcement cage is then
inserted and concrete is poured in via a
tremie pipe The concrete displaces the
bentonite as it is poured Diaphragm walls
can be 600-1500mm thick with each panel
being typically 22-8m wide They can retain
significantly more soil than most other wallswith a depth of 120m being possible due to
Table 1 Types of primary piles in secant bored piled wall
Secantprimarypile type
DescriptionCharacteristiccompression
strength (Nmm2)
Reinforcementpresent
Soft Bentonite cement 1-3 No
FirmConcrete with an admixture that
delays the development of strengthin the pile during drilling
10-20 No
HardFull strength concrete often with an
admixture that delays the developmentof strength in the pile during drilling
25-60Can be
installed inprimary pile
There is a risk of encountering any reinforcement in the primary pile when drilling
the secondary piles so it is preferable to avoid reinforcing primary piles
their ability to withstand very high lateral
loads They can be installed into almost any
type of soil and can resist water pressure
provided water bar seals are installed
across each segment (Figure 13)
Hybrid retaining wallsThe archetypal hybrid retaining wall is the
unpropped cantilever that is founded on pile
foundations Hybrid walls can be installed in
most soils and can retain water pressures
provided appropriate drainage and water
proofing measures are installed (Figure 14)
Criteria for retaining wall selectionThe primary criterion for the selection of
a retaining wall is the height required Of
secondary concern are space restrictions
as they will impact on the preferred
construction method and can preclude
certain types of walls As an example
a 2m high retaining wall adjacent to a
rural highway would likely be a gravity or
hybrid wall as it is not very high and space
restrictions are not likely to be a concern
A 4m deep basement construction within
a city centre however would most likely
require an embedded wall due to its height
and limited site access
Other criteria that should be considered
include stiffness of the wall to prevent
movement during its design life and
required water resistance which is
of particular relevance in basement
construction Water proofing construction
method and materials all have an impact on
cost and programme and should therefore
be taken into consideration
For further advice on selecting an
appropriate retaining wall solution see
Table 82 in the Manual for the geotechnical
design of structures to Eurocode 7
983123 Figure 13Diaphragm wall
983123 Figure 14Hybrid retaining wall
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 55
TheStructuralEngineer46
Technical Guidance Note
Technical
October 2013
Note 33 Level 1
991290
Eurocode 0
Web resources
The British Geotechnical Association
httpbgacityacuk
Eurocode 0
Applied practice
BS EN 1992-1-1 Eurocode 2 Design of
Concrete Structures - Part 1-1 GeneralRules for Buildings
BS EN 1992-1-1 UK National Annex to
Eurocode 2 Design of Concrete
Structures - Part 1-1 General Rules
for Buildings
BS EN 1997-1 Eurocode 7 Geotechnical
Design - Part 1-1 General Rules
BS EN 1997-1 UK National Annex to
Eurocode 7 Geotechnical Design - Part 1-1
General Rules
BS EN 15362010 - Execution of special
geotechnical work ndash bored piles
BS EN 15382010 - Execution of special
geotechnical work ndash diaphragm walls
BS EN 120631999 - Execution of special
geotechnical work ndash sheet pile walls
Glossary andfurther reading
Angle of repose -The deepest angle
of slope relative to a horizontal surface agranular material such as soil is
resting upon
Bentonite - A form of absorbent clay that
is used during the construction of some
forms of retaining wall
Caisson - A water-tight retaining sub-
structure typically used for the construction
of marine engineering works such as piers
Tremie pipe - Method of placing concrete
within a liquid or highly viscous material that
relies on the delivery pipe remaining in thefreshly placed concrete so that it displaces
the liquid
Unsupported height - The extent of a
retaining wall that has no propping
Water table - The depth at which ground
water is located
Technical Lecture SeriesConferences amp Seminars Annual Institution Events Special Interest Series A series of lectures organised in partnership by
the Institution and other leading organisations
Registration is required in advance by visiting the events section of the Institution website wwwistructeorg and following the
instructions provided Registration will close Friday 11 October Space is limited and latecomers will only be admitted to the
eventsistructeorg
Pai Lin Li Lecture
Institution members wishing to spend 4 ndash 6
weeks outside their own country studying
unrivalled opportunity to sample the technical
economic social and political conditions in
another country and to examine how these
various factors affect the practise of structural
engineering
winners John Orr and Katie Symons who will
Form an adventure in concrete
and brick
Form active design can facilitate architecturally
construction
John Orr
PhD MEng(Hons)
John Orr is a lecturer in
sustainable construction at
the University of Bath UK He
degrees from the same institution in 2009 and 2012
respectively His research interests include the design
of concrete structures using fabric formwork and
the shear behaviour and computational modelling of
concrete
International perspectives on Life Cycle
Assessment of structural materialsparticularly timber lessons to be learned
from Australasia
Australia and New Zealand in 2013 examining the
