water drainage

59
CHAPTER 1 ABOUT PWD 1.1 Introduction The Public Works Department has a glorious history in the development of the state since pre independence. The department is mainly entrusted with construction and maintenance of Roads, Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government. Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were given separate entities to handle increased scope of work in the respective field. Since the inception of the Department, it has strived through its continuous quest for excellence and putting milestones in the feat of Engineering. It is this time that the Department is treading into a new era of information technology to keep pace with the modernization. The Public Works Department being the oldest engineering department of the State, has its well woven network even below tensile level which enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state 1.2 About Public Works Department The Public Works Department has a glorious history in the development of the state since pre independence. The department is mainly entrusted with construction and maintenance of Roads, Bridges 1

Upload: pawankumarm65

Post on 13-Jan-2017

426 views

Category:

Engineering


1 download

TRANSCRIPT

Page 1: Water drainage

CHAPTER 1

ABOUT PWD

1.1 Introduction

The Public Works Department has a glorious history in the development of the state since pre

independence. The department is mainly entrusted with construction and maintenance of Roads,

Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government.

Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were

given separate entities to handle increased scope of work in the respective field. Since the inception

of the Department, it has strived through its continuous quest for excellence and putting milestones in

the feat of Engineering. It is this time that the Department is treading into a new era of information

technology to keep pace with the modernization. The Public Works Department being the oldest

engineering department of the State, has its well woven network even below tensile level which

enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state

1.2 About Public Works Department

The Public Works Department has a glorious history in the development of the state since pre

independence. The department is mainly entrusted with construction and maintenance of Roads,

Bridges and Govt. buildings. The department also acts as Technical Advisor to the State Government

in these matters.

Total road length being maintained by the department is more than 87500 KM the Department also

maintains State buildings all over Rajasthan & outside. The current annual budget allocation to the

department for construction & maintenance activities is over Rs 1000 Crores.

The Public Works Department being the oldest engineering department of the State, has its well

woven network even below tensile level which enables the P.W.D. to ensure the execution of a

variety of jobs/tasks any where in the state.

1

Page 2: Water drainage

Initially, Irrigation, Public Health engineering were units of PWD. Subsequently these units were

given separate entities to handle increased scope of work in the respective field. Since the inception

of the Department, it has strived through its continuous quest for excellence and putting milestones in

the feat of Engineering. It is this time that the Department is treading into a new era of information

technology to keep pace with the modernization. The Public Works Department being the oldest

engineering department of the State, has its well woven network even below tensile level which

enables the P.W.D. to ensure the execution of a variety of jobs/tasks any where in the state.

1.3 Agencies

1. Relief works in the event of Natural calamities like famine, flood, earthquakes et al.

2. D.R.D.A. Works like Employment Assurance Scheme (EAS) etc.

3. Assessments of rent of private premises requisitioned for housing Govt. offices.

4. Design, construction, maintenance and repairs of runway relating to the State Government.

5. Development and maintenance of Public Parks and Gardens in important Public Buildings.

6. Up keeping of Govt. Rest House and Circuit Houses.

2

Page 3: Water drainage

7. To permit construction of approaches on both sides of roads to private individual, other

institutions, factories, Petrol Pumps etc.

8. To evacuate the encroachment coming along the road sides. To evacuate the encroachment

coming along the road sides.

9. Issue of certificates periodically to Cinema Houses about stability of structures/ arrangement

related to electrical fittings conforming to Cinema Regulation Act.

10. Plantation of trees along both sides of the road.

3

Page 4: Water drainage

CHAPTER 2

INTRODUCTION

2.1 Introduction

Drainage is the process of interception and removal of water from over, and under the vicinity of the

road surface. Drainage can be surface (where water is conveyed on the road surface and drainage

channels), or subsurface (water flows underneath the pavement structure).

Surface and subsurface drainage of roads critically affects their structural integrity, life and safety to

users, and is thus important during highway design and construction. Road designs therefore have to

provide efficient means for removal of this water; hence the need for road drainage designs.

Drainage facilities are required to protect the road against damage from surface and sub surface

water. Traffic safety is also important as poor drainage can result in dangerous conditions like

hydroplaning. Poor drainage can also compromise the structural integrity and life of a pavement.

Drainage systems combine various natural and man made facilities e.g. ditches, pipes, culverts, curbs

to convey this water safely.

4

Page 5: Water drainage

2.2 Aims of document

The purpose of this document is to provide guidance for road authorities and other relevant bodies in

respect of road drainage. The document is not intended to be a comprehensive design manual for

drainage for all new roads but concentrates on the design, rehabilitation and maintenance of drainage

systems on regional and local roads. Some of the matters covered will also have applicability for

national roads particularly national secondary roads). The document suggests some basic method

sand approaches for drainage design and references other documents for the design of major new

schemes and where more rigorous drainage analysis is required.

2.3 Importance of drainage

It is essential that adequate provision is made for road drainage to ensure that a road pavement

performs satisfactorily. The main functions of a road drainage system are:

1. To prevent flooding of the road and ponding on the road surface

2. To protect the bearing capacity of the pavement and the sub grade material

3. To avoid the erosion of side slopes

The type of road drainage which is selected for a particular road will depend on such factors as to

whether it is a rural or an urban road, or if it is in cut or fill and also on ground water conditions.

Open drains are used to carry away surface water and can also pick up some subsoil water (depending

on depth).

