- Purpose - Main sequences - Resources (manpower and GSE), including location -Main activities of the assembly and integration of the subsystems -Final integration and tests EUSO-BALLOON DESIGN REVIEW, 18.12.2012, CNES TOULOUSE Sylvie Dagoret-Campagne LAL, Orsay, Baptiste Mot, IRAP, Toulouse The EUSO-BALLOON AIT- Development plan 1

Upload: rosalind-griffin

Post on 22-Dec-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

- Purpose

- Main sequences

- Resources (manpower and GSE), including location

-Main activities of the assembly and integration of the subsystems

-Final integration and tests

E U S O - B A L L O O N D E S I G N R E V I E W, 1 8 . 1 2 . 2 0 1 2 , C N E S T O U L O U S E

Sylvie Dagoret-CampagneLAL, Orsay,Baptiste Mot,IRAP, Toulouse

The EUSO-BALLOON AIT-Development plan

1

CDR – 18.12.2012

AIT Development plan and GSE 2

EUSO-BALLOON, a Highly Modular instrument

4 subsystems :• « electrical » (DP,PDM,DP)• 1 mechanical,

DP : 11 components (boards),

PDM : 5 components (boards),

PWP : 1

Each component under the responsibility (design, fabrication, procurement) of different laboratories world wide spread.

Phase B Phase C&D • Need AIT/AIV procedures• Need resource evaluation• Need time evaluation (planning)

AIT Development plan and GSE 3

Main sequences of Integrations

CDR – 18.12.2012

EC-Unit Integration: MATRA-LAL

Electronic Integration:

LAL

Data processing Integration:INFN-Naples

PDM integration:APC

Optics Tests:RIKEN-JP/UAH-

US tests

Full electronics intgration:

APCInstrumentIntegration:B.I.S CNES

Mechanics assembly:

B.I.S CNES

FinalTests:B.I.S CNES

time

AIT Development plan and GSE 4

Manpower for AIT

Full Instrument AIT

:B. Mot/IRAP

Mechanical AIT : G. Roudil/IRAP

Electronic AIT : M Dupieux/IRAP

Optical AIT : C. Catanalo/IRAP

AQ AIT : TBD / IRAP

CDR – 18.12.2012

PDM-AIT : P. Barrillon/S. Dagoret /LAL

H. Miyamoto/L

ALS. Blin/LAL C.

Moretto/LAL APC Team

DP AIT : G.

Osteria/INFN

Naples-INFN

Rome-INFN BARI-INFN IAAT-

Tuebingen

Full integration :

Subsystem/ electronic integration :

DP integration :

AIT Development plan and GSE 5

GSE-PDM

CDR – 18.12.2012

AIT Development plan and GSE 6

GSE-CAL

CDR – 18.12.2012

AIT Development plan and GSE 7

GSE-DP and GSE-Opt

CDR – 18.12.2012

AIT Development plan and GSE 8

ComponentPre-assembly

Component test

EC-Unit

HVPS

EC-ASIC

PDM-B

Pre-Integration

Assembly

IntegrationTests &Validation

PAECM2

PAECM1

THV1

THV2

TECA2

TECA1

TPD1..N

IEC1

IEC2

IEC3

IEL1

IEL2

AP1

AP2

AP3

CAPHEEC1

TrigPDM

CAKIEC1

CDR – 18.12.2012

PDM AIT activities sequence

AIT Development plan and GSE 9

PDM AIT activities list

CDR – 18.12.2012

Test name component comment duration location whocomponent pre-assembly

PAECM1 MAPMTPhoton collection efficiency and gain measurement for each channel 1 month for 36 units APC APC & LAL

PAECM2 MAPMT Sorting to fit an EC 1 hour APC APCTHV1 HVPS cable reference THV2 HVPS HV tuning (depending on PMT gains) APC APCComponent Tests

TECU1 EC-Unit static test under HV, normal air pressure 1 hour LAL LALTECU2 EC-Unit static test under HV, low pressure 12 hours APC LALTECA1 EC-ASIC visual inspection 1 hour LAL LALTECA2 EC-ASIC electronic test bench 1 week for 6 units LAL LAL

TPD1 PDM-BElectrical mechanicalcompatibilitie 1 day Korea SKKU

TPD2 PDM-B Power supply tests 1 day Korea SKKUTPD3 PDM-B ASIC configuration 1 day Korea SKKUTPD4 PDM-B ASIC readout TBD Korea SKKUTPD5 PDM-B Trigger functionality tests TBD Korea SKKUTPD6 PDM-B HVPS switch control tests TBD Korea SKKUTPD7 PDM-B DP (or CCB) interfaces TBD Korea SKKUTPD8 PDM-B HK logic and interface tests TBD Korea SKKUPre-Integration

IEC1 EC-Unit+HVPS static test under HV, normal air pressure 1 hour per EC unit APC APC&LALIEC2 EC-Unit+HVPS statistic test under HV, low pressure 12 hour / EC-Unit APC APC&LAL

IEC3 EC-Unit+HVPS+EC-ASIC light on EC-Unit+ EC-ASIC red by Test-EC-ASIC10 days assembly+15 days tests APC APC&LAL

IEL1 PDM PDM-B readout external computer LAL APC&LALIEL2 PDM+DP link CCB+PDM-B 1 week LAL APC&LAL

