04 case studies on demolition.pdf
TRANSCRIPT
Case Studies on Accidents
Relating To Demolition Works
Chan Yew Kwong
Deputy Director, Construction & Equipment Safety
OSH Specialist Dept, OSH Division
® All Rights Reserved
Agenda
• Case studies
• Overview of legal requirements pertaining to demolition works
• CP 11 – Code of Practice for demolition
• Asbestos – Health hazard in demolition works
® All Rights Reserved
Brief Description of Work
1) The work involved the demolition of 12 blocks of low rise
buildings.
2) It was raining heavily and the wind was strong prior to the
incident.
® All Rights Reserved
Brief Description of Incident
Collapse of scaffold hoarding
® All Rights Reserved
Brief Description of IncidentHole in the ground indicating the
position of a wall tie which was
fixed as an anchorage prior to the
collapse of the hoarding
How the wall ties looked like
at other unaffected areas
® All Rights Reserved
Key Findings
1) There were 2 types of PE-endorsed designs for the anchorageof the hoarding
– one for solid ground, the other for concrete ground.
2) The span of scaffold hoarding that collapsed was not erected in
accordance with the PE’s design.
3) Wall ties were used as a form of anchorage on the road asphalt
surface instead of concrete block footings.
4) The anchorage distance from the hoarding base was also too
close.
® All Rights Reserved
Lessons Learnt
1) Incident could have been prevented if the hoarding and its
anchorage system were constructed according to the PE’s
design and drawings.
2) The contractor should appoint a competent person experienced
in the hoarding erection to supervise and control the work on site.
3) The condition of the hoarding should be inspected on a regular
basis, especially after incremental weather conditions.
® All Rights Reserved
Brief Description of Work
1) The work involved the demolition, removal and replacement of
2 combined cycle plants in a power station.
2) Prior to the accident, the demolition of the embedded cooling
water stub pipes was being carried out. This was the last of
the 4 sets of cooling water stub pipes to be demolished.
® All Rights Reserved
Brief Description of Accident
This section of the
concrete block &
steel pipe was pulled
out from the hole
before lunch
Concrete block still stuck
in the hole. Deceased
was standing inside the
hole hacking the concrete
prior to the accident
® All Rights Reserved
Brief Description of AccidentThis section of the concrete
gave way and struck the Deceased
® All Rights Reserved
Key Findings
1) During the demolition of the embedded cooling water stub pipe,
there were no continuing inspections made by a designated
person to detect any hazard resulting from weakened or
deteriorated floors or walls, or loosened materials.
2) The weight of the top portion of the concrete aggravated by the
vibration generated by the pneumatic breaker used in the hacking
process probably caused the sidewall of the concrete to crack
and eventually gave way, resulting in the top right corner of the
concrete falling onto the deceased.
® All Rights Reserved
Lessons Learnt
1) Accident could have been prevented if the worker has carried
out the hacking work by standing in front of the block of the
concrete to be hacked instead of going inside the pipe hole
and worked under the block of the concrete to carry out the
hacking.
2) A designated person should be appointed to carry out continual
inspection while the demolition of the embedded cooling water
pipe was being done to detect any hazard resulting from the
work.
3) Appropriate training and briefing should be provided
for workers before they can be deployed to carry out such
demolition works.
® All Rights Reserved
Brief Description of Work
1) The work involved the expansion of a road junction and a bridge.
2) Prior to the accident, about 30m of the existing roadside drain
and its metal railings beside the footpath were demolished. The
contractor was in the process of demolishing some metal railings
beside the footpath.
® All Rights Reserved
Brief Description of Accident
One piece of 3m long metal
railing was demolished first
30m of drain and railing has been
demolished prior to accident
® All Rights Reserved
Brief Description of Accident
When the hacking started this end of the railing
swung towards the direction of the footpath with
great force and speed
® All Rights Reserved
Brief Description of Accident
Deceased was
standing here
This metal leg of the railing
panel was badly corroded
This metal leg did not
break off completely
® All Rights Reserved
Key Findings
1) When the hacking started, it caused the end of the railing with the very badly corroded metal leg to swing with great force andspeed. The force could be due to the vibrations transmitted from the concrete breaker to the railing panel.
2) No Safe Work Procedure for the demolition of railings.
® All Rights Reserved
Lessons Learnt
1) Accident could have been prevented if gas cutting was used to
cut the two metal legs and remove the railing panel instead of
using concrete breaker to hack the footings.
