white paper changes to the pmbok 4th edition
TRANSCRIPT
Page 1 of 23
www.GoBeyond20.com
White Paper on
A Project Manager’s Perspective on Changes to the Guide to the Project Management
Body of Knowledge (PMBOK® Guide) Fourth Edition
Erika Flora, MS, PMP, ITIL Expert
Principal Consultant, Beyond20
I. INTRODUCTION
On December 31, 2008, the Project Management Institute (PMI®) released the 4th
edition of the
PMBOK® Guide, the foundational book used to study and prepare for the Project Management
Professional (PMP) exam. On July 1, 2009 the exam changed over to the 4th
edition, and project
management professionals world-wide now use this new edition to prepare for the PMP exam. So,
what has changed? The good news is that many of the core concepts and order of project activities
performed are the same as in the 3rd
edition. If you took and passed the 3rd
edition exam, what
you have learned is still valid. If you have studied the 3rd
edition material, but have not yet taken
the exam, you will, unfortunately, have a lot of process Inputs, Outputs, Tools & Techniques to re-
learn and memorize.
Overall, the refresh of the new text mainly consolidates and clarifies previously confusing concepts
and includes additional concepts that today’s Project Manager deals with. This white paper
outlines these changes, in chronological fashion and in line with how projects are actually being
performed (i.e. in order of each of the five process groups - Initiating, Planning, Executing,
Monitoring and Controlling, and Closing). Thus, it takes a slightly different slant from other white
papers on the subject. For a list of changes according to each of the nine Knowledge Areas, see the
Preface to and Appendix A of the Fourth Edition in the PMBOK® Guide (pages XXII-XXIII and 349-
357).
II. OVERVIEW OF CHANGES
General
The two prevailing themes with the PMBOK® Guide 4th
edition changes are that of “clarity” and
“consistency”. In teaching 3rd
edition classes, students in every class always had some confusion
around conflicting definitions and have lots of questions around why some documents are
mentioned and why others weren’t as an Process Inputs, Outputs, Tools or Techniques. The 4th
edition seems to do a good job of addressing and alleviating these types of issues.
Project Management Processes
First, there are now 42 processes detailed in the fourth edition of the PMBOK® Guide, as compared
to 44 processes in the 3rd
edition. Two new processes have been added, two have been removed,
and four other processes have been combined into two, specifically within Project Procurement
Management, as detailed below:
Page 2 of 23
www.GoBeyond20.com
New Removed Consolidated
• Identify Stakeholders
• Collect Requirements
• Develop Preliminary
Scope Statement
• Scope Planning
• Plan Purchases and Acquisitions and
Plan Contracting > Plan Procurements
• Request Seller Responses and Select
Sellers > Conduct Procurements
A few other processes have changed process groups, for example, “Manage Project Team” is now
an Executing process; and “Manage Stakeholders” is now a Monitoring and Controlling process.
Also, to improve readability and consistency throughout, all 42 processes are now in verb-noun
format. For example, “Scope Definition” has been renamed as “Define Scope”. Since Project
Managers are performing these activities within their projects, it makes sense that the processes
would be written this way. For those of us used to the process names as they are written in the 3rd
edition, it takes a little practice to get the names straight in the 4th
edition. However, long term,
this is a much more intuitive way to refer to the processes we perform.
Portfolio, Program, and Project Management
In chapter 1 of the PMBOK® Guide 4th
edition, there is additional information on the differences
between managing a Portfolio, Program, and Project as many project managers are now finding
themselves managing programs and even portfolios; and it is important to understand and be able
to communicate the differences between them. I find this is a common question from team
members and other non-Project Managers in many organizations.
Enterprise Environmental Factors and Organizational Process Assets
Further, there is a clearer differentiation between Enterprise Environmental Factors (EEFs) and
Organizational Process Assets (OPAs). These are detailed in the table below. Also, EEFs and OPAs
serve as inputs (and outputs) to more processes in the 4th
edition and closer line up with real life.
Enterprise Environmental Factors Organizational Process Assets
• Any or all external environmental factors
and internal organizational environmental
factors that surround or influence the
project’s success. These factors are from
any or all of the enterprises involved in the
project, and include organizational culture
and structure, infrastructure, existing
resources, commercial databases, market
conditions, and project management
software.
• Any or all process related assets, from
any or all of the organizations involved in
the project that are or can be used to
influence the project’s success. These
process assets include formal and
informal plans, policies, procedures, and
guidelines. The process assets also
include the organizations’ knowledge
bases such as lessons learned and
historical information.
Project Initiation and Planning documents
There have been some changes involving the Project Management Plan, Project Charter, and
Project Scope Statement. Namely, the Project Management Plan and its subsidiary plans have
Page 3 of 23
www.GoBeyond20.com
been more clearly defined and separated out. There has also been a clearer distinction between
plans and other Project documents (see page 350 in the PMBOK® Guide for a list of these items). In
addition, there is a clearer distinction between the components of the Project Charter and the
Project Scope Statement (the Preliminary Project Scope Statement has gone away). The
differences are detailed on page 351 of the PMBOK® Guide 4th
edition.
