EHN1 civil engineering project status (JULY)
Summary:• Updating of the activities carried out on-site (Done) in JULY • List activities on going (Next steps) and scheduled for AUGUST• Final consideration
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
(1) MICRO PILESVertical & inclined drilling along TT85: (100% completed)
EHN1 civil engineering project status (JULY)
Crown beam execution: (100% completed).
Done (1/4):
06 August 20152
TASK
COMPLETED
in JUNE
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
(2) DIAPHRAGM WALLS -73 panels-
Execution EAST side: (91% completed)
EHN1 civil engineering project status (JULY)
Execution SOUTH/WEST side: (67% completed)
Done (2/4):
06 August 20153
Guide walls allowing DW excavation: (100% completed)
Execution NORTH/WEST side: (100% completed)
~85% TOTAL PANELS
EAST
N/W
S/W
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Done (3/4):
(3) TECHNICAL GALLERY -70 meters-
EHN1 civil engineering project status (JULY)
Earthworks: (100% completed). Execution TG: (72% completed). Type 3 almost done. Type 1 startedBackfilling: (25% completed).
06 August 20154
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Done (4/4):
(4) PITS EXECUTION
EHN1 civil engineering project status (JULY)
Crown beam execution: (22% completed). Start with E side. Excavation first ties level: (22% completed).
06 August 20155
Excavation head DW level: (50% completed). Start with E and N/W side areas.
Excavation second ties level: (0% completed). Only for certain DW panels …Others
First ties level execution: (13% completed). Not yet in tension-step by step-
Task in “cohabitation” with the DWs last panels execution!!
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Next Steps: Activities scheduled for August
(2) DW: Whole panels completion within 1st half of August
(3) TG: Entire length, including connection with the EHN1, within end-August.
(4) PITS: Excavation/Execution crown beam + Excavation/Execution for ties installation East side portion
EHN1 civil engineering project status (JULY)
06 August 20156
04/08/2015 =>
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi
Final Consideration:
- New long-term schedule received updated with the current on-site situation.
- The compatibility/duration of the upcoming tasks will be assessed.
- CE tasks have to be carried out in parallel. Execution of the two pits launched before DWs panels completion to avoid further delays.
- Likely (but too early to say) CE first phase completion while metallic contractor are already on-site. Risky, but feasible thanks to the Consortium.
- CE Handover unchanged for the moment (Jul-2016)
- Next status of the works end-August.
EHN1 civil engineering project status (JULY)
06 August 20157
Extension of Building 887 - 26th EHN1 Extension Integration Meeting N.Lopez – M.Manfredi