02/11/98 ISO-3D Kick-Off Meeting
Esprit Project N° 28953
Interpretation of Symbolic Objects in 3D representation
(ISO-3D)(ISO-3D)
Kick-Off Meeting
02/11/98 ISO-3D Kick-Off Meeting
Objective
To develop a Human Centred Interface methodology and tools which offer a way to analyse and interpret business information from large collection of data.
02/11/98 ISO-3D Kick-Off Meeting
Consortium organisation
MS&I (F)Prime
CEREMADE (F)Subcontractor
FUNDP (B)Contractor
TGS (F)Contractor
DMSDMS (I)Contractor
INGING (N)Contractor
IMPM (S)Subcontractor
CISIA (F)Subcontractor
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– Matra Systèmes & Information (MS&I)
• Country– France
• Position in the consortium– Prime (Coordinator)
• Part in the consortium– Ergonomics and methodology
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– University of Namur (FUNDP)
• Country– Belgium
• Position in the consortium– Technical leader (Contractor)
• Part in the consortium– 3D Visualisation and Sound
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– University of Naple (DMS)
• Country– Italy
• Position in the consortium– End User & Technical Provider (Contractor)
• Part in the consortium– DM design, 3D Visualisation and RAI
requirements
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– ING Bank (ING)
• Country– Netherlands
• Position in the consortium– End User (Contractor)
• Part in the consortium– Stock market requirements
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– TGS Europe (TGS)
• Country– France
• Position in the consortium– Dissemination leader (Contractor)
• Part in the consortium– 3D library tool provider
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– University PARIS IX Dauphine (CEREMADE)
• Country– France
• Position in the consortium– Technical Provider (Subcontractor)
• Part in the consortium– DM design, DM interpretation and 3D
Visualisation
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– University of Ljubljana (IMPM)
• Country– Slovenia
• Position in the consortium– Technical Provider (Subcontractor)
• Part in the consortium– 3D time & series visualisation
02/11/98 ISO-3D Kick-Off Meeting
Consortium detail
• Name– (CISIA)
• Country– France
• Position in the consortium– Data Mining Tool Provider (Subcontractor)
• Part in the consortium– DM & data analysis expertise
02/11/98 ISO-3D Kick-Off Meeting
Work packages
• WP1 : Project management (MS&I)• WP2 : ISO-3D specification (DMS)• WP3 : ISO-3D methodology & tools
(FUNDP)• WP4 : Project evaluation (ING)• WP5 : Exploitation & dissemination (TGS)
02/11/98 ISO-3D Kick-Off Meeting
WP1 : Project Management (MS&I)
• T1.1 : Administrative management (MS&I)Coordination between partners & communication with Commission
• T1.2 : Technical management (FUNDP)Coordination of technical work and software development and integration
02/11/98 ISO-3D Kick-Off Meeting
WP2: ISO-3D specification (DMS)
• T2.1 : End user requirements (ING)Definition of the scope of two pilot applications
• T2.2 : State of the art (MS&I)Analysis of technology and methodology background
• T2.3 : Symbolic object generation (DMS)Generation of symbolic object, especially time representation in SO
02/11/98 ISO-3D Kick-Off Meeting
WP3 : ISO-3D methodology & tools (FUNDP)
• T3.1 : Symbolic object interpretation & design (DMS)
Definition of symbolic object interpretation
• T3.2 : Source code specification (TGS)Definition of all development normalisation aspects (programmation rules, module interfaces, integration code design…)
• T3.3 : ISO-3D graphical library (FUNDP) Development of the graphic and sound library
02/11/98 ISO-3D Kick-Off Meeting
WP3 : ISO-3D methodology & tools (FUNDP)
• T3.4 : Methodology (MS&I)Definition of a formal methodology based on ergonomics feature
• T3.5 : Software methodology (MS&I)Development of a tool supporting the methodology
• T3.6 : Tool set integration (FUNDP)Integration of the graphic library, the analysis process, the methodology software & the DM tool
02/11/98 ISO-3D Kick-Off Meeting
WP4 : Project evaluation (ING)
• T4.1 : Pilot application (MS&I)Development of two pilot applications (for ING and for RAI/DMS)
