Watermael-Schuman-Josaphat railway tunnel Working visit Members of European Parliament
The Watermael-Schuman-Josaphat project: snapshot
• Direct link between the European Quarter of Brussels and Brussels Airport
• From Ottignies to Brussels-Schuman the line will be expanded to four tracks
• Develop the network in order to facilitate mobility in Belgium • More specifically, connect the economic hub of the Brussels European
District to most major Belgian cities (Mechelen/Hasselt and Leuven/Liège), without passing through the North-South junction, which is currently close to saturation
• Placing into service scheduled for the end of 2015 • Investment of around 600 Mio euro • Progress towards target: 90% completion
What?
Why?
Facts & figures
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 2
Progressively improve the capacity of the Belgian railway infrastructure Increase the safety, punctuality and capacity of our railway network to the benefit of our customers
Improve step-by-step the railway access to Brussels & its Airport; and make it a key example of intermodality ('Air Rail')
Support the development of the Belgian economy and the airport companies
Directly connect the Brussels European Quarter to the airport and to other main stations of Brussels & its hinterland
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 4
Both a clearly international project … Improved rail access to Brussels Airport & European cities
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 5
The project is part of the program for a Regional Express Network in/around Brussels
• Improve mobility in and around Brussels and reduce car traffic towards Belgian’s capital city
• Prevent regional trains from hampering fast circulation of international and intercity trains
… and a national project Regional Express Network - improved mobility in and around Brussels
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 6
8 Watermael-Schuman-Josaphat railway tunnel 21.01.2015
2. A COMPLEX AND CHALLENGING AMBITION TO IMPROVE MULTI- AND COMODALITY
9
330m
120m
6 different sections • Existing tunnel for railway • Connection underneath a cluster of
residential buildings • Tunnel underneath a road • Tunnel underneath an existing road
tunnel • Tunnel underneath a cluster of
office buildings • Schuman station below public
buildings and in the metro entrance 1150m
330m
Railway tunnel underneath existing road tunnel
10 21.01.2015 Watermael-Schuman-Josaphat railway tunnel
Défis organisationnels et techniques des travaux : extension gare Schuman
Rail: renovation of Schuman railway station (view of the “cathedral”)
Défis organisationnels et techniques des travaux : extension gare Schuman
Metro: renovation of Schuman metro station
21.01.2015 15
Pedestrians: ensure accessibility and safety for residents and
office workers
Watermael-Schuman-Josaphat railway tunnel
… all while protecting existing sites
BASEMENTS
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 16
Key facts & figures
Investment
=
70% Total budget
70%
Open air yard: ± 4 km Station /tunnel: ± 2 km Duration of the project: ± 20 years Duration of the yard: ±10 years Placing into service of WSJ-tunnel: planned for December 2015 Total investment: ± 600 Mio euro2012
18 yards • 10 completed • 7 ongoing
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 17
18 Watermael-Schuman-Josaphat railway tunnel 21.01.2015
3. WATERMAEL-SCHUMAN-JOSAPHAT TUNNEL: FOCUS ON INVOLVEMENT OF ALL STAKEHOLDERS
Appropriate measures to reduce vibrations for residents
Existing tunnel:
Layer of track ballast Layer with anti-vibrations system
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 19
Appropriate measures to prevent offices and residential buildings from collapsing
TUNNEL “CINQUANTENAIRE”
SCHUMAN JOSAPHAT
L161A
L26
Connection under a cluster of residential buildings and offices: The roof of the connection is located only 3 meters (!) below the basements Use of compensation grouting techique to prevent collapsing
Link
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 20
Appropriate measures to safeguard historical heritage
Manual excavation of walls and tunnels
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 21
Partners
21.01.2015 Watermael-Schuman-Josaphat railway tunnel 22
Political Authorities • Federal State, competent authority for public transport/Belgian railways • Brussels Capital-Region, competent authority for the Brussels territory Federal Administration • ‘Beliris’, cooperation agreement between the Belgian (Federal) State and the
Brussels Capital-Region aiming at improving the image of Brussels as the capital of Belgium and Europe
Companies • INFRABEL, the Belgian railway infrastructure manager • TUC RAIL, the engineering branch of INFRABEL