Requested Changes, Corrective and Preventive Actions (CAPA), and Defect Repairs
Whereas, these items were separated in the 3rd
edition, these have all been consolidated under the
heading of “Change Requests”. Rather, the PMBOK® Guide defines different types of requests.
Process Flow Diagrams
The old Process Flow Diagrams have been replaced by Data Flow Diagrams in this edition. At first
glance, they look complex and a bit scary, but they actually contain a lot of helpful information. I
highly recommend taking a look at them at the beginning of each chapter.
Interpersonal and Other Skills
In Chapter 1 of the PMBOK® Guide, the characteristics needed by a Project Manager have been
pared down and clarified from five to three as follows: Knowledge (of project management),
Performance (the PM is able to accomplish what they set out to do in a project), and Personal
(leadership, etc.). Also, more information has been added to the PMBOK® Guide in Appendix G on
the interpersonal and other soft skills needed and carried out by Project Managers. The 3rd
edition
did not contain a lot of information on topics like leadership, persuasion, communication, etc.
Thankfully, the 4th
edition expands on these “soft” skills regularly employed by Project Managers.
Additional new and expanded concepts are also detailed throughout this white paper, in the
appropriate section below.
III. INITIATING PROCESS GROUP
This is the stage of a project where a Project Manager is assigned, and the PM is responsible for
obtaining approval for the project and determining who needs to be involved. In the 4th
edition,
the process entitled “Develop Preliminary Project Scope Statement” is removed. Previously,
understanding the difference between this document and the Project Charter was somewhat
confusing. As a result, the authors have done away with the Preliminary Scope Statement. In
addition, they have added the process “Identify Stakeholders”. This activity was implied in the 3rd
edition and is now officially called out. Changes to the specific process are detailed below.
Project Integration Management
� Develop Project Charter
This process has changed somewhat. The concept of a “Business Case” is a new input, and
the Tools and Techniques have been pared down to only include “Expert Judgment”. Below
is the process as it appears in the 4th
edition.
Inputs Tools & Techniques Outputs
Page 4 of 23
www.GoBeyond20.com
1. Project statement of work
2. Business case
3. Enterprise environmental
factors
4. Organizational process assets
1. Expert judgment 1. Project charter
Figure 4-2: Develop Project Charter: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Communications Management
� Identify Project Stakeholders
This is a new process in the 4th
edition and is pictured below. I really like that this has been
added as its own process because this is a significant activity early on and can avoid
significant headaches later on in the project. Two deliverables worth noting are the
“Stakeholder register” and “Stakeholder management strategy”. The Stakeholder Register
is similar in nature to the Risk Register and details, for example, the names of project
stakeholders, their interests, influence, communications strategy, and documents they
should receive. This is kind of a cool addition to the PMBOK® Guide.
Inputs Tools & Techniques Outputs
1. Project charter
2. Procurement documents
3. Enterprise environmental
factors
4. Organizational process assets
1. Stakeholder analysis
2. Expert judgment
1. Stakeholder register
2. Stakeholder
management
strategy
Figure 10-2: Identify Stakeholders: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
III. PLANNING PROCESS GROUP
One the project is approved, the Project Manager can now begin planning project details. In this
process group, most of the processes have remained the same. Typically only the name has
changed. The two Procurement processes have been combined into a single process and refined to
give clarity around these activities. Details on the specific planning processes are detailed below.
Project Integration Management
� Develop Project Management Plan
The Inputs and Tools & Techniques have been updated and simplified to include the
elements below. Extraneous information like the Project Management Information System
(PMIS) and PM Methodology has been removed from this process.
Inputs Tools & Techniques Outputs
Page 5 of 23
www.GoBeyond20.com
1. Project charter
2. Outputs from planning
processes
3. Enterprise environmental
factors
4. Organizational process assets
1. Expert judgment 1. Project
management plan
Figure 4-4: Develop Project Management Plan: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Scope Management
� Collect Requirements
The name of this process was changed from “Scope Planning” in the 3rd
edition to better
align with verb-noun format. In the 4th
edition, the Inputs have been simplified; however,
there are a number of new Tools & Techniques and Outputs introduced that are worth
investigating further (see below).
Inputs Tools & Techniques Outputs
1. Project charter
2. Stakeholder register
1. Interviews
2. Focus groups
3. Facilitated workshops
4. Group creativity
techniques
5. Group decision
making techniques
6. Questionnaires and
surveys
7. Observations
8. Prototypes
1. Requirements
documentation
2. Requirements
management plan
3. Requirements
traceability matrix
Figure 5-2: Collect Requirements: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Define Scope
The name of this process has also been updated, from “Scope Definition”. In this process,
the Inputs, Outputs, Tools & Techniques have changed somewhat.
