01-01 cbss radio network planning

Upload: naquash151

Post on 30-May-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/14/2019 01-01 cBSS Radio Network Planning

    1/30

    1 cBSS Radio Network PlanningAbout This Chapter

    Radio network planning refers to planning the cBSS network according to the network

    construction target, network evolution requirements, cost requirements, types of optional

    equipment. Radio network planning specifies the number of NEs required by network

    construction, configuration parameters, and engineering parameters before the cBSS network

    construction. Radio network planning is directly related to the performances, construction costs,

    and maintenance costs of future networks.

    1.1 Process of Radio Network Planning

    Radio network planning consists of two phases: preliminary radio network planning and finalradio network planning.

    1.2 Preliminary Radio Network Planning

    Preliminary radio network planning, conducted at the early stage of a project, is relatively rough

    compared with the final network planning.

    1.3 Final Radio Network Planning

    Final radio network planning refers to performing field survey for each site based on the results

    of preliminary radio network planning and determining the engineering parameters of each cell.

    The cell planning and cell parameter settings can be simulated. Final radio network planning is

    conducted after preliminary radio network planning is complete and the commercial contract is

    entered.

    1.4 Tools for Radio Network Planning

    The tools for radio network planning helps to collect and analyze data and thus assists radio

    network planning. The commonly used tools are CDMA RND tool, Genex U-Net, and Genex

    Apus.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-1

  • 8/14/2019 01-01 cBSS Radio Network Planning

    2/30

    1.1 Process of Radio Network Planning

    Radio network planning consists of two phases: preliminary radio network planning and final

    radio network planning.

    1.1.1 Procedure of Preliminary Radio Network Planning

    The preliminary radio network planning phase covers the following activities: information

    collection, area division, radio network dimensioning, propagation model selection, antenna

    selection, initial site selection, and system simulation.

    1.1.2 Procedure of Final Radio Network Planning

    The final radio network planning phase covers the following activities: noise test, site survey

    and selection, system simulation, and cell parameter planning.

    1.1.1 Procedure of Preliminary Radio Network PlanningThe preliminary radio network planning phase covers the following activities: information

    collection, area division, radio network dimensioning, propagation model selection, antenna

    selection, initial site selection, and system simulation.

    Figure 1-1 shows the procedure of preliminary radio network planning.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-2 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    3/30

    Figure 1-1 Procedure of preliminary radio network planning

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-3

  • 8/14/2019 01-01 cBSS Radio Network Planning

    4/30

  • 8/14/2019 01-01 cBSS Radio Network Planning

    5/30

    Figure 1-2 Procedure of final radio network planning

    Final radio network planning is detailed and specific planning on radio networks. Compared

    with preliminary network planning, final network planning differs only in the fact that system

    simulation, site survey and selection, and noise test are mandatory during final network planning

    but they are optional during preliminary network planning. Table 1-2 describes the tasks

    involved in network planning.

    Table 1-2 Tasks involved in final radio network planning

    No. Task Description

    1 Noise test Mandatory

    2 Site survey and

    selection

    If some sites are unqualified or inaccessible, define the

    Search Ring (by default, one fourth of the coverage radius)

    of the sites based on the preliminary network planning and

    re-select sites.

    3 System

    simulation

    Traffic distribution analysis

    Traffic model analysis

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-5

  • 8/14/2019 01-01 cBSS Radio Network Planning

    6/30

    No. Task Description

    4 Cell parameter

    planning

    Neighbor planning, PN planning, and system parameter

    planning

    As shown in Figure 1-2, network planning is dynamic and cyclic. The whole process, from

    providing a specific requirement, to preparing the network planning scheme, and to a planning

    report, is cyclic and adjustable. For example, after system simulation, the previous network

    planning scheme can be improved, and then after the site survey and selection, the previous

    scheme can be further improved.

    1.2 Preliminary Radio Network Planning

    Preliminary radio network planning, conducted at the early stage of a project, is relatively roughcompared with the final network planning.

    1.2.1 Input of Preliminary Radio Network Planning

    This describes the data and requirements to be collected before preliminary radio network

    planning.

    1.2.2 Procedure of Preliminary Radio Network Planning

    The preliminary radio network planning phase covers the following activities: area division,

    radio network dimensioning, propagation model selection, antenna selection, site selection, and

    system simulation.

    1.2.3 Output of Preliminary Radio Network PlanningAfter the preliminary radio network planning is complete, theNominal Radio Network Planning

    Reportand theRadio Network Engineering Parameters Table should be provided.

    1.2.1 Input of Preliminary Radio Network Planning

    This describes the data and requirements to be collected before preliminary radio network

    planning.

    Related information is collected in the initial phase of network planning. The collected

    information is used for network dimensioning, network simulation, and network construction

    policies. The collected information can be used for the input of network planning or for reference.

    Before network planning, the on-site owner needs to communicate with the customers or the

    persons from the Marketing Department to get aware of the network planning requirements. The

    on-site owner also needs to analyze expected planning output, destination information, network

    construction target, network scale limitation, and construction phase planning after the

    communication.

