342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotfhtm 11
Welcome to the latest MTA Eye on the Future in which we present capital projects that are planned to be advertised
from March 2014 ndash September 2014 The Eye is hosted on our MTA Capital Program web site which assembles
key information and resources about the Capital Program in one convenient location It is another part of how we are
changing the way we do business and we hope that you find it to be useful
The MTA Capital Program is not only very important for the safety and reliability of the MTA transportation system it is
also vital to the regional economy As described in this issue of the Eye the MTA is preparing to undertake
approximately $4 billion in capital work that spans many areas including civil structural and electrical as well as new
technologies Based on the October 2009 APTA publication on the Economic Impact of Public Transportation
Investments this amount of investment is projected to create more than 98 thousand jobs and generate close to $17
billion in economic activity for the New York region These projects are vital to the reliability growth and resiliency of the system and
contribute to the regional economy We look forward to your participation
Contractors and suppliers have a critical stake in the success of the Capital Program We appreciate your interest in and support of the
projects included in this issue of the Eye
Yours truly
Thomas F Prendergast
Chairman and Chief Executive Officer
Click here for Eye on the Future
Download a Printable PDF File
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 14
Information About Contracts that Will Be Advertised for
Professional Services Construction and Equipment Procurement
MARCH 2014 ndash SEPTEMBER 2014
Letter from the Chairman
Information About Contracts
Overview
Contacts
Selected Contract Provisions
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Overview
This edition of An Eye on the Future contains information for prospective contractors engineers architects and vendors about contracts that are expected
to be advertised for bids between March 2014 ndash September 2014 by the Metropolitan Transportation Authoritys operating agencies
MTA New York City Transit (NYC Transit)
MTA Staten Island Railway (SIRTOA)
MTA Long Island Rail Road (LIRR)
MTA Metro-North Railroad (MNR)
MTA Bridges and Tunnels (BampT)
MTA Capital Construction (MTACC)
MTA Bus Company (MTA Bus)
In 1993 the MTA board approved a new service identity program for the MTA family of agencies The identity program provides for the use of the above
popular names to make clear to our customers that the various MTA affiliates and subsidiaries constitute an integrated regional transportation network
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 24
Security amp Consulting Service for NEW YORK CITY
TRANSIT ONLY
Mr Joseph Paldino
Assistant Chief Procurement Officer
Materiel Division
MTA New York City Transit
2 Broadway
New York NY 10004
Telephone (646) 252-6330
Fax(646) 252-6099
Email josephpaldinonyctcom
For all other contracts
Mr Robert Eskenazi
Senior Director Materiel Division
MTA New York City Transit
2 Broadway
New York NY 10004
Telephone (646) 252-6258
Fax (646) 252-6144
Email roberteskenazinyctcom
MTA NEW YORK CITY TRANSIT MTA STATEN ISLAND RAILWAY MTA BUS COMPANY
However for all procurement documents and official transactions the agencies retain their legal names New York City Transit Authority Staten Island
Rapid Transit Operating Authority the Long Island Rail Road Company Metro-North Commuter Railroad Company Triborough Bridge and Tunnel Authority
Capital Construction and Bus Company
With respect to the contract descriptions and other data included in this volume readers should note that they are for general information only and are not
to be construed as final The exact description of the work and other pertinent information concerning an individual contract will be found in the contract
specifications and drawings or solicitation documents which may be obtained by prospective bidders when solicitation begins Most contracts for
construction procurement of capital equipment and professional services are awarded after a competitive process including sealed bids for construction
and procurements and competitive requests for proposals for professional services
Some aspects of contracting are common to all the MTA agencies
1 MTA agencies are not subject to the Wicks Law for their construction projects
2 MTA agencies seek the best contractors suppliers and professional services firms in the business including firms owned by women and minorities for
which special efforts are made to ensure appropriate participation We pledge to do our part to make all projects successful for the agencies and
contractors alike
3 Projects already funded by Federal grants are noted in the solicitation schedule with an asterisk Some of the other projects may become eligible for
Federal funding in future grant applications
Public notices of solicitations are normally published in advance of the availability of contract documents or requests for proposals in the New York State
Contract Reporter and in one or more of the following publications
New York Post
El Diario
The Daily Challenge
Amsterdam News
Minority Commerce Weekly
Engineering News Record
Contacts
Further information about contracts adverstised here can be obtained by contacting respective agency representatives
MTA METRO-NORTH RAILROAD
Mr Charles F Hansen
Deputy Director - Capital Procurement
MTA Metro-North Railroad
347 Madison Avenue 14th Floor
New York New York 10017-3706
Telephone (212) 340-3262
Fax (212) 340-4034
E-mail hansenmnrorg
MTA LONG ISLAND RAIL ROAD
Ms Carla Butler
Contract Research Clerk
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 34
Planning amp Construction
MTA Long Island Rail Road
90-27 Sutphin Boulevard (0335)
Jamaica New York 11435
Telephone (718) 725-2622
Fax (718) 725-2676
E-mail cbutlerlirrorg
MTA BRIDGES amp TUNNELS
Ms Victoria Warren
Procurement and Materials
MTA Bridges and Tunnels
2 Broadway 24th Floor
New York New York 10004
Telephone (646) 252-7092
Fax (646) 252-7077
E-mail vprocuremtabtorg
MTA CAPITAL CONSTRUCTION
Mr David K Cannon
Senior Director and Chief Procurement Officer
Procurement and Law Department
MTA Capital Construction
2 Broadway - A899
New York New York 10004
Telephone (646) 252-2321
E-mail dcannonmtaccinfo
Selected Provisions of Capital Program Contracts
This is a summary of several provisions which are generally applicable to MTA agency projects Complete requirements for a given contract can only be
obtained from the documents for that contract Naturally all construction is performed under the laws and regulations of New York State This is not
intended to be a full summary of General Provisions
1 MTA New York City Transit the two commuter railroads and MTA Capital Construction base progress payments on the contractors monthly
submissions of cost-loaded schedules The use of CPM network diagrams is required for complex projects while simpler bar charts are required for
less complex projects
2 All the agencies contract documents contain a value engineering change proposal clause Contractors are encouraged to submit cost saving proposals
during construction and upon acceptance of the proposal would be able to share in the actual cost savings
3 Another effort to improve the management of capital projects is the use of contractor evaluation files that are kept on all ongoing work All the MTA
agencies use identical criteria to evaluate contractors and share the information with the other MTA agencies
4 The period between advertisement for bids and bid opening will vary from approximately four to eight weeks depending on size of the contract
5 Unless specifically noted in the bid document the transit facilities will be in continuous operation during the performance of the work for the majority of
contracts The contracting agency will provide the necessary maintainers flagmen diversions of service and work trains
6 Bidders will be required to submit prior to the award of the contract a program of affirmative action to provide for equal employment opportunity
Submittals will be described in the contract documents Goals for the participation of minority-owned and women-owned firms may be specified for
each contract
Minority business enterprises and women business enterprises will be afforded full opportunity to submit bids andor proposals and will not be
subjected to discrimination on the basis of race religion color sex or national origin in consideration for awarding contracts
7 A bid bond or a certified check in the amount of five to ten percent is normally required at the time of delivery of the bid The contractor must furnish a
performance bond and payment bond in amounts equal to 100 percent of the contract price
8 In addition to other requirements specifically provided in the contract each bidder must be prepared to prove to the satisfaction of the contracting
agency that he has the qualifications including but not limited to skill and experience and the necessary facilities and financial resources to complete
the work in a satisfactory manner within the time specified
9 Contracts generally require a guarantee of all apparatuses devices workmanship and materials for at least one year A security in the form of a bond
in the sum of a predetermined percentage of the amount of the contract may be required prior to the final payment Contracts may have additional
requirements which must be reviewed
10 The contractor shall also maintain at a minimum Workers Compensation Commercial General Liability and Commercial Automobile Insurance
Additional coverage may be required and will be indicated in the contract The MTA and the contracting agency shall be named as an additional insured
on the policy In general coverage requirements range from $1000000 to $5000000 combined single limit for injuries to persons (including death) and
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 44
for damage to property The limits of liability will vary depending on the size and type of projects In addition the contractor will be required to hold the
governmental agencies and contracting agency harmless Evidence of the required insurance shall be delivered to the contracting agency on an MTA
approved Certificate of Insurance prior to execution of the contract
Each insurance policy or Certificate of Insurance shall contain an agreement by the insurance company issuing the policy that the policy will not be
canceled terminated or modified without 30 days prior notice to the contracting agency At least two weeks prior to the expiration of each policy the
contractor shall endeavor to provide an updated Certificate of Insurance evidencing renewal coverage to the contract agency
The MTA has in place Owner Controlled Insurance Programs (OCIP) for the East Side Access (ESA) project the Second Avenue Subway and selected
projects in the Capital Plan Under traditional OCIPs the MTA covers the construction phase of work and provides general liability excess liability
workers compensation railroad protective and builders risk coverage to all participating contractors The ESA OCIP adds environmental liability
coverage for related engineering and environmental work
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 14
Forecast of Contracts to be Advertised and Proposals to be Solicited
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
MARCH 2014 ndash SEPTEMBER 2014
Type of
ContractSolic Month Reference Number Contract Description Agency Range
Bridges and Tunnels
Constr Mgmt MAR 2014 HH-88A Construction Management Services for HH-88A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-23A Construction Management Services for RK-23A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-44 Construction Management Services for RK-44 Painting
Contract
BampT $1M - $5M
Constr MAR 2014 RK-44 Cleaning and Painting of RFK Main Cables Suspender
Ropes and Tower Interior and Exterior
BampT $5M - $10M
Constr APR 2014 MP-21 (DB) DesignBuild Rehabilitation of the Rockaway Point
Boulevard Overpass and Jacob Riis Park Pedestrian
Bridge)
BampT $5M - $10M
Special
Services
APR 2014 RK-65B Conceptual Design and Feasibility Study for
Reconstruction of the Manhattan Plaza at the RFK Bridge
BampT $1M - $5M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 14
Information About Contracts that Will Be Advertised for
Professional Services Construction and Equipment Procurement
MARCH 2014 ndash SEPTEMBER 2014
Letter from the Chairman
Information About Contracts
Overview
Contacts
Selected Contract Provisions
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Overview
This edition of An Eye on the Future contains information for prospective contractors engineers architects and vendors about contracts that are expected
to be advertised for bids between March 2014 ndash September 2014 by the Metropolitan Transportation Authoritys operating agencies
MTA New York City Transit (NYC Transit)
MTA Staten Island Railway (SIRTOA)
MTA Long Island Rail Road (LIRR)
MTA Metro-North Railroad (MNR)
MTA Bridges and Tunnels (BampT)
MTA Capital Construction (MTACC)
MTA Bus Company (MTA Bus)
In 1993 the MTA board approved a new service identity program for the MTA family of agencies The identity program provides for the use of the above
popular names to make clear to our customers that the various MTA affiliates and subsidiaries constitute an integrated regional transportation network
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 24
Security amp Consulting Service for NEW YORK CITY
TRANSIT ONLY
Mr Joseph Paldino
Assistant Chief Procurement Officer
Materiel Division
MTA New York City Transit
2 Broadway
New York NY 10004
Telephone (646) 252-6330
Fax(646) 252-6099
Email josephpaldinonyctcom
For all other contracts
Mr Robert Eskenazi
Senior Director Materiel Division
MTA New York City Transit
2 Broadway
New York NY 10004
Telephone (646) 252-6258
Fax (646) 252-6144
Email roberteskenazinyctcom
MTA NEW YORK CITY TRANSIT MTA STATEN ISLAND RAILWAY MTA BUS COMPANY
However for all procurement documents and official transactions the agencies retain their legal names New York City Transit Authority Staten Island
Rapid Transit Operating Authority the Long Island Rail Road Company Metro-North Commuter Railroad Company Triborough Bridge and Tunnel Authority
Capital Construction and Bus Company
With respect to the contract descriptions and other data included in this volume readers should note that they are for general information only and are not
to be construed as final The exact description of the work and other pertinent information concerning an individual contract will be found in the contract
specifications and drawings or solicitation documents which may be obtained by prospective bidders when solicitation begins Most contracts for
construction procurement of capital equipment and professional services are awarded after a competitive process including sealed bids for construction
and procurements and competitive requests for proposals for professional services
Some aspects of contracting are common to all the MTA agencies
1 MTA agencies are not subject to the Wicks Law for their construction projects
2 MTA agencies seek the best contractors suppliers and professional services firms in the business including firms owned by women and minorities for
which special efforts are made to ensure appropriate participation We pledge to do our part to make all projects successful for the agencies and
contractors alike
3 Projects already funded by Federal grants are noted in the solicitation schedule with an asterisk Some of the other projects may become eligible for
Federal funding in future grant applications
Public notices of solicitations are normally published in advance of the availability of contract documents or requests for proposals in the New York State
Contract Reporter and in one or more of the following publications
New York Post
El Diario
The Daily Challenge
Amsterdam News
Minority Commerce Weekly
Engineering News Record
Contacts
Further information about contracts adverstised here can be obtained by contacting respective agency representatives
MTA METRO-NORTH RAILROAD
Mr Charles F Hansen
Deputy Director - Capital Procurement
MTA Metro-North Railroad
347 Madison Avenue 14th Floor
New York New York 10017-3706
Telephone (212) 340-3262
Fax (212) 340-4034
E-mail hansenmnrorg
MTA LONG ISLAND RAIL ROAD
Ms Carla Butler
Contract Research Clerk
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 34
Planning amp Construction
MTA Long Island Rail Road
90-27 Sutphin Boulevard (0335)
Jamaica New York 11435
Telephone (718) 725-2622
Fax (718) 725-2676
E-mail cbutlerlirrorg
MTA BRIDGES amp TUNNELS
Ms Victoria Warren
Procurement and Materials
MTA Bridges and Tunnels
2 Broadway 24th Floor
New York New York 10004
Telephone (646) 252-7092
Fax (646) 252-7077
E-mail vprocuremtabtorg
MTA CAPITAL CONSTRUCTION
Mr David K Cannon
Senior Director and Chief Procurement Officer
Procurement and Law Department
MTA Capital Construction
2 Broadway - A899
New York New York 10004
Telephone (646) 252-2321
E-mail dcannonmtaccinfo
Selected Provisions of Capital Program Contracts
This is a summary of several provisions which are generally applicable to MTA agency projects Complete requirements for a given contract can only be
obtained from the documents for that contract Naturally all construction is performed under the laws and regulations of New York State This is not
intended to be a full summary of General Provisions
1 MTA New York City Transit the two commuter railroads and MTA Capital Construction base progress payments on the contractors monthly
submissions of cost-loaded schedules The use of CPM network diagrams is required for complex projects while simpler bar charts are required for
less complex projects
2 All the agencies contract documents contain a value engineering change proposal clause Contractors are encouraged to submit cost saving proposals
during construction and upon acceptance of the proposal would be able to share in the actual cost savings
3 Another effort to improve the management of capital projects is the use of contractor evaluation files that are kept on all ongoing work All the MTA
agencies use identical criteria to evaluate contractors and share the information with the other MTA agencies
4 The period between advertisement for bids and bid opening will vary from approximately four to eight weeks depending on size of the contract
5 Unless specifically noted in the bid document the transit facilities will be in continuous operation during the performance of the work for the majority of
contracts The contracting agency will provide the necessary maintainers flagmen diversions of service and work trains
6 Bidders will be required to submit prior to the award of the contract a program of affirmative action to provide for equal employment opportunity
Submittals will be described in the contract documents Goals for the participation of minority-owned and women-owned firms may be specified for
each contract
Minority business enterprises and women business enterprises will be afforded full opportunity to submit bids andor proposals and will not be
subjected to discrimination on the basis of race religion color sex or national origin in consideration for awarding contracts
7 A bid bond or a certified check in the amount of five to ten percent is normally required at the time of delivery of the bid The contractor must furnish a
performance bond and payment bond in amounts equal to 100 percent of the contract price
8 In addition to other requirements specifically provided in the contract each bidder must be prepared to prove to the satisfaction of the contracting
agency that he has the qualifications including but not limited to skill and experience and the necessary facilities and financial resources to complete
the work in a satisfactory manner within the time specified
9 Contracts generally require a guarantee of all apparatuses devices workmanship and materials for at least one year A security in the form of a bond
in the sum of a predetermined percentage of the amount of the contract may be required prior to the final payment Contracts may have additional
requirements which must be reviewed
10 The contractor shall also maintain at a minimum Workers Compensation Commercial General Liability and Commercial Automobile Insurance
Additional coverage may be required and will be indicated in the contract The MTA and the contracting agency shall be named as an additional insured
on the policy In general coverage requirements range from $1000000 to $5000000 combined single limit for injuries to persons (including death) and
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 44
for damage to property The limits of liability will vary depending on the size and type of projects In addition the contractor will be required to hold the
governmental agencies and contracting agency harmless Evidence of the required insurance shall be delivered to the contracting agency on an MTA
approved Certificate of Insurance prior to execution of the contract
Each insurance policy or Certificate of Insurance shall contain an agreement by the insurance company issuing the policy that the policy will not be
canceled terminated or modified without 30 days prior notice to the contracting agency At least two weeks prior to the expiration of each policy the
contractor shall endeavor to provide an updated Certificate of Insurance evidencing renewal coverage to the contract agency
The MTA has in place Owner Controlled Insurance Programs (OCIP) for the East Side Access (ESA) project the Second Avenue Subway and selected
projects in the Capital Plan Under traditional OCIPs the MTA covers the construction phase of work and provides general liability excess liability
workers compensation railroad protective and builders risk coverage to all participating contractors The ESA OCIP adds environmental liability
coverage for related engineering and environmental work
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 14
Forecast of Contracts to be Advertised and Proposals to be Solicited
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
MARCH 2014 ndash SEPTEMBER 2014
Type of
ContractSolic Month Reference Number Contract Description Agency Range
Bridges and Tunnels
Constr Mgmt MAR 2014 HH-88A Construction Management Services for HH-88A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-23A Construction Management Services for RK-23A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-44 Construction Management Services for RK-44 Painting
Contract
BampT $1M - $5M
Constr MAR 2014 RK-44 Cleaning and Painting of RFK Main Cables Suspender
Ropes and Tower Interior and Exterior
BampT $5M - $10M
Constr APR 2014 MP-21 (DB) DesignBuild Rehabilitation of the Rockaway Point
Boulevard Overpass and Jacob Riis Park Pedestrian
Bridge)
BampT $5M - $10M
Special
Services
APR 2014 RK-65B Conceptual Design and Feasibility Study for
Reconstruction of the Manhattan Plaza at the RFK Bridge
BampT $1M - $5M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 24
Security amp Consulting Service for NEW YORK CITY
TRANSIT ONLY
Mr Joseph Paldino
Assistant Chief Procurement Officer
Materiel Division
MTA New York City Transit
2 Broadway
New York NY 10004
Telephone (646) 252-6330
Fax(646) 252-6099
Email josephpaldinonyctcom
For all other contracts
Mr Robert Eskenazi
Senior Director Materiel Division
MTA New York City Transit
2 Broadway
New York NY 10004
Telephone (646) 252-6258
Fax (646) 252-6144
Email roberteskenazinyctcom
MTA NEW YORK CITY TRANSIT MTA STATEN ISLAND RAILWAY MTA BUS COMPANY
However for all procurement documents and official transactions the agencies retain their legal names New York City Transit Authority Staten Island
Rapid Transit Operating Authority the Long Island Rail Road Company Metro-North Commuter Railroad Company Triborough Bridge and Tunnel Authority
Capital Construction and Bus Company
With respect to the contract descriptions and other data included in this volume readers should note that they are for general information only and are not
to be construed as final The exact description of the work and other pertinent information concerning an individual contract will be found in the contract
specifications and drawings or solicitation documents which may be obtained by prospective bidders when solicitation begins Most contracts for
construction procurement of capital equipment and professional services are awarded after a competitive process including sealed bids for construction
and procurements and competitive requests for proposals for professional services
Some aspects of contracting are common to all the MTA agencies
1 MTA agencies are not subject to the Wicks Law for their construction projects
2 MTA agencies seek the best contractors suppliers and professional services firms in the business including firms owned by women and minorities for
which special efforts are made to ensure appropriate participation We pledge to do our part to make all projects successful for the agencies and
contractors alike
3 Projects already funded by Federal grants are noted in the solicitation schedule with an asterisk Some of the other projects may become eligible for