Inputs Tools & Techniques Outputs
1. Project charter
2. Requirements documentation
3. Organizational process assets
1. Expert judgment
2. Product analysis
3. Alternatives
identification
4. Facilitated workshops
1. Project scope
statement
2. Project document
updates
Figure 5-4: Define Scope: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Page 6 of 23
www.GoBeyond20.com
� Create WBS
This process has also been pared down and simplified in the 4th
edition (see below).
Inputs Tools & Techniques Outputs
1. Project scope statement
2. Requirements documentation
3. Organizational process assets
1. Decomposition 1. WBS
2. WBS dictionary
3. Scope baseline
4. Project document
templates Figure 5-6: Create WBS: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Time Management
� Define Activities
The name of this process has been updated from “Activity Definition” in the 3rd
edition. The
Inputs, Tools & Techniques, and Outputs for this process have been pared down and
simplified in the 4th edition as shown below.
Inputs Tools & Techniques Outputs
1. Scope baseline
2. Enterprise environmental
factors
3. Organizational process assets
1. Decomposition
2. Rolling wave planning
3. Templates
4. Expert judgment
1. Activity list
2. Activity attributes
3. Milestone list
Figure 6-3: Define Activities: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Sequence Activities
This process was called “Activity Sequencing” in the 3rd
edition. In this process, the Inputs,
Outputs, Tools & Techniques have changed somewhat as shown below. The Arrow
Diagramming Method (ADM) has gone away as a Tool & Technique. With the advent of
tools like Microsoft® Project, ADM is hardly ever used in real life, so I was glad to see it go.
In addition, the Inputs and Outputs for this process have been simplified.
Inputs Tools & Techniques Outputs
1. Activity list
2. Activity attributes
3. Milestone list
4. Project scope statement
5. Organizational process
assets
1. Precedence diagramming
method (PDM)
2. Dependency
determination
3. Applying leads and lags
4. Schedule network
templates
1. Project schedule
network diagrams
2. Project document
activities
Figure 6-5: Sequence Activities: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
Page 7 of 23
www.GoBeyond20.com
©2008 Project Management Institute, Inc. All Rights Reserved.
� Estimate Activity Resources
This process has been updated to be in verb-noun format, from “Activity Resource
Estimating” in the 3rd
edition. Some of the Inputs for this process have also changed. For
example, Resource Calendars has taken the place of “Resource availability”, and Project
Management Plan has been removed as an Input. The Outputs have also been simplified
(from five outputs to three).
Inputs Tools & Techniques Outputs
1. Activity list
2. Activity attributes
3. Resource calendars
4. Enterprise environmental
factors
5. Organizational process
assets
1. Expert judgment
2. Alternatives analysis
3. Published estimating
data
4. Bottom-up estimating
5. Project management
software
1. Activity resource
requirements
2. Resource
breakdown
structure
3. Project document
updates Figure 6-8: Estimate Activity Resources: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Estimate Activity Durations
This process was called “Activity Duration Estimating” in the 3rd
edition. The Inputs and
Outputs of this process have changed slightly with the 4th edition. The “Project
Management Plan” is no longer an Input; and the Output “Activity attributes (updates)” is
now called “Project document updates”.
Inputs Tools & Techniques Outputs
1. Activity list
2. Activity attributes
3. Activity resource
requirements
4. Resource calendars
5. Project scope statement
6. Enterprise environmental
factors
7. Organizational process
assets
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Three-point estimates
5. Reserve analysis
1. Activity duration
estimates
2. Project document
updates
Figure 6-10: Estimate Activity Durations: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Develop Schedule
This process name has been updated from “Schedule Development” in the 3rd
edition.
Further, under Inputs, “Enterprise Environmental Factors” has been added, and the “Project
Management Plan” has been removed. In Tools & Techniques, “Project Management
Page 8 of 23
www.GoBeyond20.com
Software” has been renamed as a “Scheduling Tool”, and “Adjusting Leads and Lags” is now
called “Applying leads and lags”. Under Tools & Techniques, the “Scheduling Model” and
“Applying Calendars” have been removed. The Outputs have been significantly pared down
(from eight outputs to four) as shown below. As with the 3rd
edition, this remains as one of
the longer processes with a number of process elements contained within.