    The following information is required in the preliminary radio network planning phase:

    l Information provided by the Marketing Department, project documents before deployment,

    and destination information, such as population, area, and terrain

    l Requirements for network construction, including coverage service type, coverage,

    capacity, and quality requirements, if the contract is signed

    l Available sites and frequency, especially available sites of the initial network

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-6 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    7/30

    l Exact scenario definition of the area to be planned

    l Propagation model corrected by the CW test

    l Digital map and software platform for network planning

    If the existing network is expanded or migrated, the following information is required: recentnetwork optimization report, configuration of the existing network, drive test documents of the

    existing network, traffic measurement data of the existing network, and customer complaints

    against the existing network.

    1.2.2 Procedure of Preliminary Radio Network Planning

    The preliminary radio network planning phase covers the following activities: area division,

    radio network dimensioning, propagation model selection, antenna selection, site selection, and

    system simulation.

    1.2.2.1 Area Division

    Area division is the first step in network planning. By performing area division, the target

    coverage area is divided into different sub-areas based on the radio propagation environments,

    coverage rates, and traffic distribution.

    1.2.2.2 Radio Network Dimensioning

    Being an activity involved in preliminary radio network planning, the Radio Network

    Dimensioning (RND) refers to integrated dimensioning and planning of the numbers of BTSs

    and carriers required based on the results of coverage and capacity. The construction scale,

    constructionperiod, economic cost, and manpower cost of the network can be planned according

    to the network dimensioning results.

    1.2.2.3 Propagation Model Selection

    This describes how to select the propagation models and how to configure the related parameters.

    1.2.2.4 Antenna Selection

    This describes how to select appropriate antennas for a target network coverage area.

    1.2.2.5 Initial Site Selection

    This describes how to select appropriate sites and carry out site planning on the paper map or

    the electrical map according to the RND results, available site resources, coverage requirements,

    and analysis of the existing networks. The sites selected based on the theoretical calculation

    should conform to the ideal cellular network mesh structure.

    1.2.2.6 System Simulation

    System simulation refers to performing Monte Carlo simulation based on the results of initial

    site selection and the traffic model. The simulation results are used to locate the radio coverageproblem, and to check whether the network scale and the cell configuration meet the network

    construction requirements. Through adjusting site parameters, you can solve the radio coverage

    problem, and output engineering parameters for site construction, and cell parameters required

    by network construction.

    Area Division

    Area division is the first step in network planning. By performing area division, the target

    coverage area is divided into different sub-areas based on the radio propagation environments,

    coverage rates, and traffic distribution.

    The target coverage area, however, generally does not have obviously marked sub-areas. Indifferent sub-areas, such as urban areas and rural areas, the radio propagation environments,

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-7

  • 8/14/2019 01-01 cBSS Radio Network Planning

    8/30

    coverage rates, and traffic distribution are different. Thus, the quantity of BTSs differs in two

    areas with the same size. Generally, areas are divided into the following types:

    l Dense urban areas

    l Urban areas

    l Suburban areas

    l Rural areas

    Some special coverage areas can be divided into scenic spots, forests, grassland, or other types

    of terrain. Area scenario division directly affects network planning. Therefore, site survey at the

    early stage of network planning is necessary for the collection of information about the radio

    propagation environment. The results of site survey are the basis of scenario division.

    Table 1-3 describes the basis of area division.

    Table 1-3 Basis of area division

    Area Type Description

    Dense urban

    areas

    Areas that have very dense population, prosperous economy, large traffic,

    comparatively dense and tall buildings in the center of a city, and shopping

    centers with full vitality

    Urban areas Areas that have less dense population, less prosperous economy, large call

    traffic, dense buildings in the center of a city, and shopping centers with

    vitality

    Suburban

    areas

    Areas that have moderate population, developing and promising economy,

    moderate traffic, less dense buildings in the center of an area, and shopping

    centers with a moderate scale

    Rural areas Areas that have small population, developing economy, and less traffic

    Radio Network Dimensioning

    Being an activity involved in preliminary radio network planning, the Radio Network

    Dimensioning (RND) refers to integrated dimensioning and planning of the numbers of BTSs

    and carriers required based on the results of coverage and capacity. The construction scale,

    construction period, economic cost, and manpower cost of the network can be planned according

    to the network dimensioning results.

    Input of RND

    Table 1-4 describes the input of RND.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-8 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    9/30

    Table 1-4 Input of RND

    Input ofRND Description

    Service type Based on the requirements of network operators, determine the services thatrequire continuous coverage. Therefore, the cell radius is estimated based on

    the service type, and the network is dimensioned based on the cell radius.

    Dense urban areas and urban areas have high requirement for the service rate

    of continuous coverage, and therefore the cell radius is relatively small.

    Suburban areas and rural areas have low requirements for the service rate of

    continuous coverage, and therefore the cell radius is relatively large.

    NOTEServices are classified into voice service and data services of different rates. Voice

    service and data service should be analyzed separately.