Federal funding in future grant applications
Public notices of solicitations are normally published in advance of the availability of contract documents or requests for proposals in the New York State
Contract Reporter and in one or more of the following publications
New York Post
El Diario
The Daily Challenge
Amsterdam News
Minority Commerce Weekly
Engineering News Record
Contacts
Further information about contracts adverstised here can be obtained by contacting respective agency representatives
MTA METRO-NORTH RAILROAD
Mr Charles F Hansen
Deputy Director - Capital Procurement
MTA Metro-North Railroad
347 Madison Avenue 14th Floor
New York New York 10017-3706
Telephone (212) 340-3262
Fax (212) 340-4034
E-mail hansenmnrorg
MTA LONG ISLAND RAIL ROAD
Ms Carla Butler
Contract Research Clerk
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 34
Planning amp Construction
MTA Long Island Rail Road
90-27 Sutphin Boulevard (0335)
Jamaica New York 11435
Telephone (718) 725-2622
Fax (718) 725-2676
E-mail cbutlerlirrorg
MTA BRIDGES amp TUNNELS
Ms Victoria Warren
Procurement and Materials
MTA Bridges and Tunnels
2 Broadway 24th Floor
New York New York 10004
Telephone (646) 252-7092
Fax (646) 252-7077
E-mail vprocuremtabtorg
MTA CAPITAL CONSTRUCTION
Mr David K Cannon
Senior Director and Chief Procurement Officer
Procurement and Law Department
MTA Capital Construction
2 Broadway - A899
New York New York 10004
Telephone (646) 252-2321
E-mail dcannonmtaccinfo
Selected Provisions of Capital Program Contracts
This is a summary of several provisions which are generally applicable to MTA agency projects Complete requirements for a given contract can only be
obtained from the documents for that contract Naturally all construction is performed under the laws and regulations of New York State This is not
intended to be a full summary of General Provisions
1 MTA New York City Transit the two commuter railroads and MTA Capital Construction base progress payments on the contractors monthly
submissions of cost-loaded schedules The use of CPM network diagrams is required for complex projects while simpler bar charts are required for
less complex projects
2 All the agencies contract documents contain a value engineering change proposal clause Contractors are encouraged to submit cost saving proposals
during construction and upon acceptance of the proposal would be able to share in the actual cost savings
3 Another effort to improve the management of capital projects is the use of contractor evaluation files that are kept on all ongoing work All the MTA
agencies use identical criteria to evaluate contractors and share the information with the other MTA agencies
4 The period between advertisement for bids and bid opening will vary from approximately four to eight weeks depending on size of the contract
5 Unless specifically noted in the bid document the transit facilities will be in continuous operation during the performance of the work for the majority of
contracts The contracting agency will provide the necessary maintainers flagmen diversions of service and work trains
6 Bidders will be required to submit prior to the award of the contract a program of affirmative action to provide for equal employment opportunity
Submittals will be described in the contract documents Goals for the participation of minority-owned and women-owned firms may be specified for
each contract
Minority business enterprises and women business enterprises will be afforded full opportunity to submit bids andor proposals and will not be
subjected to discrimination on the basis of race religion color sex or national origin in consideration for awarding contracts
7 A bid bond or a certified check in the amount of five to ten percent is normally required at the time of delivery of the bid The contractor must furnish a
performance bond and payment bond in amounts equal to 100 percent of the contract price
8 In addition to other requirements specifically provided in the contract each bidder must be prepared to prove to the satisfaction of the contracting
agency that he has the qualifications including but not limited to skill and experience and the necessary facilities and financial resources to complete
the work in a satisfactory manner within the time specified
9 Contracts generally require a guarantee of all apparatuses devices workmanship and materials for at least one year A security in the form of a bond
in the sum of a predetermined percentage of the amount of the contract may be required prior to the final payment Contracts may have additional
requirements which must be reviewed
10 The contractor shall also maintain at a minimum Workers Compensation Commercial General Liability and Commercial Automobile Insurance
Additional coverage may be required and will be indicated in the contract The MTA and the contracting agency shall be named as an additional insured
on the policy In general coverage requirements range from $1000000 to $5000000 combined single limit for injuries to persons (including death) and
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 44
for damage to property The limits of liability will vary depending on the size and type of projects In addition the contractor will be required to hold the
governmental agencies and contracting agency harmless Evidence of the required insurance shall be delivered to the contracting agency on an MTA
approved Certificate of Insurance prior to execution of the contract
Each insurance policy or Certificate of Insurance shall contain an agreement by the insurance company issuing the policy that the policy will not be
canceled terminated or modified without 30 days prior notice to the contracting agency At least two weeks prior to the expiration of each policy the
contractor shall endeavor to provide an updated Certificate of Insurance evidencing renewal coverage to the contract agency
The MTA has in place Owner Controlled Insurance Programs (OCIP) for the East Side Access (ESA) project the Second Avenue Subway and selected
projects in the Capital Plan Under traditional OCIPs the MTA covers the construction phase of work and provides general liability excess liability
workers compensation railroad protective and builders risk coverage to all participating contractors The ESA OCIP adds environmental liability
coverage for related engineering and environmental work
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 14
Forecast of Contracts to be Advertised and Proposals to be Solicited
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
MARCH 2014 ndash SEPTEMBER 2014
Type of
ContractSolic Month Reference Number Contract Description Agency Range
Bridges and Tunnels
Constr Mgmt MAR 2014 HH-88A Construction Management Services for HH-88A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-23A Construction Management Services for RK-23A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-44 Construction Management Services for RK-44 Painting
Contract
BampT $1M - $5M
Constr MAR 2014 RK-44 Cleaning and Painting of RFK Main Cables Suspender
Ropes and Tower Interior and Exterior
BampT $5M - $10M
Constr APR 2014 MP-21 (DB) DesignBuild Rehabilitation of the Rockaway Point
Boulevard Overpass and Jacob Riis Park Pedestrian
Bridge)
BampT $5M - $10M
Special
Services
APR 2014 RK-65B Conceptual Design and Feasibility Study for
Reconstruction of the Manhattan Plaza at the RFK Bridge
BampT $1M - $5M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 34
Planning amp Construction
MTA Long Island Rail Road
90-27 Sutphin Boulevard (0335)
Jamaica New York 11435
Telephone (718) 725-2622
Fax (718) 725-2676
E-mail cbutlerlirrorg
MTA BRIDGES amp TUNNELS
Ms Victoria Warren
Procurement and Materials
MTA Bridges and Tunnels
2 Broadway 24th Floor
New York New York 10004
Telephone (646) 252-7092
Fax (646) 252-7077
E-mail vprocuremtabtorg
MTA CAPITAL CONSTRUCTION
Mr David K Cannon
Senior Director and Chief Procurement Officer
Procurement and Law Department
MTA Capital Construction
2 Broadway - A899
New York New York 10004
Telephone (646) 252-2321
E-mail dcannonmtaccinfo
Selected Provisions of Capital Program Contracts
This is a summary of several provisions which are generally applicable to MTA agency projects Complete requirements for a given contract can only be
obtained from the documents for that contract Naturally all construction is performed under the laws and regulations of New York State This is not
intended to be a full summary of General Provisions
1 MTA New York City Transit the two commuter railroads and MTA Capital Construction base progress payments on the contractors monthly
submissions of cost-loaded schedules The use of CPM network diagrams is required for complex projects while simpler bar charts are required for
less complex projects
2 All the agencies contract documents contain a value engineering change proposal clause Contractors are encouraged to submit cost saving proposals
during construction and upon acceptance of the proposal would be able to share in the actual cost savings
3 Another effort to improve the management of capital projects is the use of contractor evaluation files that are kept on all ongoing work All the MTA
agencies use identical criteria to evaluate contractors and share the information with the other MTA agencies
4 The period between advertisement for bids and bid opening will vary from approximately four to eight weeks depending on size of the contract
5 Unless specifically noted in the bid document the transit facilities will be in continuous operation during the performance of the work for the majority of
contracts The contracting agency will provide the necessary maintainers flagmen diversions of service and work trains
6 Bidders will be required to submit prior to the award of the contract a program of affirmative action to provide for equal employment opportunity
Submittals will be described in the contract documents Goals for the participation of minority-owned and women-owned firms may be specified for
each contract
Minority business enterprises and women business enterprises will be afforded full opportunity to submit bids andor proposals and will not be
subjected to discrimination on the basis of race religion color sex or national origin in consideration for awarding contracts
7 A bid bond or a certified check in the amount of five to ten percent is normally required at the time of delivery of the bid The contractor must furnish a
performance bond and payment bond in amounts equal to 100 percent of the contract price
8 In addition to other requirements specifically provided in the contract each bidder must be prepared to prove to the satisfaction of the contracting
agency that he has the qualifications including but not limited to skill and experience and the necessary facilities and financial resources to complete
the work in a satisfactory manner within the time specified
9 Contracts generally require a guarantee of all apparatuses devices workmanship and materials for at least one year A security in the form of a bond
in the sum of a predetermined percentage of the amount of the contract may be required prior to the final payment Contracts may have additional
requirements which must be reviewed
10 The contractor shall also maintain at a minimum Workers Compensation Commercial General Liability and Commercial Automobile Insurance
Additional coverage may be required and will be indicated in the contract The MTA and the contracting agency shall be named as an additional insured
on the policy In general coverage requirements range from $1000000 to $5000000 combined single limit for injuries to persons (including death) and
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 44
for damage to property The limits of liability will vary depending on the size and type of projects In addition the contractor will be required to hold the
governmental agencies and contracting agency harmless Evidence of the required insurance shall be delivered to the contracting agency on an MTA
approved Certificate of Insurance prior to execution of the contract
Each insurance policy or Certificate of Insurance shall contain an agreement by the insurance company issuing the policy that the policy will not be
canceled terminated or modified without 30 days prior notice to the contracting agency At least two weeks prior to the expiration of each policy the
contractor shall endeavor to provide an updated Certificate of Insurance evidencing renewal coverage to the contract agency
The MTA has in place Owner Controlled Insurance Programs (OCIP) for the East Side Access (ESA) project the Second Avenue Subway and selected