Inputs Tools & Techniques Outputs
1. Activity list
2. Activity attributes
3. Project schedule network
diagrams
4. Activity resource
requirements
5. Resource calendars
6. Activity duration estimates
7. Project scope statement
8. Enterprise environmental
factors
9. Organizational process
assets
1. Schedule network
analysis
2. Critical path method
3. Critical chain method
4. Resource leveling
5. What-if scenario analysis
6. Applying leads and lags
7. Schedule compression
8. Scheduling tools
1. Project schedule
2. Schedule baselines
3. Schedule data
4. Project document
updates
Figure 6-12: Develop Schedule: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Cost Management
� Estimate Costs
The name of this process used to be “Cost Estimating” in the 3rd
edition. With the 4th
edition, the Inputs of this process have significantly changed. With the exception of EEFs
and OPAs, all Inputs are new. The Tools & Techniques have changed somewhat. “Expert
judgment” and “Three-point estimates” are new. “Project Management software” has
changed to “Project management estimating software”, and “Determine resource cost
rates” has gone away. Outputs have been simplified (from four outputs to three). In the
3rd edition, the three deliverables - Project scope statement, WBS, and WBS dictionary -
were all called out as separate Inputs to this process. In the 4th edition, however, these
have been consolidated into a single “Scope baseline” Input.
Inputs Tools & Techniques Outputs
1. Scope baseline
2. Project schedule
3. Human resource plan
4. Risk register
5. Enterprise environmental
factors
6. Organizational process
1. Expert judgment
2. Analogous estimating
3. Parametric estimating
4. Bottom-up estimating
5. Three-point estimates
6. Reserve analysis
7. Cost of quality
1. Activity cost
estimates
2. Basis of estimates
3. Project document
updates
Page 9 of 23
www.GoBeyond20.com
assets
8. Project management
estimating software
9. Vendor bid analysis Figure 7-2: Estimate Costs: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Determine Budget
The name of this process was “Cost Budgeting” and is now “Determine Budget”. For the
Inputs, “Project scope statement”, “WBS”, and “WBS dictionary” have been consolidated
into a single Input, the “Scope baseline”. The “Cost management plan” has been removed,
and a few Inputs were renamed slightly. Organizational Process Assets (OPAs) were added.
In Tools & Techniques, “Parametric estimating” has been removed, and “Expert judgment”
& “Historical relationships” has been added. Last, the Outputs have been simplified (from
four outputs to three).
Inputs Tools & Techniques Outputs
1. Activity cost estimates
2. Basis of estimates
3. Scope baseline
4. Project schedule
5. Resource calendars
6. Contracts
7. Organizational process
assets
1. Cost aggregation
2. Reserve analysis
3. Expert judgment
4. Historical relationships
5. Funding limit
reconciliation
1. Cost performance
baseline
2. Project funding
requirements
3. Project document
updates
Figure 7-4: Determine Budget: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Quality Management
� Plan Quality
The “Quality Planning” process has been renamed “Plan Quality” in the 4th
edition. Also,
there are now four Cost of Quality types as “Failure Costs” has been divided into “Internal
Failure Costs” and “External Failure Costs”. In the process Inputs, Only “Enterprise
environmental factors” and “Organizational process assets” are the same. All other Inputs
are new for this process. In Tools & Techniques, many of these T&Ts are new (five elements
have increased to nine). Whereas, the Outputs have been simplified (six outputs have been
reduced to five).
Inputs Tools & Techniques Outputs
1. Scope baseline
2. Stakeholder register
3. Cost performance baseline
4. Schedule baseline
1. Cost benefit analysis
2. Cost of quality
3. Control charts
4. Benchmarking
1. Quality
management plan
2. Quality metrics
3. Quality checklists
Page 10 of 23
www.GoBeyond20.com
5. Risk register
6. Enterprise environmental
factors
7. Organizational process
assets
5. Design of experiments
6. Statistical sampling
7. Flowcharting
8. Proprietary quality
management
methodologies
9. Additional quality
planning tools
4. Process
improvement plan
5. Project document
updates
Figure 8-2: Plan Quality: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Human Resource Management
� Develop Human Resource Plan
This process was previously called “Human Resource Planning” in the 3rd
edition. Within
this process, “Roles and responsibilities”, “Project organization charts”, and “Staffing
management plans” were all listed as outputs in the 3rd
edition. These, however, have been
consolidated into the “Human resource plan” in the 4th
edition. Outside of the process, the
number of project interfaces contained in the PMOBOK Guide® increased from three to five
to include: Organizational, Technical, Interpersonal, Logistical (new), and Political (new).
Inputs Tools & Techniques Outputs
1. Activity resource
requirements
2. Enterprise environmental
factors
3. Organizational process
assets
1. Organization charts and
position descriptions
2. Networking
3. Organizational theory
1. Human resource
plan
Figure 9-2. Develop Human Resource Plan: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Communications Management
� Plan Communications
This process has been renamed from “Communications Planning” and has been slightly
expanded in the 4th
edition. “Stakeholder register” and “Stakeholder management
strategy” are new Inputs. Whereas, “Project scope statement” and “Project Management
plan” have been removed as Inputs. “Communication models” and “Communication
methods” are new Tools & Techniques; and “Project document updates” is a new Output.