2) No worker should be in the vicinity of the operation zone of the
excavator mounted with hydraulic breaker when it is in operation.
3) The contractor should appoint a competent person experienced inthe type of demolition work concerned to supervise & control thework on site.
4) Appropriate training and briefing should be provided for workersbefore they can be deployed to carry out such demolition works.
® All Rights Reserved
Brief Description of Work
1) The Work involved addition and alteration works to an existing
school.
2) Prior to the accident, the deceased was demolishing a partition
brick wall inside a toilet.
® All Rights Reserved
Brief Description of Accident
® All Rights Reserved
Brief Description of Accident
® All Rights Reserved
Brief Description of Accident
Partition wall that
has collapsed and
hit the Deceased
on his head
® All Rights Reserved
Brief Description of Accident
® All Rights Reserved
Key Findings
1) Deceased had hacked the partition wall from the bottom section
using a 10-pound hammer.
2) The partition wall was simply resting on the ground and abutted
against the adjacent main wall. There was no interlocking joint
between the partition wall and the main wall.
3) As-built detailed drawings of the toilet walls were not made
available to the contractor prior to the hacking work.
4) In-house demolition procedures were not effectively implemented.
® All Rights Reserved
Lessons Learnt
1) Accident could have been prevented if the wall was demolished
in the reverse manner to that of its construction, i.e. the partition
wall should be hacked from the top section and extended down
progressively so as to maintain its structural stability.
2) Workers should be grouped in teams of two or more when
carrying out demolition works.
3) The contractor should appoint a competent person experienced in
the type of demolition work concerned to supervise and control
the work on site.
4) Appropriate training and briefing should be provided for workersbefore they can be deployed to carry out such demolition works.
® All Rights Reserved
Legal requirements for demolition works
Workplace Safety & Health Act 2006
• Every occupier is to take, so far as is reasonably practicable, such measures to ensure that: > the workplace;> all means of access to or egress from the workplace; and> any machinery, equipment, plant, article or substance kept in the workplace,are safe & without risks to health to every person within those premises (including members of public)
• Every employer is to take, so far as is reasonably practicable, such measures as are necessary to ensure the safety and health of his employees at work
® All Rights Reserved
Legal requirements for demolition works
WSH (Risk Management) Regulations 2006
• Employers / Principals of workplaces are to:
– Assess risk to workers arising from work before work commences
– Eliminate the risk where possible, or if not take measures to control the risk such as:
• (i) Substitution
• (ii) Engineering controls
• (iii) Administrative controls, including safe work procedures
• (iv) Provision and use of suitable personal protective equipment
– Establish Safe Work Procedures
– Communicate the risk & control measures to the workers
® All Rights Reserved
Legal requirements for demolition works
WSH (Construction) Regulations 2007• All worksites to implement an OSHMS – audit/review once
every 6 months
• Convene regular site co-ordination meeting :- to coordinate various works carried out on site;
- ensure measures are taken for works to be carried out sequentially and systematically with due regard to the safety and health of workers
- to be presided by the project manager
• Implement permit-to-work system
• Appoint WSH co-ordinator (contract sum less than $10m)
• Safety and health training for workers and person who oversees or supervises any work processes
® All Rights Reserved
Legal requirements for demolition works
WSH (Construction) Regulations 2007
PART X -DEMOLITION
Regulation
69. General duty on occupier
70. Preparation of demolition work
71. Protection of adjacent structures
72. Removal of load bearing structures
73. Demolition of walls, partitions, etc.
74. Access to floor
75. Barricades, catch platforms and warning signs
76. Mechanical method of demolition
® All Rights Reserved
• The building or structure should be examined and, if necessary, tests carried out, to determine its condition, and whether constituent materials have deteriorated in strength which could result in instability arising due to a particular demolition process.
• The demolition contractor is required to appoint a competent person experienced in the type of demolition work concerned to supervise and control the work on site.
• A programme should be drawn up in which the proposed sequence and methods of operations are clearly indicated.
CP 11 – Code of Practice for Demolition
® All Rights Reserved
• The demolition contractor should be responsible for ensuring that plant and equipment is maintained in good working condition at all times.
• All workmen, during demolition work, shall wear adequate protective clothing and where appropriate helmets, goggles, safety footwear, safety harness and industrial gloves.
• Buildings and other structures should generally be (hand demolition) demolished in the reverse order to that of their construction.
CP 11 – Code of Practice for Demolition
® All Rights Reserved