5

The survey indicated that existing road drainage systems use a mix of open drains, pipes and french

drains depending on road circumstances. The maintenance of these systems is variable and in general

most counties indicate reservations about the adequacy of current maintenance arrangements. The

separate forms of drainage systems in common use are considered briefly in this review of current

practice.

2.4 Open Drains

Open drains are the most common form of road drainage on rural national and non national roads.

Maintenance practice from the data available indicates various levelsof attention to the open drain

system. Opening of drainage inlets and/or total removal of road margin, to ensure rapid removal of

5

Page 6: Water drainage

road surface water, appears to be common practice. However, frequency of inlet opening is perceived

to be inadequate in many circumstances.

Open drains have the advantage of being easily inspected for blockages and are also effective at

draining the road sub grade provided the drain flows to an adequate outfall. Open drains are

generally, but not always, within the road limits. In circumstances where open drains are on private

property the Authority’s powers under the Roads Act should be exercised to ensure that drain age is

not interfered with. The review suggests that drains outside the road limits may

not be receiving adequate attention.

2.5 French Drains

French drains are used extensively on sections of the national network and to a limited extent on non-

national roads. The drains generally include pipe work in conjunction with stone media. Maintenance

levels are low and this may affect the long term performance. In most instances maintenance is

carried out as problems manifest themselves, with few counties having an annual maintenance

programme.

2.6 Piped Drainage

Piped drainage systems are essential in urban areas and are also used in rural areas where space is

limited. Piped systems can be sealed or open-jointed. The normal practice is to use sealed systems in

urban areas and open-jointed systems in rural areas. Piped systems with gullies require regular

maintenance and while in many instances these systems are cleaned annually the data received

suggests that the frequency of maintenance is generally considered inadequate6

6

Page 7: Water drainage

Chapter 3Road

3.1 IntroductionA road is a thoroughfare, route, or way on land between two places, which has been paved or

otherwise improved to allow travel by some conveyance, including a horse, cart, or motor vehicle.

Roads consist of one, or sometimes two, roadways (carriageways) each with one or more lanes and

also any associated sidewalks (British English: pavement) and road verges. Roads that are available

for use by the public may be referred to as public roads or highways.

3.2 Type of Road:FREEWAYS:

Freeways have strict classification rules.

1. Multi-Lane, divided road

2. No cross traffic.

3. No stop lights (except for ramp meters).

4. No stop signs.

5. No parking.

6. No stopping (except for toll booths, freeway access metering)

7. Highest speed limits. (relative to region)

8. Some have minimum speed limits.

7

Page 8: Water drainage

9. Limited access

3.3 MAJAOR HIGHWAYS:

Purposely built as a major throughway.

• Higher speeds. Speed limits should be near or equal to Interstate or Freeway speed limits in

the same area. (typically within 10-20 Kmph)

• Multiple lanes in each direction.

• Separated directions of travel.

• Turning traffic is typically limited to specified turn lanes or freeway style ramps to minimize

obstructions to thru traffic.

• Partially limited access with few minor streets intersecting with this road. Intersections are

most often with primary roads or other highways.

8

Page 9: Water drainage

3.4 MINOR HIGHWAYS:

Minor Highways vary widely from large multi-lane roads with stoplights and higher speed limits, to small residential streets with stops signs. Some minor highways may zigzag thru an area with many turns on local streets. A Minor Highway thru the main street of a small town often retains focus on local access with pedestrian traffic and on street parking.

A side street is a street that intersects a main street and ends there. It is generally of little importance

to through traffic. Being the last mile of the road system, it generally carries little traffic. Common

characteristics of a side street include low speed limits (usually not more than 30 mph or 50 km/h),

curbside parking, and few or no painted line markings to display lanes. Intersections in urban or

suburban areas are usually marked by stop signs, or occasionally yield signs in some suburban areas

when intersecting other side streets. In rural areas, some intersections are uncontrolled.

Most side streets are lined with residences. Occasionally, a place of worship or a school may be

located on a side street, but in a residential area, it is rare to find any commercial development (this is

often prohibited by local zoning laws, unless directly adjacent to a major street).

9

Page 10: Water drainage

CHAPTER 4

DRAINAGE

4.1 Introduction

Drainage is the natural or artificial removal of surface and sub-surface water from an area. Many

agricultural soils need drainage to improve production or to manage water supplies.

The civil engineer is responsible for drainage in construction projects. They set out from the plans all

the roads, street gutters, drainage, culverts and sewers involved in construction operations. During the

construction process he/she will set out all the necessary levels for each of the previously mentioned

factors.

Civil engineers and construction managers work alongside architects and supervisors, planners,

quantity surveyors, the general workforce, as well as subcontractors. Typically, most jurisdictions

have some body of drainage law to govern to what degree a landowner can alter the drainage from his

parcel.

4.2 Types of drainage

There are basically three types of drainage applied to highways that ;

1. Subsurface drainage

2. Surface drainage

3. Cross drainage

4.2.1 SUBSURFACE DRAINAGE

Subsurface drainage is concerned with the interception and removal of water from within the

pavement. Some of the sources of subsurface water include; infiltration through surface cracks,

capillary rise from lower layers, seepage from the sides of the pavement to mention but a few.

Application of side slopes on the road surface, installing of drainage beds in the pavement and use of

transverse drains are some of the measures of effecting subsurface drainage.

10

Page 11: Water drainage

When groundwater cannot be effectively removed or intercepted by surface drainage, subsurface

drainage techniques are required. As discussed in previous sections of this workbook, if water is not

removed from sub grade or pavement structures it may create instability, reduce load bearing

capacity, increase the danger of frost action and create a safety hazard by freezing of the traveled

surface.