Inputs Tools & Techniques Outputs
1. Stakeholder register
2. Stakeholder management
strategy
3. Enterprise environmental
1. Communication
requirements analysis
2. Communication
technology
1. Communications
management plan
2. Project document
updates
Page 11 of 23
www.GoBeyond20.com
factors
4. Organizational process
assets
3. Communication models
4. Communication methods
Figure 10-6. Plan Communications: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Risk Management
� Plan Risk Management
This process was changed from “Risk Management Planning”. Other than the name change,
only the Inputs of this process have changed. The “Project Management plan” was
removed; and the Inputs “Cost management plan”, “Schedule management plan”, and
“Communications management plan” have been added as pictured below.
Inputs Tools & Techniques Outputs
1. Project scope statement
2. Cost management plan
3. Schedule management plan
4. Communications
management plan
5. Enterprise environmental
factors
6. Organizational process
assets
1. Planning meetings and
analysis
1. Risk management
plan
Figure 11-2. Plan Risk Management: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Identify Risks
This process was previously called “Risk Identification” in the 3rd
edition. In this revised
process, there are significantly more Inputs and Tools & Techniques. As a result, this has
become a large process with numerous elements.
Inputs Tools & Techniques Outputs
1. Risk management plan
2. Activity cost estimates
3. Activity duration estimates
4. Scope baseline
5. Stakeholder register
6. Cost management plan
7. Schedule management plan
8. Quality management plan
9. Project documents
10. Enterprise environmental
factors
1. Documentation reviews
2. Information gathering
techniques
3. Checklist analysis
4. Assumptions analysis
5. Diagramming techniques
6. SWOT analysis
7. Expert judgment
1. Risk resister
Page 12 of 23
www.GoBeyond20.com
11. Organizational process
assets Figure 11-6. Identify Risks: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Perform Qualitative Risk Analysis
The only thing different about this process is the new name (previously named the “Quality
Risk Analysis” process) and the addition of “Expert judgment” as a Tool & Technique.
Inputs Tools & Techniques Outputs
1. Risk register
2. Risk management plan
3. Project scope statement
4. Organizational process
assets
1. Risk probability and
impact assessment
2. Probability and impact
matrix
3. Risk data quality
assessment
4. Risk categorization
5. Risk urgency assessment
6. Expert judgment
1. Risk register updates
Figure 11-8. Perform Qualitative Risk Analysis: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Perform Quantitative Risk Analysis
In this process, the name (previously called “Quantitative Risk Analysis”) and Inputs have
changed slightly. The Inputs “Project scope statement” and “Project Management plan”
have been removed; and additional plan documents, namely “Cost management plan” and
“Schedule management plan” have been added as new Inputs. Also, there are now two
Tools & Techniques listed under “Data gathering and representation techniques” (versus
three in the 3rd edition), and “Expert judgment” has been added as a separate Tool &
Technique. The “Decision tree analysis” has also been removed as a Tool & Technique.
Inputs Tools & Techniques Outputs
1. Risk register
2. Risk management plan
3. Cost management plan
4. Schedule management plan
5. Organizational process
assets
1. Data gathering and
representation
techniques
2. Quantitative risk analysis
and modeling techniques
3. Expert judgment
1. Risk register updates
Figure 11-11. Perform Quantitative Risk Analysis: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Plan Risk Responses
Page 13 of 23
www.GoBeyond20.com
The name of this process has changed from “Risk Response Planning”. In addition, the Tool
& Technique “Strategy for both threats & opportunities” has been removed. “Expert
judgment” has been added as a Tool & Techniques. Last, “Project document updates” has
been added as a new process Output as pictured below.
Inputs Tools & Techniques Outputs
1. Risk register
2. Risk management plan
1. Strategies for negative
risks or threats
2. Strategies for positive
risks or opportunities
3. Contingent response
strategies
4. Expert judgment
1. Risk register updates
2. Risk-related contract
decisions
3. Project
management plan
updates
4. Project document
updates Figure 11-17. Plan Risk Responses: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
In addition to the process changes, Acceptance has been added a new positive risk
response. In the PMBOK® Guide 3rd
edition, Acceptance was only seen as a negative
response.
Project Procurement Management
� Plan Procurements
This process has been consolidated from two processes (“Plan Purchases and Acquisitions”
and “Plan Contracting”). Thus, this has become a very detailed and robust Project
Management process. Also, the term Contract SOW has changed to Procurement SOW in
4th
edition. “Evaluation Criteria” has been renamed “Source Selection Criteria” and
additional detail has been included around the different criteria.
Inputs Tools & Techniques Outputs
1. Scope baseline
2. Requirements
documentation
3. Teaming agreements
4. Risk register
5. Risk-related contract
decisions
6. Activity resource
requirements
7. Project schedule
8. Activity cost estimates
9. Cost performance baseline
10. Enterprise environmental
1. Make-or-buy analysis
2. Expert judgment
3. Contract types
1. Procurement
management plan
2. Procurement
statements of work
3. Make-or-buy
decisions
4. Procurement
documents
5. Source selection
criteria
6. Change requests
Page 14 of 23
www.GoBeyond20.com
factors
11. Organizational process
assets Figure 12-2. Plan Procurements: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
IV. EXECUTING PROCESS GROUP
Once all planning activities have been completed, the project is kicked off and enters the Execution
phase. Many of the process in this process group have changed to verb-noun format, and two
processes have moved to this process group from the Monitoring and Controlling process group.
Detailed changes to the specific processes during project execution are detailed below.
Project Integration Management
� Direct and Management Project Execution
The Inputs of this process have been pared down from the 3rd
edition (from seven Inputs to
four. Preventive & Corrective Actions and Defect repairs have been consolidated into
“Change Requests”); and EEFs and OPAs have been added as Inputs. Under Tools &
Techniques, “PM methodology” has been replaced by “Expert judgment”. The process
Outputs have also been pared down from seven to five as detailed below.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Approved change requests
3. Enterprise environmental
factors
4. Organizational process
assets
1. Expert judgment
2. Project management
information system
1. Deliverables
2. Work performance
information
3. Change requests
4. Project
management plan
updates
5. Project document
updates Figure 4-6. Direct and Manage Project Execution: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Quality Management
� Perform Quality Assurance
The Inputs, Outputs, Tools & Techniques in this process have been pared down significantly
(particularly the Inputs) in the 4th
edition.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Quality metrics
3. Work performance
information
1. Plan Quality and Perform
Quality Control tools and
techniques
2. Quality audits
1. Organizational
process assets
updates
2. Change requests
Page 15 of 23
www.GoBeyond20.com
4. Quality control
measurements
3. Process analysis 3. Project
management plan
updates
4. Project document
updates Figure 8-8. Perform Quality Assurance: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Human Resource Management
� Acquire Project Team
In this process, the Inputs have been consolidated to include only EEFs, OPAs, and the
Project Management Plan. Under Outputs, “Staffing management plan (updates)” has been
renamed “Project management plan updates”.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Enterprise environmental
factors
3. Organizational process
assets
1. Pre-assignment
2. Negotiation
3. Acquisition
4. Virtual teams
1. Project staff
assignments
2. Resource calendars
3. Project
management plan
updates Figure 9-7. Acquire Project Team: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Develop Project Team
Within this process, the input “Resource Availability” was renamed as “Resource calendars”.
In the Tools & Techniques, “General management skills” was renamed “Interpersonal skills”.
Last, “Enterprise environmental factors” has been added as a process Output.
Inputs Tools & Techniques Outputs
1. Project staff assignments
2. Project management plan
3. Resource calendars
1. Interpersonal skills
2. Training
3. Team-building activities
4. Ground rules
5. Co-location
6. Recognition and rewards
1. Team performance
assessments
2. Enterprise
environmental
factors updates
Figure 9-9. Develop Project Team: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
In addition, the stages of team development have been expanded in the PMBOK® Guide as
follows: Forming, Storming, Norming, Performing, and Adjourning (new).
� Manage Project Team
Page 16 of 23
www.GoBeyond20.com
I like that this process has been moved from the Monitoring and Controlling process group
into Executing. The PMBOK® Guide states that it did this because, “the activities are now
more proactive to ensure project performance if optimized”. Further the process Inputs
have been pared down from nine to five, which make it easier to digest and remember.
Under Tools & Techniques, “Interpersonal skills” has been added. In Outputs, “Enterprise
environmental factors updates” has been added; and “Change requests” has replaced
Corrective Action and Preventive Actions (CAPA).
Inputs Tools & Techniques Outputs
1. Project staff assignments
2. Project management plan
3. Team performance
assessments
4. Performance reports
5. Organizational process
assets
1. Observation and
conversation
2. Project performance
appraisals
3. Conflict management
4. Issue log
5. Interpersonal skills
1. Enterprise
environmental
factors
2. Organizational
process assets
3. Change requests
4. Project
management plan
updates Figure 9-11. Manage Project Team: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Communications Management
� Distribute Project Information
This process has been renamed from “Information Distribution” in the 3rd
edition. Further,
all of the Inputs for this process are new. The Tools & Techniques have been pared down,
from four to two; and the only Output remaining is “Organizational process assets updates”.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Performance reports
3. Organizational process
assets
1. Communication methods
2. Information distribution
tools
1. Organizational
process assets
updates
Figure 10-9. Distribute Information: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Manage Stakeholder Expectations
This process was also renamed (from “Manage Stakeholders”) and moved from the
Monitoring and Controlling process group into Executing. The PMBOK® Guide states that
this change was made to reflect that, “the activities are now more about doing than
recording/reporting”. In this process, the Inputs have been expanded from two to five to
include: Stakeholder register, Stakeholder management strategy, PM plan (which contains
the Communications plan), Issue log (moved from T&T), and the Change log. In Tools &
Page 17 of 23
www.GoBeyond20.com
Techniques, Interpersonal and Management skills were added. There are also a few small
changes in the Outputs section.