    Cell target

    load

    The cell target load, indicated by percentage, is determined by the network

    construction target. It is subject to the following factors:l Uplink target load: If a low value is set, the dimension of the cell radius is

    large and fewer sites need to be planned. Therefore, the initial investment

    cost can be reduced. But when the number of subscribers increases, the

    radius of the cell is shortened, resulting in blind areas. For dense urban

    areas and urban areas, the uplink target load should be high enough to

    satisfy the requirements for capacity. For suburban areas and rural areas,

    the uplink target load can be relatively low to expand the network coverage

    and to reduce the initial investment cost. The typical value of the uplink

    target load is 50%60%.

    l Downlink target load: The value of the target load can be set relatively

    high, because the actual value is relatively high. The typical value is 90%.

    Traffic

    model

    The traffic model is determined by service parameters. Service parameters

    refer to the traffic volumes of each service used by a single subscriber.

    l For the voice service, the service volume of a single subscriber is indicated

    by traffic volume that is measured in Erl.

    l For the data service, the service volume of a single subscriber is indicated

    by busy hour throughput that is measured in bit/s.

    The value of the service volume of a single subscriber must be set according

    to actual situations, such as local economic development, consumption habits,

    living habits, and the expenses on mobile communications. For the service

    volume of a single subscriber:l If the value is set too high, more BTSs are required because the cell radius

    is very small. As a result, the initial investment cost is very high.

    l If the value is set too low, fewer BTSs are required because the cell radius

    is very large. As a result, the network capacity is so low that network

    expansion may be required shortly after the construction.

    Number of

    subscribers

    Refers to number of the mobile subscribers within the coverage of radio

    network services.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-9

  • 8/14/2019 01-01 cBSS Radio Network Planning

    10/30

    Input ofRND Description

    Propagation

    model

    Used to predict the impact that terrain and human actions have on path loss.

    An appropriate model can ensure the accuracy of dimensioning. The

    propagation model is selected on the basis of scenarios and geographical

    environments.

    Planning area Areas within the coverage of radio signals. The size of this area is determined

    by the requirements of the operator.

    Maximum

    number of

    available

    carriers every

    sector

    Refers to the maximum number of available carriers in each sector of a BTS.

    Relatedparameters of

    devices and

    terminals

    Includes the transmit power, height of antennas, antenna gain, type of feeders,and length of feeders.

    Target

    network

    quality

    Refers to the coverage rate, system blocking rate, and frame error rate.

    RND

    Coverage and capacity are considered during the RND phase, of which the procedure is described

    in Table 1-5 and shown in Figure 1-3.

    Table 1-5 Description of the RND procedure

    RND Process Description

    Obtain customer requirements for

    network construction. Get to know the

    objective and the policy of the network

    planning scheme by communicating

    with the marketing personnel.

    -

    Carry out capacity dimensioning of the

    network configuration that meets the

    capacity requirement.

    Figure 1-4 shows the capacity dimensioning

    process. The number of required BTSs and the

    number of required carriers are calculated

    according to the traffic model and the capacity that

    each type of BTS has. After capacity dimensioning,

    the CE configuration is required for each BTS. The

    detailed configuration of channel resources

    depends on BTS coverage and the number of

    subscribers that a BTS supports.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-10 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    11/30

    RND Process Description

    Carry out the coverage dimensioning

    and calculate the site coverage radius

    according to the specific network

    capacity (CDMA network load) and

    customer requirements.

    Figure 1-5 shows the coverage dimensioning

    process. During coverage dimensioning, the three

    should be taken into consideration: scenario type of

    the planning area, frequency scope, and network

    evaluation software. According to the principle of

    balancing between uplink and downlink, the

    maximum of allowed loss is calculated. The

    number of required BTSs can be calculated

    according to the coverage radius of a single site and

    the coverage area.

    Calculate the number of BTSs and that

    of carriers required according to the

    coverage and capacity results. Evaluate

    network configuration that meets

    requirements of both the coverage and

    the capacity. Export theHuawei Radio

    Network Plan Proposal.

    -

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-11

  • 8/14/2019 01-01 cBSS Radio Network Planning

    12/30

    Figure 1-3 RND procedure

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-12 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    13/30

    Figure 1-4 Capacity dimensioning

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-13

  • 8/14/2019 01-01 cBSS Radio Network Planning

    14/30

    Figure 1-5 Coverage dimensioning

    Output of RND

    Table 1-6 describes the output of RND.

    Table 1-6 Output of RND

    Item Output of RND

    1 Results of the link budget, such as site scale of each scenario, cell radius, and

    required number of BTSs that meets the coverage requirement

    2 Required number of BTSs, BTS type, and number of carriers

    3 Results including site scale of each scenario, cell radius, system resource

    requirements, number of BTSs, site type, and number of carriers, to meet the

    coverage and capacity requirements

    4 TheRadio Network Dimensioning Report, which is used for future reference

    Propagation Model Selection

    This describes how to select the propagation models and how to configure the related parameters.

    The propagation model selection phase consists of the following activities:

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-14 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    15/30

    l Selecting propagation models

    Appropriate propagation models should be selected for different scenarios. The commonly

    used propagation models are Okumura-Hata and Cost231-Hata.

    l Configuring the related parameters

    Table 1-7 describes the methods of configuring propagation model parameters.

    Table 1-7 Methods of configuring propagation model parameters

    Method Description

    Propagation

    model

    calibration

    This method is performed if the project time permits.

    Referring to the

    similar model

    The propagation model parameters are valued by referring to the

    calibrated model parameters in a similar radio environment. This

    method is commonly used in the phase of network dimensioning.

    Antenna Selection

    This describes how to select appropriate antennas for a target network coverage area.

    The antenna functions as the interface between the radio transceiver and the outside propagation

    medium. One antenna can function as a receiver and a transmitter. Network coverage is achieved

    by means of the antenna, so the selection of antenna types has a direct impact on the coverage

    quality and interference control.

    The specifications of the antenna performance include the working band, gain, polarization

    mode, beamwidth, preset tilt angle, tilt method, tilt adjustment range, front-to-back suppression

    ratio, secondary lobe suppression ratio, and zero-point filling. The gain, horizontal beamwidth,

    and vertical beamwidth are interrelated according to the structure of the antenna.

    Table 1-8 describes the requirements for the antenna type selection in different scenarios.

    Table 1-8 Requirements for antenna selection in different scenarios

    Scenari

    o Sector Antenna Type Selection

    Dense

    urban

    areas

    Urban

    areas

    3-

    sectored

    The antennas with bipolarization and 60 degrees to 65 degrees

    horizontal beamwidth are recommended.

    According to the BTS distribution and the building construction, the

    antennas with 1316 dBi gains are recommended. The antennas with

    1012 dBi gains or lower in the micro-cell/ODU great hypsography

    situation can be selected.

    The preset tilt antennas (36 degrees recommended) or electrical tilt

    antennas are preferred. The zero-point filling can be ignored because

    the distance between sites in urban areas is small. In addition, the

    antenna support must be mechanically adjustable from 015 degrees.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-15

  • 8/14/2019 01-01 cBSS Radio Network Planning

    16/30

    Scenario Sector Antenna Type Selection

    Suburban

    areas

    3-

    sectored

    The antennas with 65 degrees or 90 degrees horizontal beamwidth are

    recommended. If the surrounding BTSs are densely distributed, refer

    to the antenna type selection in urban areas. If the surrounding BTSs

    are sparsely distributed and the possibility of future expansion is

    slight, refer to the antenna type selection in rural areas.

    Whether the antenna has a preset tilt angle depends on actual

    situations. Usually, the antenna has a very small preset electrical tilt

    or does not have any preset electrical tilt. Refer to the cases in urban

    areas and rural areas on the basis of the distance between sites.

    Rural

    areas

    3-

    sectored

    Vertical polarization and space diversity.

    The directional antennas with 90 degrees horizontal beamwidth and

    1618 dBi gain are recommended. The following antennas with

    different beamwidth are recommended for special areas: 210 heart-shaped antennas at the mountainside, omni-directional antennas at the

    basin, and 8-shaped antennas at the valley.

    Typically, the mechanical tilt is recommended. The antenna without

    preset tilt angle is recommended. If the antenna is mounted more than

    50 meters high and the near end coverage is required, set the zero-

    point filling (more than 15%) to mandatory.

    Rural

    areas

    Omni-

    directio

    nal

    Vertical polarization and space diversity.

    The antennas with 11 dBi gain are recommended. If the required

    coverage distance is not long but the antenna is installed in a high

    position, the antennas with 3 degrees or degrees preset electrical tiltcan be used. If the required height is less than 50 meters, ordinary

    antennas can be used.

    When the 1X and 1xEV-DO networks are under co-site construction, there are two modes of

    antenna systems: sharing antenna system and not-sharing antenna system. Select the antenna

    system based on actual network resources for final network planning. The mode of sharing

    antenna system can save the space and the cost. But the two network systems may be mutually

    interfered, and certain loss is caused. Thus, forward and reverse coverage is affected. If 1X and

    1xEV-DO networks do not share the antenna system, no loss is caused, and accordingly forward

    and reverse coverage is not affected. But a large space is required.

    Initial Site Selection

    This describes how to select appropriate sites and carry out site planning on the paper map or

    the electrical map according to the RND results, available site resources, coverage requirements,

    and analysis of the existing networks. The sites selected based on the theoretical calculation

    should conform to the ideal cellular network mesh structure.

    The input information for initial site selection is listed as follows:

    l Dimensioning results, including network scale of each scenario and cell radius

    l Available site resources

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-16 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    17/30

  • 8/14/2019 01-01 cBSS Radio Network Planning

    18/30

    Item Action Description

    4 Predict the

    coverage.

    After the initial site selection, verify the quality of the network

    coverage through coverage dimensioning.

    Evaluate the coverage quality by observing the distribution of the pilotlevel and receiving level in the dimensioning results.

    l For plots, adjust the antenna direction and the tilt angle if the

    coverage level does not satisfy the requirements.

    l For large areas where the coverage level does not satisfy the

    requirements, add sites to increase the coverage if the distance

    between sites is extremely far. If the distance between sites is not

    extremely far, check whether the setting of parameters for the

    coverage prediction is proper.

    The output of initial site selection specifies the number of sites, site types, site locations

    (longitude and latitude), and engineering parameters of each site (antennal model, azimuth, tilt,

    and gain). The output is used for preliminary network planning.

    System Simulation

    System simulation refers to performing Monte Carlo simulation based on the results of initial

    site selection and the traffic model. The simulation results are used to locate the radio coverage

    problem, and to check whether the network scale and the cell configuration meet the network

    construction requirements. Through adjusting site parameters, you can solve the radio coverage

    problem, and output engineering parameters for site construction, and cell parameters required

    by network construction.

    The system simulation process in the preliminary planning phase is the same as that in the final

    planning phase. The differences between the preliminary planning phase and the final planning

    phase are as follows:

    l In the preliminary planning phase, as the time and the cost are limited, a site does not go

    through a field survey. The site is not available unless it is confirmed by the customer.

    Therefore, the estimated values of engineering parameters are used in the preliminary

    planning phase.

    l In the final planning phase, each site goes through field survey and should be confirmed

    as available. The engineering parameters must be confirmed. For example, the type and the

    length of feeders must conform to the actual requirements. If the system simulation resultsin the final planning phase do not meet the requirements, it is difficult to take corrective

    measures, if required.

    Input and Output of System Simulation

    Table 1-10 describes the input of the system simulation phase. After system simulation, the

    System Simulation Reportshould be provided.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-18 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    19/30

    Table 1-10 Input of system simulation

    Item Input

    1 Engineering parameters table

    2 Propagation model

    3 Scenarios, channel types, service types, traffic model, antenna parameters, and

    network parameters

    4 Simulation software and digital electric map

    Procedure of Simulation

    System simulation refers to using planning simulation software and simulating the actual

    network environment to achieve network coverage and QoS prediction.

    When the initial site selection and pilot coverage prediction satisfy the requirements, the system

    simulation conducts the Monte Carlo simulation according to the corresponding service type,

    traffic model, number of subscribers, and subscriber distribution. Usually, the system simulation

    takes a long time.

    Locate the problematic areas through system simulation. Export engineering parameters and cell

    parameters by adjusting the sites or taking other measures to satisfy the requirements of site

    construction.

    Figure 1-6 shows the simulation process by illustrating Huawei network planning software U-

    NET.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-19

  • 8/14/2019 01-01 cBSS Radio Network Planning

    20/30

    Figure 1-6 Simulation procedure of preliminary radio network planning

    Different from a simple network coverage prediction, the simulation focuses on the detailed

    analysis of the traffic model, subscriber behavior, and subscriber distribution in the network.

    These parameters are closely related to network capacity.

    The analysis of simulation results focuses on coverage prediction and Monte Carlo simulation

    so that you can check whether the RX and the Ec/Io satisfy the requirements. In addition, the

    simulation results also concern the access success ratio, pilot pollution, soft handoff ratio, uplink

    and downlink load analysis, and the access failure from which the causes and solutions can be

    found out.

    Through the analysis of simulation results, you can determine whether the network scale and

    cell configuration achieve the network construction objective.

    1.2.3 Output of Preliminary Radio Network Planning

    After the preliminary radio network planning is complete, theNominal Radio Network Planning

    Reportand theRadio Network Engineering Parameters Table should be provided.

    Table 1-11 describes the output of preliminary radio network planning.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-20 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    21/30

    Table 1-11 Output of preliminary radio network planning

    Output Report Topic

    Nominal Radio Network

    Planning Report

    l Network construction policy

    l Initial site planning

    l Suggestions for antenna selection

    l Simulation result evaluation

    Radio Network Engineering

    Parameters Table

    l Number of BTSs

    l Site location

    l Antenna type, azimuth angle, and tilt angle

    l Cell parameters, such as channel power and soft handoff

    parameters

    1.3 Final Radio Network Planning

    Final radio network planning refers to performing field survey for each site based on the results

    of preliminary radio network planning and determining the engineering parameters of each cell.

    The cell planning and cell parameter settings can be simulated. Final radio network planning is

    conducted after preliminary radio network planning is complete and the commercial contract is

    entered.

    1.3.1 Input ofFinal Radio Network Planning

    This describes the input of final radio network planning, that is, the output of preliminary radionetwork planning and the contract information.

    1.3.2 Procedure of Final Radio Network Planning

    The final radio network planning phase involves the following activities: noise test, site survey

    and selection, system simulation, and cell parameter planning.

    1.3.3 Output of Final Radio Network Planning

    This describes the output of final radio network planning. The output, including the information

    on BTS planning and the information on radio parameter planning, is presented in theRadio

    Network Planning Report,Radio Network Planning Engineering Parameters Table, andRadio

    Network Planning Cell Parameters Table.

    1.3.1 Input of Final Radio Network Planning

    This describes the input of final radio network planning, that is, the output of preliminary radio

    network planning and the contract information.

    The required input of final radio network planning is as follows:

    l Nominal Radio Network Planning Report

    l Radio network engineering parameters table

    l Requirements defined in the contract

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-21

  • 8/14/2019 01-01 cBSS Radio Network Planning

    22/30

    1.3.2 Procedure of Final Radio Network Planning

    The final radio network planning phase involves the following activities: noise test, site survey

    and selection, system simulation, and cell parameter planning.

