03 tsl rolling gates design by jeremy augustijn

26
1 Challenge the future Third Set of Locks Rolling gate design Challenges in the Design of Extreme Lock Gates Ir. Jeremy Augustijn

Upload: delft-infrastructures-mobility-initiative

Post on 12-Jul-2015

242 views

Category:

Design


1 download

TRANSCRIPT

Page 1: 03 tsl rolling gates design by jeremy augustijn

1

Challenge the future

Third Set of Locks

Rolling gate design

Challenges in the Design of Extreme Lock Gates

Ir. Jeremy Augustijn

Page 2: 03 tsl rolling gates design by jeremy augustijn

2

Challenge the future

Who are we?

Iv-Groep is active in six markets: Buildings & Structures Industry & Energy Infrastructure & Ports Maritime Oil & Gas Water

Page 3: 03 tsl rolling gates design by jeremy augustijn

3

Challenge the future

Offices Worldwide

Page 4: 03 tsl rolling gates design by jeremy augustijn

4

Challenge the future

Choice of words

• “Challenges”

• “Extreme”

• “Difficult”

• “Paradox”

• “Unprecedented”

• “Problems”

WE LOVE IT

Page 5: 03 tsl rolling gates design by jeremy augustijn

5

Challenge the future

3rd set of locks, overview

Subtitle

Page 6: 03 tsl rolling gates design by jeremy augustijn

6

Challenge the future

What’s so special?

SIZE

SEISMIC

FATIGUE

DIFFERENTIAL HEAD

DRY

OUTAGE

FLOATING

99.6%

AVAILABILITY

SHIP

IMPACT

Page 7: 03 tsl rolling gates design by jeremy augustijn

7

Challenge the future

Head / Fatigue / Floatability

• 2 x 8 gates; lockage process

• 250.000 cycles of operation

• Gatun Lake •Pacific

•Uplockage (Ocean Lake)

•G1 G2

•Lock Head 1

•G3 G4

•Lock Head 2

•G5 G6

•Lock Head 3

•G7 G8

•Lock Head 4

• Limitation allowable operational stresses

• Requirements details

• Buoyancy chamber: low

Page 8: 03 tsl rolling gates design by jeremy augustijn

8

Challenge the future

Floating Employers Requirement:

All lock gates shall be stable

while floating upright without the

aid of additional floating

equipment, cables, or supports.

Page 9: 03 tsl rolling gates design by jeremy augustijn

9

Challenge the future

Flotation hull panels

Page 10: 03 tsl rolling gates design by jeremy augustijn

10

Challenge the future

Lower wagon assembly

Employers Requirement:

Each of the wagon attachments to the gate shall be designed to allow

wagon replacement in less than 4 hours.

Traditional lower wagon design: •Floating of gate: 8-16 hours •Divers operation: Lock unavailable

Page 11: 03 tsl rolling gates design by jeremy augustijn

11

Challenge the future

Support system

Page 12: 03 tsl rolling gates design by jeremy augustijn

12

Challenge the future

Upper wagon

Page 13: 03 tsl rolling gates design by jeremy augustijn

13

Challenge the future

Lower wagon

17-12-2013 “SMART RIVERS

2013”

Page 14: 03 tsl rolling gates design by jeremy augustijn

14

Challenge the future

Lower wagon: Top of gate

17-12-2013 “SMART RIVERS

2013”

Page 15: 03 tsl rolling gates design by jeremy augustijn

15

Challenge the future

Load Limiting Device

17-12-2013 “SMART RIVERS

2013”

Page 16: 03 tsl rolling gates design by jeremy augustijn

16

Challenge the future

Gate drive mechanism

• Drive force acts central to gate

• Redundancy: Double / thinner ropes

17-12-2013 “SMART RIVERS

2013”

Page 17: 03 tsl rolling gates design by jeremy augustijn

17

Challenge the future

Guiding Bearing and Sealing

Employers Requirements:

Leakage: The maximum allowable leakage rate per meter of lock gate seals and

sealing surfaces at any point shall not exceed 10 liters/minute when the gate is

subjected to normal and maintenance operating conditions. The overall average

leakage rate per meter of lock gate seals and sealing surfaces shall not exceed 5

liters/minute.

• Traditional New Panama gates

Page 18: 03 tsl rolling gates design by jeremy augustijn

18

Challenge the future

Guiding/Sealing on concrete

Page 19: 03 tsl rolling gates design by jeremy augustijn

19

Challenge the future

0

1

2

0 0.5 1 1.5 2 2.5 3

Spec

tral

Acc

eler

atio

n (g

)

Period (s)

PACIFIC LOCKS

Level 1 - 475-year

Level 2 - 1000-year

• Lock head +

gates models:

Time histories

• Gate models:

Response

spectra

Seismic design criteria

Page 20: 03 tsl rolling gates design by jeremy augustijn

20

Challenge the future

Seismic design criteria

• “Full scale” oscillation tests

Page 21: 03 tsl rolling gates design by jeremy augustijn

21

Challenge the future

Seismic scale model laboratory tests

Page 22: 03 tsl rolling gates design by jeremy augustijn

22

Challenge the future

Structural design

& Optimization of gates

Fatigue

Check/Optimize

Dry Outage

Check/Optimize

Drawings Weight

Estimate

Seismic

Check/Optimize

Page 23: 03 tsl rolling gates design by jeremy augustijn

23

Challenge the future

Detail Engineering

Page 24: 03 tsl rolling gates design by jeremy augustijn

24

Challenge the future

Conclusions

• Engineering of scales has its limits

• Crossing these often requires innovation

• “Borrowing” from other fields or disciplines can be a good

method to find interesting, precedented solutions

Page 26: 03 tsl rolling gates design by jeremy augustijn

26

Challenge the future

Iv-Infra b.v.

Trapezium 322

3364 DL Sliedrecht

P.O. Box 135

3350 AC Sliedrecht

The Netherlands

Phone: +31 (0)88 943 32 00

E-mail: [email protected]

www.iv-infra.nl

Fultonbaan 30

3439 NE Nieuwegein

The Netherlands

Phone: +31 (0)30 602 30 30

E-mail: [email protected]

www.iv-infra.nl