AIT Development plan and GSE 10

PDM-AIT Activities list

CDR – 18.12.2012

Test name component comment duration location who

Assembly

AP1 9 EC-Units+PDM-Framemechanical integration and screwing 1 day APC LAL

AP29 EC-Units+6 EC-ASIC+PDM-Frame

mechanical integration and screwing 1 day APC LAL

AP39 EC-Units+6 EC-ASIC+HVPS+PDM-Frame cabling 1 week APC APC

AP4

9 EC-Units+6 EC-ASIC+HVPS+PDM-B+PDM-Frame

mechanical integration and cabling 1 week APC LAL

Calibration

CAPHEEC1 EC-Units+EC-ASIC

Photon counting calibration (Test-EC-ASIC) 3 weeks APC APC&LAL

CAKIEC1 EC-Units+EC-ASICKI channels calibration (Test-EC-ASIC) 3 weeks APC APC&LAL

Validation

TrigPDM PDM + light sourceapply a fast moving light spot few days APC APC&LAL

SWLOG PDM + light sourceapply a variable light source few days APC APC&LAL

AIT Development plan and GSE 11

DP-Activities sequence

CDR – 18.12.2012

AIT Development plan and GSE

DP-AIT Activities list

ID512

Test name component comment duration location who

ID1 LVPS+HK+CPU

1-2 monthes Naples

IAAT and INFN

(NA-BA-Roma2)

and Korea

ID2 LVPS+HK+CPU+GPS+CLK SPI tests

ID3LVPS+HK+CPU+GPS+CLK+CCB

ID4LVPS+HK+CPU+GPS+CLK+CCB CCB through SPI

ID5LVPS+HK+CPU+GPS+CLK+CCB

CCB through Spacewire

ID6LVPS+HK+CPU+GPS+CLK+CCB+PDM-B

…ID1 ID5

CDR – 18.12.2012

AIT Development plan and GSE 13

Computer

PDM board

EC-ASICboard

Power supply Logic

analyzer

NI(PC interface)

Multimeter

Charge injection

EC-ASIC board

ASIC

PDM board

Pre-Integration EC-ASIC and PDM-B

CDR – 18.12.2012

AIT Development plan and GSE 14

PDM-B-DP Pre-Integration

CDR – 18.12.2012

EC-HV

EC-DYNODE

HVPS2

HVPS1

MA

PM

T

EC-ANODE

EC-ASIC

PDM-B

IR-CAM

Batteries

PWP

LVP

S-D

P1

LVP

S-D

P2

LVPS-PDM

LVP

S-H

K

HK

CCB

CLKB

GPSR

CPU

DST

SIREN

CNES Telemetry

EXT

Bat Controller

TLS

Sensors

Motors

SPACEWIRE/PCI

EC-Front

EC-Back

DPINTERFACES TESTED UP TO NOW FOR HARDWARE

DP PDM

AIT Development plan and GSE 16

Optical AIT Activities list

Test name component comment duration location who

TOP1 Lenses 1,2,3 acceptance tests 1 week/lens IKEGAMI RIKEN

TOP2 Lenses 1+2+3 performances tests 1 month Alabama UAH

TOP3 Lenses 1+2+3

validation tests for integrated instrument TBD CNES IRAP

TOP 1 TOP 2

CDR – 18.12.2012

AIT Development plan and GSE 17

PWP Activities sequence

CDR – 18.12.2012

CDR – 18.12.2012

AIT Development plan and GSE 18

Activities- Task forms

• All activities are referred by an acronym,

• Each activity is performed in a sequence of AIT-AIV of a subsystem of of the instrument

• They are tracked in activity forms by AIT managers

• Description :• Component,• Configuration,• GSE,• Task details, procedures, results

Example of description of a task

AIT Development plan and GSE 19

Final AIT-AIV

Resp : IRAP location : CNES

1. Overview of Integration Phases

2. Sequence of integrations

3. Global tests

4. Transport and flight campaign preparation

5. Flight campaign #1

CDR – 18.12.2012

AIT Development plan and GSE 20

1.SEQUENCE FOR INTRUMENT INTEGRATION

CDR – 18.12.2012

Preliminary

+ IR-CAM Assembly

AIT Development plan and GSE 21

2.GLOBAL TESTS

CDR – 18.12.2012

Preliminary

AIT Development plan and GSE 22

3.TRANSPORT AND FLIGHT-CAMPAIGN PREPARATION

CDR – 18.12.2012

Preliminary

AIT Development plan and GSE 23

Flight campaign #1

CDR – 18.12.2012

Preliminary

AIT Development plan and GSE 24CDR – 18.12.2012

Conclusions

• Main phases of AIT identified :• Subsystems• Instrument (Final),

• Many activities identified for subsystem AIT and their component integration,• Test procedures assessed,• Some activities can be done in parallel, some in sequences.• Merging points.

• Activities are inserted in a sequence of AIT of the subsystems,• Types of activities:

• Component tests, pre-integration, assembly, integration, tests and validation, calibration.

• Resources in manpower for AIT distributed, location of the activities, including the management.

• Resources in GSE listed,• Timing estimated,• Activities follow-up:

• AIT-AIV will be controlled and tracked by the AIT managers using activities forms.