waste water facilities plan update
DESCRIPTION
Waste Water Facilities Plan Update. Public Hearing Presentation. November 2, 2009. Palmer Engineering Company / Hazen & Sawyer / CDP. What is a Facilities Plan?. Required by the Federal and State Government 401 KAR 5:006 The Clean Water Act, 33 USC 1313 The Clean Water Act, 33 USC 1288 - PowerPoint PPT PresentationTRANSCRIPT
Waste Water Facilities Plan Update
November 2, 2009Palmer Engineering Company / Hazen & Sawyer / CDP
Public Hearing Presentation
What is a Facilities Plan?
Required by the Federal and State Government 401 KAR 5:006 The Clean Water Act, 33 USC 1313 The Clean Water Act, 33 USC 1288
Requirements 401 KAR 5:006
Facilities Plan Requirements
Facilities Plan Boundary Existing Facilities Population Projections (20 Yrs) Flow Projections (20 Yrs) Environmental Considerations Alternatives Analysis Schedule
Why Does WMU Need a Facilities Plan Update?
Required when: (401 KAR 5:006) Major changes to the Facilities 20 Years since previous Facilities Plan Current Facilities Plan: 1972 / 1973
Consent Decree with Environmental Protection Agency
Facilities Plan Approval Process
• Draft Plan• Clearinghouse Comments• Resubmit• Local Agency Approval• Public Hearing• Final Approval
Environmental Agency Involvement
U.S. Department of Fish and Wildlife Kentucky Department of Fish and Wildlife Kentucky Heritage Council Kentucky State Nature Preserves Commission Kentucky Department for Environmental
Protection State Clearinghouse
WMU Existing Waste Water Facilities
Includes: 150 miles of gravity sanitary sewer 15 Miles of Force Main 17 Pump Stations 1 WWTP
7.2 MGD (Average) 24 MGD (Peak)
1 Class A Bio-solids facility
Existing Facilities Condition Aging Infrastructure (I/I) 27 Recurring Sanitary Sewer Overflows (SSOs)
Licking River Watershed – 14 Kentucky River Watershed – 13 Pump Station SSO Locations – 5 Manhole SSO Locations – 21 SC-WWTP SSO Locations – 1
Watersheds 2 River 14 Sub-watersheds Licking River - 8 Kentucky River - 6
Population Projections
Census Data University of Louisville Data Center Comprehensive Plan WMU Database
Flow Projections
Customer Data Flow Monitoring WWTP Flow Data
20 Year Flow Projections
Avg. DayPeak Day
• Licking River 7.2 MGD 24.0 MGD
• Kentucky River 2.0 MGD 10.0 MGD
Alternatives Considered
• Single Treatment Plant– SC WWTP Expansion
• River Watershed Treatment Plants (2)– New Kentucky River WWTP– No SC WWTP Expansion
Alternatives Evaluated
• Capacity Requirements• Environmental Considerations• Constructability• Implementability• Cost
• Capital / O&M / Present Worth
• Recommended Alternative• River Watershed Treatment Plants (2)
Discharge Alternatives
• Deep Branch Discharge• Kentucky River Discharge
Recommended Discharge Alternative• Kentucky River Discharge
Schedule / Costs
Project Year Costs1. LHC Improvements 2013 $37,000,0002. Maryland Avenue, Wabash, & 2012 $1,500,000
Smith Manor PS3. Bel-Air & Westside PS 2013 $900,0004. East Interceptor Improvements 2021 $1,950,000
(Madison / Washington / Flanagan Ave.)5. Hood Creek Int. / PS / FM TBD $5,800,0006. Hancock Creek Int. / PS / FM TBD $8,800,0007. West Interceptor TBD $7,700,000
Impact of Rate Plan for Wastewater
Summary
• Required Element• Sets Direction• Consent Decree Compliance• Position for the Future