• T4.2 : Benchmark method (ING)Criteria definition for the pilot applications evaluation
• T4.3 : Project result evaluation (ING)Evaluation of the pilot applications
02/11/98 ISO-3D Kick-Off Meeting
WP5 : Exploitation & Dissemination (TGS)
Definition of the falling of the project in terms of market potential, potential other users outside the consortium, dissemination means– Exploitation plan at Month 3
02/11/98 ISO-3D Kick-Off Meeting
Planning (1/2)
Nº Nom de la tâche
1 WP1:Project management
2 T1.1 : Adiministrative Management
3 T1.2 : Technival Management
4 WP2 : Users Requirements
5 T2.1 : Users Requirements
6 Deliverables (User requirements, Exploitation plan, Consortium agreement)
7 T2.2 : State of the Art
8 T2.3 : Symbolic Objects Generation
9 Deliverables (State of the Art, SO generation, Cost statement, Technical progress report)
10 WP3 : ISO-3D Methodology & Tools
11 T3.1 : SO Interpretation & Design
12 T3.2 : Source Code Specification
13 Deliverables (SO Interpretation & Design, Source Code Specification)
14 T3.3 : ISO-3D Graphic Library
15 T3.3.1 : GL Development
16 T3.3.2 : Sound Library
17 T3.3.3 : Analysis process
18 Deliverables (ISO-3D graphic library V2.0, ISO-3D graphic library description)
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N1998 1999 2000
02/11/98 ISO-3D Kick-Off Meeting
Planning (2/2)
Nº Nom de la tâche
21 Deliverables (ISO-3D Methodology, ISO-3D graphic library V1.0)
22 T3.5 : Methodology Software
23 Deliverables (ISO-3D methodology Software)
24 T3.6 : Tools Set Integration
25 Deliverables (Cost statement, Technical progress report)
26 Deliverables (ISO-3D Library Tool Set, ISO-3D Library User Guide, ISO-3D methodology tool set, ISO-3D methodology user guide)
27 WP4 : Project Evaluation
28 T4.1 : Pilot Demonstrator
29 T4.2 : Benchmark Method
30 Deliverables (Pilot demonstrator, Guideline evaluation report)
31 T4.3 : Project Evaluation
32 WP5 : Exploitation & Dissemination
33 Deliverables (Pilot evaluation report, final cost statement, final technical progress report)
F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N1998 1999 2000
02/11/98 ISO-3D Kick-Off Meeting
EffortTask Durat MS&I FUNDP IMFM CISIA TGS ING DMS
WP1 24 11,5 6 1 1,5 1T1.1 24 10T1.2 24 1,5 6 1 1,5 1
WP2 6 3 0,5 1 5 0,5 5 7T2.1 3 1,5 2 2T2.2 3 1,5 0,5 1 0,5 0,5 1T2.3 3 4,5 3 4
WP3 12 15 14,5 10 1 5 3 11,5T3.1 2 2 1,5 1 0,5 1,5T3.2 2 1 1,5
T3.3 8 2 10 8 2,5 8,5T3.3.1 5 1 4 5 1,5 5T3.3.2 3 0,5 3 0,5 0,5T3.3.3 3 0,5 3 3 0,5 3
T3.4 5 4 1 0,5T3.5 4 4 1T3.6 3 2 3 1 1 1,5 1
WP4 5 3 2 1 5,5 4,5T4.1 2 2 1,5 1 1,5 2T4.2 2 1 0,5T4.3 3 1 0,5 3 2
WP5 24 1 1 1 2,5 1,5 1
TOTAL 24 33,5 24 12 6 10 16,5 25
02/11/98 ISO-3D Kick-Off Meeting
Budget (in Ecu)
GLOBAL FUNDINGMS&I 433 200 216 600FUNDP 140 980 140 980IMFM 40 500 40 500CISIA 79 800 39 900TGS 153 900 76 950ING 246 240 123 120DMS 95 000 95 000CEREMADE 76 950 76 950
1 266 570 810 000
Advance = 220000 <=> 27,16%
02/11/98 ISO-3D Kick-Off Meeting
Discussion
02/11/98 ISO-3D Kick-Off Meeting
Lunch
02/11/98 ISO-3D Kick-Off Meeting
Project Organisation
• Project management : meeting each 3 months (or more if necessary) ==> 8 meetings
• Technical management : at the same time & call meeting each two weeks
02/11/98 ISO-3D Kick-Off Meeting
Project Organisation
• Pack Office Version : office pro 97 (to discuss)
• Web site (to discuss)
• Documentation validation process (to discuss)
• Quality plan (to discuss)
02/11/98 ISO-3D Kick-Off Meeting
Six Months Work
Nº Nom de la tâche
4 WP2 : Users Requirements
5 T2.1 : Users Requirements
6 Deliverables (User requirements, Exploitation plan, Consortium agreement)
7 T2.2 : State of the Art
8 T2.3 : Symbolic Objects Generation
9 Deliverables (State of the Art, SO generation, Cost statement, Technical progress report)
M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D1998 1999 2000
Project Plan (WP1) MS&I T0User Requirements (WP2) ING T0+3Exploitation Plan (WP5) TGS T0+3
State of the art (WP2) MS&I T0+6SO Generation (WP2) DMS T0+6Cost Statement All T0+6Technical Progress Report All T0+6
02/11/98 ISO-3D Kick-Off Meeting
02/11/98 ISO-3D Kick-Off Meeting
Good By; I wish you a good back journey;See you next time