Field investigations carried out during the route reconnaissance and design stages may not always

reveal sub drainage problems. These less obvious problems can be effectively dealt with during

construction. Field investigations should be carried out during the wet season and may include soil

and/or geologic studies, borings or trenches to locate groundwater, inspections of natural and cut

slopes in the local area, and measurement of discharge when possible. Sites with potential slope

stability problems should be more thoroughly evaluated. When groundwater tables approach the

ground surface, such as in low, swampy areas, the gradeline should be placed high enough to keep

water from being drawn up into the fill by capillary action. Whenever possible, well graded granular

materials, such as coarse sand, should be used for fill construction. For a detailed discussion of

grading requirements for filter materials the reader is referred to the Earth Manual published by the

U.S. Department of the Interior (1974).

Three types of sub drainage systems are commonly used:

(1) Pipe underdrains. This system consists of perforated pipe placed at the bottom of a narrow

trench and backfilled with a filter material such as coarse sand. It is generally used along the toes of

cut or fill slopes. The trench should be below the groundwater surface and dug into a lower, more

inpervious soil layer to intercept groundwater. The drains may be made of metal, concrete, clay,

asbestos-cement, or bituminous fiber and should be 15 centimeters (6 inches) in diameter or larger.

(2) Drilled drains. This system consists of perforated metal pipes placed in holes drilled into cut or

fill slopes after construction.

(3) French drains. This system consists of trenches backfilled with porous material, such as very

coarse sand or gravel. This type of drain is apt to become clogged with fines and is not

recommended.

11

Page 12: Water drainage

A major difficulty in selecting a drainage system is the lack of adequate performance data for various

drainage methods. A good knowledge of seasonal groundwater fluctuations, variation in lateral and

vertical permeability, and the ratio of vertical to lateral permeability are critical. Long term

monitoring of drainage performance is important in determining appropriate prescriptions for future

installations. For example, perforated drains are commonly prescribed but often will not function

properly as a result of clogging of pores with fines or from geochemical reactions leading to the

formation of precipitates. Several methods may be used to prevent plugging depending on soil

characteristics and material availability. The first is to enclose the perforated pipe with geotextile

fabric. Second, surround the pipe with an open graded aggregate material, which in turn is

surrounded by a fabric. The use of fabric eliminates the need for an inverted filter consisting of

various sized gravel and sand layers. Third, if fabric is not available, surround the pipe with a graded

aggregate filter. Although the cost of installing such a drainage system is high, it may effectively

reduce final road costs by decreasing the depth of base rock needed, thereby reducing subgrade

widths and associated costs for clearing, excavating, and maintenance.

4.2.2 SURFACE DRAINAGE

Surface drainage deals with arrangements for quickly and effectively leading away the water that

collects on the surface of the pavement, shoulders, slopes of embankments, cuts and the land

adjoining the highway. Reducing the erosive power of water can achieved by reducing its velocity. If, for

practical reasons, water velocity cannot be reduced, surfaces must be hardened or protected as much as

possible to minimize erosion from high velocity flows. Road surface drainage attempts to remove the surface

water before it accelerates to erosive velocities and/or infiltrates into the road prism destroying soil strength by

increasing pore water pressures. This is especially true for unpaved, gravel, or dirt roads.

The main source of surface water in most places is precipitation in form of rain. When precipitation

falls on an area, some of the water infiltrates in to the ground while a considerable amount remains on

top of the surface as surface run off.

Dip locations are determined at the time the grade line is established on the ground or during vertical

alignment design. The total length of the two vertical curves comprising the dip should be sufficient

to allow the design vehicle to pass safely over them at the design speed. The minimum vertical

distance between the crest and sag of the curves should be at least 30 cm (1 ft). It is important that the

dip be constructed at a 30 degree or greater angle downgrade and that the dips have an adverse slope

12

Page 13: Water drainage

on the downroad side. The downroad side of the dip should slope gently downward from the toe of

the road cut to the shoulder of the fill. The discharge point of the dip should be armored with rock or

equipped with a down-drain to prevent erosion of the fill. Equipment operators performing routine

maintenance should be aware of the presence and function of the dips so that they are not

inadvertently destroyed.

MEASURES ADOPTED FOR SURFACE DRAINAGE

1. The proper cross slope should be provided for both to pavement and shoulders

2. The subgrade should be sufficiently above the highest level of ground water table or the

natural ground level

3. Side drainage should have to be provided at edges of right-of-way where the road is in

embankment and the edge of the roadway in cutting

4. On hill roads, water may flow towards the road depending on the slope and rainfall

5. Catch water drains should be provided to intercept the flow down.

COLLECTION OF SURFACE WATER

The water collected is lead into natural channels or artificial channels so that it does not interfere with

the proper functioning of any part of the highway.

Surface drainage must be provided to drain the precipitation away from the pavement structure.

4.2.2.1 CLASSIFICATIONOF SIDE DRAINAGE

There are different types of road side drainage, classified according to the type of construction, which

is as follows;

Trapezoidal surface drainage

A trapezoidal ditch is the most efficient hydraulically and should be used for ditches carrying a large

amount of water. The flat bottom spreads out the flow and helps reduce erosion problems. They are more

13

Page 14: Water drainage

difficult to construct, but the Soil and Water Conservation District and Natural Conservation Service can

provide assistance.

V-shaped lined surface drainage

A V–shaped ditch is easy to construct, especially with a grader. However, the bottom of the V is prone to

erosion and can be difficult to maintain.

