woodglen lake dredging and restoration

31
Woodglen Lake Dredging and Restoration Department of Public Works and Environmental Services

Upload: fairfax-county

Post on 22-Nov-2014

2.184 views

Category:

News & Politics


1 download

DESCRIPTION

Woodglen Lake Dredging and Restoration Department of Public Works and Environmental Services

TRANSCRIPT

Page 1: Woodglen Lake Dredging and Restoration

Woodglen Lake Dredging and Restoration Department of Public Works and Environmental Services

Page 2: Woodglen Lake Dredging and Restoration

Woodglen Lake Facts

Lake Surface Area = 12.5 acres

Sediment Pool Capacity = 160,000 cubic yards (CY)

Current sediment in lake = 32,500 CY

Estimated annual sediment load = 1,244 CY

17 feet

32,500 CY

Page 3: Woodglen Lake Dredging and Restoration

Watershed

Drainage Area = 740 acres (1.15 square miles)

Pohick Creek Watershed

Sideburn Branch

Page 4: Woodglen Lake Dredging and Restoration

Woodglen Lake

Page 5: Woodglen Lake Dredging and Restoration

Woodglen Lake: Sediment Thickness

Page 6: Woodglen Lake Dredging and Restoration

Woodglen Lake: Water Depth

Page 7: Woodglen Lake Dredging and Restoration

Inactive Dewatering Basin

Woodglen Lake: Dewatering Basin

Available Exclusively by DigitalGlobe

©2013 Microsoft Corporation © 2012 Nokia

Page 8: Woodglen Lake Dredging and Restoration

Lake Restoration and Dredging Project

Project Goals

Restore sediment pool capacity

Downstream water quality benefits

Lake water quality

Esthetics

Improve lake water quality and habitat

Stabilize stream segment

Provide long term maintenance improvements

Page 9: Woodglen Lake Dredging and Restoration

Dredging Alternatives

1. Mechanically dredge deposited sediment and haul wet

2. Drain lake and dry deposited sediment in place before hauling

Page 10: Woodglen Lake Dredging and Restoration

PRE-DREDGING: An estimated 35,000 cubic yards of sediment had accumulated in the lake, forming islands and reducing water levels to less than three feet in most areas.

Lake Barton Example

Page 11: Woodglen Lake Dredging and Restoration

Lake Barton Example: Pre-Dredging

Page 12: Woodglen Lake Dredging and Restoration

Lake Barton Example: Dredging in Progress

DREDGING: Dredging took place without draining the lake.

Page 13: Woodglen Lake Dredging and Restoration

Lake Barton Example: Dredging in Progress

Page 14: Woodglen Lake Dredging and Restoration

Lake Barton Example: Completed Project

Page 15: Woodglen Lake Dredging and Restoration

Lake Needwood Example

Lake Needwood: Montgomery County, MD

Dredging: The lake was drained and the sediment was dried in-place.

Page 16: Woodglen Lake Dredging and Restoration

Lake Needwood Example: Dredging

Page 17: Woodglen Lake Dredging and Restoration

Dredge Alternative – In the Wet

General Sequence Establish access and staging areas

Conduct dredging utilizing barges

Haul wet sediment to disposal site for drying

Benefits Less weather dependent

Quicker initial start to dredging

Less potential for schedule extensions or delay

Concerns Increased sediment handling effort at disposal area

Potentially higher cost

Page 18: Woodglen Lake Dredging and Restoration

Dredge Alternative – In the Dry

General Sequence Initiate drawdown of lake Establish access and staging areas Establish diversion channels within lake Conduct dredging

Benefits Higher daily sediment removal rates Minimal sediment handling effort at disposal area Potentially lower cost

Concerns Very weather dependent Higher potential for delays due to weather Typically more odor from entire lake bottom being exposed Need to relocate/salvage fish

Page 19: Woodglen Lake Dredging and Restoration

Dredging: 32,500 Cubic Yards

Woodglen Lake

Staging Area

Page 20: Woodglen Lake Dredging and Restoration

Lake Restoration

In-lake forebay

Wetland planting

Shoreline stabilization

Fish habitat

Fish stocking

Lake Barton: Fish stocking by Virginia Game and Inland Fisheries

Fish habitat created from salvaged trees

Page 21: Woodglen Lake Dredging and Restoration

Chesapeake Bay Preservation Areas

Buffer Restoration

Page 22: Woodglen Lake Dredging and Restoration

Woodglen Lake: Shoreline Restoration

Page 23: Woodglen Lake Dredging and Restoration

Woodglen Lake: Shoreline Restoration

Woodglen Lake Existing Conditions

Page 24: Woodglen Lake Dredging and Restoration

Shoreline Protection Options

Page 25: Woodglen Lake Dredging and Restoration

Fish Habitat Structures

Page 26: Woodglen Lake Dredging and Restoration

Stream Stabilization

Page 27: Woodglen Lake Dredging and Restoration

Woodglen Lake: Site Access & Staging

Page 28: Woodglen Lake Dredging and Restoration

Access During Construction

Lake Barton

Page 29: Woodglen Lake Dredging and Restoration

Huntsman Lake

2011

Available Exclusively by DigitalGlobe

©2013 Microsoft Corporation © 2012 Nokia

Woodglen Lake

Page 30: Woodglen Lake Dredging and Restoration

Woodglen Lake Dredging and Restoration Project Timeline and Coordination

Community coordination at Design and Construction phase

June 2013: Final Design

July 2013: Construction bid advertisement

September/October 2013: Begin dredging

Project duration: 6 - 7 months

Lake may be drained for entire project (dredging method depends on project bidding) Partial lake drawdown alternative to be evaluated

Page 31: Woodglen Lake Dredging and Restoration

Woodglen Lake Dredging and Restoration

Contacts

Dipmani Kumar, Project Manager 703-324-4612

[email protected]

Matt Meyers, Branch Chief 703-324-5651

[email protected]

Partners: