© 2011 hcl axon – proprietary & confidential telenor global roll out global erp roll out –...
TRANSCRIPT
© 2011 HCL AXON – Proprietary & Confidential
Telenor Global Roll Out
Global ERP Roll Out – Our Approach
2
Introductions Summary proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
3
Introductions Summary Proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
4
Oracle capability
3250 Consultants
North
America
1270
EMEA
400
Latin
America
100ANZ
100
India
1170
APAC
210Consultants
Global Oracle Team
22 Specialisations and Accreditation in all areas relevant to Telenor global rollout
40% of the team are either Chartered Accountants or hold master degree in business
Very senior, experienced EBS delivery team
A commitment from our entire GLOBAL leadership team to see Telenor through to success
Oracle Consultants 3250+
Active customers 190 +
Countries 31
Offices 60
Global Delivery Centers 15
MARQUEE CUSTOMERS Practice Summary
5
Your delivery team
Kevin Deeley-GrahamProgramme Manager
Idnan ModiDeployment Manager
Tammy MittelstaedtDelivery Assurance
David ReesProgramme Architect
Kannan P. M. Palanisamy Integration Lead
Tim PuddefootFunctional Lead
Ganesh ChidambaramWave Deployment Lead
Olav Tennøy Solution Architect
Off-shoreteams
6
Our proposition to Telenor
Telenor Knowledge
Value Driven
Strong Team
Proven supplier to Telenor on Integration proof of concept Will leverage resources and learnings Proven ability to work in multi-vendor
Alternative approach can reduce programme cost by 20% and improve delivery certainty post DTAC
Risk sharing reflected in our fees approach A compelling approach to our management, deployment and
development teams
Senior team each has over 15 years experience Delivered over 50 back-office projects Many large global deployments
Partnership Approach
Relationship, transparency and trust. Easy to work with. Sensitive and experienced with Shared Services deployments Problem solvers to avoid commercial implications
7
Introductions Summary Proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery variants Commercial Offer
Agenda
8
Cultural Compatibility in Global Delivery
A shared focus across all parties on the achievement of Telenor’s business objectives
Agreed, shared behaviours, defined at the outset. Honesty, joint working and pragmatism are key
Clearly defined accountabilities for each party and each team member contributing to a common goal
GERP is a major transformation programme that will require multiple vendors and skills. Cultural compatibility can make or break the programme.
9
Key elements of the GERP Programme
Org & Process Change Org design and roles Training Comms
Programme Governance Governance PMO and planning Standards and
control
Design Authority Develop template Protect template Assess change
Build and Test Factories System build Testing Security
TSS Team Process specialists Centralised
expertise Data ownership
GP and DTAC Users Local knowledge Data prep/reconciliation Super users
10
Programme Management Team and Design Authority Based in Norway
Core TeamCentral
Central DeployTeam
Org & Process Change
TSS core transformation Services • Shared Service transition• Manage User Acceptance• End user readiness
TSS core transformation Services • Shared Service transition• Manage User Acceptance• End user readiness
Core Team and Release Management• Programme management• Cross vendor and wave PMO• Central Deployment co-ordination• Release management
Core Team and Release Management• Programme management• Cross vendor and wave PMO• Central Deployment co-ordination• Release management
Design Authority
(CRB)
Solution Design Authority• Solution Governance and CR
assessment on changes
Solution Design Authority• Solution Governance and CR
assessment on changes
a
Wave
Build
Core Norway
Local BU team
Norway - extended team
“Offshore” teams
Legend
Org & Process Change
Central team deployed locally
11
Offshore Build Teams Based in India
Offshore COE
Build
Testing
Data
Core TeamCentral
Central Deployteam
Org & Process Change
Design Authority
(CRB)
Industrialised Offshore CoE Delivery
• Local build extensions• Independent Testing• Data Migration factory• Development factory• Training Materials • Security extensions• Environment
Management
Industrialised Offshore CoE Delivery
• Local build extensions• Independent Testing• Data Migration factory• Development factory• Training Materials • Security extensions• Environment
Management
a
Wave
Build
Core Norway
Local BU team
Norway - extended team
“Offshore” teams
Legend
Org & Process Change
Central team deployed locally
12
Regional Wave Delivery Teams Provide Local Functional Support at Key Stages
TSS
GPOffshore COE
Build
Testing
Data
Core TeamCentral
Central Deployteam
Org & Process Change
India Deployment Wave hub• Manage end to end plan for the
wave• Co-ordinate local deployment
activities across countries• Integrate with Telenor change
activities in the plan
India Deployment Wave hub• Manage end to end plan for the
wave• Co-ordinate local deployment
activities across countries• Integrate with Telenor change
activities in the plan
Design Authority
(CRB)
Wave DeployTeam
DTAC
Local BU team• Business readiness and
local process changes• Data preparation and
reconciliation• Local Cutover
Local BU team• Business readiness and
local process changes• Data preparation and
reconciliation• Local Cutover
a
Wave
Build
Core Norway
Local BU team
Norway - extended team
“Offshore” teams
Legend
Org & Process Change
Central team deployed locally
13
GERP Programme Plan
14
GERP Programme Structure
Programme Manager
Programme Management Office
Global Design Authority(EAI, Apps, Process, Data)
Deployment Manager
Org & Process Change
Business Lead/Sponsor
Country Business Owner
Process CoE
Legend
Org & Process Change
Deployment
Business Roles
Release
Delivery Areas
Retained systems ReleaseLeads
1
RICEFW
Data Migration
Change & Communication
User Acceptance
Training
Wave Deployment Lead
India WaveHub
Provide environments
Co-ordinate retained systems changes in line with plan
Build and Test Teams
Role MappingDeploy & C/O
Testing
P2P etcFI
Steerco
Business Prioritisation Board
TSS Core Programme Management
Release Management (IT)
QA
Country Process Owners
Local Project Manager
Local Change & Training
Local ITTeams
Key users – data prep, UAT
Local (in country) structures
Country HR Lead
Local Functional
Country Project Manager
15
Programme Delivery Method
Part of our implementation is bringing the best of iGDM and your method together
The method defines our phases, workstreams and deliverables
Provides best practice templates
Provides our planning framework
Helps align all resources around a common process
...an effective delivery method makes the programme low risk and predictable
16
HCL Accelerators and TemplatesAccelerators Benefits
iGDM: Project Controls –governance frameworks, risk and communication approach
Best practice framework for de-risking for global multi geo, multi time zone projects and ensures right levels of communication and control.
iLoad - HCL internal tool to migrate data into Oracle Applications
Baseline tool reducing overall effort especially in a standard global template.
iSetup: standard Oracle tool which helps easy migration of configurations between instances
Reduces effort , de-risks set up across instances
APSE (Axon Project Support Environment).
Real life project activity status – and workflow driven solution review process. Reduces overall effort and risk and promotes adherence to project timelines. Especially designed for global projects with multi geo and multi time zone teams
Project Deliverables Standard Test scripts, Training Materials, Environment Plans, Data extract and load scripts, standard global roll out plans, cutover plans to be used as a baseline and checklist reducing effort and risk
Testlink Bugzilla Test Management Suite
With preloaded test scripts for all Oracle modules in scope for Telenor. Will reduce effort to build vanilla test cases
Usage Tracking Route Program Monitors post go live system usage and performance enabling corrective actions around user training needs and lack of adherence to business and system processes