    1.3.2.1 Noise Test

    A noise test is performed to check the interference and noises in the operating band, and thus

    appropriate measures can be taken to ensure smooth running of the network.

    1.3.2.2 Site Survey and Selection

    Site survey and selection are important during network planning. You can carry out a site survey

    for the candidate sites or the candidate site areas.

    1.3.2.3 System Simulation

    System simulation refers to performing Monte Carlo simulation based on the results of initial

    site selection and the traffic model. The simulation results are used to locate the radio coverage

    problem, and to check whether the network scale and the cell configuration meet the network

    construction requirements. Through adjusting site parameters, you can solve the radio coverage

    problem, and output engineering parameters for site construction, and cell parameters required

    by network construction.

    1.3.2.4 Cell Parameter Planning

    After specifying the size, BTS configuration, and BTS location of a network, interconnect

    detailed cell parameter planning with all BTSs and cells.

    Noise Test

    A noise test is performed to check the interference and noises in the operating band, and thus

    appropriate measures can be taken to ensure smooth running of the network.

    The noise test is optional, because the electromagnetic environment of each band is different. If

    required, on-site noise test must be performed by using an electric logging device or a YBT250

    tool.

    If strong noise interference exists over a frequency band, you must clear the noise or apply for

    new frequencies. In the phase of site selection, you must conduct noise tests in the areas that

    have heavy traffic or important landmarks to ensure that strong noise interference does not and

    will not exist. In this way, the network performance is guaranteed.

    After a noise test is complete, theNoise TestReportshould be provided for future reference.

    Site Survey and Selection

    Site survey and selection are important during network planning. You can carry out a site survey

    for the candidate sites or the candidate site areas.

    Survey tools and personnel cooperation: a GPS and a compass The project designers and the

    engineers of the operator should participate in the site survey.

    For each recommended site, collect network planning information and environment information

    to confirm that the site meets the construction requirements. The information required for a site

    survey is as follows:

    l

    Site information: site location (latitude and longitude), height, azimuth angle, site type,space ofthe equipment room, antenna installation (mode and location), transmission

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-22 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    23/30

    condition, power condition, grounding condition of the equipment room, business

    consideration (possibility of renting a site location or rent cost)

    l Environment information: type and distribution of the typical propagation environment,

    average height of buildings, plant distribution (type, height, and density), location of the

    coverage target, description of the adjacent environmentl In the case of co-site construction, you must consider available resources for the equipment

    room and the platform, antenna isolation, possible effect, and preventive measures.

    If the survey results of a site meet the construction requirements, the site can be selected. From

    the aspects of height, antenna space availability, and equipment room availability, you can

    conduct a simple survey and select one or two candidate sites.

    After the final site is confirmed, the Site Survey Reportshould be provided. The site survey

    report includes survey records of all sites, detailed description of the related items, subsequent

    preparations, and selected sites.

    System Simulation

    System simulation refers to performing Monte Carlo simulation based on the results of initial

    site selection and the traffic model. The simulation results are used to locate the radio coverage

    problem, and to check whether the network scale and the cell configuration meet the network

    construction requirements. Through adjusting site parameters, you can solve the radio coverage

    problem, and output engineering parameters for site construction, and cell parameters required

    by network construction.

    The system simulation process in the preliminary planning phase is the same as that in the final

    planning phase. The differences between the preliminary planning phase and the final planning

    phase are as follows:

    l In the preliminary planning phase, as the time and the cost are limited, a site does not gothrough a field survey. The site is not available unless it is confirmed by the customer.

    Therefore, the estimated values of engineering parameters are used in the preliminary

    planning phase.

    l In the final planning phase, each site goes through field survey and should be confirmed

    as available. The engineering parameters must be confirmed. For example, the type and the

    length of feeders must conform to the actual requirements. If the system simulation results

    in the final planning phase do not meet the requirements, it is difficult to take corrective

    measures, if required.

    Input and Output of System Simulation

    Table 1-13 describes the input of the system simulation phase. After system simulation, the

    System Simulation Reportshould be provided.

    Table 1-12 Input of system simulation

    Item Input

    1 Engineering parameters table

    2 Propagation model

    3 Scenarios, channel types, service types, traffic model, antenna parameters, and

    network parameters

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-23

  • 8/14/2019 01-01 cBSS Radio Network Planning

    24/30

  • 8/14/2019 01-01 cBSS Radio Network Planning

    25/30

    Figure 1-7 Simulation procedure of preliminary radio network planning

    Different from a simple network coverage prediction, the simulation focuses on the detailed

    analysis of the traffic model, subscriber behavior, and subscriber distribution in the network.

    These parameters are closely related to network capacity.

    The analysis of simulation results focuses on coverage prediction and Monte Carlo simulationso that you can check whether the RX and the Ec/Io satisfy the requirements. In addition, the

    simulation results also concern the access success ratio, pilot pollution, soft handoff ratio, uplink

    and downlink load analysis, and the access failure from which the causes and solutions can be

    found out.

