03 adam hand
DESCRIPTION
Presentation delivered by Adam Hand on "Superpave" at the California Asphalt Pavement Association Spring Conference April 25, 2013 in Ontario, CA.TRANSCRIPT
Superpave Superpave Contractor’s PerspectiveContractor’s Perspective
California Asphalt Pavement ConferenceCalifornia Asphalt Pavement Conference
Adam J.T. Hand, PhD, PEAdam J.T. Hand, PhD, PE
Ontario, CAOntario, CA April 24, 2013April 24, 2013
Outline Experiences
Academic – UNR, WRSC, WT, Purdue Industry – GCI, Several RolesService – SP ETG, NCHRP, AAPT, NAPA, …
Lessons Learned MaterialsLabs and Equipment ImplementationLab vs. FieldProduction & Construction
Context – Superpave and QC/QA All at Once
Lessons Learned Things We Worried About:
Aggregate Properties (CAA, FAA, FEP)Mix Design VerificationRestricted Zone
PMBs How to Handle RAP Performance Testing Tenderzone
Lessons Learned Asphalt Binder Specification – Chemical Goal
Physical Property Spec - Huge Improvement Still - PG+, MSCR, PPA, CRM, TB
Aggregates Not Big Change in California – Early 1990’sRestricted Zone – Guide
ARZ, BRZ, TRZ can ALL Perform WellSome Sand May Be NeededWashed Crusher Fines, Chips?P200 Must Be Managed – Mix Sensitivity
ASTM STP December 2000
p200 Management - 19mm Example
012
34567
89
10
4.0 5.0 6.0 7.0% AC
% A
ir V
oids
At Target p200 = Solid LinesAt Field Observed p200 = Dashed Lines
Reduction in AC at 4.0% AV = 0.8% due to +1.5% p200
Reduction in AV at Opt AC = 1.8% due to +1.5% p200
Lessons Learned
Δ from AASHTO Standards = Challenging…NDesign
Min VMA (increase vs. production)D/A (smaller NMAS mixes)FEP (3:1)T283 (conditioning and minimums)Adding Conflicting Requirements
Use or Generate Data via Shadow Specs First
Everything is Bigger in the Lab Bigger Samples (4x)
Bigger EquipmentMore Square Footage$ Investment
SGC 4800g
Hveem1200g800lbs - Really?
Everything is Bigger in the Lab
Everything is Bigger in the Lab
Compactors and Verification Superpave Center and ETG – SGC’s
10 yearsSGCs are NOT all the same
SGC Frame ComplianceInternal Angle Verification NeededDON’T Buy a Headache!!!Follow Your Owner?
Superpave Center – Mix VerificationAggregates BatchingDust Correction
Will Now Know Source of Δ
Everything is Bigger in the Lab HWTD
Hamburg Wheel Track Device (HWTD) Colorado →Texas, … (Rutting and Stripping) Slabs or paired cylindrical samples, 7 ± 2% AV (Cores OK) 8”diam x 1.75” steel wheel, 50pass/min, 158lb load 50ºC and 20k passes or ½” rut depth, SIP 50ºC and PG64 (5k), PG70 (10k), PG76 (20k) ≤ ½” r & R not yet published
AASHTO T324 Hamburg Test Method ILS by AMRL
SGC 4800g
Hveem1200g
ILS AMRL Prepared all Samples Only Cutting and Test Method Variability
9.5mm 19mm
AASHTO T324 Hamburg ILS
AASHTO T324 Hamburg ILS Observations
Very Significant Variability in Results Between LabsDid Not Publish Precision Statement
Conduct Ruggedness Experiment First Key Factors Affecting Results:
Starting location of the wheelWheel track alignment on the sampleNumber of sensors and sensor locationsGyratory sample cutting and mold
Closely Inspect your New Equipment Utah DOT Similar Experience – Great Job Addressing
Before Implementation Encourage Similar in California
Dry Tensile Strengths vs. Binder Grade
Date of Design AgencyMethod/Sample
DiameterLaboratory Who Performed
Testing
Mix Design Nominal
Maximum SizeBinder Grade
Aggregate Source
Ant-Strip Method
Dry Tensile Strength (psi)
3/25/2010 Caltrans Hveem/4” Construction Materials Engineers 12.5mm PG 64-28PM Source ALime Slurry Marination
86
1/31/2012 NDOT Hveem/4” NDOT 19.0mm PG 64-28NV Source ALime Slurry Marination
100
1/31/2012 NDOT Hveem/4” NDOT 19.0mm PG 64-28NV Source ALime Slurry Marination
76
5/29/2012 FAA Marshall/4” Eastern Sierra Engineering 12.5mm PG 64-28 Source ALime Slurry Marination
71
8/24/12 NDOT Hveem/4” NDOT 19.0mm PG 64-22 Source ALime Slurry Marination
125
10/1/2012 Caltrans Hveem/4” Construction Materials Engineers 9.5mm PG 64-28TR Source ALime Slurry Marination
77
3/1/2013* Caltrans Hveem/4” Construction Materials Engineers 19.0mm PG 64-28 Source ALime Slurry Marination
84
3/22/2013* Caltrans Superpave/6” GARCO - Stockton 19.0mm PG 64-28 Source ALime Slurry Marination
94
*- The 3/22/2013 Superpave 6” diameter dry tensile strength data was performed using the same gradation and optimum asphalt content obtained from the 3/1/2013 Hveem design as to permit a direct comparison of sample size vs. dry tensile strength.