projects in the Capital Plan Under traditional OCIPs the MTA covers the construction phase of work and provides general liability excess liability
workers compensation railroad protective and builders risk coverage to all participating contractors The ESA OCIP adds environmental liability
coverage for related engineering and environmental work
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 14
Forecast of Contracts to be Advertised and Proposals to be Solicited
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
MARCH 2014 ndash SEPTEMBER 2014
Type of
ContractSolic Month Reference Number Contract Description Agency Range
Bridges and Tunnels
Constr Mgmt MAR 2014 HH-88A Construction Management Services for HH-88A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-23A Construction Management Services for RK-23A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-44 Construction Management Services for RK-44 Painting
Contract
BampT $1M - $5M
Constr MAR 2014 RK-44 Cleaning and Painting of RFK Main Cables Suspender
Ropes and Tower Interior and Exterior
BampT $5M - $10M
Constr APR 2014 MP-21 (DB) DesignBuild Rehabilitation of the Rockaway Point
Boulevard Overpass and Jacob Riis Park Pedestrian
Bridge)
BampT $5M - $10M
Special
Services
APR 2014 RK-65B Conceptual Design and Feasibility Study for
Reconstruction of the Manhattan Plaza at the RFK Bridge
BampT $1M - $5M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
342014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf_introhtm 44
for damage to property The limits of liability will vary depending on the size and type of projects In addition the contractor will be required to hold the
governmental agencies and contracting agency harmless Evidence of the required insurance shall be delivered to the contracting agency on an MTA
approved Certificate of Insurance prior to execution of the contract
Each insurance policy or Certificate of Insurance shall contain an agreement by the insurance company issuing the policy that the policy will not be
canceled terminated or modified without 30 days prior notice to the contracting agency At least two weeks prior to the expiration of each policy the
contractor shall endeavor to provide an updated Certificate of Insurance evidencing renewal coverage to the contract agency
The MTA has in place Owner Controlled Insurance Programs (OCIP) for the East Side Access (ESA) project the Second Avenue Subway and selected
projects in the Capital Plan Under traditional OCIPs the MTA covers the construction phase of work and provides general liability excess liability
workers compensation railroad protective and builders risk coverage to all participating contractors The ESA OCIP adds environmental liability
coverage for related engineering and environmental work
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 14
Forecast of Contracts to be Advertised and Proposals to be Solicited
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
MARCH 2014 ndash SEPTEMBER 2014
Type of
ContractSolic Month Reference Number Contract Description Agency Range
Bridges and Tunnels
Constr Mgmt MAR 2014 HH-88A Construction Management Services for HH-88A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-23A Construction Management Services for RK-23A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-44 Construction Management Services for RK-44 Painting
Contract
BampT $1M - $5M
Constr MAR 2014 RK-44 Cleaning and Painting of RFK Main Cables Suspender
Ropes and Tower Interior and Exterior
BampT $5M - $10M
Constr APR 2014 MP-21 (DB) DesignBuild Rehabilitation of the Rockaway Point
Boulevard Overpass and Jacob Riis Park Pedestrian
Bridge)
BampT $5M - $10M
Special
Services
APR 2014 RK-65B Conceptual Design and Feasibility Study for
Reconstruction of the Manhattan Plaza at the RFK Bridge
BampT $1M - $5M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 14
Forecast of Contracts to be Advertised and Proposals to be Solicited
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
MARCH 2014 ndash SEPTEMBER 2014
Type of
ContractSolic Month Reference Number Contract Description Agency Range
Bridges and Tunnels
Constr Mgmt MAR 2014 HH-88A Construction Management Services for HH-88A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-23A Construction Management Services for RK-23A
Construction Contract
BampT $1M - $5M
Constr Mgmt MAR 2014 RK-44 Construction Management Services for RK-44 Painting
Contract
BampT $1M - $5M
Constr MAR 2014 RK-44 Cleaning and Painting of RFK Main Cables Suspender
Ropes and Tower Interior and Exterior
BampT $5M - $10M
Constr APR 2014 MP-21 (DB) DesignBuild Rehabilitation of the Rockaway Point
Boulevard Overpass and Jacob Riis Park Pedestrian
Bridge)
BampT $5M - $10M
Special
Services
APR 2014 RK-65B Conceptual Design and Feasibility Study for
Reconstruction of the Manhattan Plaza at the RFK Bridge
BampT $1M - $5M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 24
Constr MAY 2014 RK-65A Reconstruction of the Bronx Plaza at the RFK Bridge BampT OVER $50M
Constr JUN 2014 BB-28 (Sandy)BB-2 Rehabilitation of walls roadway fire lines ceiling
Mechanical Electrical and Communication systems
inside the tunnel Replacement of Brooklyn Plaza
structural slab and Environmental Remediation at Hugh L
Carey Tunnel
BampT OVER $50M
Constr JUN 2014 HH-88A Reconstruction of Upper and Lower Plaza and Southbound
Approach
BampT $10M - $50M
Constr JUN 2014 RK-23A Reconstruction and Rehabilitation of Manhattan Approach
Ramps to and from 124th 125th St
BampT OVER $50M
Constr JUL 2014 RK-76 Misc Structural Repair at RFK Bridge BampT $10M - $50M
Long Island Rail Road
Constr APR 2014 E01848 [Sandy] NY Western Rail Yards Fire Alarm System [Design-Build] LIRR $500K - $1M
Constr JUN 2014 E01817 [Sandy] Design-Build for Long Beach Branch Signal System LIRR $5M - $10M
Constr JUN 2014 L10001 Ellison Avenue Bridge Replacement LIRR $10M - $50M
Constr JUL 2014 L09986 Hicksville North Track Siding LIRR $10M - $50M
Metro-North Railroad
Constr MAR 2014 M08817 Rehabilitate - 2 Elevators (SE12) - Grand Central Terminal MNR $1M - $5M
Constr JUN 2014 M08793 Construction - GCT TrainshedStructure MNR $10M - $50M
Constr JUN 2014 M09198 Construction of Culvert located at MP JS5100 - Salisbury
Mills
MNR $1M - $5M
Constr JUN 2014 M09403E01881 Construction 4 Substations MNR $10M - $50M
MTA Bus
Constr MAR 2014 SF04-7408 DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp
BAISLEY PARK DEPOTS
MTA BUS $1M - $5M
Constr MAR 2014 SF07-7411 JFK APRON MTA BUS $5M - $10M
Constr APR 2014 SF01-7407 SECURITY IMPROVEMENTS FAR ROCKAWAY amp
BAISLEY PARK
MTA BUS $5M - $10M
Constr APR 2014 SF07-7314 FAR ROCKAWAY ROOF DECK REPLACEMENT MTA BUS $1M - $5M
New York City Transit
Constr MAR 2014 A36151 ACCESS IMPROVEMENTS AT GRAND CENTRAL
STATION
NYCT $10M - $50M
Constr MAR 2014 A36906A36908 STATION COMPONENT REPAIRS AT 5 LOCATIONS NYCT $5M - $10M
Constr MAR 2014 C33840 STRUCTURE OVERCOATING BROADWAY JUNCTION - NYCT $10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 34
NEW LOTS AVENUE
Purchase MAR 2014 C34915 LINE STRUCTURE OVERCOATING ABUTMENT TO
KINGS HWY
NYCT $10M - $50M
Constr MAR 2014 C34916 LINE STRUCTURE OVERCOATING KINGS HWY TO
WEST 8 ST
NYCT $10M - $50M
Constr MAR 2014 P36444(SANDY) SANDY REPAIRS RESTORATION OF CRANBERRY
AND RUTGERS TUBE
NYCT OVER $50M
Constr MAR 2014 S32765 INTERLOCKING MODERNIZATION WEST 4TH ST NYCT OVER $50M
Constr APR 2014 A36891 STATION COMPONENT REPAIRS 2 LOCATIONS NYCT $5M - $10M
Constr APR 2014 A36909 COMPONENT REPAIRS AT 5 STATIONS - CANARSIE NYCT $10M - $50M
Constr APR 2014 A37547 STRUCTURAL STEEL REPAIR 9TH AVENUE STATION NYCT $5M - $10M
Constr APR 2014 A37593(SANDY) SANDY REPAIRS SOUTH FERRY NYCT OVER $50M
Constr APR 2014 A46010 STATION RENEWAL AND COMPONENT REPAIRS 9
STATIONS
NYCT OVER $50M
Constr APR 2014 C33848 PERIMETER HARDENING RCC amp 130 LIVINGSTON NYCT $5M - $10M
Constr APR 2014 C43046 HYDROGEN GAS VENTILATION 19 COMMUNICATION
ROOMS
NYCT $5M - $10M
Constr APR 2014 C43749 REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE
ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL
SECURITY BOLLARDS REMOVE amp REPLACE WWII
MEMORIAL
NYCT $10M - $50M
Constr APR 2014 E31114 REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22
LOCATIONS
NYCT $10M - $50M
Constr APR 2014 E40805 REHABILITATE PUMP ROOMS 4 LOCATIONS NYCT $5M - $10M
Constr APR 2014 T80276(SANDY) SANDY REPAIRS ST GEORGE INTERLOCKING NYCT OVER $50M
Constr APR 2014 W32366 REPLACE BUS RADIO SYSTEM NYCT OVER $50M
Constr MAY 2014 C43753 CONSTRUCT BUS COMMAND CENTER NYCT $10M - $50M
Constr JUN 2014 A36905 STATION COMPONENT REPAIRS 3 STATIONS NYCT $5M - $10M
Constr JUN 2014 A36921 STATION COMPONENT REPAIRS 4 LOCATIONS NYCT $5M - $10M
Purchase JUN 2014 B40660 PURCHASE 256 ARTICULATED BUSES NYCT OVER $50M
Constr JUN 2014 P36415 REHABILITATION OF CIRCUIT BREAKER HOUSE
PEARL STREET
NYCT $5M - $10M
Constr JUN 2014 P36446(SANDY) SANDY REPAIRS RESTORATION OF CLARK STREET
TUBE
NYCT $10M - $50M
Constr JUN 2014 SF07-7346 SLIDING GATE REPLACEMENT AT JACKIE GLEASON
BUS DEPOT
NYCT $1M - $5M
Constr JUN 2014 W32372 PASSENGER STATION LAN AT 20 STATIONS NYCT $10M - $50M
Constr JUL 2014 A36890 STATION COMPONENT REPAIRS 49TH STREET NYCT $5M - $10M
Constr JUL 2014 C34914 SHOP REPAIRS AND UPGRADE NYCT $10M - $50M
Constr JUL 2014 D37467 PBX UPGRADE PHASE 1 NYCT $10M - $50M
Constr JUL 2014 P80275 NEW POWER SUBSTATION PRINCES BAY NYCT $10M - $50M
Constr JUL 2014 ST12-0139 INTEGRATED SERVICE INFORMATION amp
MANAGEMENT B DIVISION MODULE 1
NYCT $10M - $50M
Constr JUL 2014 W32697 INSTALL PUBLIC ADDRESS AND CUSTOMER
INFORMATION SCREENS AT 87 LOCATIONS
NYCT $10M - $50M
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-allagency_newhtm 44
Constr AUG 2014 A36090 STATION RENEWALS OF 9 STATIONS NYCT OVER $50M
Constr AUG 2014 A36916 STATION COMPONENTS EASTCHESTER - DYRE
AVENUE
NYCT $5M - $10M
Constr AUG 2014 C33076 EMERGENCY GENERATOR REPLACEMENT AT
CASEY STENGEL DEPOT
NYCT $1M - $5M
Constr AUG 2014 C34829 RTO FACILITIES HARDENING PH 2 NYCT $10M - $50M
Constr AUG 2014 C34913 CAR WASHER REPAIRS AT 3 YARDS NYCT $10M - $50M
Constr AUG 2014 E31380 THREE BUS WASHERS AT M J QILL BUS DEPOT NYCT $5M - $10M
Constr SEP 2014 A36150 ADA AT 57 STREET PHASE 2 NYCT $10M - $50M
Constr SEP 2014 A36865 STATION COMPONENT REPAIRS AT 4 STATIONS NYCT $10M - $50M
Constr SEP 2014 A36871 STATION COMPONENT REPAIRS AT TWO STATIONS NYCT $5M - $10M
Constr SEP 2014 A36884 STATION COMPONENT REPAIRS 103 STREET NYCT $5M - $10M
Constr SEP 2014 C34912 CAR WASHER REPAIRS AT CONEY ISLAND YARD NYCT $1M - $5M
Constr SEP 2014 E34022 7 HYDRAULIC ELEVATOR NYCT $10M - $50M
Constr SEP 2014 P36447(SANDY) SANDY REPAIRS RESTORATION OF 53RD ST TUBE NYCT OVER $50M
Capital Construction
Constr MAR 2014 CM014B GCT Concourse and Facilities Fit-Out MTACC Over $100M
Constr MAR 2014 CS084 Systems Package 2 Traction Power Systems MTACC $50M - $100M
Constr APR 2014 C-52123-1 Architectural Electrical and Fire Protection Upgrades for
the 34th St Penn Station Complex
MTACC $1M - $5M
Constr APR 2014 CH057 Harold Structures Part 3 48th St Bridge D Approach
Phase I and Eastbound Re-Route Approach
MTACC $50M - $100M
Partially Funded by Federal grant(s)
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 120
Brief Descriptions of Work to be Advertised
Letter from the Chairman
Information About Contracts
Forecast of Contracts and Proposals
Brief Descriptions of Work to be Advertised
MTA New York City Transit
MTA Long Island Rail Road
MTA Metro-North Railroad
MTA Bridges amp Tunnels
MTA Capital Construction
MTA Bus Company
Bridges and Tunnels
Brief Description of Work
MAR 2014
HH-88A
CONSTRUCTION MANAGEMENT SERVICES FOR HH-88A CONSTRUCTION CONTRACT
$1M - $5M
The consultant will provide construction administration inspection and support service for HH-88A Construction project The Consultant shall provide all on-
site inspection and ensure that the materials furnished and the works performed are in accordance with the contract documents Construction schedule
requires multiple shifts Following is a representative list of the primary duties and responsibilities of the Consultant
Inspect the work of the Contract notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records of
the progress of the Contract
Provide Lead Abatement services which may include on-site inspections Air-monitoring and sampling and testing
Provide the Engineer with the necessary data for the processing of partial payments final payment extra work orders material approvals
subcontractor approvals and all other required reports and correspondence
Conduct progress meetings and special meetings as required Assist the Engineer in the project close-out procedure
