COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

 ALCATEL-LUCENTHARDWARE INSTALLATION OF ISAMGPEC - FIXED NETWORKSFebruary - March 2013

Page 2: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 2/72

2

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

1. Floor Preparation

2. Installing Racks

3. Mounting Rack Equipment

4. Rack Cabling

5. Installing Boards

6. Fibre Optic Cable Management

7. MDF Cabling

8. SA Telkom Specific ISAM Configurations

9. Installing Side Plates and Door

 AGENDA

Page 3: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 3/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

1. Floor Preparation 

Page 4: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 4/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Floor PlanExample of Floor Plan for Mixed Rack Configuration 

Page 5: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 5/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Positioning RacksCutting Tiles for Cable Routing Left and Right of Rack for raised floor

Page 6: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 6/72

Page 7: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 7/72COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

2. Installing Racks 

Page 8: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 8/72COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Floor Drilling Pattern for Row of Racks Back to Back  

Floor Drilling for Rack Anchoring

Page 9: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 9/72COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

• The transport

bracket ismounted on theuniversal rack toprotect the doorfrom damageduring transport.

• On site thebracket isremoved.

Transport BracketFD Rack 3FE 28688 AA 

Page 10: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 10/72COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

10 

3. Mounting Rack Equipment

Page 11: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 11/72

Page 12: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 12/72COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Mounting the Standard Fan Unit 3EC 37533 NB

Mounting the Fan Unit

The fan unit is available intwo versions:

• Standard fan unit 3EC37533 NB (40,5V-57V;plastic version)

Page 13: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 13/72COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Mounting the Premium Fan Unit 3EC 37533 ND

Mounting the Fan Unit

• Premium fan unit3EC 37533 ND (40,5V-72V and low noisefunctionality; metalversion)

Page 14: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 14/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

 Adding a 7302 FD Subrack in Existing Racks

•For thermal and cabling reasons, any Alcatel-Lucent subracks(with a maximum of 2 active subracks and 1 passive/splittersubrack) must be positioned in the FD cabinet.

• ISAM LT subracks must be mounted at the bottom of the rack onrack vertical pitch number 60 (subrack pitch number 1). This way,

a free air inlet is created of about 75 mm below the bottom ISAMsubrack.

• The distance between 2 indication lines (identical to the distancebetween 2 mounting holes) is 25 mm. This results in a bottom FDLT mounting position of 60 x 25 = 1500 mm from the top of the

rack.

•  Above the top ISAM subrack, an free air exhaust space of 75 mmmust be foreseen.

Warnings !

Page 15: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 15/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

15 

4. Rack Cabling

Page 16: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 16/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

for Racks with NFXS-A 3FE 26685 AACL

Rack Cabling

Danger 1 — 

 Before working on the power supplyunit, verify if it is not live. If the power supply islive, which can deliver -48Vdc or -60Vdc, you mustuse an insulated tool kit and consult the manual onworking on live components.

Danger 2  —   Avoid risk of electric shock! Always wear protective gloves and footwear for allhandling tasks. Carefully follow the instructions.

Page 17: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 17/72

Page 18: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 18/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

External Power Interface on Backpanel

Page 19: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 19/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Cables that can be used for the external power cabling

External Power Cabling

 All the power cables have to be equipped with an 8 mm lug at one end. The color of thepower cables must be according to local installation practices.

Page 20: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 20/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Sample Cabling

Connecting the Power Cables

Page 21: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 21/72

Page 22: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 22/72

Page 23: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 23/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

 Alarm Cabling

The rack alarm extension cable(code 3FE 26690 AC, length 1100 mm) canbe used for the alarm extension between

the bottom and middle subrack andbetween the middle and top subrack incase of the NFXS-A 3FE 26685 AACL.

 Alarm Cable comes from therack itself to the shelf in thebottom (down port) 1

2

3

Page 24: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 24/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Rack/Subrack Alarm Extension

The cable must be connected to the RJ45 connectors on the subrack backplane as follows:• The left RJ45 connector is used to connect the alarm cable going to the subrack above

• The right RJ45 connector is used to:• connect the alarm cable from the subrack below (for the uppermost subrack(s))• connect the rack lamps (for the lowermost subrack only)

Page 25: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 25/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Door Alarm

Two cables need to be assembled and routed in order to use the door alarm feature:

• The cables are composed of an insulated wire with a minimal cross-section 0.75 mm2 andof sufficient length.

