yakima t.o.c. load assist
DESCRIPTION
Presenters: Michael Dixon Ben Gheliuc Group Members: Haidar Al Gharash Daniel Gheliuc Fue Her Zach McCurter Capstone Advisors: Faryar Etesami Evan Thomas Yakima Sponsors: Mark Elliot Chris Sautter. Yakima T.O.C. Load Assist. overview. Introduction / Background - PowerPoint PPT PresentationTRANSCRIPT
YAKIMA T.O.C. LOAD ASSIST
Presenters:Michael DixonBen Gheliuc
Group Members:Haidar Al GharashDaniel GheliucFue HerZach McCurter
Capstone Advisors:Faryar Etesami
Evan Thomas
Yakima Sponsors:Mark Elliot
Chris Sautter
OVERVIEW Introduction / Background Internal/External Customers PDS Criteria House of Quality Technical Risk Management Project Timeline Summary
BACKGROUND Current Yakima Designs.
COMPETITORS Thule
Malone
PREVIOUS ATTEMPTS Yakima’s first load assist design
TARGET PERSONA Average 45 year old 5’ 2” woman
Paddles a sea kayakRides a bikeDrives a Subaru Outback
INTERNAL CUSTOMERS Yakima PSU Capstone Team Dr. Evan Thomas Dr. Faryar Etasami PSU Machine Shop
EXTERNAL CUSTOMERS Chris Sautter Mark Elliot Yakima Legal Department Yakima Financial Department End-User
Target Persona
PDS CRITERIA Ergonomics
Ease of use for target personaMax load assist
CostTarget retail - $500
SafetyPinch points
Clear existing IP/Patents Testing
Yakima internal standards – ISO #
HOUSE OF QUALITY
TECHNICAL RISK MANAGMENT
Load Assist mechanism fails Clearence / height Weight Cost Testing
PROJECT TIMELINETask Assign Date Finish Date Tasks due
Discussion of ideas and scope of project Dec-13-11 Jan-11-12
Internal and External Research Jan-9-12 Feb-3-12
Draft Design Jan-23-12 Feb-29-12
PDS Report Jan-16-12 Jan-30-12 Jan-30-12
PDS Report Presentation Jan-30-12 Feb-13-12 Feb-13-12
Evaluation Of Drafted Design Feb-13-12 March-5-12
Design/make Product Feb-20-12 March-15-12
End of the Term Progress Report Feb-27-12 March-12-12
Progress Report Presentation Feb-27-12 Feb-27-12 Feb-27-12
Presentation design to Sponsor March-12-12 March-14-12
Testing and Prototyping March-14-12 April-4-12
Redesigning Concept And Prototype March-21-12 April-18-12
Repeat Testing April-11-12 April-25-12
Manufacture Final Product April-25-12 May-23-12