Review contractorrsquos CPM or Bar Chart schedule
Assist in the resolution of disputes among the contractors Make recommendations to the Engineer for such changes in the work as the Consultant
may consider necessary or desirable Provide an analysis of the validity and need for proposed change orders and assist the Authority in the
subsequent negotiations
Duration of Contract 27 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 220
RK-23A
CONSTRUCTION MANAGEMENT SERVICES FOR RK-23A CONSTRUCTION CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-23A construction contract
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 43 Months
RK-44
CONSTRUCTION MANAGEMENT SERVICES FOR RK-44 PAINTING CONTRACT
$1M - $5M
Under this contract the consultant will provide construction management services for RK-44 paint project
Inspect the work of the contractor notify the contractor in writing of any and all unacceptable work and maintain accurate and detailed written records
of the progress of the Contract
Ensure that all required permits have been obtained prior to the start of work Make recommendations as to the capabilities of contractors
subcontractors and sources of materials and equipment proposed by them Review contractorrsquos schedule
Establish and implement the procedures to be followed for the expediting and processing of shop drawings catalog cuts and submittals
Conduct progress meetings and special meetings as required Assist in the resolution of disputes among the contractors
Make recommendations to the Engineer for such changes in the work as the consultant may consider necessary or desirable Provide an analysis of
the validity and need for proposed change orders and assist the Authority in the subsequent negotiations
Assist the Engineer in the project close-out process
Duration of Contract 39 Months
RK-44
CLEANING AND PAINTING OF RFK MAIN CABLES SUSPENDER ROPES AND TOWER INTERIOR AND EXTERIOR
$5M - $10M
Under this Project the contractor shall perform cleaning and painting of various bridge elements at RFK bridge It also includes annual washingspot
painting of the Authority-wide toll plazas
Provide as-needed Maintenance and Protection of Traffic (MPT) to allow for construction activities
Coordinate the work of this project with other contractors working on the RFK Bridge
Blast clean RFK tower interior to SSPC SP-10 (Bare Metal) and coat with a high performance epoxy coating system
Over coat painting of main cables and suspender ropes
Over coat painting of the tower exterior below roadway
Wash and spot paint Authority-wide toll plazas
Duration of Contract 36 Months
Bridges and Tunnels
Brief Description of Work
APR 2014
MP-21 (DB)
DESIGNBUILD REHABILITATION OF THE ROCKAWAY POINT BOULEVARD OVERPASS AND JACOB RIIS PARK PEDESTRIAN BRIDGE)
$5M - $10M
Under this design-build contract the contractor will replace the Rockaway Point Boulevard Bridge amp rehabilitate the Jacob Riis Park Pedestrian Bridge
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 320
Investigate the existing conditions and review available documentation
Develop design documents at different established milestone for the Authoritys review and approval Prepare complete design
Install new bearings stringer and deck to current loading and seismic standards
Comply with all design criteria phasing approach environmental permits and approvals schedule fire and security requirements
Provide Maintenance and Protection of Traffic (MPT) as needed
Prepare as-built documentation
Duration of Contract 24 Months
RK-65B
CONCEPTUAL DESIGN AND FEASIBILITY STUDY FOR RECONSTRUCTION OF THE MANHATTAN PLAZA AT THE RFK BRIDGE
$1M - $5M
Provide conceptual design and feasibility study for the reconstruction of the Manhattan Plaza Structure associated ramps and toll collection system
Meet with the Authority Personnel to review the scope of work
Research available documentation perform all necessary investigations and surveys and meeting with Authority personnel
Review available documents and traffic studies to determine the optimum recommended alternatives for reconstruction of the Manhattan Plaza and
upgrades to associated ramps
Perform a feasibility studyDesign Brief equivalent to 10 design discussing alternatives make recommendations for final design Once final alternative
is selected produce the conceptual design
Duration of Contract 48 Months
Bridges and Tunnels
Brief Description of Work
MAY 2014
RK-65A
RECONSTRUCTION OF THE BRONX PLAZA AT THE RFK BRIDGE
OVER $50M
The scope of this Project includes staged replacement of the Bronx Plaza concrete deck along with portions of the supporting steel seismic upgrades
substructure repairs construction of several new piers and complete replacement of the toll plaza
Concrete repairs to piers and cap beams and steel repairs
Construction of new piers as well as extension of pier caps to support new deck between the mainline and the Manhattan-Queens ramp
Construction of an overhead walkwaytoll canopy and staged replacement of the Toll Plaza and concrete deck as well as significant portions of the
supporting steel and installation of seismic isolation bearings
Replacement of the Bronx Service Building Substation along with all utilities serving the plaza all deck lighting and plaza high mast lighting within
project limits
Modifications to the Bronx Crossing Truss spans to remove the median barrier and install temporary concrete barrier
Coordination with E-Zpass equipment provider to ensure access for installation and testing of toll collection equipment
Duration of Contract 56 Months
Bridges and Tunnels
Brief Description of Work
JUN 2014
BB-28 (Sandy)BB-28BB-54BB-12
REHABILITATION OF WALLS ROADWAY FIRE LINES CEILING MECHANICAL ELECTRICAL AND COMMUNICATION SYSTEMS INSIDE THE
TUNNEL REPLACEMENT OF BROOKLYN PLAZA STRUCTURAL SLAB AND ENVIRONMENTAL REMEDIATION AT HUGH L CAREY TUNNEL
OVER $50M
Under this contract the contractor will repair or replace various tunnel structural elements roadway ventilation and utility elements including mechanical
electrical and communication system Also under this contract the Brooklyn Plaza structural slab will be replaced This is a Sandy project and as this
project will contain FEMA funding it is subjected to relevant federal regulations
Repair concrete liner replace tunnel ceiling panel and wall tile system
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 420
Replace communicationtraffic control systems
Replace interior and transition lighting systems and other associated items
Replace tunnel pump system low tension duct system including catwalk and associated components
Rehabilitate Brooklyn Plaza roadway surface and drainage from portal to Gowanus Express way approach
Provide Maintenance and Protection of Traffic (MPT) as required and prepare as-built documentation
Duration of Contract 60 Months
HH-88A
RECONSTRUCTION OF UPPER AND LOWER PLAZA AND SOUTHBOUND APPROACH
$10M - $50M
Construction of a new mechanical space on the rooftop of the facility building relocation of utilities from the lower maintenance garage including a water
line HVAC boilers chillers pumps and electrical distribution equipment A new emergency generator needs to be installed Underground fuel tanks are to
be removed including associated environmental remediation Underground sewage holding tanks and oilwater separator will be replacedrehabilitated under
this contract Roofing of the facility building is to be replaced
Staged removal of HVAC equipment in the lower level maintenance garage removal of electrical distribution equipment fire sprinkler system and
heating units and underground fuel tanks
Construction of a new space in the rooftop of the facility building for housing the HVAC system Replace roofing of the facility building
Staged installation of new boilers chillers air handlers domestic HW heater fire protection and vent stacks in the facility building
Construction of a new electrical enclosure and emergency generator in the facility lot
Relocate city water main to facility building
Rehabreplace sewage holding tanks and oilwater separators in facility lot
Duration of Contract 18 Months
RK-23A
RECONSTRUCTION AND REHABILITATION OF MANHATTAN APPROACH RAMPS TO AND FROM 124TH 125TH ST
OVER $50M
This project includes staged replacement of the On and Off Ramps from 124th Street 125th Street concrete deck along with portions of the supporting
steel seismic upgrades substructure repairs
Remove existing concrete bridge deck and steel crossbeams and replace with new concrete bridge deck and steel stringers and existing steel
roadway edge barriers and replace with F-shaped concrete barriers at 125th Street On and Off-Ramps ndash Steel girder supported spans 1st Avenue to
Pier 58
Remove existing concrete cellular structures and replace with expanded polystyrene fill structure and existing concrete approach slab and replace with
new approach slab at 125th Street On and Off-Ramps ndash 2nd Avenue to 1st Avenue
Remove existing structure drainage system and install new drainage system
Install new seismic isolation bearings and sliding bearings Install new micro-pile supported concrete piers Install new steel bent cap Install new steel
girders
Miscellaneous electrical and utility relocation and reconstruction
Provide as-needed maintenance and protection of traffic
Duration of Contract 34 Months
Bridges and Tunnels
Brief Description of Work
JUL 2014
RK-76
MISC STRUCTURAL REPAIR AT RFK BRIDGE
$10M - $50M
This Project includes Miscellaneous steel and concrete repairs at various sections of RFK Bridge
Concrete repairs to piers cap beams pedestals stem walls and parapets
Steel repairs for Floor-beams Stringers Diaphragm and Truss Chords
Misc Drainage pipe Repairs
Provide as-needed maintenance and protection of traffic
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 520
Provide as-built drawings
Duration of Contract 18 Months
Long Island Rail Road
Brief Description of Work
APR 2014
E01848 [Sandy]
NY WESTERN RAIL YARDS FIRE ALARM SYSTEM [DESIGN-BUILD]
$500K - $1M
Design-Build for replacement of the Fire Alarm System at West Side Yard with a new Fire Alarm and Detection System Phase 1 includes 3 Maintenance
of Equipment buildings and 1 Facility Pump Building Contractor shall provide As-Built drawings training basic warranty and technical support for the new
system that will interface with support other data sources at LIRR and will have local monitoring
Remove and demolish existing Fire Alarm System and all devices components
Provide non-proprietary fire alarm system hardware and software
Provide visual alarm strobe lights and supervised wiring
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUN 2014
E01817 [Sandy]
DESIGN-BUILD FOR LONG BEACH BRANCH SIGNAL SYSTEM
$5M - $10M
Design-Build project for replacement of the bi-directional signal system along LIRRs Long Beach Branch with operation boundaries between Valley Tower
and Long Beach StationTerminal
Design Submittals for 90 Design Package and 100 Design Package
Manufacturer assembly and delivery of Central Instrument Location [CIL] houses huts and cases
Construction Submittals including CILs grade crossing huts master locations transmitters and battery
Detailed work plans for all work on Right of Way including delivery staging and installation of CILs and grade crossing huts
Conduct integrated factory testing of signal equipment including hardware and software
Conduct comprehnsive onsite testing to support signal system cutover
Duration of Contract 22 Months
L10001
ELLISON AVENUE BRIDGE REPLACEMENT
$10M - $50M
Design-Build for replacement of of the Ellison Avenue Roadway Bridge crossing the LIRR Main Line between Carle Place and Westbury Stations
Complete Final Design for Bridge Replacement
Demolition of existing Roadway Bridge
Construction of new Roadway Bridge including abutments side spans wing walls superstructure deck and assorted finishes including fencing
Duration of Contract 24 Months
Long Island Rail Road
Brief Description of Work
JUL 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 620
L09986
HICKSVILLE NORTH TRACK SIDING
$10M - $50M
Utility relocations retaining wall construction signal bridge removal and new signal bridge installation
Relocate existing utilities to new ductbanks to provide space for new retaining wall and tracks
Construct new retaining wall to support new North Track Siding extension
Remove existing signal bridge to construct retaining wall
Install new portal signal bridge to support new North Track Siding extension
Duration of Contract 8 Months
Metro-North Railroad
Brief Description of Work
MAR 2014
M08817
REHABILITATE - 2 ELEVATORS (SE12) - GRAND CENTRAL TERMINAL