Min Dry Tensile Strength
Dry Tensile Strength = f(PG Binder Grade)
Mix TypeAggregate
SourceBinder Type
Asphalt Content (BDW)
Compaction Method
Dry Tensile
Strength (psi)
Hamburg Rut Depth @ 15,000 passes (in)
Hamburg Inflection
Point (No. of Passes)
¾” HMA Source A PG64-28 5.5 Hveem – 4” 84 n/a n/a
¾” HMA Source A PG64-28 5.5 Gyratory– 6” 94 0.1 >25,000
¾” HMA Source A PG70-10 5.5 Gyratory– 6” 211 n/a n/a
• Dry Tensile Specification > 120 psi• Hamburg Rut Depth < 0.5in after 15,000 passes• Hamburg Inflection point – min. 10,000 passes
Tensile Strength Specimens under Tensile Stress/Strain What Material Can Resist Tension? Key Drivers of Tensile Strength
BondBinder Stiffness
Should PG70- 10 vs. PG64-22 vs. PG64-28 all have same TSDry?
Binder Stiffness vs. Grade (1/2 or 2x) NCHRP Report 444, "Compatibility of a Test for
Moisture-Included Damage With Superpave Volumetric Mix Design“No Difference in Hveem and Superpave TS
Impacts of Lab Turnaround Time Function of:
Project Location/LogisticsTest MethodAvailable Resources
Test and TimeVolumetrics and In-Place Density ≈ 1-2 daysWTD ≈ 3 daysTSR ≈ 7 days
Risk (Production TSR Example)≈ 2000 to 4000 tons/ day x $100/ton in-place
Over $1M per week (2kx$100x7days) – WOW!How to Address Risk?
Plant Production Aggregate Plant Balance? VSI Crushers? RAP Fractionation?
Treat Like Aggregate Additional Feed Bins and ControlsDrive with Acceptance Criteria
Volumetric SpecificationsSensitivity to p200
More Washing?Baghouse Controls?
Aggregate BreakdownSGC = Plant?How Addressed?
ASTM STP December 2000
p200 Management - 19mm Example
012
34567
89
10
4.0 5.0 6.0 7.0% AC
% A
ir V
oids
At Target p200 = Solid LinesAt Field Observed p200 = Dashed Lines
Reduction in AC at 4.0% AV = 0.8% due to +1.5% p200
Reduction in AV at Opt AC = 1.8% due to +1.5% p200
Aggregate Breakdown Mix Design to Post-Plant (Lab to Field) Must Consider in
Mix Design Process Production Start-up Gradation Acceptance
Does Breakdown in Lab Mixer and SGC = Breakdown in Drum or Dryer and Pugmill?NO
What Gradation Should be Used in Mix DesignStockpile, Hot Bin, Coldfeed?
What Gradation Should be Used for Acceptance?Coldfeed, Hot Bin, or Post-Plant?
24
What About Production? Lab Mix Design to Field Production
Differences are Real – Must Address What Occurs During Production that Affects
Gradation and Volumetrics?Breakdown in the Drum (p200 ↑) If p200 ↑ Post Plant what will be Done to Maintain
4.0% Air Voids, …?Reduce %AC?
� Reduced Durability� Is this Good or Bad?
%AC
Ru
ttin
g
Du
rab
ility
Lab Mix Design to Field Production Mix Design Purpose? How to Address Δ’s - What is End Goal? End Product Quality
Field Adjust AC and Grad to Desired Volumetrics
Appropriate TV Δ’s P200 dosing in MD? Test Strip %AC, Gradation, Volumetrics – Same Sample …
Aggregate Breakdown Example
0
10
20
30
40
50
60
70
80
90
100
Percent Passing
Sieve Size ^ 0.45 Power (mm)
Hot Bin Blend
Ignition Oven Gradation
Spec Limit
Target Values
0.0750.15
0.30 0.60 1.18 2.36 4.75 9.50 12.5 19.0
Over 5% on coarse sieves and 2% on p200
Asphalt Binder Set Point Verification (Hot Drop)
Plant Set Point = Mix Design OBCIn-Spec – Go to ProductionOut-of-Spec - Repeat, Repeat, Repeat
ProductionPlant Setpoint = Mix Design OBC
Standard Process � if PSP and OBC Δ ≤ 0.4% OK� If PSP and OBC Δ ≥ 0.4% Shut Down
QC/QA � if PSP and OBC Δ ≥ 0.0% PWL Compomised� Typical σT = 0.20
Lab Mix Design to Field Production
Lab to Field No %AC Set Point Change?
Impact on Volumetrics
Impact on %AC PWL/PFσ%AC = 0.20 typical (CT, AMRL, …)Off Target, no Set Point or TV Δ
%AC Pay Factors for Spec Tolerances = ±0.4%
0.75
0.80
0.85
0.90
0.95
1.00
1.05
0.00 0.10 0.20 0.30 0.40 0.50
Standard Deviation
Pay
Fac
tor
Offset = 0Offset = 0.1Offset = 0.2Typical Variability
1.01
0.95
%AC Pay Factors for Spec Tolerances = ±0.3%
0.75
0.80
0.85
0.90
0.95
1.00
1.05
0.00 0.10 0.20 0.30 0.40 0.50
Standard Deviation
Pay
Fac
tor
Offset = 0Offset = 0.1Offset = 0.2Typical Variability
0.94
0.83
Superpave Experiences 2005
Stockpile ManagementPre-Superpave
Superpave Experiences -32
Stockpile ManagementPost-Superpave
Additional Feeder Bins RAP Fractionation 12 Bins at 1 Hot Plant?
Accurately Metering Baghouse Fines?
Wasting Baghouse Fines?
Superpave is Technology Friendly Can Technically Address in Lab
Neat, PMBRAPRASWMA…
We Can Field Produce
Field Observations NMAS
¾” has ¾” Rock in It t/NMAS ≥ 3, Max by Density Measurement
BRZ can = Segregation (everywhere) & Workability Challenges – Training and QC Critical
Density Matters!!!Get All but 1.5% ImmediatelyFewer PneumaticsTenderzone (not something new)
Truck Loading Focus MTV’s Joints
Field Observations Have Compacted up to 5.5” Lift with ¾” NMAS We Can Place and Compact Superpave Mixes
Tenderzone - special Kneeding compactors?
Training is Critical to Success!
Training Needs
Significant Training Required:Professional and TechnicalMix Designers and TechniciansEstimating StaffPlants StaffConstruction Operations Staff Inspection StaffAgency/Contractors/Engineering Firms
Consider FHWA Efforts in Early 1990’s
My Gut Importance of Training Will Be WAY Under Estimated Lab Investment will Be Too Slow - Logistics Issues? Issues with Differences in Caltrans and AASHTO and
City/County Specs – Design, Equipment, Acceptance, Mix Management, … will ExistGrad+D/A Spec, Grad +Vol Independent SamplesHWTD, Dry Tensile Strength, Lab to Field
Could Have HWTD Challenges if Not Patient Could Not Address Aggregate Breakdown and Mix
Sensitivity Some Aggregate Sources will Be Challenging Required Plant Investments will Be Underestimated There will Need to Be Specification Iterations
Moving Forward Superpave = HUGE Step ForwardSuperpave = HUGE Step Forward Late Adoption will Eliminates Others Early ChallengesLate Adoption will Eliminates Others Early Challenges InvestmentInvestment
LabsLabsPlant $ – VSI’s, RAP Feeder Bins, Baghouse ControlsPlant $ – VSI’s, RAP Feeder Bins, Baghouse Controls
Con Ops – No ProblemsCon Ops – No Problems Technology – RAP, RAS, WMA, … friendly - JDITechnology – RAP, RAS, WMA, … friendly - JDI Get Lab Equipment and Methods Right FIRSTGet Lab Equipment and Methods Right FIRST We Will All Need to Continually ImprovementWe Will All Need to Continually Improvement
Binder, Mix Design, Perf Tests, Mix to Structural Binder, Mix Design, Perf Tests, Mix to Structural Design, Test Methods and SpecificationsDesign, Test Methods and Specifications
We Will Make Better Products and That Will Be Good for We Will Make Better Products and That Will Be Good for Our IndustryOur Industry
QuestionsQuestions