0 harmonization process, work plan, and schedule chicago il. march 5, 2007 hitsp project 2007 work...
TRANSCRIPT
1Harmonization Process, Work Plan, and Schedule
Chicago IL. March 5, 2007
HITSP Project 2007 Work Plan and Schedule
Contract HHSP23320054103EC
2Harmonization Process, Work Plan, and Schedule
Agenda
Work Plan and Schedule Overview
Release 2.0 Detail Schedule– Key Points
– Implementation Testing
Emergency Responder EHR and Security and Privacy Detail Schedule – Key Points
3Harmonization Process, Work Plan, and Schedule
Standards Harmonization Work Plan Tasks
I
Harmonization Request
II
RequirementsAnalysis
III
Identificationof Candidate
Standards
IV
Gaps,Duplications
and Overlaps
Resolution
V
Standards Selection
VI
Constructionof
InteroperabilitySpecification
VII
InspectionTest
VIII
InteroperabilitySpecification
Releaseand
Dissemination
IXProgram Management
3 months
3 weeks
3 months 4 weeks 2 months
Work Plan and Schedule Overview
On-going
Requirements, Standards Selection, and Design
Public and Panel Review
and Input
Inspection Test, Public and Panel Comment
Implementation Support and
Testing
Comment Resolution and Panel Approval
Interoperability Specification Construct
Development
IS Docs V 1.0
Review Draft
Summary of comment resolution
IS Docs V 1.0
Summary of comment resolution
Requirements, Standards
Selection, and Design
Consolidated comments
Consolidated comments
Annual Updates as Required
PROCESS
TASKS
DOCUMENTATION
4Harmonization Process, Work Plan, and Schedule
Key Activities and Milestones
Activity 1: Version 2.0 of Existing Use Cases– Minor updates to CE, BIO, and EHR based on implementation and other TC activities; includes
minor technical updates to CE ISC-32 for CCD
– Scheduled for release May 11, 2007
Activity 2: Ongoing work for Existing Use Cases (e.g. Security and Privacy)– Security and Privacy Work Group updates; along with other ongoing updates to CE, BIO, EHR
– Scheduled for release October 15, 2007
Activity 3: Emergency Responder EHR Use Case– New Emergency Responder EHR IS
– Scheduled for release October 15, 2007
Activity 4: New Use Cases Expected in March 2007– Detailed schedule to be determined upon review of use cases
Work Plan and Schedule Overview
5Harmonization Process, Work Plan, and Schedule
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
HITSP 2007 Timeline
02/05/07HITSP Board
04/23/07HITSP Board
07/09/07HITSP Board
10/09/07HITSP Board
03/19/07HITSP Panel
05/11/07HITSP Panel
09/07/07HITSP Panel
03/06 – 03/08TC Face to Face
Chicago IL
5/08 – 5/10TC Face to Face
Arlington VA
6/18 – 6/20TC Face to Face
San Diego CA
09/04 – 09/06TC Face to Face
Arlington VA
Requirements, Standards Selection, and Design
Public Input Inspect Test and Public Comment
Implementation Support and Testing
(with annual updates as required)
Comment Resolution and Panel Approval
01/19 – 04/12
04/13 – 05/03
IS Construct Development
04/13 – 07/19 07/20 – 08/16 08/17 – 10/15
Implementation Support and Testing(includes minor document updates)
EHR, CE and BIO v 2.0
Activity 1 – Version 2.0 of Existing EHR, CE, BIO ISs
Activity 2 – On-going Work for Existing EHR, CE, BIO ISs (e.g. Security and Privacy) Activity 3 – New Emergency Responder EHR Use Case
On-going Support
10/15/07HITSP Panel
07/16/07HITSP Panel
02/12/07HITSP Panel
Activity 4 –New Use Cases from AHIC
Detail Schedule to be Established Upon Review of the Use Cases
Work Plan and Schedule Overview
S&P and EHR-ER v 1.0, EHR, CE, and BIO v M.m
6Harmonization Process, Work Plan, and Schedule
Version 2.0 of Existing EHR, BIO, CE ISs
Release 2.0 Detailed Schedule
Activity Date
Implementation Testing (via Connectathon and other activities) Now - April
TC Face to Face in Chicago to start to disposition correction requests
March 6 – 8
March 19 Panel Meeting to review progress on version 2.0 March 19
TC Construct Updates (with on-going correction request disposition and Panel input)
March 9 – April 20
Project Team Editorial Review, Audit, and Publication April 23 – April 27
Release Summary of Updates 10 days in advance of Panel meeting April 27
May 11 Panel Meeting to approve minor updates to CE, BIO, and EHR version 2.0
May 11
7Harmonization Process, Work Plan, and Schedule
Key Points about the Release 2.0 Schedule
The TC have until April 20th to finalize Release 2.0. Prior to April 20th you need to…..
– Review and disposition any comments resulting from Implementation Testing. Determine what changes need to be made to the IS document based on comments and based on your 2007 SOWs
– Make the changes to the working version of the IS documents using TRACK changes (see Bob Yencha for location of the working version of these documents)
– Document a summary of the release 2.0 changes as the last section of each document (see Bob Yencha for an example of a change summary section and the appropriate level of detail).
– Coordinate changes to all XTC documents through Bob Yencha
There is NO formal comment period for release 2.0, therefore it is CRITICAL that each TC set up a schedule of meetings where members of the Panel can participate in the review and finalization of the release 2.0 changes.