17
Ensuring Effective Global Co-ordination
Benefits of APSE
• Drives project procedures• Document relationships• Electronic Sign-off & status
tracking• Web access to encourage
usage by broader project team including the business
• Collaborative working environment
• Working with global delivery teams
• Real-time reporting on all aspects of the project available to everyone
• Document Mgmt for Compliance
18
Risks to Achieving Telenor Objectives
Develop TSS into an established and mature shared services business
Implement a template solution and achieve cost savings
Provide greater transparency, visibility and business agility
GERP will be a role model implementation for other rollouts and shared services
19
GERP Programme Risks
Risk Impact Likelihood
Failure to Achieve a Template Design
H M• Defined up front design principles• Formalised design close out• Active sponsor involvement in design issues
Retained Systems and Legacy Integration
H M• Early engagement• Stub and connectivity testing• Reusable common components
Lack of Dedicated Market/TSS Resources
M M• Clear expectation exchanges and OSA attendance• Clear RACI and responsibility split• Realistic resource based planning
Timezone Challenges
M H• Use of APSE• Man marking• Clearly defined handoffs
Successful Data Migration
M M• Cleansing – early / transparent reporting• Reconciliation – early / active business involvement• Testing – early / active use of migrated data in testing
Mitigation
20
Introductions Summary proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
21
Recap - HCL Deployment Team
GPOffshore COE
Build
Testing
Data
Core TeamCentral
Central Deployteam
Org & Process Change
Design Authority
(CRB)
Wave DeployTeam
a
Wave
Build
Core Norway
Local BU team
Norway - extended team
“Offshore” teams
Legend
Org & Process Change
Central team deployed locally
DTAC
22
Optimisation of GP plan
M-2
M-1
M1
M2
M3
M4
M5
M6
M7
M8
M9
M10
M11
M12
Aug
Sep
Oct
No
v
Dec
Jan
Feb
Mar
Ap
r
May
Jun
e
July
Au
g
Sep
t
Phases Sub-Phases
Supplier Knowledege KTRemaining Analysis
Ramp-upDesignBuild and UTTest ST1 ST2 PSV RegrData conversion
Training TtT TrainUser Acceptance Test UATHandover and Release
Stabilization
Implementation
Migration
Preparation
Proposed GP deployment plan (SI view)
Month
Migration
D2 GP Stabilization
ImplementationMob
OAT ?
Training Material
Phased BuildSIT
Load 1 Load 2 Load 3
Mobilisation and KT to start prior to
contract if possible
1 All build work, EAI and retained systems changes
have same end date
3
Day by day plan complete design and spec work in 8 weeks
including retained systems and EAI
23 data loads into
individual test phases
5
4 weeks training - dependent on UAT
8
4 weeks Regression test
– after UAT
7
2 cycles of SIT – 4 weeks each
6
All integrations need to be tested in System Test 2
4
23
Robust off-shore development management process
24
Minimise changes to the Global Template and retain pace
Programme Steering Committee
Programme
EAMO2C
P2P
RTR TSS & GP Process Owners
Business Process Owner / Head of Service
Design Authority (CRB)
Escalate
Process Team
Tele
no
r
HC
L
Team Lead
Change required
Challenge
Workshop Attendees
Line ManagersLocal Process OwnersBenefit OwnersChange ChampionsLocal Key Users
Localisation Requirements
Solution & Process Validation
Localisation & Integration Workshops
Design Forums
DesignCo-ordination
Design Teams
EA, Process, Application, Technology, Data, Change
Business
Non Standard Template Requirement
Decision criterion:• Agreed authority level for
each decision type• Decision making Service
Level Agreements• Contingency budget
available for drawdown• Process assignment (global
v Local)• Clear principles agreed by
business
Business Prioritisation Board
(GPO, Country)
Preliminary Prioritisation
Work-around, or future release
Reject
Business Sponsor
25
Introductions Summary Proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
26
Approach & Plan for DTAC Established Induction’
approach to mobilisation and KT.
Extend existing governance & controls
to DTAC
1Reduced build effort through reuse of
RICEFW templates. Build can happen parallel to design
3
Day by day plan updated from GP learning's – earlier
engagement possible
2
Reuse test artefacts and refine risk that require testing to
reduce cost
4
Use implementation tool
kit from GP to reduce BU resource
effort
5
Reduced time required due to
load programmes build and tested
6
Regression test for changes only
7
27
Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15Planning and mobilisation Design - TLS Build and Unit testTesting (systems, Integration and UAT) ST1 ST2 SIT1 SIT2 UATFinal Prep ( Regression, Cutover) FPTrainingMigration & c/oStabilizationMobilisation & DTAC BU team Validate Process TLS changes PrepBuild Build
Test ST SIT SIT UATCut-Over & Go-Live FPTrainingMigration & c/oStabilization
Mobilise
Program PlanProject Activities
MobiliseDesign
Design
2012 2013
Dependencies across GP and DTAC in parallel
Need to manage Critical path on
environments across waves
Tight timings on design to allow build and test durations
Plan well in advance with Tieto
28
Introductions Summary Proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
29
HCL reduce the risk of integration element
•Understands existing services and can expand on them to make them standard
•Leverage re-use due to past knowledge – map standards
Standardise integration and re-use services
•We know the key Telenor systems and understand Cassini
•Standard workshops for integration with templates to be agreed across partners and drive common approached
Common approach to integration design
•Carry smoke tests with BU systems
•Carry out signature handshakes with BU
•Create stubs to isolate testing in advance of SIT
Reduce risk through early testing
•Strong collaboration with TSS Pakistan
•Understand Tieto with approach to manage additional scope
•Know stakeholders at TSS and how decisions work
Developed trusted relationships
•Look to set up early sessions to understand architectures
•Identify key systems and owners critical to integration
•Agree clear hand-offs across partners
Plan ahead for long lead times
30
Introductions Summary Proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
31
There are a number of risks that need to be managed in later waves
High level of parallel wave activity creates risks to be managed
2012 2013 2014
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
StabilizeD2 DIGI
D2 Tn Hungary Stabilize
StabilizeTn Sweden MobileD2
StabilizeD2 DTAC
StabilizeD2 Tn Serbia
StabilizeGPD2
DTAC design and validation prior to completing testing and closing solution gaps
and defects
Short validation window for identifying and building
legacy integration dependencies in line with
OBES plan
Potential environments overlaps between waves
with each one needing QA systems for testing
Parallel phases required larger team sizes and resource constraints
SAP data migration and process
alignment
Limited duration between D2 and design end
activity that allows loacl BU integration spec,
build and test durations
32
Stabalise
Alternative approach – reducing cost and risk
Deploy Pilot
Release (build/test/tech deploy)
LocalisationDesign
End to End Wave & Go Lives
Technical Go Live
Business Go Lives
Handover CR Specs
Early engage
Process CoE GFS & Release Engine
DSI Local Deployment
6 month 6 month
Wave N
Legend
6 month
GP
Deploy (Data & bus ready)
LocalisationDesign
Early engage
Wave 2
6 month
DTAC(Thailand)
DIGI (Malaysia)
Release (build/test/tech deploy)
Retain rapid go-live cadence
Wave N+ 2
Deploy ( Data & bus ready)
Release (build/test/tech deploy)
Localisation Design
Early engage
Sweden Serbia Hungary
33
Same scope in the same overall timelines, with more time per phase and wave to reduce risk
Apr May Jun Jull Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jull Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jull Aug Sep Oct Nov Dec
GPFP
UT Tr
DTAC DIGI
SW SR HU
Alternate plan - grouped by region
Test
KeyPilot deploy
Wave 2Release 2
A&P Design Build Test
2012 2013 2014
Wave 1Release 1
A&P Design
Assumed Pilot Release pilot
Des/Build
FP FP
Build Test
Tech Go Live Bus roll inBAU Update
Release
Release
APAC
Europe
Complete GP before starting DTAC-avoid delaying both and retrofitting CR’s
2
Sequential release approach critical path with
use of environments across parralell waves
5Decoupled go-live - flexible business adoption window -
elected a 3 month roll in window a
4
Synchronised project and BAU code drops to
manage retrofit adoption
6
Flexible long lead time to plan local IT and business
dependencies
1
Regional grouping to maximise alignment
3
End date met – each wave has
12 months
7
34
Estimated 21.5% saving of cost for DTAC
Recognises the increase in efficiency as the waves and solution mature
Reduces risk of delays to 2014 based on– More flexible business roll in dates and
decoupled dependencies
– Extended up front analysis and
design time to plan complex integration
– Reduces peaks demands on TSS, GP &
GERP resources
DTAC to be delivered 1 to 2 months later than compliant approach
Cost saving across the total programme expected to be similar or larger given additional overlaps in later waves
Recommended approach reduces cost and risk
Offshore %
+
100%Delivery efficiency gains over time
Cost per
Entity
Full Industrialisation
Wave 1
Wave 2
Wave 3 Wave 4
35
Introductions Summary Proposition Global Delivery GP Delivery DTAC Delivery Integration Delivery Variants Commercial Offer
Agenda
36
BU Target Price (NOK)
GP 25,180,526
DTAC 18,460,439
Commercial Offer
excluding VAT and other applicable taxes
© 2011 HCL AXON – Proprietary & Confidential
Questions & Answers