$1M - $5M
This contract is for the rehabilitation and increased capacity of (2) Grand Central Terminal Elevator Cars SE1 and SE2 serving the lower level track 100
track 14 and the loading dock at Depew Place This work includes
Demolition and installation of new elevator cars with new piston hydraulic systems
Installation of new hydraulic and HVAC systems in elevator machine room
Installation of new elevator management systems with integration into existing building management system
Duration of Contract 24 Months
Metro-North Railroad
Brief Description of Work
JUN 2014
M08793
CONSTRUCTION - GCT TRAINSHEDSTRUCTURE
$10M - $50M
This contract will provide for the construction of the rehabilitation of portions of the upper and lower levels of the train shed in Grand Central Terminal The
rehabilitation will consist of repairs to deteriorated steel and concrete at various locations in the roof above the upper level tracks and at locations above the
lower level tracks Work will be required to be performed on week nights and over weekends to minimize disruption to the train service This work will
include
Repair of deteriorated reinforced concrete roof slabs including demolition placement of formwork and reinforcement casting of concrete and placement
of waterproofing
Repair of deteriorated structural steel components including deleading and removal of the existing elements and replacement with new steel plate and
angles to restore the integrity of the components All restored components will then be painted
Removal and replacement of a deteriorated reinforced concrete platform slab in the terminal
Removal and replacement of a deteriorated concrete roof slab over an electrical substation All work will be performed from scaffolding erected above
the substation components
Duration of Contract 27 Months
M09198
CONSTRUCTION OF CULVERT LOCATED AT MP JS5100 - SALISBURY MILLS
$1M - $5M
This contract is for the rehabilitation of the culvert located at MP JS5100 in Woodbury New York It consists of a 95 feet long arched concrete culvert with a
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 720
3 feet wide by 4 feet 10 inches high opening The unreinforced culvert is located under a single track and a service road It exhibits three major cracks
located along the culvert Cracks 1 and 2 which are minor are located 85 and 265 feet north of the centerline of the track respectively Crack 3 which is
located 42 feet north of the track centerline exhibit a 12 inches settlement of the remaining outlet This portion of the outlet is undermined This Work
includes
Mobilization and access road improvements
Removal of the undermined portion following excavation support of the service road located north of the track
Installation of a cast in place concrete outlet portion
Slope remediation
Pressure grout and crack repairs
Inlet protection
Duration of Contract 12 Months
M09403E01881
CONSTRUCTION 4 SUBSTATIONS
$10M - $50M
This contract calls for the construction of three (3) specific DC traction power substation on the Hudson Line The Hudson Line substations included in this
contract are A-13 (Riverdale) A-25 (Tarrytown) and A-33 (Harmon Yard) In addition the 4th substation designated as B-52 (Brewster) is located on the
Harlem line This Work includes
Fabrication will utilize a prefabricated (modular) structure(s)
New Substation construction to incorporate conservative safe elevations from flooding
Each substation will be rated 2 x 2000kw at 750 VDC output
New cables insulated and rated for 2kv service between each feeder breaker and third rail as between the negative bus and running rails
The incoming utility feeders are from either Con-Edison or NYSEG
AC switchgear A33 includes an additional (4) AC feeds for the Harmon Yard facilities
Duration of Contract 24 Months
MTA Bus
Brief Description of Work
MAR 2014
SF04-7408
DEPOT EQUIPMENT CHASSIS WASH - LAGUARDIA amp BAISLEY PARK DEPOTS
$1M - $5M
This project will consist of new depot equipment for maintenance and facilities operations a new chassis wash at both the LaGuardia Depot and the
Baisley Park Depot located in the borough of Queens
Duration of Contract 6 Months
SF07-7411
JFK APRON
$5M - $10M
This project is for facility renovation that will consist of replacing the deteriorated apron and select exterior bus parking at the JFK Depot located in the
borough of Queens
Duration of Contract 10 Months
MTA Bus
Brief Description of Work
APR 2014
SF01-7407
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 820
SECURITY IMPROVEMENTS FAR ROCKAWAY amp BAISLEY PARK
$5M - $10M
This project will consist of security improvement to protect critical MTA infastructures to ensure the secure continuation of MTA operations at the Far
Rockaway and Baisley Park depots located in the borough of Queens
Duration of Contract 15 Months
SF07-7314
FAR ROCKAWAY ROOF DECK REPLACEMENT
$1M - $5M
This project is for facility renovation that will consist of replacing the deteriorated roof deck of the main building at the Far Rockaway Depot located in the
borough of Queens
Duration of Contract 8 Months
New York City Transit
Brief Description of Work
MAR 2014
A36151
ACCESS IMPROVEMENTS AT GRAND CENTRAL STATION
$10M - $50M
This project will provide improved access at Grand Central Station on the IRT Lexington Avenue Line located in Manhattan Work will include the installation
of an additional stair on the west side of the 42nd Street entrance platform improvements and improvements to fare control areas
Duration of Contract 36 Months
A36906A36908
STATION COMPONENT REPAIRS AT 5 LOCATIONS
$5M - $10M
This project will repair station components at 3 locations on the Lexington Avenue Line in the borough of Manhattan and 2 locations on the Queens
Boulevard Line in the borough of Manhattan Work will include the repair of columns and column bases repair of drip pans repair of underpass walls and
ceilings and platform edge repairs with new ADA warning strips The locations are
59 Street LEX
51 Street LEX
Astor Place LEX
5th Avenue QBL
7th Avenue QBL
Duration of Contract 13 Months
C33840
STRUCTURE OVERCOATING BROADWAY JUNCTION - NEW LOTS AVENUE
$10M - $50M
This project will paint a portion of the elevated steel structure of the BMT Canarsie Line from south of Broadway Junction to south of New Lots Avenue in the
borough of Brooklyn This project also includes steel repairs Work will include
Surface preparation and structural steel painting
Removal of all loose lead based paint dirt grease and grime from the elevated structure
Use of SSPC containment system to capture all lead paint and debris
Limited repairs of steel member and columns
Duration of Contract 26 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 920
C34915
LINE STRUCTURE OVERCOATING ABUTMENT TO KINGS HWY
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Abutment to Kings Highway on the Culver Line in the borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
C34916
LINE STRUCTURE OVERCOATING KINGS HWY TO WEST 8 ST
$10M - $50M
This project is for the overcoat painting of the elevated street structure from Kings Highway to West 8th Street Culver Line in the Borough of Brooklyn The
work for this project will include
Surface preparation and structural steel painting
Removal of all loose lead based paint (to refusal dirt grease and grime) from elevated steel structure
Application of three (3) coats of alkyd paint to all steel surfaces
All lead paint chips and debris are to be captured using SSPC containment system and will be disposed of as hazardous waste
Repair of selected structural steel components
Duration of Contract 24 Months
P36444(SANDY)
SANDY REPAIRS RESTORATION OF CRANBERRY AND RUTGERS TUBE
OVER $50M
This project is for the restoration of the Rutgers Tube and the Cranberry Tube These tubes experienced extensive damage due to salt water intrusion during
Super storm Sandy Work will include
Replacement of communication and power cables within both tubes
Replacement of tunnel lighting and signals within both tubes
Restoration of 2 pump rooms within the Rutgers Tube
Restoration of 2 pump rooms within the Cranberry Tube
Restoration of CBH 596 in the Rutgers Tube
Restoration of CBH 502 in the Cranberry tube
Restoration of 3 fan plants
Restoration of substation equipment
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
S32765
INTERLOCKING MODERNIZATION WEST 4TH ST
OVER $50M
This project will modernize and improve the reliability of the West 4th Street Interlocking located on the 6 Avenue Line in the borough of Manhattan Work
will include replacement with a new Solid State (SSI) interlocking and the construction of new relay rooms to house all associated equipment This project
is necessary for the future implementation of Communications Based Train Control (CBTC) Work will include
Construction of new signal relay room Reporting facility Fire Suppression HVAC Rooms
Replacement of all interlocking wayside signal equipment such as but not limited to stops signs switches and signal heads
Installation of a new messenger system and new cables as required for vital traffic circuits
All signal power and signal power distribution necessary for the installation
Provisions for LED Starting Lights and Holding Lights
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1020
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
APR 2014
A36891
STATION COMPONENT REPAIRS 2 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at two stations on the 4th Avenue Line in the borough of Brooklyn The tasks include
At 9th Street Station Platform column and beam repairs at selected locations Trackwall structural crack repairs Trackwall tile replacement in areas
impacted by structural crack repairs At 59th Street Station Platform edge replacement Platform tactile warning strip installation Platform slab crack
repair Platform modification to create an ADA-compliant boarding zone Platform beam repair at selected locations Mezzanine partial floor slab
replacement Mezzanine floor inlet drain line replacement
Duration of Contract 12 Months
A36909
COMPONENT REPAIRS AT 5 STATIONS - CANARSIE
$10M - $50M
This project is for station component repairs at 5 Stations on the Canarsie Line in the borough of Brooklyn The work for this project include the repair of
sidewalk roof structures facades platforms and structural steel This project is located at
Graham Ave
Wilson Avenue
Atlantic Avenue
Grand Street
Montrose Ave
Duration of Contract 24 Months
A37547
STRUCTURAL STEEL REPAIR 9TH AVENUE STATION
$5M - $10M
This project will rehabilitate the Lower Level of the 9th Avenue Station on the West End Line in the borough of Brooklyn which also connects to NYCTs
38th St Yard Work will include
Repairreplacement of corroded structural steel (columns and beams) concrete and west Portal
Surface preparation and structural steel painting
Duration of Contract 18 Months
A37593(SANDY)
SANDY REPAIRS SOUTH FERRY
OVER $50M
This project is for the restoration of South Ferry Station Complex located in the borough of Manhattan South Ferry Station Complex was extensively
damaged due to salt water intrusion during Super storm Sandy
Replacement of tunnel lighting
Replacement fo damaged mainline track switches
Restoration of South Ferry Fan Plant
Restoration of South Ferry Pump Room
Restoration of South Ferry Interlocking
Restoration of employee facilities
Installation of new electrical and mechanical systems
Water leak mitigation
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1120
Restoration of station HVAC system
Restoration of signal relays
Duration of Contract 24 Months
A46010
STATION RENEWAL AND COMPONENT REPAIRS 9 STATIONS
OVER $50M
This project will perform station renewal at 7 stations and repair of station components at 2 stations on the Culver Line in the borough of Brooklyn Work will
include the repair of structural deficiencies throughout the station and improvements to architectural treatments The locations for this project are
Avenue X Station
Avenue U Station
Avenue P Station
Bay Parkway Station
Avenue I Station
18 Avenue Station
Ditmas Avenue Station
Kings Highway Station
Avenue N Station
Duration of Contract 40 Months
C33848
PERIMETER HARDENING RCC amp 130 LIVINGSTON
$5M - $10M
This project will enhance the security of NYC Transits Rail Control Center (RCC) in the borough of Manhattan and 130 Livingston Plaza in the borough of
Brooklyn Work for this project includes
Installation of planters bollards
Installation of bollards both fixed and retractable as appropriate
Installation of Delta Barriers
Site exploration and any necessary modifications
Installation of any necessary lighting CCTV alarms or other equipment necessary for the control and monitoring of the retractable bollards and Delta