Inputs Tools & Techniques Outputs
1. Stakeholder register
2. Stakeholder management
strategy
3. Project management plan
4. Issue log
5. Change log
6. Organizational process
assets
1. Communication methods
2. Interpersonal skills
3. Management skills
1. Organizational
process assets
updates
2. Change requests
3. Project management
plan updates
4. Project document
updates Figure 10-11. Manage Stakeholder Expectations: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Procurement Management
� Conduct Procurements
This process has been consolidated from two 3rd
edition processes, namely “Request Seller
Responses” and “Select Sellers”. It combines numerous elements from these two processes
and is, as a result, one of the longer processes in the 4th
edition (as pictured below).
Inputs Tools & Techniques Outputs
1. Project management plan
2. Procurement documents
3. Source selection criteria
4. Qualified seller list
5. Seller proposals
6. Project documents
7. Make-or-buy decisions
8. Teaming agreements
9. Organizational process
assets
1. Bidder conferences
2. Proposal evaluation
techniques
3. Independent estimates
4. Expert judgment
5. Advertising
6. Internet search
7. Procurement
negotiations
1. Selected sellers
2. Procurement
contract award
3. Resource calendars
4. Change requests
5. Project
management plan
updates
6. Project document
updates Figure 12-4. Conduct Procurements: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
V. MONITORING AND CONTROLLING PROCESS GROUP
In the Monitoring and Controlling process group, about half of the processes have been renamed in
verb-noun format. Also, two processes that were in this group in the PMBOK® Guide 3rd
edition
have been moved to the Execution process group in the 4th
edition.
Project Integration Management
� Monitor and Control Project Work
There have been significant wording changes to this process.
Page 18 of 23
www.GoBeyond20.com
Inputs Tools & Techniques Outputs
1. Project management plan
2. Performance reports
3. Enterprise environmental
factors
4. Organizational process
assets
1. Expert judgment 1. Change requests
2. Project
management plan
updates
3. Project document
updates Figure 4-8. Monitor and Control Project Work: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
� Perform Integrated Change Control
This process has been renamed (from “Integrated Change Control) and has been
significantly pared down as an overall process in the 4th
edition. In Tools & Techniques,
“Change control meetings” is a new element.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Work performance
information
3. Change requests
4. Enterprise environmental
factors
5. Organizational process
assets
1. Expert judgment
2. Change control meetings
1. Change request
status updates
2. Project
management plan
updates
3. Project document
updates
Figure 4-10. Perform Integrated Change Control: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Scope Management
� Verify Scope
This process was previously named “Scope Verification” in the 3rd
edition. In addition, some
of the Inputs and Outputs for this process have been renamed and/or changed.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Requirements
documentation
3. Requirements traceability
matrix
4. Validated deliverables
1. Inspection 1. Accepted
deliverables
2. Change requests
3. Project document
updates
Figure 5-11. Verify Scope: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Page 19 of 23
www.GoBeyond20.com
� Control Scope
The “Control Scope” process has been renamed (from “Scope Control”) and has also been
pared down (for example, numerous Inputs were consolidated under the “Project
Management plan”).
Inputs Tools & Techniques Outputs
1. Project management plan
2. Work performance
information
3. Requirements
documentation
4. Requirements traceability
matrix
5. Organizational process
assets
1. Variance analysis 1. Work performance
measurements
2. Organizational process
assets updates
3. Change requests
4. Project management
plan updates
5. Project document
updates Figure 5-13. Control Scope: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Time Management
� Control Schedule
The “Control Schedule” process has been renamed (from “Schedule Control”). In addition,
The Inputs, Outputs, and Tools & Techniques have slightly changed in the 4th
edition. In
particular, in Tools & Techniques, there are a number of new elements, i.e.: Resource
leveling, What-if scenario analysis, Adjusting leads and lags, and Schedule compression.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Project schedule
3. Work performance
information
4. Organizational process
assets
1. Performance reviews
2. Variance analysis
3. Project management
software
4. Resource leveling
5. What-if scenario
analysis
6. Adjusting leads and lags
7. Schedule compression
8. Scheduling tool
1. Work performance
measurements
2. Organizational
process assets
updates
3. Change requests
4. Project management
plan updates
5. Project document
updates Figure 6-15. Control Schedule: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Cost Management
� Control Costs
“Control Costs” used to be called “Cost Control” in the 3rd
edition. There are some
additional changes to the “Control Costs” process itself as well with the 4th
edition. For
Page 20 of 23
www.GoBeyond20.com
example, in Tools & Techniques, “Performance measurement analysis” has been renamed
“Earned value management”; and “To-complete performance index” is introduced as a new
Tool & Technique (and includes, for example, BAC and EAC).
