00_9533 - systems completion sequence (05-apr-10) (3)

Upload: sayafrands6252

Post on 02-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    1/13

    TRIPATRA

    SYSTEMS COMPLETION

    AREA PLAN

    BANYU URIP PROJECT

    CEPU - BOJONEGORO

    Mobil Cepu Ltd.

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    2/13

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    3/13

    TRIPATRA

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities

    2 (Nitrogen)

    2 (MCC)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Diesel & Chem. Storage.)

    2 (Closed Drain)2 (Essential Power)1 (Open Drain)

    1 (Raw Water)

    System Completion and Turnover -

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    2. First Oil Utilities

    M23

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    4/13

    TRIPATRA

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities

    2 (Nitrogen)

    2 (MCC)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Diesel & Chem. Storage.)

    2 (Closed Drain)2 (Essential Power)1 (Open Drain)

    1 (Raw Water)

    System Completion and Turnover -

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    M24

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    5/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities

    1 (Open Drain)1 (Raw Water)

    6 (CO Tank)2 (Nitrogen)

    2 (MCC)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Essential Power)

    2 (Diesel & Chem. Storage.)

    2 (Closed Drain)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    6. 1 st Oil Store / Inject

    M25

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    6/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities

    6. 1 st Oil Store / Inject

    1 (Open Drain)1 (Raw Water) 4 (Prod. Water)

    4 (SRU)

    4 (AGRU) 4 (AGE)4 (Chem. Inj. process)

    4 (Pri. Separation)

    4 (Gas comp & TEG)

    4 (AmineTank)

    2 (Nitrogen)

    2 (MCC)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Essential Power)

    2 (Diesel & Chem. Storage.)

    6 (CO Tank)

    2 (Closed Drain)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    4. First Oil Process

    M26

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    7/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities

    4. First Oil Process

    6. 1 st Oil Store / Inject

    1 (Open Drain)1 (Raw Water)

    3 (Raw Water)

    4 (Prod. Water)

    4 (SRU)

    4 (AGRU) 4 (AGE)4 (Chem. Inj. process)

    3 (GTG)

    4 (Pri. Separation)

    4 (Gas comp & TEG)

    4 (AmineTank)

    2 (Nitrogen)

    2 (MCC)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Essential Power)

    2 (Diesel & Chem. Storage.)

    6 (CO Tank)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    3. Non-1 st Oil Utilities

    M27

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    8/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities3. Non-1 st Oil Utilities4. First Oil Process

    6. 1 st Oil Store / Inject

    1 (Open Drain)1 (Raw Water)

    3 (Raw Water)

    7 (CO Tank)4 (Prod. Water)

    4 (SRU)

    4 (AGRU) 4 (AGE)4 (Chem. Inj. process)

    3 (GTG)

    6 (CO Tank)5 (Prod. Water)

    5 (SRU)5 (Steam Boiler)

    5 (Gas comp & TEG)

    4 (Pri. Separation)5 (Pri. Separation)

    4 (Gas comp & TEG)

    4 (AmineTank)

    2 (Nitrogen)

    2 (MCC)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Essential Power)

    2 (Diesel & Chem. Storage.)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    5. Non-1 st Oil Process

    7. Non-1 st Store / Inject

    M28

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    9/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities3. Non-1 st Oil Utilities4. First Oil Process5. Non-1 st Oil Process

    6. 1 st Oil Store / Inject

    7. Non-1 st Store / Inject

    1 (Open Drain)1 (Raw Water)

    3 (Raw Water)

    7 (CO Tank)4 (Prod. Water)

    4 (SRU)

    4 (AGRU) 4 (AGE)4 (Chem. Inj. process)

    3 (GTG)

    6 (CO Tank)5 (Prod. Water)

    5 (SRU)5 (Steam Boiler)

    5 (Gas comp & TEG)

    4 (Pri. Separation)5 (Pri. Separation)

    4 (Gas comp & TEG)

    4 (AmineTank)

    2 (Nitrogen)

    2 (MCC)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    2 (Essential Power)

    2 (Diesel & Chem. Storage.)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    M29

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    10/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities3. Non-1 st Oil Utilities4. First Oil Process5. Non-1 st Oil Process

    6. 1 st Oil Store / Inject

    7. Non-1 st Store / Inject

    2 (Nitrogen)

    2 (MCC) 4 (Pig Area)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG) 5 (Prod. Water)

    5 (SRU)5 (Steam Boiler)

    2 (EDG)2 (BFW, DeminWater, Fuel Gas)

    2 (Diesel & Chem. Storage.)