Barriers
Duration of Contract 12 Months
C43046
HYDROGEN GAS VENTILATION 19 COMMUNICATION ROOMS
$5M - $10M
This project will provide ventilation for 19 communication rooms at multiple locations in Brooklyn Queens Manhattan and the Bronx to meet NYS Uniform
Fire Prevention and Building Codes prescriptive requirement for hydrogen gas concentration thresholds The following are the locations 1 MR 35 59th
Street 2 MR 120 Bedford Ave 3 MR 259 Union Tpk 4 MR 390 149th Street Grand Concourse 5 MR 322 14th St 7th Avenue 6 MR 406 14th St Lexington
7 MR 102 Essex Street 8 MR 469 Grand Central 9 MR 11 Times Square 10 MR 98 Flushing Ave 11 MR 174C Jay Street 12 MR237 Carroll Street 13
MR 345 Utica Avenue 14 MR 408 Bleecker Street 15 MR 461 Queens Borough Plaza 16 MR 159 81 Street 17 MR 105 Chambers Street 18 MR 148
168 Street 19 MR 161 59 Street Columbus Circle
Duration of Contract 17 Months
C43749
REPAIR LIVINGSTON PLAZA FACcedilADE REPLACE ROOF UPGRADE amp MAINTAIN ELEVATORS INSTALL SECURITY BOLLARDS REMOVE amp
REPLACE WWII MEMORIAL
$10M - $50M
This project will upgrade amp maintain elevators repair the exterior facade install security bollards replace the Jay Street WW II Memorial and re-roof NYC
Transits Livingston Plaza facility in Brooklyn Work will include
Obtain accurate field information data measurements Verify in-situ conditions circuitry and terminations replace elevator controllers motors hoist
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1220
ropes traveler cables cab door operator assemblies and install new rope grippers while maintaining the remaining elevators
Coordinate with the existing pedestrian shed installer design and secure approval of all temporary work platforms
Rake repoint all exterior block joints remove lintel block re-flash and re-seal all window openings replace damaged block
Remove replace sidewalk sections and install foundations amp bollards
Remove the WWII Memorial from the Jay Street building and re-install in the Livingston Plaza Lobby and
Replace the existing multi-level roofing system while maintaining waterproof integrity
Duration of Contract 31 Months
E31114
REPLACE PROGRAMMABLE LOGIC CONTROLS AT 22 LOCATIONS
$10M - $50M
This project will replace the obsolete Programmable Logic Controller (PLC) components of the fan control system with new PLCs at 22 vent plant locations
Work will include
Secure A amp P to obtain accurate field information for the production of all hardware [racks wiring harnesses etc]
Verify in-situ conditions and circuitry terminations
Upon receipt of all components De-Commission facility [only 3 at a time]
Remove amp replace all internal wiring from the field termination boards to the PLC
Replacement of PLC control equipment and Human-Machine Interface [HMI] hardware wiring software and programming of Rail Control Center lsquohead-
inrsquo equipment
Re-direct remote control to the RCC via an existing Fiber Optic network at 15 of the 22 locations
Assist NYCT CPM in verifying the new wiring and de-bugging the programs if warranted
Test to verify PLC performance remote operation and indication
Re-Commission facility
Duration of Contract 40 Months
E40805
REHABILITATE PUMP ROOMS 4 LOCATIONS
$5M - $10M
This project will rehabilitate pump rooms at four locations systemwide Pumps at each location perform the essential service of removing water from the
system and they are past their useful lives Along with replacement of all obsolete equipment this project will include replacement of discharge lines new
power feeds and improvement of the automatic alarm system that alerts the Hydraulics Control Center of any problems that develop as well as
modifications to the physical enclosures to help protect the investment Locations for this project include
Walton Ave Bronx
Brook Avenue Bronx
146th Street Manhattan
148th Street Manhattan
Duration of Contract 27 Months
T80276(SANDY)
SANDY REPAIRS ST GEORGE INTERLOCKING
OVER $50M
Severe storm damage left the Staten Island Railroad system inoperable at St George Terminal Flooding in the interlocking irreparably damaged vital signal
systems Switches Power cables and all other cables and wiring were submerged in flood water This project is the flood repairs for St George yard and
interlocking Work for this project is expected to include track and switch replacement replacement of third rails provision of rail lubrication system signal
modernization and drainage improvements The work proposed under this project is as follows approximately East Portal of the Tunnel to the west end of
the station platforms on Track 1 through 12 and Tracks 10A 11 and 12 through the Ballpark station and track NS2 (Substation) The project consists of
replacing all the tracks ties contact rail and switches within the limits of the project The VA dwarf signals will be refurbished and the lighting will be
rehabilitated
Duration of Contract 24 Months
W32366
REPLACE BUS RADIO SYSTEM
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1320
OVER $50M
The objective this project is to replace old outdated analog radio equipment including base stations mobile and portable radios with a new digital radio
system The project will improve two way communications with buses support vehicles in the field and critical to day-to-day bus operations
bullFurnish and install a new radio base station network that can support both voice and data transmission for all NYC Transit bus operations The new
system shall be scalable with the capacity to accommodate up to 12000 radio devices and ensure adequate radio frequency coverage in NYC
bullRetrofit all NYC Transit buses revenue and non-revenue vehicles with new digital radios all associated hardware and software and provide
portablehandheld radios to dispatchers
Duration of Contract 50 Months
New York City Transit
Brief Description of Work
MAY 2014
C43753
CONSTRUCT BUS COMMAND CENTER
$10M - $50M
This project will construct a modernized Bus Command Center that will serve MTA buses and NYCT DOB buses The new command center will be built
across from the East New York Bus Depot in the vicinity of Fanchon Place and Jamaica Avenue The command center shall include bus dispatch consoles
radios telephones and equipment hardware and software necessary for a fully functional bus command operating center It shall also include the
modernized operating theater with video walls acoustic speakers modernized computer monitors and displays
Duration of Contract 24 Months
New York City Transit
Brief Description of Work
JUN 2014
A36905
STATION COMPONENT REPAIRS 3 STATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at three stations on the Fulton Street Line in the borough of Brooklyn The tasks
include Platform repairs at Kingston-Throop Avenue Ralph Avenue and Liberty Avenue Stations At Kingston- Throop Avenue and Ralph Avenue Stations
Platform edge rubbing board replacement Platform tactile warning strip installation Platform slab crack repair and associated concrete topping slab
replacement Platform modification to create an ADA-compliant boarding zone Replacement of water pipe insulation on hanging pipe beneath platform
edge At Liberty Avenue Station Platform slab crack repair and associated concrete topping slab replacement
Duration of Contract 12 Months
A36921
STATION COMPONENT REPAIRS 4 LOCATIONS
$5M - $10M
This project is for component repairs to eliminate deficient conditions at four stations on the Brooklyn-Queens Crosstown Line in the borough of Brooklyn
Locations for this project include Broadway Station Myrtle - Willoughby Avenue Station Clinton - Washington Avenue Station and 21st Street ndash Van Alst
Avenue Station Platform repairs include Platform edge replacement Platform tactile warning strip installation Platform slab crack repair Platform
modification to create an ADA-compliant boarding zone At 21st Street ndash Van Alst Avenue Station Trackwall tile replacement at the southbound platform
Trackwall tile repair at selected locations at the southbound platform At Broadway Station and Myrtle - Willoughby Avenue Station Station Painting
Duration of Contract 12 Months
B40660
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1420
PURCHASE 256 ARTICULATED BUSES
OVER $50M
This project will purchase 256 60-FT low floor articulated buses which provide service on identified high capacity bus routes These buses shall be designed
to operate in Authority revenue service for a minimum of 12 years or 500000 miles These buses will meet Enviornmental Protection Administration (EPA)
emission standards as well as Americans with Disabilities Act (ADA) Standards
Duration of Contract 22 Months
P36415
REHABILITATION OF CIRCUIT BREAKER HOUSE PEARL STREET
$5M - $10M
This project will rehabilitate Circuit Breaker House (CBH) 275 on the IRT Clark Street Line in the Borough of Manhattan Work will include the removal of
existing breakers and install new equalizer breakers telephone lighting and cable from the Pearl Street Substation to the tracks and from CBH 275 to the
tracks Restore remote control to the CBH
Duration of Contract 20 Months
P36446(SANDY)
SANDY REPAIRS RESTORATION OF CLARK STREET TUBE
$10M - $50M
This project is for the restoration of the Clark Street Tube The Clark Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of 4 circuit breaker houses (229 278 301 284)
Restoration of mainline track
Replacement of substation equipment
Duration of Contract 24 Months
SF07-7346
SLIDING GATE REPLACEMENT AT JACKIE GLEASON BUS DEPOT
$1M - $5M
This project will replace the existing defective concrete slabs and sliding gates as well as adjacent chain link fences at the entrance of the Jackie Gleason
Depot in the borough of Brooklyn The work includes but is not limited to civil electrical and mechanical work It will provide all labor materials tools and
equipment necessary for installing testing and putting into operation the sliding gates
Duration of Contract 8 Months
W32372
PASSENGER STATION LAN AT 20 STATIONS
$10M - $50M
Passenger Station LAN is a fiber-based network infrastructure deployed in a ring configuration (originating from the main Comm Room passing around the
station areas and back to the Comm Room) with strategically-placed access nodes throughout (enclosures housing Ethernet switches for future IP
connectivity) used specifically for local transport of all current and near future applications This project will install Passenger Station LAN at 20 stations
throughout the system The network will provide a communications infrastructure to support the following applications
New Fare Payment System
Help Point Intercom (HP0
Next Train Arrival Information
Station Advisory Information Displays (SAID)
Passenger Identification CCTV (PID)
Wireless Access for Wayside to Train Data Communications Transit Employee Mobile Applications and Passenger mobile device access
Duration of Contract 17 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1520
New York City Transit
Brief Description of Work
JUL 2014
A36890
STATION COMPONENT REPAIRS 49TH STREET
$5M - $10M
This project will eliminate deficient conditions at 49th Street Station on the Broadway Line in the borough of Manhattan Work will include
Repair of street stairs
Repair of platform edge
Repair of stair ceiling concrete and steel beams
Duration of Contract 18 Months
C34914
SHOP REPAIRS AND UPGRADE
$10M - $50M
This project will replace and repair high-priority deficient components at the Pitkin Shop in the borough of Brooklyn and the Concourse Shop in the borough
of the Bronx in order to bring the listed facilities to a State of Good Repair and to provide the existing facilities with adequate service needed to maintain and
prolong the useful life of the subway fleet Work will include At Pitkin Maintenance Shop Partial replacement of roofing systems at Pitkin Maintenance
Shop and new roofing system at Pitkin Oil House Install new overhead crane Replace 2 DC Power Stinger Systems with new ones At Concourse
Maintenance Facility Replace 3 DC Power Stinger System with new ones Install new duct work within the yard and positive and negative cables
Duration of Contract 18 Months
D37467
PBX UPGRADE PHASE 1
$10M - $50M
This project will replace and upgrade obsolete or incompatible sub-systems in the mission-critical Private Branch Exchanges (PBXs) that NYCT uses for
voice and data communications routing Locations include
333 W 53 Street Manhattan
East New York Depot Brooklyn
Coney Island Yard Brooklyn
Roosevelt Avenue Station Queens
East 180 Street Shop Bronx
Livingstong Plaza Brooklyn
207 Street Yard Manhattan
Duration of Contract 33 Months
P80275
NEW POWER SUBSTATION PRINCES BAY