Urban surface drainage

A U–shaped ditch is more efficient hydraulically and a good shape for erosion control. It can be built with

an excavating machine and is easy to maintain. However, most U–shaped ditches in New York State are

too steep on the road side of the ditch. Two ways to solve the problem are to cuff the break of the ditch

and the shoulder with a grader or the excavator bucket, or curl the bucket back during the final pass to

make a rounded shape.

14

Page 15: Water drainage

4.2.3 CROSS DRAINAGE

When stream have to cross a roadway or when water from a side drainage have to be diverted to

water course across the roadway, then a cross drainage work such as culvert or small bridge is

provided.

On less important roads, in order to reduce the construction cost of drainage structures, sometimes

submersible bridges or course way are constructed. During the flood the water will flow over the

road. Cross drains are often needed to intercept the longitudinal, or down-road, flow of water in order to

reduce and/or minimize surface erosion. In time, traffic will cause ruts to form, channeling surface water

longitudinally down the road.

REQUIREMENT OF HIGHWAY DRAINAGE SYSTEM

1. The surface water from the carriage way and shoulder should effectively be drained off

without allowing it to percolate to sub grade

2. The surface water from the adjoining land should be prevented from entering the roadway.

3. The surface drainage should have sufficient capacity and longitudinal slope to carry away

all the surface water collected.

15

Page 16: Water drainage

4. Flow of surface water across the road and shoulders and along slopes should not cause

formation of erosion.

16

Page 17: Water drainage

CHAPTER 5

CULVERTS

5.1 IntroductionReducing the erosive power of water can achieved by reducing its velocity. If, for practical reasons,

water velocity cannot be reduced, surfaces must be hardened or protected as much as possible to

minimize erosion from high velocity flows. Road surface drainage attempts to remove the surface

water before it accelerates to erosive velocities and/or infiltrates into the road prism destroying soil

strength by increasing pore water pressures. This is especially true for unpaved, gravel, or dirt roads.

A culvert helps move water under a road or driveway to a stream, lake, or detention basin. While

culverts can, and have been, defined in many ways (such as any span under 20 feet), for drainage, a

culvert is usually prefabricated and comes in standard sizes. In addition, a culvert is allowed to have

the ends completely submerged.

The first item we need to understand is the amount of flow a culvert will need to carry. Then we can

look at the materials, installation, inspection, and maintenance.

Water moves across the road surface laterally or longitudinally. Lateral drainage is achieved by

crowning or by in- or out- sloping of road surfaces (Figure 79). Longitudinal water movement is

intercepted by dips or cross drains. These drainage features become important on steep grades or on

unpaved roads where ruts may channel water longitudinally on the road surface.

• Hydrological analysis

• Hydraulic analysis

Runoff

The first step in determining the size of a culvert (or other drainage structure, including ditches) is

calculating the runoff or flow coming to a culvert. Several methods exist for determining the amount

of flow. TR–55; the Soil Conservation Service’s Graphical method; the Bureau of Public Roads; the

Rational method; and other methods are used to determine the amount of runoff. The Rational

method, used for small watersheds, is useful to explain the concepts of runoff.

17

Page 18: Water drainage

Runoff at a specific site is controlled by many factors including the intensity of precipitation, the area

of the watershed, and the proportion of rainfall which gets to the culvert.

Fig 5.1 Precipitation and runoff (hydrograph)

5.2 Hydrological analysis

This deals mainly with precipitation and runoff in the area of interest. When rainfall, which is the

main source of water, falls onto an area some of the water infiltrates into the soil while the remaining

portion either evaporates or runs off.

The portion that remains as runoff is the one of major importance in the design of surface drainage

facilities.

5.3 Determination of runoff

Runoff at a particular point is determined with respect to a given catchment area and depends on a

number of factors such; type and condition of the soil in the catchment, kind and extent of vegetation

or cultivation, length and steepness of the slopes and the developments on the area among others.

The following formula known as the rational formula is used for calculation of runoff water for

highway drainage.

Q= 0.028CIA

18

Page 19: Water drainage

Where:

Q = maximum runoff in m3 per sec

C = a constant depending upon the nature of the surface

I = the critical intensity of storm in mm per hour occurring

during the time of concentration.

A = the catchment area in km2

5.4 Hydraulic Design

Once the design runoff Q is determined, the next is the hydraulic design of drains. The side drainage

and other structures are designed based on the principles of flow through open channels.

If Q is the quantity of surface water (m3/sec) to be removed by a side drainage and V is allowable

velocity of flow (m/s) on the side drainage, the area of cross section A of the channel (m2) is found

from the relation below:

Q=A.V

The velocity of unlined channel must be high enough to prevent silting and it should not be too high

as to cause erosion. The allowable velocity should be greater than one (1m/sec) for lined channel.

The slope S of the longitudinal drain of known or assumed cross section and depth of flow ,may

determined by using Manning’s formula for the design value of velocity of flow V, roughness

coefficient n and hydraulic radius R.

Manning’s Formula

V=1/n*R2/3*S1/2

Where:

V=Average velocity m/sec

19

Page 20: Water drainage

n=Manning’s roughness coefficient

R=Hydraulic radius

S=Longitudinal slope of channel.

Manning’s Roughness coefficient

N= 0.02 for unlined ordinary ditches

=0.05 to 0.1 for unlined ditches with heavy vegetation

=0.013 for rough rubble

=0.04 for stone riprap

=0.015 for pipe culverts

Hydraulic Radius = Cross sectional area

Wetted perimeter

5.5 Time of concentration (t c)

Time of concentration is that time required for water to travel all the way from catchments area to

the designed element.