    Through the analysis of simulation results, you can determine whether the network scale and

    cell configuration achieve the network construction objective.

    Cell Parameter Planning

    After specifying the size, BTS configuration, and BTS location of a network, interconnect

    detailed cell parameter planning with all BTSs and cells.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-25

  • 8/14/2019 01-01 cBSS Radio Network Planning

    26/30

    Cell parameters vary slightly with network types. Table 1-13 describes the cell parameters and

    planning methods.

    Table 1-13 Cell parameters and planning methods

    CellParameter Planning Method

    Location area

    planning

    NOTEThis parameter is planned for the 1X system only.

    l The value of the LAC cannot be set extremely large. The maximum

    value of the LAC depends on the paging channel capacity and

    processing capability of the BSC.

    l The value of the REG_ZONE cannot be set extremely small. The

    minimum value of the REG_ZONE depends on the access channel

    capacity.

    l The LAC planning should comply with the geographical position andthe action of MSs so that the border of a location area is not updated.

    l A location area cannot cross multiple MSC areas. The location area that

    crosses multiple BSC areas is not recommended.

    l In the case of multiple carriers, the carriers in one sector should be in

    the same location area.

    l Places with heavy traffic should not be in the border of a location area.

    Neighboring

    cell list (intra-

    frequency

    neighboringcell, inter-

    frequency

    neighboring

    cell, and inter-

    system

    neighboring

    cell)

    l Neighboring cells should be firstly configured for the sectors in the local

    BTS.

    l The geographically adjacent cells should be configured to neighboring

    cells.

    l Neighboring cells should be mutually related. In some special

    situations, a single neighboring cell is required.

    l In dense urban areas and urban areas, necessary neighboring cells

    should be configured, and on the other hand, excessive neighboring cells

    should be avoided.

    l In suburban areas, the geographically adjacent cells should be

    configured to neighboring cells to ensure timely handoff and to avoid

    call drop.

    l The neighboring cells with the strongest signals should be arranged in

    the front of the neighboring cell list to avoid interference.l The hard handoff of neighboring cells should be carried out in the places

    with light traffic as possible.

    PN code l Phases between different pilots should be arranged at intervals. When

    the pilots with different PN offset of other sectors appear in the Active

    Searching window of the current sector, the interference to the current

    sector should be lower than the preset threshold.

    l For the PN multiplexing distance between two BTSs with the same pilot,

    the interference that other sectors with the same PN offset cause to the

    current sector should be lower than the preset threshold.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-26 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    27/30

    CellParameter Planning Method

    Cell channel

    power matching

    Power distribution proportion of common channels (such as pilot channel,

    synchronization channel, and paging channel) and traffic channels.

    Handoff

    parameter

    planning and

    access

    parameter

    planning

    You must set the values of these parameters according to the actual

    network situations.

    Color code NOTEThis parameter is planned for the 1xEV-DO system only.

    l The color codes should vary with the subnets in the access network

    (AN).

    l The color codes corresponding to the subnets in an adjacent AN should

    be different from the color codes corresponding to the subnets in the

    AN.

    l The color codes corresponding to the subnets in one city (including the

    suburban areas) should be different. The color codes corresponding to

    the subnets in different cities (including the suburban areas) can be

    multiplexed.

    Subnet NOTEThis parameter is planned for the 1xEV-DO system only.

    l The entire network should be planned globally. The subnet locations

    should be unique in the entire network. Different operators are assigneddifferent network segments.

    l The value of a subnet cannot be set extremely large. The maximum

    value of a subnet depends on the CC channel capacity. The value of a

    subnet cannot be set extremely small. The minimum value of a subnet

    depends on the AC channel capacity. The calculation of the CC channel

    capacity and the AC channel capacity is omplex. You can get the

    calculation results from simulation results. Usually, one subnet is

    configured for an AN.

    l The subnet planning should comply with the geographical position and

    the action of MSs. This can reduce the location updates of MSs at the

    border of a subnet.

    l A subnet cannot cross multiple ANs.

    1.3.3 Output of Final Radio Network Planning

    This describes the output of final radio network planning. The output, including the information

    on BTS planning and the information on radio parameter planning, is presented in theRadio

    Network Planning Report,Radio Network Planning Engineering Parameters Table, andRadio

    Network Planning Cell Parameters Table.

    Table 1-14 describes the output of final radio network planning.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-27

  • 8/14/2019 01-01 cBSS Radio Network Planning

    28/30

    Table 1-14 Output of final radio network planning

    Output Description

    Information on radio

    network BTS planning

    l Site information

    l Design of the antenna system

    l Selection of the BTS equipment type

    Information on radio

    parameter planning

    l PN planning

    l Neighboring cell planning

    l Location area planning

    l 1xEV-DO color code planning

    l 1xEV-DO subnet planning

    l Planning of the system parameters, such as power parameters,

    switching parameters, and access parameters

    After the final radio network planning is complete, theRadio Network Planning Report,Radio

    Network Planning Engineering Parameters Table, andRadio Network Planning Cell

    Parameters Table should be provided. Table 1-15 describes the topics of the reports.