$10M - $50M
This project will install a new power substation at Princes Bay in the borough of Staten Island Work will include furnishing and installing the high tension
switchgear power transformer rectifier DC feeder breakers positive and negative cables ventilation system etc
Duration of Contract 28 Months
ST12-0139
INTEGRATED SERVICE INFORMATION amp MANAGEMENT B DIVISION MODULE 1
$10M - $50M
This project will provide consistent and timely information about the current state of B Division service to staff and customers moving the organization
toward centralized monitoring and control The successful delivery of integrated service information and management will lead to improved service safety
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1620
and security This project will provide coverage for all stations within the entire B Division The design furnish and testing of signal data acquisition
equipment at the first 8 Tower and Communication rooms has started This includes collecting the data in the field and routing it to the Rail Control Center
Duration of Contract 26 Months
W32697
INSTALL PUBLIC ADDRESS AND CUSTOMER INFORMATION SCREENS AT 87 LOCATIONS
$10M - $50M
This project will install PACIS cabinet at 87 stations systemwide These are among the only remaining stations without any form of PACIS system The
system to be Installed under the project will feature audio and text messaging capabilities and will be connected to the NYCT communication network
Duration of Contract 33 Months
New York City Transit
Brief Description of Work
AUG 2014
A36090
STATION RENEWALS OF 9 STATIONS
OVER $50M
This project will repair 9 stations on the Sea Beach Line in the borough of Brooklyn All station elements will be repaired during this project The 9 stations
are 20th Avenue 8th Avenue Fort Hamilton Parkway 18th Avenue Kings Highway New Utrecht Avenue Bay Parkway Avenue U and 86th Street Work
will include
Repair of street-level control houses
Repair of tunnel structures supporting the control houses
Replacement of passageway enclosures
Replacement of platform metal stairs and canopies
Repair of platform
Additionally station aesthetics will be remedied and artwork will be installed
Duration of Contract 46 Months
A36916
STATION COMPONENTS EASTCHESTER - DYRE AVENUE
$5M - $10M
This project is for component repairs to eliminate deficient conditions at the Dyre Avenue Station on the Dyre Avenue Line in the borough of the Bronx
Work will include
Provide new platform piles and platform
Repair control house roof
Provide new thruspan at tracks over control house
Minor electrical work that is affected by component repairs
Repair track girders
Provide new canopy roofing
Duration of Contract 48 Months
C33076
EMERGENCY GENERATOR REPLACEMENT AT CASEY STENGEL DEPOT
$1M - $5M
This project is for the replacement of an emergency generator at the Casey Stengel Depot in the borough of Queens Work for this project includes civil
mechanical and electrical work to replace the existing emergency generator with automatic transfer switch (ATS) The scope of this project includes
Replacement of generator Installation of new panels transformer and ATS Upgrade of the emergency loads (ie increase loads to emergency generator)
Duration of Contract 18 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1720
C34829
RTO FACILITIES HARDENING PH 2
$10M - $50M
This project will install equipment that will enhance security and access control at 17 NYC RTO facilities throughout the system as part of the agencys
security initiatives Work will involves
Installation of CCTVs and video recording equipment
A new fiber optics network to connect the employee facility with the communication room as required
New door hardware and swipe card system
Electrical circuits to support communication work
Duration of Contract 24 Months
C34913
CAR WASHER REPAIRS AT 3 YARDS
$10M - $50M
This project will replace existing car washer components and perform first priority repairs at 239th Street Yard Concourse Yard and Pelham Yard in the
borough of the Bronx This work is required to bring the listed facilities to a State of Good Repairs and to provide the existing facilities with adequate service
needed to maintain and prolong the useful life of the subway fleet
Removal and disposal of the selected existing car washer components including piping brushes motors and pumps
Upgrade to the structures and utilities
Miscellaneous architectural repairreplacement work at car washers and control rooms
Additional structural supports
Duration of Contract 19 Months
E31380
THREE BUS WASHERS AT M J QILL BUS DEPOT
$5M - $10M
This project consists of providing one new bus washer and upgrading 2 existing bus washers in the wash area of the Michael J Quill Bus Depot in the
borough of Manhattan Work includes
Install one new bus washer and integrate the new bus washing system with the existing water reclamation and drainage systems
Provide associated electrical power lines new breakers and disconnect switches and controls to operate new equipment
Rerouting existing fire alarm system and electrical conduits that interfere with new work
Provide insulation and heat tracing for the outdoor piping in the vicinity of the detergent fill box
Replace worn out components at the two existing bus washers and install two new splash panels and resurface the bus washer floor
Duration of Contract 16 Months
New York City Transit
Brief Description of Work
SEP 2014
A36150
ADA AT 57 STREET PHASE 2
$10M - $50M
This is the second and final phase to provide full ADA (Americans with Disabilities Act) accessibility at the 57th St Station on the BMT Broadway Line in
the borough of Manhattan The station has been identified as an ADA Key Station Work will include
Construction of two ADA-compliant elevators
Construction of a new extension to the station mezzanine with a new structure under 7th Avenue
Construction of new ADA-compliant facilities
Construction of two mezzanine to platform stairs
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1820
Relocation of utility and transit duct banks
Duration of Contract 38 Months
A36865
STATION COMPONENT REPAIRS AT 4 STATIONS
$10M - $50M
This project will repair station components at 4 stations on the Jamaica Line in the boroughs of Brooklyn and Queens The stations to be addressed are 121
Street 111 Street 104 Street and Myrtle Avenue Stations Work for this project will include
Replacement of platform slabs
Replacement of all platform stairs
Repairs of platform girders and wind screens
Replacement of platform lights beyond canopy
Painting and 18 Feet of canopy extension at platform stairs
Duration of Contract 25 Months
A36871
STATION COMPONENT REPAIRS AT TWO STATIONS
$5M - $10M
This project will repair station components at the Beverly Road Station and Newkirk Avenue Station on the Nostrand Line in the borough of Brooklyn Work
will include repair and replacement of the platform edge
Duration of Contract 18 Months
A36884
STATION COMPONENT REPAIRS 103 STREET
$5M - $10M
This project will repair station components at the 103 Street Station on the Lexington Line in the borough of Manhattan Work will include
Repair of street and platform stairs
Installation of new concrete platform finishes platform edges
Repair of ventilator structure ceiling and walls
Repair of mezzanine ceioling walls floors
Painting of the entire station
Duration of Contract 24 Months
C34912
CAR WASHER REPAIRS AT CONEY ISLAND YARD
$1M - $5M
This project will bring the car washer at Coney Island Yard in the borough of Brooklyn to a State of Good Repair by doing proper component replacement
Work will include
Component replacement of existing car washer including associated electrical IampC and enviornmental work
Replacement of lower roof system
Replacement of existing water storage tank with four new 1250 gallon tanks
Installation of new compressed air system
Replacement of existing ejector pumps with new portable hoist equipment
Duration of Contract 14 Months
E34022
7 HYDRAULIC ELEVATOR
$10M - $50M
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 1920
This project will replace seven hydraulic elevators systemwide in order to achieve more reliable and efficient operations Locations include three at Brooklyn
Bridge Station two at 125 St and two at 51 St Station All are located on the IRT Lexington Avenue Line in the borough of Manhattan Work will include the
replacement of elevator cabs and equipment within the elevator cabs shaftways pits and machinery rooms Shaftways pits and machinery rooms are to
remain but will be modified as required for new equipment All elevators are to meet ADAAG requirements
Duration of Contract 24 Months
P36447(SANDY)
SANDY REPAIRS RESTORATION OF 53RD ST TUBE
OVER $50M
This project is for the restoration of the 53rd Street Tube The 53rd Street Tube experienced extensive damage due to salt water intrusion during Super
storm Sandy Work will include
Replacement of communication and power cables within the tube
Replacement of signals and signal equipment
Restoration of Circuit Breaker House 565
Electrical and lighting work
Installation of Emergency Alarm systems
Duration of Contract 24 Months
Capital Construction
Brief Description of Work
MAR 2014
CM014B
GCT CONCOURSE AND FACILITIES FIT-OUT
Over $100M
The work under this contract covers the construction of the new LIRR Grand Central Terminal (GCT) Concourse facility Work elements includes
foundations underground utilities CMU walls structural steel framing mechanical electrical plumbing fire protection and architectural finishes This
contract also provides for the construction for the fit-out of 44th Street and 50th St Ventilation Facilities The scope of work includes but is not limited to
Construction of the new LIRR GCT Concourse
Intermodal Connections and Interfaces with MNRrsquos GCT including dining concourse 45th street cross passageway and the 47th St cross
passageway
44th Street Ventilation Facility and 50th Street Ventilation Facility Fit-Out
Installation of elevators and escalators using the designated Contract VM014 Contractor
Perform the local station testing of GCT concourse and caverns
Duration of Contract 48 Months
CS084
SYSTEMS PACKAGE 2 TRACTION POWER SYSTEMS
$50M - $100M
This Contract is for furnishing and installing multiple tunnel systems for the entire length of the ESA Project The work shall include but is not limited to the
following
Fabricate install test and commission all traction power substations and wayside equipmnet for the East Side Access Project
Plan and execute inegrated system tests to ensure proper integration of elements in this contract package with related elements installed under other
contract packages
Provide on-site and office support for owner-directed system verification tests Railroad-directed pre-revenue tests and other system activation activities
Duration of Contract 46 Months
Capital Construction
Brief Description of Work
APR 2014
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months
352014 MTA - Eye on the Future
httpwp1mtahqorgmtacapitaleotf-descriphtm 2020
C-52123-1
ARCHITECTURAL ELECTRICAL AND FIRE PROTECTION UPGRADES FOR THE 34TH ST PENN STATION COMPLEX
$1M - $5M
This Contract is for architectural electrical and fire protection upgrades for the 34th Street Penn Station Complex The work shall include but is not limited
to providing all labor material and equipment deemed necessary and incidental to perform the following
Installation of photoluminescence strips at various stairs walls and columns
Installation of downstands at various stairways and exit gates
Installation of photoluminescence signage
Installation of detectable warning strips integrated with photoluminescence as various platforms
Install new exit gates and integrate them into the existing electromagnetic gate system
Duration of Contract 20 Months
CH057
HAROLD STRUCTURES PART 3 48TH ST BRIDGE D APPROACH PHASE I AND EASTBOUND RE-ROUTE APPROACH
$50M - $100M
This Contract is for earth and site work utility relocations track realignment drainage hazardous material abatement demolition of existing structures and
construction of new heavy civil structures within the LIRR Harold Interlocking located in Queens The work ncludes but is not limited to providing all labor
material and equipment deemed necessary and incidental to perform the following
Construction of the new Mainline 48th Street Bridge
Construction of the Tunnel D Pit and Approach Structure
Construction of the loop box structure extension
Installation of Retaining Walls
Construct Catenary Structures
Installation of monitoring devices for existing structures and ground conditions
Duration of Contract 24 Months