• One end of the cable is equipped with a 6.35X0.81 mm insulated female fast-on connector.

• The other end must be connected to the door contact. The door alarm contact can beconnected to the fast-on connectors DOOR_ALARM_A and DOOR_B on the backplane

Page 26: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 26/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

External Alarm Extension

The cable is connected on the “CO Alarms up”connector in the lower subrack and on the

 “CO Alarms down” connector of the uppersubrack. The external alarm cable is a signalcable with a Sub-B 15-pins connector (cablecode 3FE 27753 AA).

Page 27: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 27/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

27 

5. Installing Boards

Page 28: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 28/72

Page 29: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 29/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

7302 FD subrack equipped only with LT boards and splitter boards

Subrack Areas and Slot Positions

Slot Positions in 7302 FD-Combo (with NT redundancy) 

Slot Positions in 7302 FD-Combo (no NT redundancy) 

Page 30: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 30/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

7302 FD subrack equipped with combined LT/splitter boards

Subrack Areas and Slot Positions

Slot Positions in 7302 FD subrack equipped with combined LT/splitter boards

(with NT redundancy) 

Slot Positions in 7302 FD subrack equipped with combined LT/splitter boards(no NT redundancy) 

Page 31: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 31/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

The building blocks of these configurations are one of the following:• duplets: LT board and splitter board

• triplets: LT board, splitter board and POTS board• quadruplets: LT board, splitter board, ISDN board and ISDN board

Supported Mixed LT/Splitter Configurations

Page 32: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 32/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing ESD Sensitive Boards

ESD Awareness Symbol 

Carefully follow these rules when handling ESD sensitive boards.• Transport and store boards in ESD protective bags or boxes• Make sure to wear a grounded wrist strap before handling• DO NOT touch circuit traces or components on the board• Handle boards at front and side edges only.

Ejector Handle 

Page 33: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 33/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

5mm Stiffener

To adjust the difference between the width of the NT board (30mm) and thewidth of the LT board (25mm), a 5mm stiffener is mounted by default beside the

slot for NTB in all delivered 7302 FD subracks.

Note: In case the stiffener isremoved (for example, for makingan NT redundant configuration), itshould be retained for later usewhen the system is converted backto an 18 LT system.

Page 34: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 34/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing the NT Boards

 A 7302 FD subrack has one or two redundant Network Termination (NT) boards.The single (first) NT board is inserted in slot NT A, the redundant board, if any, in slot NT B

Danger: Risk of eye damage or skinburns by LASER emission. Wheninstalling optical boards or handlingoptical fibers, never look insideconnectors of boards or fibers whenthese are not connected.

The board first displays a heartbeat signal,that is, the green “PWR” LED is flashing. Then it displays an enabling operation signal,that is,

• the green “PWR” LED is steady on, • the green “A/S” LED is steady on, • the red “ALM” LED is off. 

Page 35: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 35/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing an NT I/O Board

Each subrack containing one or two redundant NT boards can have only one NT I/Oapplique.

Page 36: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 36/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing LT Boards in 7302 FD Subrack

The board first displays a heartbeat signal,that is, the green “PWR” LED is flashing. Then it displays an enabling operationsignal, that is,

• the green “PWR” LED is steady on, • the red “ALM” LED is off. 

Page 37: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 37/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing Splitter Boards in 7302 FD SubrackThe splitter boards are placed to the right of the corresponding LT board.

Page 38: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 38/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing Combined LT/Splitter Boards in 7302 FDSubrack

The board first displays a heartbeatsignal, that is, the green “PWR” LED isflashing. Then it displays an enabling

operation signal, that is,

• the green “PWR” LED is steady on, • the red “ALM” LED is off. 

Page 39: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 39/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

39 

6. Fibre Optic Cable Management

Page 40: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 40/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Fiber Optic Cable

Danger: Never look into the end of an optical fiber while optical power is being appliedto the fiber. When cleaning or taking measurements, avoid eye exposure to open-endedfibers and optical connectors. The fibers and connectors may be connected to a laser

transmitter.

Page 41: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 41/72

Page 42: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 42/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Optical Fiber Management Capacity

For Optical LT Boards 

Fiber Management Capacity per LT Slot 

Note: Up to 18 LT boards are supported in an FD subrack, on the conditionthat there are no rack and cabling restrictions at the customer side. Thefollowing tables show the fiber management capacity per subrack for thedifferent optical fiber types if the Alcatel-Lucent fiber management kit 3FE61087 AA is being used.