The time taken by water to flow along the longitudinal drain is determined from the length of the

longitudinal drain L the nearest cross drainage or a water course and allowable velocity of the flow V

in the drain.

T = V/L

The total time for inlet flow and flow along the drain is taken as time of concentration or the design

value of rain fall duration.

T c = T1+ T2

20

Page 21: Water drainage

Where,

T1 = overland flow time in minutes

T2 = channel flow time in minute

T1 = [(0.885x L3)/H] 0.385

Where,

L = the length of overland flow in km from critical point the mouth of the drain.

H = total fall of level from the critical point to the mouth of the drain in meters.

Note:

From the rainfall intensity –duration- frequency curves the rainfall I is found in mm/sec.

Corresponding to duration T and frequency of return period.

The required depth of flow in the drain is calculated for convenient bottom width and side slope of

drain. The actual depth of the open channel drain may be increased slightly to give a free body. The

hydraulic mean radius of flow R is determined.

The required longitudinal slope S of the drain is calculated using Manning formula adopting suitable

value of roughness coefficient.

21

Page 22: Water drainage

22

Page 23: Water drainage

CHAPTER 6

ABOUT THE MATERIAL

6.1 Introduction

Culvert pipes come in many materials, shapes, and sizes. Each material has its own characteristics

and advantages. The four most common materials are corrugated metal pipe (CMP), plastic, concrete,

and smooth steel. The pipes are generally thought of in two broad categories which correspond to the

way they carry loads, rigid and flexible.

Flexible pipe (CMP and plastic) gains strength by transferring some of the load into the surrounding

soil. Imagine what would happen if you drove a fully loaded truck over a flexible pipe. It would

crush. It gains strength from the surrounding soil when it flexes.

Flexible pipes must be backfilled properly and have a minimum amount of cover or the loads do not

build up in the soil and the pipe will fail. They are generally less expensive to place than rigid pipes

but do not last as long. Coatings may increase their lifespan. Failure to bed the pipe carefully will

shorten the life of the pipe and may cause premature failure.

Rigid pipes (concrete, heavy steel, and masonry) are strong enough by themselves to carry all loads.

The transferring of loads is of secondary benefit. They generally last longer than flexible pipes but

are much more expensive to place. Cranes and larger equipment are usually needed to set them.

6.2 Corrugated metal pipe

Sometimes referred to as CMP (corrugated metal pipe), metal pipe is the most common type of

material used in culverts. The versatility of the pipe and the wide range of shapes and sizes available

make it a very useful product.

The base metal can be steel or aluminum. Coatings can be added to increase lifespan, reduce

corrosion, and improve hydraulics (flow capacity). Steel is the most common metal used, but is

usually galvanized for corrosion protection. The steel may be mixed or coated with an aluminum

alloy which is more durable than galvanizing alone and does not increase the price significantly. Or,

the pipe can be made of all aluminum. Care should be taken when installing an aluminum pipe,

because it is easily damaged. Asphalt and concrete coatings are sometimes added for durability,

improved flow characteristics, and resistance to wear from stream bed materials.

23

Page 24: Water drainage

Metal pipes are manufactured in a variety of shapes as shown. Listed beside each are some of the

reasons for using the different shapes. ROUND Easy and inexpensive to manufacture. Has a high

flow capacity. Sizes up to 12 inches in diameter.

6.3 Plastic Plastic pipe, usually made of high density polyethylene (HDPE), is the fastest growing pipe in terms

of use. It is easy to construct due to its light weight and is easy to maneuver and cut. It can be used in

a variety of applications including lining existing pipes. It can be lined with a smooth section of

plastic to increase flow capacity and improve strength. Plastic pipe is flammable and can be burned.

The pipes are limited in size to about six feet and are uneconomical for many applications if more

than four feet in diameter. New processes may provide more pipe types and sizes in the future. Plastic

pipes only come in a round shape currently, up to 6 feet in diameter for smooth pipes, and 2 feet for

corrugated pipes.

Figure 7.1 - Pipe shapes (metal)

6.4 Concrete

Concrete pipe comes in a variety of shapes and sizes. It can be pre–cast or cast–in–place and

primarily used in deep fills or urban areas where construction costs are high. It is more expensive

than plastic or metal pipe but is very durable and has a long life. Cranes and other heavy equipment

are usually needed to place the pipe.

Concrete pipes come in several shapes, but the most common are round and elliptical. Elliptical pipe

may be vertical or horizontal in alignment. Concrete box culverts are some of the most common

bridge and large culvert types built.

6.5 Heavy steel

Solid steel pipe, sometimes made from old boilers, tank cars, or pipelines can be economical when

available locally. It is usually very durable. However, the durability of the pipe is usually unknown

24

Page 25: Water drainage

and the pipe can deteriorate quickly. The major problem, with steel culverts, however, is the joints.

They need to be well built or failure at the joint can allow infiltration of fines and settlement at the

surface. Steel pipes are usually round and come in limited sizes.

25

Page 26: Water drainage

6.5 Durability

Concrete pipe is the most durable with an expected life of 75 to 100 years. It is expensive to install,

but in deep fills and urban areas (villages and cities) it is usually justified by comparing the cost of

replacement to the amount of time between replacement.

Solid steel is usually the next most durable. However, if you buy a used pipe, the lifespan may be

very short.

