vertical navigation (for pbn)

25
The European Organisation for the Safety of Air Navigation Vertical Navigation (for PBN) David De Smedt EUROCONTROL September 2012

Upload: truonglien

Post on 03-Jan-2017

233 views

Category:

Documents


2 download

TRANSCRIPT

The European Organisation for the Safety of Air Navigation

Vertical Navigation (for PBN) David De SmedtEUROCONTROL

September 2012

Navigation Specifications

ICAOICAONAVIGATION NAVIGATION

SPECIFICATIONSSPECIFICATIONS

International NS in Volume II of PBN ManualInternational NS in Volume II of PBN Manual

Designation RNAV 5RNAV 2RNAV 1

Designation RNAV 10

For Oceanic and Remote Continental navigation

applications For En Route & Terminal navigation applications

* Under development

RNP SPECIFICATIONSRNP SPECIFICATIONSRNAV SPECIFICATIONSRNAV SPECIFICATIONS

DesignationRNP with additional requirements to be

determined (e.g. 3D, 4D etc)

Designation

B-RNP 1

RNP AR APCHfor various phases of

flight

RNP 2*

A-RNP*RNP 0.3*

RNP APCH*

Designation RNP 4

For Oceanic & Remote Continental navigation

applications

*

*

ICAO Recommendations

ICAO (36th Assembly Oct 2007): – States and planning and implementation regional groups

(PIRGs) should complete a PBN implementation plan by 2009 to achieve:

– Implementation of RNAV and RNP operations for en route and terminal areas according to established timelines and intermediate milestones; and

– Implementation of approach procedures with vertical guidance (APV) (Baro-VNAV and/or augmented GNSS) for all instrument runway ends, either as the primary approach or as a back-up for precision approaches by 2016 with intermediate milestones as follows:

• 30% by 2010• 70% by 2014.

ICAO Recommendations

37th ICAO Assembly (Oct 10):Concerning Approach with Vertical guidance (APV), the resolution added:– implementation of straight-in LNAV only procedures, as

an exception, for instrument runways at aerodromes where there is no local altimeter setting available and where there are no aircraft suitably equipped for APV operations.

PBN in Europe

VAL +/- 50m (10-7)

/GPS + GBASTBDConcept2012-2015GBAS CAT II/III

/GPS + GBASICAO SARPsConcept2008-2015GBAS CAT I

AMC 20-28GPS + SBAS1

(EGNOS)HAL +/- 40m (10-7)

Implementation2010APV SBAS

AMC 20-27GPS/Baro+/- 0.3NM (95%) Implementation2008APV Baro

AMC 20-26GPSDepends on

required accuracy <0.3NM (95%)

ImplementationIndividual Implement

ation

RNP AR APCH

AMC 20-27GPS+/- 0.3NM (95%) Implementation2006RNP APCH

Approach / Landing

(TGL10 Rev 1)DME/GPS+/- 1NM (95%) Implementation2006+RNAV 1 (≈ P-RNAV)

Arrival / Departure

AMC 20-4VOR/DME/

GPS*/ INS*+/- 5NM (95%) Mandatory 1998RNAV 5 (B-

RNAV)En-Route

EASA Certification

Documentation

Enabling Systems

Required Performance

Current Situation

Target Date

Operational Concept

Flight Phase

APVs

RNP Approaches - Vertical Guidance

RNP APCHRNP APCH

Lateral Guidance onlyLateral Guidance only WithWith Vertical GuidanceVertical Guidance

LNAVLNAV LPLPLP

Expected to be flown as

CDFA

SBAS supported

Lateral only

LNAV/VNAVLNAV/VNAV LPVLPV

APV-Baro APV-SBAS(SBAS supported

Localiser Performance with vertical guidance)

200 ft

RNP APCH LNAV/VNAV (APV Baro)

NPA (VOR/DME)

250ft

RNP APCH LNAV (GPS)

NPA (VOR)

ILS and GBAS (CAT I)

NPA (NDB)

300ft350ft

ILS, GBAS & MLS (CAT II/IIII)

Actual minima depends on obstacles around the intended approach path (including approach and missed approach segments of flight)OCH minima is further more limited to 300ft in the case of a NPA runway (NPA lighting for instance)

RNP APCH LP (SBAS)

<200 ft

NPA (LOC only)

RNP APCH LPV (APV SBAS)

Source: EU Ops 1.430

Minimum OCH per Approach Type

8

PBN approach terminology versus charting terminology

• RNP APCH =

RNAV (GNSS) or

RNAV (GPS)

• RNP AR = RNAV (RNP)

• (to keep it simple!)