materials particularly with respect to embodied
materials particularly timber is also explored
Katie Symons MEng MA
(Cantab) MIStructE MICE CEng
Katie Symons has a keen
interest in the sustainability of
the built environment especially
the embodied energy andcarbon of buildings She presented her research
undertaken during a secondment to the University of
Society conference in Sydney in July 2012 She
has had journal papers published on the subject of
evaluating embodied energy and carbon
Thursday 17 October
Registration from 1730
Lecture at 1800
International HQ
Further ReadingThe Institution of Structural Engineers
(2013) Manual for the geotechnical design
of structures to Eurocode 7 London The
Institution of Structural Engineers
The Institution of Civil Engineers (2012) ICE
manual of geotechnical engineering London
Thomas Telford
The Institution of Structural Engineers
(2004) Design and construction of deep
basements including cut and cover structures
London The Institution of Structural Engineers
CIRIA (2000) Publication C516 Modular
gravity retaining walls design guidance
London CIRIA
CIRIA (2003) Publication C580 EmbeddedRetaining Walls London CIRIA
![Page 5: 1-33 Retaining Wall Construction](https://reader036.vdocuments.site/reader036/viewer/2022082621/5695d3f21a28ab9b029fb8dc/html5/thumbnails/5.jpg)
7242019 1-33 Retaining Wall Construction
httpslidepdfcomreaderfull1-33-retaining-wall-construction 55
TheStructuralEngineer46
Technical Guidance Note
Technical
October 2013
Note 33 Level 1
991290
Eurocode 0
Web resources
The British Geotechnical Association
httpbgacityacuk
Eurocode 0
Applied practice
BS EN 1992-1-1 Eurocode 2 Design of
Concrete Structures - Part 1-1 GeneralRules for Buildings
BS EN 1992-1-1 UK National Annex to
Eurocode 2 Design of Concrete
Structures - Part 1-1 General Rules
for Buildings
BS EN 1997-1 Eurocode 7 Geotechnical
Design - Part 1-1 General Rules
BS EN 1997-1 UK National Annex to
Eurocode 7 Geotechnical Design - Part 1-1
General Rules
BS EN 15362010 - Execution of special
geotechnical work ndash bored piles
BS EN 15382010 - Execution of special
geotechnical work ndash diaphragm walls
BS EN 120631999 - Execution of special
geotechnical work ndash sheet pile walls
Glossary andfurther reading
Angle of repose -The deepest angle
of slope relative to a horizontal surface agranular material such as soil is
resting upon
Bentonite - A form of absorbent clay that
is used during the construction of some
forms of retaining wall
Caisson - A water-tight retaining sub-
structure typically used for the construction
of marine engineering works such as piers
Tremie pipe - Method of placing concrete
within a liquid or highly viscous material that
relies on the delivery pipe remaining in thefreshly placed concrete so that it displaces
the liquid
Unsupported height - The extent of a
retaining wall that has no propping
Water table - The depth at which ground
water is located
Technical Lecture SeriesConferences amp Seminars Annual Institution Events Special Interest Series A series of lectures organised in partnership by
the Institution and other leading organisations
Registration is required in advance by visiting the events section of the Institution website wwwistructeorg and following the
instructions provided Registration will close Friday 11 October Space is limited and latecomers will only be admitted to the
eventsistructeorg
Pai Lin Li Lecture
Institution members wishing to spend 4 ndash 6
weeks outside their own country studying
unrivalled opportunity to sample the technical
economic social and political conditions in
another country and to examine how these
various factors affect the practise of structural
engineering
winners John Orr and Katie Symons who will
Form an adventure in concrete
and brick
Form active design can facilitate architecturally
construction
John Orr
PhD MEng(Hons)
John Orr is a lecturer in
sustainable construction at
the University of Bath UK He
degrees from the same institution in 2009 and 2012
respectively His research interests include the design
of concrete structures using fabric formwork and
the shear behaviour and computational modelling of
concrete
International perspectives on Life Cycle
Assessment of structural materialsparticularly timber lessons to be learned
from Australasia
Australia and New Zealand in 2013 examining the
materials particularly with respect to embodied
materials particularly timber is also explored
Katie Symons MEng MA
(Cantab) MIStructE MICE CEng
Katie Symons has a keen
interest in the sustainability of
the built environment especially
the embodied energy andcarbon of buildings She presented her research
undertaken during a secondment to the University of
Society conference in Sydney in July 2012 She
has had journal papers published on the subject of
evaluating embodied energy and carbon
Thursday 17 October
Registration from 1730
Lecture at 1800
International HQ
Further ReadingThe Institution of Structural Engineers
(2013) Manual for the geotechnical design
of structures to Eurocode 7 London The
Institution of Structural Engineers
The Institution of Civil Engineers (2012) ICE
manual of geotechnical engineering London
Thomas Telford
The Institution of Structural Engineers
(2004) Design and construction of deep
basements including cut and cover structures
London The Institution of Structural Engineers
CIRIA (2000) Publication C516 Modular
gravity retaining walls design guidance
London CIRIA
CIRIA (2003) Publication C580 EmbeddedRetaining Walls London CIRIA