003000115 e 03
TRANSCRIPT
-
8/13/2019 003000115 e 03
1/24
Alcatel-Lucent GSM
IO 115 - Change AC powered
MBO to DC powered MBO
BTS Document
Customization Procedure
3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
2/24
Status RELEASED
Shor t title io115
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel.
BLANK PAGE BREAK
2 / 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
3/24
-
8/13/2019 003000115 e 03
4/24
Contents
4 / 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
5/24
1 Overview
1 Overview
This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.
3DF 00300 0115 UAZZA Ed.03 5 / 24
-
8/13/2019 003000115 e 03
6/24
1 Overview
1.1 Presentation
Use this scenario to change AC powered MBO to DC powered MBO. Heatersand service light and socket remain AC powered.
1.2 PrerequisitesThe following specific information (inputs) is needed to complete the scenario:
All items required by this operation are available
All tools required by this operation are available.
1.3 Scheduling
This procedure can be performed for a MBO found in a store room or for aalready installed MBO that must be switched OFF.
1.3.1 Human Resources
Two persons are required to perform this task.
1.3.2 Duration
40 minutes + optional 30 minutes to remove the batteries and battery breaker.
1.4 Telecom / Supervision Outage
If the equipment integrated into network it must be stopped and powered OFF.
All telecommunication resources are lost.
1.5 Resources
1.5.1 Tools
The following table lists the tools to be used to complete the task.
Tool Size
Torx screwdriver 10
Torx screwdriver 20
Torx screwdriver 30
Socket wrench 8 mm
Socket wrench 10 mm
Open ended key 13 mm
Flat screw driver 5 mm
6 / 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
7/24
1 Overview
1.5.2 Supplies
The following table lists the supplies to be used to complete the task.
Item Mnemonic Reference
DC Power Unit Kit for MBO DCPKM 3BK 27393 AAAA
3DF 00300 0115 UAZZA Ed.03 7 / 24
-
8/13/2019 003000115 e 03
8/24
1 Overview
8 / 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
9/24
2 Scenario
2 Scenario
This section describes the tasks to be performed during change AC poweredMBO to DC powered MBO.
3DF 00300 0115 UAZZA Ed.03 9 / 24
-
8/13/2019 003000115 e 03
10/24
2 Scenario
2.1 Replace AC Power Items
2.1.1 Open the MBO Roof
Note: When removing the roof refer also to labelling at front of roof. For safety
conditions, it is recommended to handle the roof by two installers.
To open the top roof:
1. Open the front doors of the MBO
2. Remove the four screws at front of rack
H13
3. Locate the two hinges at rear of rack
4. Open the top roof about 20
5. Push it a little to rear to engage bolt in cut-out
10/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
11/24
2 Scenario
6. Remove the rear of roof from the bolt of hinges
7. Remove the top roof from the rack.
2.1.2 Switch OFF the MBO
To switch OFF the MBO:
1. Switch OFF the site power breaker
2. Switch OFF the battery breaker if equipped
3. Switch OFF F3 to F5 breakers on ACMU panel.
2.1.3 Remove the PM 12 Modules
To remove the PM12 modules:
1. On ADAM4 remove the blue cable from the -48V clamp
2. On ADAM4 remove the black cable from the 0V clamp
3. Remove the black cable from the BOMU grounding stud
4. If batteries are equipped remove the the blue cable from the BATT. -48Vclamp
3DF 00300 0115 UAZZA Ed.03 11/ 24
-
8/13/2019 003000115 e 03
12/24
2 Scenario
5. If batteries are equipped remove the the black cable from the 0V clamp
Figure 1: Cables on ADAM 4
6. Remove the power cables from the PM12 modules
7. Attach the power cables to the upright using cable ties
8. Loosen the screws fixing the PM12 modules and remove the modulesfrom the STASR
9. Loosen the screws fixing the ADAM4 and remove the ADAM4 from theSTASR
10. Loosen the screws fixing the subrack and remove the subrack.
2.1.4 Option: Remove the Batteries
To remove the batteries:
1. Loosen the screws fixing battery cover and remove the cover
H13
H13
H13H13
H13
H13
12/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
13/24
2 Scenario
2. Remove gas-hose from batteries (be careful, Batteries and T- connectorsare fragile. Use hot air blower to soften gas-hoses)
3. Remove the caps from the pole pins of battery
4. On (+) terminal at the right lower battery, remove the nut/screw, disconnectthe cable that goes to the circuit breaker and the temperature sensor cable
5. On (-) terminal at the left upper battery disconnect the cable that goes tothe circuit breaker
3DF 00300 0115 UAZZA Ed.03 13/ 24
-
8/13/2019 003000115 e 03
14/24
2 Scenario
6. Remove the electrical jumpers between the elements of battery
7. Remove all elements of battery
8. Loosen the screws fixing the battery breaker and remove the breaker
9. Fit back the battery cover and fix it with the screws
10. Loosen the screws fixing the battery breaker and remove the breaker.
14/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
15/24
2 Scenario
2.2 Install the DC Power Items
2.2.1 Connect the Circuit Breaker
In the following description, connection position is given referring to the backview of the circuit breaker.
To connect the cables to the circuit breaker:
1. Connect the SCBL1 blue cable (3BK 26646 AAAA) to the circuit breakertop left position
SCBL1(Blue)
SCBL2(Blue)
SCBK3(Variant AAAA
Black)
SCBK3(Variant ABAA
Black)
Figure 2: DC Breaker Rear and Side Views
2. Connect the SCBL2 blue cable (3BK 26647 ABAA) to the circuit breakerbottom left position
3. Connect the SCBK3 black cable (3BK 27841 AAAA) to the circuit breakertop right position
4. Connect the SCBK3 black cable (3BK 27841 ABAA) to the circuit breakerbottom right position.
5. Fit the edge protection on the upper part of the upright
3DF 00300 0115 UAZZA Ed.03 15/ 24
-
8/13/2019 003000115 e 03
16/24
2 Scenario
6. Install the circuit breaker on the top of the MBO. Fix it with the M5 screws orM5 nuts, depending on MBO variant.
2.2.2 Connect the Cables to the X9 Clamp
To connect the cables to the X9 clamp:
1. Fit the clamp 1AB 07331 0007 to the angle 3BK 26676 AAAA
2. Connect the blue cable (3BK 26647 ABAA) to the X9 clamp left part
3. Connect the blue cable coming from BOMU to the X9 clamp right part
16/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
17/24
2 Scenario
4. Connect the clamp to the rack
5. Connect the SCBK3 black cable (3BK 27841ABAA) to the BOMU 0Vgrounding stud.
3DF 00300 0115 UAZZA Ed.03 17/ 24
-
8/13/2019 003000115 e 03
18/24
2 Scenario
2.2.3 Install the DC IN Filter
To install the DC IN filter:
1. Remove the cap closing the hole for DC IN filter
2. Remove the nut from the filter
3. Run the filter through the hole from inside the MBO
4. Fix the filter by tightening the nut. Make sure that the sealin gring is incorrect position. See detail in Figure 3.
5. Remove the nuts and washers from the DC IN filter end and 0V groundingstud
6. Run the SCBL1 blue cable (3BK 26646 AAAA) through the rubber cap
7. Connect the SCBL1 blue cable (3BK 26646 AAAA) to the lower part of theDC IN filter and fix it with the screw and washer.
Make sure that the cable is oriented towards the back side not towardsthe door side.
Rubber Cap
MBS Roof
Externally GroundingBolt M6
InternallyGrounding Bolt M6
Rubber Cap
Mounting Orientationfor Sealing Ring
Take care of orientation.Cable must be oriented towardsback side not towards door side.
SCBL1 (Blue)
SCBK3 (Black)
Figure 3: DC IN Connection
18/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
19/24
2 Scenario
Figure 4: DC IN Correct Cable Position
8. Fit the rubber protective cap to the lower end of the DC IN filter
Figure 5: DC IN Inside MBO View
9. Connect the SCBK3 black cable (3BK 27841 AAAA) to the grounding studinside the MBO and fix it with the screw and washer
2.2.4 Connect the DC IN Cables
To connect the DC IN cables:
1. Crimp terminal lugs on both DC IN cables at site side
2. Run the blue cable coming from site distribution panel through the rubberprotective cap
3DF 00300 0115 UAZZA Ed.03 19/ 24
-
8/13/2019 003000115 e 03
20/24
2 Scenario
3. Connect the -48V blue cable coming from site distribution panel to the DC INfilter and fix it with screw and washer.
Make sure that terminal lugs are fixed as shown in the following figure.
Figure 6: Terminal Lugs Correct Position
4. Fit the rubber protective cap to the upper end of the DC IN filter
5. Connect the 0V black cable coming from site distribution panel to the DCIN grounding stud
6. Fit the labels on the MBO top side
20/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
21/24
2 Scenario
The following picture shows the final arrangement of installed items andcables.
7. Close the MBO roof
Follow the reverse procedure from Open the MBO Roof (Section 2.1.1) toclose the MBO roof.
8. Close the front doors of the MBO.
3DF 00300 0115 UAZZA Ed.03 21/ 24
-
8/13/2019 003000115 e 03
22/24
2 Scenario
22/ 24 3DF 00300 0115 UAZZA Ed.03
-
8/13/2019 003000115 e 03
23/24
Appendix A : Completion Check List (CCL) for IO115
Appendix A: Completion Check List (CCL) for IO115
Date, Time and Duration of Work Start End Duration
Responsible: Visa: Date:
Traffic Outage
Start End Comments
1
2
3
4
5
6
3DF 00300 0115 UAZZA Ed.03 23/ 24
-
8/13/2019 003000115 e 03
24/24