Once you hand over the updated IS documents to the Project Team, we will conduct an editorial review and an audit of the changes against the comments. We will release to the Panel on April 27th for approval May 11th.
Release 2.0 Detailed Schedule
8Harmonization Process, Work Plan, and Schedule
Implementation Testing for Release 2.0
The HITSP team leveraged the IHE Connectathon to identify vendors to support implementation testing of the existing HITSP interoperability specifications
– Prior to the IHE Connectathon, the HITSP/NIST team identified 14 vendors that were demonstrating the IHE profiles as part of the HIMSS Interoperability Showcase in February 2007.
– These vendors agreed to sign up as “HITSP vendors” to support the implementation testing of the IS documents associated with the relevant IHE profiles
Following the Connectathon, the HITSP worked with the vendors to gather their feedback
– The HITSP team provided each vendor with the HITSP IS documents relevant to their applications and requested from the vendors relevant documents, messages, acknowledgements and/or logs.
– Vendors were also asked to participate in facilitated feedback sessions led by Lori Reed-Fourquet from the HITSP Project Team.
As of March 2, 2007, 10 HITSP Connectathon vendors have provided feedback. In addition, one NHIN vendor has provided feedback and two other NHIN vendors have agreed to provide feedback in the near future.
Release 2.0 Detailed Schedule
9Harmonization Process, Work Plan, and Schedule
Implementation Testing Results for Release 2.0
IHE Profile HITSP Document ACEP ACUOALER
T
ALLSCRIPT
S
CAPMED
CAQHECLIPSYS
GE HXTI IBMINITIA
TEMIE
NEXTGEN
U. WA TOTAL
NA ISBIO-02 Biosurveillance Interoperability Specification 1 0 7 8 16
NA ISCE-03 Consumer Empowerment Interoperability Specification 1 5 1 0 6
XDS ISTP-13 Manage Sharing of Documents 1 0 11 1 2 1 13
PIX IST-22 Patient ID Cross Referencing 2 2 2 1 8 1 1 0 17
PDQ IST-23 Patient Demographics Query 1 2 3 1 6
NA IST-24 Biosurveillance Pseudonymize 1 0 1 1
NA IST-25 Anonymize Transaction 0 2 2
XD-Lab ISC-37 Lab Report Document 1 6 7
NA ISC-39 Encounter Message 0
NA ISC-47 Resource Utilization Message 4 0 0 4
XDS-MS ISC-48 Encounter Document 3 0 3 5 11
XDS-I ISTP-49 Radiology Report Document 2 4 0 4
RFD ISTP-50 Retrieve Form for Data Capture 4 0 2 6
General Feedback 2 2 2 1 1 8
Total 4 3 0 12 0 5 5 0 0 29 11 11 8 13 101
Release 2.0 Detailed Schedule
10Harmonization Process, Work Plan, and Schedule
Version 1.0 of the Security and Privacy Constructs and Emergency Responder EHR IS
Activity Date
Requirements and Design Now – April 12
TC Face to Face in Chicago to document Requirements, Standards Selection, and Design (RSSD)
March 6 – 8
March 19 Panel Meeting to review progress March 19
TC approves RSSD April 6
Project Team Editorial Review and Publication April 9 - 12
Public and Panel Review and Input on the RSSD April 13 – May 3
TCs Construct Development and Comment Disposition April 13 – July 19
TC Face to Face in Arlington to triage comments and continue IS development
May 8 - 10
May 11 Panel Meeting to review summary of comments received and status of IS development
May 11
TC Face to Face in San Diego to continue IS development June 18 - 20
July 16 Panel Meeting to review summary of comment disposition and draft IS docs
July 16
Continued on next page…
ER-EHR and S&P Detailed Schedule
11Harmonization Process, Work Plan, and Schedule
Activity Date
Inspection Test and Public Comment July 20 – August 16
Comment Resolution and Re-publication August 17 – October 8
TC Disposition Comments and Update Documents August 17 – September 21
TC Face to Face in Arlington to complete comment resolution and update documents
September 4 - 6
September 7 Panel Meeting to review progress of comment resolution
September 7
Project Team Editorial Review, Audit, and Re-publication September 24 – October 5
Release 5 days in advance of Panel meeting October 8
October 15 Panel Meeting to Approve ISs October 15
Version 1.0 of the Security and Privacy Constructs and Emergency Responder EHR IS
ER-EHR and S&P Detailed Schedule
12Harmonization Process, Work Plan, and Schedule
Key Points about the Emergency Responder EHR and Security and Privacy Schedule
The TC have until April 6th to finalize the Requirements, Standards Selection and Design (RSSD) Document
– Please see Sarah Quaynor if you have any questions or comments on the RSSD template
Once you hand over the RSSD to the Project Team, we will conduct an editorial review and release for a public review and input period from April 13th to May 3rd
– The comments on the RSSD will feed into the Interoperability Specification
– You DO need to disposition all comment on the RSSD and document the dispositions but you DO NOT need to republish the RSSD
– So….after you hand over the RSSD, you may start working on the Interoperability Specifications – you do not need to wait!
The TCs will then have until mid-July to produce the Interoperability Specifications
The ISs will go through a 4 week period of inspection test and public comment
The TCS will then have from August 17 to September 21st to disposition comment and republish the ISs for Panel approval by October 15th
ER-EHR and S&P Detailed Schedule