Page 43: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 43/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Optical Fiber Management Capacity

Fiber Management Capacity per Subrack for NGLT-x Boards 

Note: The limitation in capacity is driven by the fiber management kit.

Fiber Management Capacity per Subrack for NELT-x Boards 

Page 44: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 44/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Optic Modules / Fiber Cables

Managing Fiber Optic Cables for NT Boards andNTIO Boards

The NTs can be populated with either single-mode or multimode SFP and XFPmodules. The NTIO can be populated with either single-mode or multimode SFPmodules. The number of receptacles depends on the board type. Each of theconnectors are LC connectors and have a Tx port and an Rx port.

Routing FiberCables from NTsand NTIO

i ib i bl f d

Page 45: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 45/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Managing Fiber Optic Cables for LT Boards

The GPON SFPs require an SC/APC connector. For NELT-A and NELT-B, 90° fiberconnector strain relief boots are required.

Note 1: In the case of bidirectional fiber optic cables as usedwith the NGLT, the transmit and receive signals are carried onthe same fiber and only have one optical connector.

Note 2: The NGLT-x boards must only be used in ISAMsystems with an FD 100Gbps (NANT-D) or an FD 320Gbps(NANT-E) NT board

ib i h d G b d

Page 46: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 46/72

46

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Fiber connection on the NELT and NGLT board

• The common cable bending area in front of the shelf (or the

board) is 5 cm. In order to be able to shut the rack door thefiber start may not take more than 5 cm. To help theoperator to achieve this a cable bending element can beused.

Fib ti kit

Page 47: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 47/72

47

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Fiber routing kits

When optical LT boards (NELT and NGLT) are deployed in ISAM shelves, extrafiber guiding elements can be installed to guarantee a proper fiber handling.

Fiber guiding kit for one FD-16 (7302) shelf : 3FE-61087-AAAA

Fiber guiding kit for one FD-8 (7330) shelf : 3FE-61087-BAAA

Fiber guiding kit for one FD-2 (7356 REM) shelf : 3FE-61087-CAAA

Fiber routing kit are not mandatory but guarantee professional cabling

Without Fiber routing kit, there is no limitation of the number of fiber

and fiber dimension.

FD-16 Fiber guiding kit : 3FE-61087-AAAA

Page 48: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 48/72

48

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

FD 16 Fiber guiding kit : 3FE 61087 AAAA

The FD-16 fiber kit includes:

3FE-24348-ABAA (19 per shelf)3FE-29345-AAAA (2 per shelf)

FD-8 Fiber guiding kit : 3FE-61087-BAAA

Page 49: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 49/72

49

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.49 | Fiber management in FD | 2007

FD 8 Fiber guiding kit : 3FE 61087 BAAA

The FD-8 fiber kit includes:

1 bracket 3FE-61417-BAAA per shelf

8 plastic fiber guides 3FE-24348-ACAA

•   The fiber guide shall be cut-off depending on routing direction

FD 8 Fib idi d t il

Page 50: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 50/72

50

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

FD-8 - Fiber guiding details

Guiding for 16 x 1.6 mm fibers (up routing)

50 | Fiber management in FD | 2007

FD 8 Fib idi d t il

Page 51: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 51/72

51

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

FD-8 - Fiber guiding details

Guiding for 32 x 1.6 mm fibers (up routing)

FD-2 Fiber guiding kit : 3FE-61087-CAAA

Page 52: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 52/72

52

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

FD 2 Fiber guiding kit : 3FE 61087 CAAA

The FD-2 fiber kit includes:

1 bracket 3FE-61417-BAAA per shelf

2 plastic fiber guides 3FE-24348-ACAA

•   The fiber guide shall be cut-off as shown

FD 2 Fiber g iding details

Page 53: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 53/72

53

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

FD-2 - Fiber guiding details

Guiding for 32 x 1.6 mm fibers

FD 2 Fiber guiding details

Page 54: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 54/72

54

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

FD-2 - Fiber guiding details

Guiding for 16 x 3 mm fibers

16x3mm32x1.6mm

Routing Fiber Optic Cables from LT Boards

Page 55: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 55/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Routing Fiber Optic Cables from LT Boards

Fiber optic cables from LT boards must be routed through the MDF cable area andthen up to the top of the subrack. It is also recommended to use protection tubes

in the rack cabling areas to clearly separate the fiber optic cables from the MDFcabling.