Plastic and corrugated metal are about the same in durability. Steel pipe is better able to handle bed

loads and debris but is very susceptible to corrosion due to low pH water (acidic) which is found in

the Southern Tier and parts of the Adirondacks. Other areas may have high alkalinity in the soil. In

those areas, plastic pipe or lining of pipes may be necessary to keep pipe from corroding early. Plastic

and corrugated metal pipes have a 25 to 50 year life if designed and built properly. Also, bed load can

cause premature failure. Lining of existing pipes, or adding liners during construction may be useful.

6.6 SIZE AND CAPACITY

How large of a pipe is needed? Several factors need to be considered. First let’s discuss the factors.

Then we will bring all of the results together below.

The flow capacity of a pipe is determined by several factors including the:

• Area and shape of the opening of the pipe

• Allowable head or amount of backwater

• Kind of inlet

• Culvert length and slope

• Material used (roughness of the pipe)

• Other factors including constrictions of flow due to debris, tailwater, or channel alignment

6.6.1 Area and shape of opening

By far the most critical factor for determining capacity is the area of the opening of the pipe. The

amount of flow that can go through a culvert is directly proportional to the area of the opening.

26

Page 27: Water drainage

Doubling the area doubles the capacity of the pipe. An 18–inch diameter pipe has more than twice the

capacity of a 12–inch diameter pipe because the area is more than twice as large.

(18–inch diameter pipe area = 254 in2 vs. 12–inch diameter pipe area = 113 in2).

6.6.2 Allowable head or depth of water at the inlet

The allowable head is the maximum depth of flow before either the road is overtopped by the water

backed up at the culvert, or damage to the road or adjacent property is likely to occur. The

overtopping does not have to be at the pipe. In many cases, the flow crosses the road downhill from

the culvert due to natural alignments or planned changes in the roadway. Damage could be a washout

of the roadway due to overflow or inundation of a building that is built lower than the roadway

elevation.

The greater the allowable depth, the more flow can be pushed through the pipe. Increases in the cover

over a pipe (and therefore increases in allowable depth) can greatly increase the allowable flow in the

pipe. Care must be taken to use existing allowable heads or increases in the height of the roadway.

Lowering the pipe to get more cover does not work. The pipe will probably fill in with sediment and

the area of the opening will be diminished, reducing the flow capacity by far more than the increase due

to extra head.

27

Page 28: Water drainage

CHAPTER 7MATERIALS, SHAPES, and SIZES

Culvert pipes come in many materials, shapes, and sizes. Each material has its own characteristics

and advantages. The four most common materials are corrugated metal pipe (CMP), plastic, concrete,

and smooth steel. The pipes are generally thought of in two broad categories which correspond to the

way they carry loads, rigid and flexible.

Flexible pipe (CMP and plastic) gains strength by transferring some of the load into the surrounding

soil. Imagine what would happen if you drove a fully loaded truck over a flexible pipe. It would

crush. It gains strength from the surrounding soil when it flexes.

Flexible pipes must be backfilled properly and have a minimum amount of cover or the loads do not

build up in the soil and the pipe will fail. They are generally less expensive to place than rigid pipes

but do not last as long. Coatings may increase their lifespan. Failure to bed the pipe carefully will

shorten the life of the pipe and may cause premature failure.

Rigid pipes (concrete, heavy steel, and masonry) are strong enough by themselves to carry all loads.

The transferring of loads is of secondary benefit. They generally last longer than flexible pipes but

are much more expensive to place. Cranes and larger equipment are usually needed to set them.

7.1 Corrugated metal pipe

Sometimes referred to as CMP (corrugated metal pipe), metal pipe is the most common type of

material used in culverts. The versatility of the pipe and the wide range of shapes and sizes available

make it a very useful product.

The base metal can be steel or aluminum. Coatings can be added to increase lifespan, reduce

corrosion, and improve hydraulics (flow capacity). Steel is the most common metal used, but is

usually galvanized for corrosion protection. The steel may be mixed or coated with an aluminum

alloy which is more durable than galvanizing alone and does not increase the price significantly. Or,

the pipe can be made of all aluminum. Care should be taken when installing an aluminum pipe,

because it is easily damaged. Asphalt and concrete coatings are sometimes added for durability,

improved flow characteristics, and resistance to wear from stream bed materials.

28

Page 29: Water drainage

7.2 Plastic Plastic pipe, usually made of high density polyethylene (HDPE), is the fastest growing pipe in terms of

use. It is easy to construct due to its light weight and is easy to maneuver and cut. It can be used in a

variety of applications including lining existing pipes. It can be lined with a smooth section of plastic to

increase flow capacity and improve strength. Plastic pipe is flammable and can be burned. The pipes are

limited in size to about six feet and are uneconomical for many applications if more than four feet in

diameter. New processes may provide more pipe types and sizes in the future. Plastic pipes only come in

a round shape currently, up to 6 feet in diameter for smooth pipes, and 2 feet for corrugated pipes.

Figure 7.1 - Pipe shapes (plastic)

Figure 7.2 - Pipe shapes (metal)

29

Page 30: Water drainage

7.3 Concrete

Concrete pipe comes in a variety of shapes and sizes. It can be pre–cast or cast–in–place and

primarily used in deep fills or urban areas where construction costs are high. It is more expensive

than plastic or metal pipe but is very durable and has a long life. Cranes and other heavy equipment

are usually needed to place the pipe.

Concrete pipes come in several shapes, but the most common are round and elliptical. Elliptical pipe

may be vertical or horizontal in alignment. Concrete box culverts are some of the most common

bridge and large culvert types built.