    2 (WTP, FireWater)

    1 (Open Drain)1 (Raw Water)

    3 (Raw Water)

    5 (Gas comp & TEG)7 (CO Tank)

    6 (CO Tank)

    2 (Essential Power)4 (Prod. Water)

    4 (Pri. Separation)5 (Pri. Separation)

    4 (Gas comp & TEG)

    4 (SRU)

    4 (AGRU) 4 (AGE)4 (Chem. Inj. process)4 (Amine

    Tank)

    3 (GTG)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    M30

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    11/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities3. Non-1 st Oil Utilities4. First Oil Process5. Non-1 st Oil Process

    6. 1 st Oil Store / Inject

    7. Non-1 st Store / Inject

    2 (Nitrogen)

    2 (MCC) 4 (Pig Area)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 - Air

    2 (GTG)

    2 (Essential Power)4 (Prod. Water)

    4 (SRU)

    4 (AGRU) 4 (AGE)2 (EDG) 4 (Chem. Inj. process)

    2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater)

    5 (Pri. Separation)4 (Pri. Separation)

    4 (Gas comp & TEG)

    5 (SRU)4 (AmineTank)5 (Steam Boiler)

    2 (Diesel & Chem. Storage.)

    5 (Prod. Water)

    1 (Open Drain)1 (Raw Water)

    3 (Raw Water)

    3 (GTG)5 (Gas comp & TEG)

    7 (CO Tank)

    6 (CO Tank)

    2 (Flare KO Drum)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    M31

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    12/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities3. Non-1 st Oil Utilities4. First Oil Process5. Non-1 st Oil Process

    6. 1 st Oil Store / Inject

    7. Non-1 st Store / Inject

    2 (Nitrogen)

    2 (MCC) 4 (Pig Area)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    3 (GTG)2 (Essential Power)

    4 (Prod. Water)

    4 (SRU)

    4 (AGRU) 4 (AGE)2 (EDG) 4 (Chem. Inj. process)

    2 (BFW, DeminWater, Fuel Gas)

    2 (WTP, FireWater) 6 (CO Tank)

    1 (Open Drain)1 (Raw Water)

    3 (Raw Water)

    7 (CO Tank)

    5 (Prod. Water) 4 (Pri. Separation)5 (Pri. Separation)

    4 (Gas comp & TEG)

    5 (SRU)5 (Steam Boiler)

    2 (Diesel & Chem. Storage.) 4 (AmineTank)

    5 (Gas comp & TEG)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First Oil

    M32

    Raw Water Utility to EPC5

  • 8/10/2019 00_9533 - Systems Completion Sequence (05-Apr-10) (3)

    13/13

    TRIPATRA

    System Completion and Turnover -

    KeyMilestones

    Month 22 23 24 25 26 27 28 29 30 31 32 33

    Week 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48

    1. Early Utilities2. First Oil Utilities3. Non-1 st Oil Utilities4. First Oil Process5. Non-1 st Oil Process

    6. 1 st Oil Store / Inject

    7. Non-1 st Store / Inject

    1 (Open Drain)1 (Raw Water)

    2 (Nitrogen)

    2 (MCC) 4 (Pig Area)

    2 (Closed Drain)

    2 (LP Flare)

    2 (HP Flare)

    2 (Flare KO Drum)

    2 - Air

    2 (GTG)

    3 (GTG)2 (Essential Power)

    4 (Prod. Water)

    5 (Prod. Water) 4 (Pri. Separation)5 (Pri. Separation)

    4 (Gas comp & TEG)5 (Gas comp & TEG)

    4 (SRU)

    5 (SRU)4 (AGRU) 4 (AGE)5 (Steam Boiler)

    2 (EDG)

    7 (CO Tank)

    6 (CO Tank)

    4 (Chem. Inj. process)2 (BFW, DeminWater, Fuel Gas)

    2 (Diesel & Chem. Storage.)

    2 (WTP, FireWater)

    4 (AmineTank)

    3 (Raw Water)

    = Static Commissioning= Dynamic Commissioning= Start-up= Stable Operation

    First OilRaw Water

    M33

    Utility to EPC5