Run the fibers left and/or rightthrough cable inlets and ducts:

1. to the left fiber duct forboards in slots 01 to 08

2. to the right fiber duct forboards in slots 09 to 16 andpositions NTIO/17 and

NTB/18

Page 56: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 56/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

56 

7. MDF Cabling

Dummy Front Panels

Page 57: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 57/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Dummy Front PanelsDummy front panels must be mounted onany unused slot of a subrack for thefollowing purposes:

• In case of an active FD-LT subrack:• to ensure EMC compliance• to ensure thermal compliance via a

correct airflow in the subrack• to ensure safety by avoiding direct

contact with backplane connectors

• To allow MDF pre-cabling towards LTboards (FD-LT subrack) or splitter boards(splitter subrack) when needed.

MDF Cabling Guidelines

Page 58: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 58/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

MDF Cabling GuidelinesBundle and route the cables in an orderly and efficient way.

MDF Cable Bundle 

Risk of performance degradation for VDSL when non- VDSL-specific cables are used for LINE cabling.It is recommended to upgrade the LINE SIDE cabling ofthe subrack, when VDSL deployment is foreseen.

Handling Baillocks

Page 59: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 59/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Handling Baillocks

Slotted Angled Screwdriver 

Locking and unlocking the baillocks with the tool requires some skill and exercise

Lock/unlock Top/Bottom Baillock on LT Board

Page 60: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 60/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Lock/unlock Top/Bottom Baillock on LT Board

Interconnection Cabling in Rack with 7302 FD-Combo

Page 61: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 61/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Interconnection Cabling in Rack with 7302 FD ComboSubrack (48-line)

This section describes the cabling for ADSL interconnection cabling (48-line)

between the LT boards and the splitterboards in a 7302 FD-Combo subrack.

Cable Type 

The required cable is an S-shaped, 175

mm long cable (3FE 27677 AA )

S-Shaped Interconnection Cable (48-line) 

Interconnection Cabling in Rack with 7302 FD-Combo

Page 62: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 62/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Interconnection Cabling in Rack with 7302 FD ComboSubrack (72-line)

This section describes the cabling for ADSL interconnection cabling (72-line)between the LT boards and the splitterboards in a 7302 FD-Combo subrack.

Cable Type 

S-Cable (72-line) 

The required cable is the S-cable (3FE

60300 AA). This cable consists of threeindividual 24-line cables and two Metral-HDXS-72 connectors. Length is 140 mm.

24-pair Bundle - Line Number Distribution

Page 63: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 63/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

24-pair Bundle - Line Number Distribution

Wiring Lists for MDF Cable Connectors

Page 64: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 64/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Wiring Lists for MDF Cable Connectors

Page 333-3537302_Hardware_Installation_Manual.pdf

Page 65: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 65/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

65 

8. SA Telkom Specific ISAM Configurations

SA TELKOM Specific

Page 66: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 66/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

• Equipment Layout

• Configuration Scenarios (1A, 1B, 2A, 2B)

• Indoor & Outdoor Pictures

SA TELKOM Specific

Page 67: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 67/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

67 

9. Installing Side Plates and Door

Installing Side Plates

Page 68: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 68/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing Side Plates

When mounting or dismounting theside plate, always remove the

corner upright item 4 first. Eachside plate is mounted with 5 screwsand washers on the frontand 5 on the side.

Side plate item 1Screw M4 item 2Washer M4 item 3

Installing Door

Page 69: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 69/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing Door

Installing Key Lock

Page 70: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 70/72

COPYRIGHT © 2011 ALCATEL-LUCENT. ALL RIGHTS RESERVED.

Installing Key LockReplacing a Latch Lock With a Key Lock  

Unscrew M16 Nut  Remove M16 Nut from Latch Lock  

Remove M16 Nut from Key Lock   Key Lock Bushing 

1 2

3 4

Place Key Lock   Place M16 Nut 

5 6

Tighten M16 Nut 

7

Page 71: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 71/72

Page 72: 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

8/10/2019 04_ALU-GPEC - Hardware_Installation_of_ISAM.pdf

http://slidepdf.com/reader/full/04alu-gpec-hardwareinstallationofisampdf 72/72