7.4 Heavy steel

Solid steel pipe, sometimes made from old boilers, tank cars, or pipelines can be economical when

available locally. It is usually very durable. However, the durability of the pipe is usually unknown

and the pipe can deteriorate quickly. The major problem, with steel culverts, however, is the joints.

They need to be well built or failure at the joint can allow infiltration of fines and settlement at the

surface. Steel pipes are usually round and come in limited sizes.

Figure 28 - Pipe shapes (steel)

30

Page 31: Water drainage

7.5 Durability

Concrete pipe is the most durable with an expected life of 75 to 100 years. It is expensive to install,

but in deep fills and urban areas (villages and cities) it is usually justified by comparing the cost of

replacement to the amount of time between replacements.

Solid steel is usually the next most durable. However, if you buy a used pipe, the lifespan may be

very short.

Plastic and corrugated metal are about the same in durability. Steel pipe is better able to handle bed

loads and debris but is very susceptible to corrosion due to low pH water (acidic) which is found in

the Southern Tier and parts of the Adirondacks. Other areas may have high alkalinity in the soil. In

those areas, plastic pipe or lining of pipes may be necessary to keep pipe from corroding early. Plastic

and corrugated metal pipes have a 25 to 50 year life if designed and built properly. Also, bed load can

cause premature failure. Lining of existing pipes, or adding liners during construction may be useful.

31

Page 32: Water drainage

7.6 SIZE AND CAPACITY

How large of a pipe is needed? Several factors need to be considered. First let’s discuss the factors.

Then we will bring all of the results together below.

The flow capacity of a pipe is determined by several factors including the:

1. Area and shape of the opening of the pipe

2. Allowable head or amount of backwater

3. Kind of inlet

4. Culvert length and slope

5. Material used (roughness of the pipe)

7.6.1 Area and shape of opening

By far the most critical factor for determining capacity is the area of the opening of the pipe. The

amount of flow that can go through a culvert is directly proportional to the area of the opening.

Doubling the area doubles the capacity of the pipe. An 18–inch diameter pipe has more than twice the

capacity of a 12–inch diameter pipe because the area is more than twice as large.

(18–inch diameter pipe area = 254 in2 vs. 12–inch diameter pipe area = 113 in2).

Figure 7.4 - Factors determining flow capacity of a pipe

7.6.2 Allowable head or depth of water at the inlet

The allowable head is the maximum depth of flow before either the road is overtopped by the water

backed up at the culvert, or damage to the road or adjacent property is likely to occur. The overtopping

does not have to be at the pipe. In many cases, the flow crosses the road downhill from the culvert due to

32

Page 33: Water drainage

natural alignments or planned changes in the roadway. Damage could be a washout of the roadway due to

overflow or inundation of a building that is built lower than the roadway elevation.

The greater the allowable depth, the more flow can be pushed through the pipe. Increases in the cover

over a pipe (and therefore increases in allowable depth) can greatly increase the allowable flow in the

pipe. Care must be taken to use existing allowable heads or increases in the height of the roadway.

Lowering the pipe to get more cover does not work. The pipe will probably fill in with sediment and

the area of the opening will be diminished, reducing the flow capacity by far more than the increase

due to extra head.

Figure 7.5 - Shape of openings

33

Page 34: Water drainage

7.6.3 Kind of inlet

The most common inlet (and outlet) type is the projecting pipe. Small increases in the capacity can be

gained by using the mitered or headwall inlet. Also, use of special ends on both the upstream and

downstream side can reduce scour, improve appearance, and make maintenance easier. The extra

capacity in a culvert due to use of inlets is anywhere from no increase to 10 percent increase in the

flow capacity.

Most commonly, inlets are placed to improve characteristics other than flow. Mitering the pipe to fit

the slope makes the slope safer for errant vehicles and is easier to maintain. However, the ends are

susceptible to failure if the ends are not anchored properly. A set of #8 rebars placed on a one–foot

grid over the opening allows the highway department to eliminate the use of guiderail. The bars help

keep debris out of the pipe. Care must be taken to leave an opening below the grate to allow the

majority of the flow through the pipe or plugging can occur and damage the pipe.

Special ends can be purchased to attach to the ends of most round pipes. The price can be very high

for larger pipes, but the ends protect against scour, have good appearances, and can be protected by a

rebar grate in the same way a metered end is protected. In addition, if there is a need to extend the

pipe in the future, the end can be removed, a new section of pipe added to the first section, and the

end replaced.

Figure 7.6 - Inlet (outlet) designs (projecting, mitered, and headwall)

34

Page 35: Water drainage

Headwalls are usually used with high flows, major alignment changes near the openings which cause

heavy scour, and deeper pipes which warrant more expensive protection. The headwalls can be made

on concrete, precast concrete and masonry, gabion baskets, plastic, and timber. Concrete is more

expensive, but fits the opening better and reduces the chances of piping. Gabion baskets are fairly

labor intensive, but can be shaped to fit the pipe. Masonry and precast concrete do not fit the pipe and

usually some grout or concrete must be placed around the opening to get a good fit. Timber and other

items (tires, sandbags) are not as effective due to shorter life spans and uncertainty about durability.

7.6.4 Culvert length and slope

For most small culverts (60 feet or less) the capacity of the pipe is not affected by the slope. The

opening of the pipe will control the amount of water that can get into the pipe. Increasing the slope

will increase the velocity of the flow but the capacity will NOT increase.

