quality management program (qmp) review htcp program iri news
TRANSCRIPT
![Page 1: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/1.jpg)
2014 WisDOT Quality Management Program Update
![Page 2: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/2.jpg)
Quality Management Program (QMP) Review HTCP Program IRI News
Outline
![Page 3: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/3.jpg)
QUALITY MANAGEMENT
FHWA Six Building Blocks of Quality Assurance 1. Contractor Quality Control
2. Aids to Acceptance
3. Dispute Resolution
4. Independent Assurance
5. Lab Accreditation or Qualification
6. Technician Qualification and Certification
![Page 4: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/4.jpg)
• Quality of Materials and Proper Installation is key
• Three part Quality Management Program (QMP) -• QC Testing by Contractors• QV Testing by Department Staff• Independent Assurance/Oversight by Department Staff
• Contractor QC testing for acceptance is the center piece of the department's Quality Management Program.
QMP Review
![Page 5: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/5.jpg)
Section 701 General QMP Requirements –
701.2.2 Quality Control Plan Submit 10 business days before production or placement Engineer reviews and comments
701.2.3 Personnel Certification Personnel required to be trained and certified by HTCP
701.2.4 Laboratory Certification Contractor Portable and fixed labs to be reviewed and qualified See department website for list Ken Nwankwo POC for qualification, 608-246-5388
QMP Review
![Page 6: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/6.jpg)
Section 701 General QMP Requirements –
701.2.5 Equipment Contractor furnishes the necessary equipment and supplies for
performing quality control testing. The engineer may inspect the measuring and testing devices to
confirm both calibration and condition. Calibrate testing equipment according to CMM 8-30 and maintain a
calibration record at the laboratory.
QMP Review
![Page 7: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/7.jpg)
Section 701 General QMP Requirements –
701.2.6 Documentation Document daily – results to WisDOT contact person same day Use forms provided in CMM chapter 8. Enter data into the applicable MRS software within 5 business days
after results are available. If the original document is handwritten and then transferred to an
electronic document, the original handwritten document should be maintained as the “source” document.(CMM 8-30.9.6)
QMP Review
![Page 8: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/8.jpg)
Section 701 General QMP Requirements –
701.2.6 Documentation Document daily – results to WisDOT contact person same day Use forms provided in CMM chapter 8. Enter data into the applicable MRS software within 5 business days
after results are available. If the original document is handwritten and then transferred to an
electronic document, the original handwritten document should be maintained as the “source” document.(CMM 8-30.9.6)
QMP Review
![Page 9: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/9.jpg)
Section 701 General QMP Requirements – 701.3 Contractor Testing
QC testing Random Sampling Required Use Sampling and Testing Methods in Spec and CMM Notify Engineer of failed tests Engineer may observe sampling and testing
701.4 Department Testing QV Testing – usually a percentage of QC Testing Random Sampling Required Use same Sampling and Testing Methods as Contractor Testers required to be certified thru HTCP
QMP Review
![Page 10: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/10.jpg)
Section 701 General QMP Requirements –
701.3 Independent Assurance Evaluates Department QV and Contractor QC Performs Independent Assurance Program
Split Sample testing Proficiency sample testing Witness sampling and testing Test Equipment Calibration checks Reviews contract req’d data and contractor process control information Can request additional sampling and testing Checks to assure testers are certified by HTCP
QMP Review
![Page 11: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/11.jpg)
Dispute resolution process for non-conforming materials - Section 106.3.4.3.5 - defined as:
Engineer and contractor to make every effort to avoid conflict
Contractor Inspections, testing, corrective actions and process control charts are to be used to determine solution
Third party testing will be used if resolution cannot be made by evaluating existing data
QMP Review
![Page 12: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/12.jpg)
Highway TechnicianCertification Program
![Page 13: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/13.jpg)
HTCP CERTIFICATION
FHWA Six Building Blocks of Quality Assurance 1. Contractor Quality Control
2. Aids to Acceptance
3. Dispute Resolution
4. Independent Assurance
5. Lab Accreditation or Qualification
6. Technician Qualification and Certification
![Page 14: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/14.jpg)
• Certification/Training is provided by HTCP- UW Platteville
• Multistate-locations, 30% in Platteville
• Certification good for 3 Years
• Training is provided January thru July
• Skilled Technicians trained to national and state standards
• Certification is achieved by demonstrating proficiency thru Testing Sampling Techniques, Lab Procedures and Specification knowledge
HTCP CERTIFICATION
![Page 15: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/15.jpg)
HTCP CERTIFICATION
![Page 16: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/16.jpg)
• Re-Certification required every 3 Years• Certification now expires June of 3rd year
• How:• Retake the course• Take the written test on exam day• Schedule a test at HTCP-Platteville• Attend a comprehensive testing site
HTCP RE-CERTIFICATION
![Page 17: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/17.jpg)
![Page 18: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/18.jpg)
TRANSPORTATION MATERIALS SAMPLING (AGGREGATE SAMPLING)
HMA TRUCK BOX SAMPLING (NEW via On-line) AGGTEC- I AGGTEC- II ATTS HMA-IPT HMA-TPC HMA-MD PCCTEC-I PCCTEC-II CONCRETE STRENGTH TESTING (CST) GRADINGTEC- I PROFILER NUCDENSITYTEC- I
HTCP Certifications
![Page 19: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/19.jpg)
![Page 20: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/20.jpg)
![Page 21: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/21.jpg)
HMA Truck Box Sampling •QV sampling and testing has increased for HMA
•Threshold for QV testing increased from 1/30,000 tons per mix design to 1/5,000 per mix design.
•This requirement has increased the workload for sampling
• Decision was to add more samplers by utilizing AGG-Techs
•HMA-TBS is a self paced course on on-line.
![Page 22: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/22.jpg)
HMA Truck Box Sampling
•QV sampling and testing has increased for HMA
•Threshold for QV testing increased from 1/30,000 tons per mix design to 1/5,000 per mix design.
•This requirement has increased the workload for sampling
• Decision was to add more samplers by utilizing AGG-Techs
![Page 23: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/23.jpg)
• Now Effective• New Localized Roughness Threshold• New Category IV PCC and HMA (urban pavement)
thresholds• Regional training – April 7 thru April 17
• ½ Day on Spec review, PROVAL Use and Data Analysis
• If attending, please bring laptop to load PROVAL and review MRS Data
• Engineer post testing ride of pavement needs increased attention
• Will be become part of Standard Spec in 2015
IRI Ride News
![Page 24: Quality Management Program (QMP) Review HTCP Program IRI News](https://reader038.vdocuments.site/reader038/viewer/2022110400/56649db05503460f94a9ecc4/html5/thumbnails/24.jpg)
Contacts for IRI Specification and Testing:
Joe Wilson, 608-246-7955, [email protected] Sorensen, 608-246-3855, [email protected] Parry, 608-246-7939, [email protected]
WisDOT Ride QMP