9

Chart example

Up to 4 different minima Up to 4 different minima boxes on 1 chart!boxes on 1 chart!

Conventional NPA

36

18

LATERAL VERTICAL

LOCLOC/DME

VORVOR/DME

NDBNDB/DME

Description System Performance Approach conducted to a MDA/MDH Lateral Guidance based on ground based NAVAIDS As Displayed /

MDA/MDH

FAFFAF

Step Down Fix

11

0.3NM (95%)

RNP APCH with CDFALATERAL VERTICAL

Description System Performance

MDA/MDH

Approach conducted to a MDA/MDH Lateral Guidance only based on GPS (with RAIM) GPS (RAIM)

36

18FAFFAF

Minima Line: LNAV

Step Down Fix

12VNAV: 20-27

Baro VNAV

0.3NM (95%)

GPS

APV Baro ApproachLATERAL VERTICAL

Description System Performance

DA/DH

Approach conducted to Decision Altitude / Height Lateral guidance based on GPS (with RAIM) and vertical guidance based on Baro

GPS (RAIM) and Barometric altimetry

36

18FAFFAF

Minima Line: LNAV/VNAV

13

APV SBAS Approach

Description System Performance Approach conducted to a Decision Altitude / Height Lateral and vertical guidance based SBAS GPS + SBAS

HAL: 40m

GPS+

SBAS

LATERAL VERTICAL

DA/DH

36

18FAPFAF

Minima Line: LPV

VAL: 50m

GPS + SBAS

14

AMC 20-27 requirements (VNAV)• Multi-sensor system using GNSS approved in accordance with AC20-

130A or ETSO-C115b / TSO-C115b

• GNSS sensor approved in accordance with ETSO-C129 / TSO-C129 Class B1, C1, B3, C3 or ETSO-C145 / TSO-C145 class Beta, operational class 1, 2 or 3

• Air Data Computer (paragraph 6.2.2)

• Nonnumeric vertical deviation display, allowing the fight crew to readily distinguish if the vertical deviation exceeds ±75 feet

• If the nonnumeric display does not permit the fight crew to readily distinguish excessive vertical deviations, the approach must be conducted with the flight director and/or the autopilot and a numeric display should allow the pilot to readily distinguish if the vertical deviation exceeds ±75 feet

15

AMC 20-27 requirements

The PANS OPS (ICAO Doc 8186, Volume III) nominal obstacle clearance margin, excluding the additional buffer for abnormal operation, is 246 ft.

16

AMC 20-27 certification memo 1/2• EASA CM - AS – 002 Issue 01 Section 7: ACCEPTANCE OF

PREVIOUS DEMONSTRATION OF COMPLIANCE WITH FAA AC 20-129 FOR CREDIT FOR AMC 20-27 AIRWORTHINESS AND OPERATIONAL APPROVAL

The AFM should include a limitation that BARO-VNAV approaches to airfields at elevations above 5000 ft (MSL) are not permitted

• EASA CM - AS – 002 Issue 01 Section 5: THE USE OF GNSS/SBAS GEOMETRIC ALTITUDE AS A SOURCE OF ALTITUDE FOR APPROACHES TO LNAV/VNAV MINIMA

Standalone: ETSO-C146c Class Gamma, operational class 2 or class 3

Integrated: ETSO-C145c class Beta, operational class 2 or class 3

the flight crew should be able to retrieve an approach to LNAV/VNAV minima only when the approach has been appropriately coded, i.e. a GNSS/FMS indicator of ‘A’ in the ARINC 424 coded Navigation Database

17

AMC 20-27 certification memo 1/2• EASA CM - AS – 002 Issue 01 Section 6: PROVISIONING OF