Inputs Tools & Techniques Outputs
1. Project management plan
2. Project funding
requirements
3. Work performance
information
4. Organizational process
assets
1. Earned value
management
2. Forecasting
3. To-complete
performance index
4. Performance reviews
5. Variance analysis
6. Project management
software
1. Work performance
measurements
2. Budget forecasts
3. Organizational process
assets updates
4. Change requests
5. Project management
plan updates
6. Project document
updates Figure 7-7. Control Costs: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Quality Management
� Perform Quality Control
There are some small wording changes in this process with the 4th
edition. Note: This is one
of the larger, more complex processes contained in the PMBOK® Guide.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Quality metrics
3. Quality checklists
4. Work performance
measurements
5. Approved change requests
6. Deliverables
7. Organizational process
assets
1. Cause and effect
diagrams
2. Control charts
3. Flowcharting
4. Histogram
5. Pareto chart
6. Run chart
7. Scatter diagram
8. Statistical sampling
9. Inspection
10. Approved change
requests review
1. Quality control
measurements
2. Validated changes
3. Validated deliverables
4. Organizational
process assets
updates
5. Change requests
6. Project management
plan updates
7. Project document
updates Figure 8-10. Perform Quality Control: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Communications Management
� Report Performance
Page 21 of 23
www.GoBeyond20.com
This process has been renamed (was previously “Performance Reporting” in the 3rd
edition)
and its elements have been pared down in the 4th edition (as shown below). In addition,
the Tools & Techniques terminology is, for the most part, new.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Work performance
information
3. Work performance
measurements
4. Budget forecasts
5. Organizational process
assets
1. Variance analysis
2. Forecasting methods
3. Communication methods
4. Reporting systems
1. Performance reports
2. Organizational
process assets
updates
3. Change requests
Figure 10-13. Report Performance: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Risk Management
� Monitor and Control Risks
This process used to be named “Risk Monitoring and Control” and has been updated to the
verb-noun format in the 4th
edition. The process elements are pretty much the same as
they appear in the 3rd
edition, with some small wording changes.
Inputs Tools & Techniques Outputs
1. Risk register
2. Project management plan
3. Work performance
information
4. Performance reports
1. Risk reassessment
2. Risk audits
3. Variance and trend
analysis
4. Technical performance
measurement
5. Reserve analysis
6. Status meetings
1. Risk register updates
2. Organizational
process assets
updates
3. Change requests
4. Project management
plan updates
5. Project document
updates Figure 11-19. Monitor and Control Risks: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Procurement Management
� Administer Procurements
This process was renamed from “Contract Administration” in the 3rd
edition. Wording of
process elements, however, is very similar to the 3rd
edition. There have been only some
minor changes made.
Inputs Tools & Techniques Outputs
1. Procurement documents 1. Contract change control 1. Procurement
Page 22 of 23
www.GoBeyond20.com
2. Project management plan
3. Contract
4. Performance reports
5. Approved change requests
6. Work performance
information
system
2. Procurement
performance reviews
3. Inspections and audits
4. Performance reporting
5. Payment systems
6. Claims administration
7. Records management
system
documentation
2. Organizational
process assets
updates
3. Change requests
4. Project
management plan
updates
Figure 12-6. Administer Procurements: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
VI. CLOSING PROCESS GROUP
As seen with the 3rd
edition, there are two processes contained within the Closing process group.
The wording of both processes has been revised. Process specific changes are detailed below.
Project Integration Management
� Close Project or Phase
This process was renamed from “Close Project” in the 3rd
edition.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Accepted deliverables
3. Organizational process
assets
1. Expert judgment 1. Final product, service,
or result transition
2. Organizational process
assets updates Figure 4-12. Close Project or Phase: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
Project Procurement Management
Close Procurements
This process used to be called “Contract Closure” in the 3rd
edition and has been updated to
follow the verb-noun format.
Inputs Tools & Techniques Outputs
1. Project management plan
2. Procurement
documentation
1. Procurement audits
2. Negotiated settlements
3. Records management
system
1. Closed procurements
2. Organizational
process assets
updates Figure 12-8. Close Procurements: Inputs, Tools & Techniques, and Outputs
A Guide to the Project Management Body of Knowledge-Fourth Edition (PMBOK® Guide).
©2008 Project Management Institute, Inc. All Rights Reserved.
VII. CONCLUSION
Page 23 of 23
www.GoBeyond20.com
Insert text here.
VIII. REFERENCES
A Guide to the Project Management Body of Knowledge (PMBOK® Guide) Fourth Edition. The
Project Management Institute, Inc. 2008.