    Table 1-15 Output reports of final radio network planning

    Output Report Topic

    Radio Network PlanningReport

    l

    Network construction policies in different phasesl BTS planning

    l Cell parameter planning

    l Analysis of the simulation results

    l Solutions to coverage capacity in special scenarios

    l Required number of CEs in each site

    Radio Network Planning

    Engineering Parameters Table

    l Number, name, longitude and latitude of the BTS

    l Sector name, cell ID, and cell name

    l TRX ID and frequency

    l LAC, RAC, and PN code

    l Color code and subnet (1xEV-DO)

    l Antenna type, polarization mode, horizontal and vertical

    half power angle, and gain

    l Height, azimuth angle, and azimuth angle of the antenna

    l Power amplifier type, and combining and dividing mode

    l Type and length of the feeder

    l Cell coverage target

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline

    1-28 Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    Issue 2.0 (2008-03-12)

  • 8/14/2019 01-01 cBSS Radio Network Planning

    29/30

    Output Report Topic

    Radio Network Planning Cell

    Parameters Table

    l LAC/REG-ZONE configuration

    l Neighboring cell configuration

    l Frequency and PN code

    l Color code and subnet (1xEV-DO)

    l System parameters, such as power parameters,

    switching parameters, and access parameters

    1.4 Tools for Radio Network Planning

    The tools for radio network planning helps to collect and analyze data and thus assists radio

    network planning. The commonly used tools are CDMA RND tool, Genex U-Net, and GenexApus.

    CDMA RND Tool

    The RND tool, which is independently developed by Huawei, is a network dimensioning tool

    based on cumulative experiences of the RND. The tool is one of the important tools for

    preliminary network planning. With the iterative algorithm, the RND tool achieves the balance

    between the network coverage and the capacity, and accordingly simplifies network

    dimensioning. The functional modules of the RND tool are link budget, capacity budget, traffic

    model building, budget of the number of BTSs, and CE configuration budget.

    The tool can calculate the following dimensioning results based on the existing and preset

    relevant data:

    l Required number of BTSs that meet the coverage and capacity requirements

    l Coverage and capacity limitation

    l CE limitation

    l Throughput of the entire network, such as total forward throughput and total reserve

    throughput

    l Required number of BTSs that meet the coverage requirements

    l

    Forward and reverse coverage limitationl Coverage radius and coverage area of a single BTS

    l Required number of BTSs that meet the capacity requirements

    l Forward and reverse capacity limitation

    Genex U-Net

    The Genex U-Net, which is independently developed by Huawei, is a tool of radio network

    planning. Running on the Windows 2000 and Windows XP operating systems, the Genex U-

    Net supports 2G and 3G technologies and supports incumbent networks such as GSM/TDMA,

    GPRS-EDGE, WCDMA, and CDMA. In addition, it has the advantages of flexible user interfaceand easy operation.

    cBSS

    Network Planning Guideline 1 cBSS Radio Network Planning

    Issue 2.0 (2008-03-12) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd

    1-29

  • 8/14/2019 01-01 cBSS Radio Network Planning

    30/30

    Being a kind of simulation software of radio network planning, the Genex U-Net provides the

    global support for initial network design, dense network planning construction, and network

    optimization.

    The Genex U-Net has the following applications:

    l Used before the network construction. The Genex U-Net is used for nominal network

    planning, model calibration, prediction and simulation, and site analysis to ensure good

    effect of the network construction.

    l Used in network construction and expansion. The Genex U-Net performs parameter

    planning and simulation. In addition, this tool can analyze the network coverage and

    performance under different parameter configurations. In this way, reasonable parameters

    can be configured to ensure optimal network performance.

    l Used in network optimization. The Genex U-Net is used for network adjustment and

    optimization.

    Functions of the Genex U-Net are as follows:

    l Network construction and radio parameter model construction

    l Traffic modelling and capacity prediction

    l CDMA simulation based on the Monte-Carlo (supporting 1xRTT and 1xEV-DO)

    l CDMA coverage prediction (supporting 1xRTT and 1xEV-DO)

    l Statistic analysis

    Other functions of the Genex U-Net

    l Automatic planning for neighboring cells

    l Automatic PN planning and PN multiplexing checking

    l Propagation model calibration

    Genex Apus

    The Genex Apus, which is independently developed by Huawei, is a kind of Genex software.

    The Genex Apus is used in the network planning phase. The main functions are neighboring cell

    planning and PN planning.

    The Genex Apus has two modules: neighboring cell planning and PN planning. The module of

    neighboring cell planning implements automatic neighboring cell planning. The module of PNplanning implements automatic planning for PN codes. The following describes the two

    functions on the whole.

    l Neighboring cell planning

    Based on the BTS sector topology and radio parameters (such as the latitude and longitude,

    azimuth angle, and tilt angle, height of the antenna, and transmit power) related to the

    network sectors, the module can set multiple radio propagation models, and implement

    neighboring cell planning for the CDMA network.

    l PN planning

    Based on the BTS topology, the module implements automatic planning for PN codes.

    1 cBSS Radio Network Planning

    cBSS

    Network Planning Guideline