STEERING AND MONITORING SIGNALS WITH BAROMETRIC ANGULAR VERTICAL DEVIATIONS AS OPPOSED TO THE LINEAR DEVIATIONS ASSUMED IN AMC 20-27→ alternate means of monitoring to be proposed by applicant

→ project specific Certification Review Item (CRI) will be issued

18

AMC 20-28 requirements (LPV)• Status: Comment Review Document (CRD)

• Final Approach Segment

• Standalone: ETSO-C146 Class Gamma, operational class 3

• Integrated: ETSO-C145 class Beta, operational class 3

• Class D: ETSO-C146 Class Delta, operational class 4

• FTE: vertical guidance from 700ft HAT to DA(H) should be stable within ½FSD where FSD=±0.25 x (glide path angle)

→ FTE considered ILS look-alike

• Display of distance to threshold + “Vector to Final” function

The case for RNP APCH• Safety

– Vertically guided approach allows stabilized approaches with standard crew ops procedures

• Reduces runway excursions caused by unstabilized approach– Improved situation awareness reduces CFIT risk– Reduced pilot workload compared to conventional step-down

approach and CDFA– Better obstacle design criteria

(low temperature protection in LNAV/VNAV procedure design)

• Improved Access– No dependence on ground based Navaids

• Low Cost • Reduced minima

– For example DH as low as 200ft based on SBAS LPV– Potential for straight-in instead of offset approach (due to reduced

obstacle clearance surfaces from RNP and/or lack of navaid siting problems)

20

IATA-EUROCONTROL survey

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Enhan

ced V

ision

System

(EVS)

LPV S

BASGBAS

FANS 1/A - V

DL Mod

e 2

FANS 1/A H

FDL

Headu

p Disp

lay (H

UD)

ATN - VDL M

ode 2

Electro

nic Flig

ht Bag

(EFB)

FMS WPR

ADS-C

FANS 1/A SatC

om

FANS 1/A - A

CARS VDL M

ode A

Other M

ulti-F

uncti

on D

isplay

(MFD) fi

tted

RNP AR A

pproa

chADS-B

OUT

Fixed R

adius

Transit

ion (F

RT)

APV Baro V

NAV (LNAV - V

NAV)

Requir

ed Tim

e of A

rrival

(RTA)

ARINC 62

3

RNP App

roach

(LNAV)

8kHz3

3 VHF ra

dios

Fixed R

adius

Turn (R

F)

Multi M

ode R

eceiv

er - M

MRRNAV 10

GNSSMODE S

ACARS

RNAV 1 / P

-RNAV

RNAV 5IN

S - IRS

DME - DME po

sition

upda

te

Autothr

ust (A

-THR)

Autopil

ot - F

light

Directo

r VNAVEFIS

Autopil

ot - F

light

Directo

r LNAVFMS

Deg

ree

of E

quip

age

Available Planned Not Available

LNAV status – 12th September 2012

Nb of minima :Nb of minima :TODAY312 implemented (20%)395 planned (25%)End 2016682 implemented (43%)25 planned (1%)

LNAV/VNAV status – 12th Sept. 2012

Nb of minima :Nb of minima :TODAY137 implemented (9%)268 planned (17%)End 2016384 implemented (24%)21 planned (1%)

LPV status – 12th September 2012

Nb of minima :Nb of minima :TODAY21 implemented (1%)353 planned (22%)End 2016337 implemented (21%)37 planned (2%)

There is a need for support to:• Better understand PBN and RNP APCH• Achieve global approval of GPS usage first• Find a way through ICAO provisions• Get guidance for implementationThis is what the following Support Groups are here for:• ICAO PBN TF• EUROCONTROL RAISGImplementation projects:• co-funded by EUROCONTROL and EC (Aurigny, Beluga, Mielec)• funded by EC/GSA (GIANT, GIANT2, ACCEPTA, FillGAPP, SHERPA)• funded by SESAR JU (5.6.3 and call for interest)• Supported by EUROCONTROL and IATA (e.g. in Greece)

Support to implementation initiatives

EUROCONTROL PBN Approach Map Tool:

https://extranet.eurocontrol.int/http://prisme-newgis.hq.corp.eurocontrol.int/pbn/

QuestionsQuestions