For culverts of more than 60 feet, the slope and length do make a difference but usually only at very

flat slopes (1 percent or less [3 inches per 20–foot section of pipe]). In fact, increasing the slope

beyond 2 percent (5 inches per section of pipe) can actually cause problems due to increases in

velocity of the water leaving the pipe.

7.4.5 Material used Concrete, steel, and smooth plastic may have slightly more capacity than corrugated pipes. However,

this is only true for pipes that are fairly long and flat. In most cases, the selection of the material to be

used is a function of cost, availability, ease of construction, maintenance, and longevity. In many

cases, the smoother pipes are used at flat slopes because they are less likely to fill with sediment and

plug. However, use of smooth pipes on steep slopes can actually cause erosion and other problems.

Figure 7.6 - Corrugated pipe special end section

35

Page 36: Water drainage

CHAPTER 8SLOPES AND EROSION CONTROL

8.1 HOW TO STOP EROSION

Stopping erosion is difficult. Keeping erosion from occurring in the first place is usually more successful.

Many of the maintenance activities performed on roads and streets would be unnecessary if erosion was

controlled. As an example, stopping erosion from occurring at the top of a hill will reduce the ditching at

the bottom of the hill. Approximately 30 tons of material can be eroded from a mile of ditches before you

can see the damage! To remove and replace 30 tons of material is a lot of work.

Also, you need to be concerned about erosion during construction and maintenance work. The work can

cause additional erosion.

8.2 TYPES OF EROSION

Three types of erosion are common: surface, rill, and galley. Different soils erode differently. For most

highway materials you can be sure of two things. One, unprotected materials will erode and cause

sedimentation. Two, the flatter the slope the fewer erosion problems occur.

• Surface Surface or sheet erosion occurs when rainfall dislodges soil on the surface of

material, and the water plus soil flows in sheets. The washing of shoulders is often started

by this process.

• Rill Rill erosion occurs when the velocity of the flow is great enough to dislodge soil in

addition to that dislodged by rainfall. Rill erosion is typified by the narrow little channels

that form in banks and slopes that are not protected from erosion.

• Gully Gully erosion occurs when rill erosion combines and concentrates the flow of runoff

into gullies. Washouts between pavement and shoulders are usually gully erosion.

36

Page 37: Water drainage

8.3 SEDIMENTATION

All of the material removed by erosion is deposited at some location downstream from the erosion.

This process of sedimentation usually occurs where a change in the speed of the flow occurs. Filling

of culverts, ditches, streambeds, and even lakes is a result of sedimentation. Stopping erosion will

eliminate or reduce many of the problems associated with poor drainage.

8.4 SLOPES Even very flat ground erodes. The reason you do not notice the erosion is that sedimentation occurs at

the same location as the erosion. Steep terrain erodes very quickly. You need to reduce erosion

problems. In addition, for slopes you have to be concerned about three factors: stability, safety, and

maintenance.

Figure 9.2 - Slopes

37

Page 38: Water drainage

8.4.1 Stability

Most highway materials are stable at slopes of 1:2 or flatter. Slopes steeper than 1:2 are more prone

to erosion and washouts. If saturated, the entire slope may fail.

8.4.2 Safety Slopes along the edge of roads, including ditches and banks, need to be kept fairly flat to allow errant

vehicles a safe place to drive. Slopes of 1:3 or flatter are considered safe. If the slope is less than 3 feet

high a 1:2 slope is acceptable. More information on roadside safety can be found in the Cornell Local

Roads Program’s manual.

8.4.3 Maintenance Mowing slopes is the most common maintenance technique. If slopes are 1:2 or flatter, the mowing crews

can easily mow the slope. Minor repairs may be needed to fix small washouts and erosion.

8.4.4 Options If a slope is too steep, several items need to be examined to repair the problem:

• Stabilize Unstable slopes can be stabilized by use of geotextiles or other earth

reinforcement materials. If you have a high steep slope that is showing signs of distress,

GET HELP.

• Retaining walls Use of gabions, concrete, and block retaining walls may be needed on very

steep slopes or to help stabilize the toe of an existing slope. If a slope is so steep the

erosion mitigations listed below will not work, a retaining wall may be needed. GET HELP

to determine the best course of action.

• Signing Slopes steeper than 1:3 (1:2 for 3 or fewer feet in height) need to be protected. As a

minimum, signs should be used to delineate the slope and warn motorists of the hazard. See

Chapter 17B New York Code of Rules and Regulations (NYCRR) for future information.

38

Page 39: Water drainage

• Guiderail Guiderail should be used on steep slopes. It needs to be installed and used

correctly as part of an overall plan to upgrade the roads. The NYSDOT publication,

Guiderail III, has valuable information about the use of guiderail to protect slopes.

39

Page 40: Water drainage

CHAPTER 9

CONCLUSION

After this research many problems were discovered such as potholes, corrugations, water lodging,

ruts ,erosion on the edge of the road as the result of inspection, practical checking of the whole road

and all areas surrounding the road. In order to maintain the life span and purpose of the road as

designing Road side drainage of adequate size and capacity, the discharge and all dimensions

produced can be used for the construction as it designed.Terefore we conclude our major project by

researching and knowing the major problems and thus understanding it.

40

Page 41: Water drainage

Chapter 10

Learning and outcome

1. Learning how to work in professional environment.

2. Learning the technology

3. Punctuality,time evaluation,priority deciding

4. Helped in developing knowledege about the technology

5. Overcoming hurdles and meeting hurdles

6. Implementation of theoritical knowledge in practical.

7. I built my knowledge about tha drain construction and also able to make road side drains.

41