user guide procure it version 3 - … · procure it version 3 user guide procure it version 3 user...
TRANSCRIPT
William Li | A/Senior Business Documentation Standards Officer NSW Procurement NSW Department of Finance and Services T 02 9372 8713 F 02 9372 8889 E [email protected]
USER GUIDE
PROCURE IT Version 3.1
Issued on 24 October 2013
COPYRIGHT
This Procure IT version 3.1 User Guide has been prepared by NSW Procurement and Legal
Services Branch for and on behalf of the Crown in right of the State of New South Wales. This
User Guide is protected by Crown copyright.
© State of New South Wales – NSW Procurement, for and on behalf of the Crown in right of the
State of New South Wales, 2001.
All rights reserved. No part of this User Guide may be produced by any process, electronic or
otherwise, in any material form or transmitted to any other person or stored electronically in any
form, without the prior written permission of the State of New South Wales, except as permitted
under the Copyright Act 1968.
.
SCHEDULE OF DOCUMENT AMENDMENTS
Revision
Number
Date Update Description
3.0 28 February 2011 Document Original - first publication
24 April 2012 Change of Department name and logo
3.1 24 October 2013 • It is aligned with legislative changes, e.g. removal of
reference to SCCB, agency head is now the
Contract Authority and SME policy framework has
been updated.
• Management fee clauses removed.
• Annexure 6 Management fee Audit Confidential
Disclosure Agreement removed.
• New clause 25.2 (c) inserted in Customer Contract
• New clause 19.1 (c) inserted in Head Agreement.
PROCURE IT Version 3 User Guide
PROCURE IT Version 3 User Guide
Table of Contents
THE PROCURE IT FRAMEWORK 5
1. HEAD AGREEMENT 6
2. CUSTOMER CONTRACT (PANEL ARRANGEMENT ) 6
3. CUSTOMER CONTRACT (NON-PANEL ARRANGEMENT ) 7
PART 1 - HEAD AGREEMENT 8
IMPORTANT ASPECTS OF THE HEAD AGREEMENT 9
PREPARING AND EXECUTING A HEAD AGREEMENT 13
PRE-TENDER ACTIONS 14
POST-TENDER ACTIONS 15
PART 2 – CUSTOMER CONTRACT 17
ENTERING INTO A CUSTOMER CONTRACT (NON-PANEL ARRANGEMENTS) 17
IMPORTANT ASPECTS OF THE CUSTOMER CONTRACT 18
CHANGE CONTROL 28
PREPARING AND EXECUTING A CUSTOMER CONTRACT 33
PART 3 – DICTIONARY 45
PART 4 - MODULES 47
PROCURE IT Version 3.1 User Guide 5
PROCURE IT Version 3.1 User Guide
The Procure IT Framework
NSW Procurement Board has issued a Direction to require all NSW Government
agencies to use the Procure IT Framework for the acquisition of information and
communications technology related Products and Services.
The Procure IT Framework for panel arrangement is made up of:
• Part 1 – Head Agreement
• Part 2 – Customer Contract (including General Order Form)
• Part 3 – Dictionary
• Part 4 – Modules (including Module Order Forms)
The Procure IT Framework for non panel arrangement is made up of:
• Part 2 – Customer Contract (including General Order Form)
• Part 3 – Dictionary
• Part 4 – Modules (including Module Order Forms)
The Procure IT Framework is designed so that Products and Services can be acquired:
(a) as a result of a panel arrangement where an entity acts as the Contract
Authority and establishes a master purchasing arrangement (i.e. Standing
Offer) where a number of Contractors agree to offer certain Products and/or
Services to Eligible Customers at pre-agreed Prices and on pre-agreed core
terms and conditions, for a defined Term (Panel Arrangement ); or
(b) using an alternate procurement process that does not involve a Panel
Arrangement (Non-Panel Arrangement ).
The Procure IT Framework provides for the use of three different types of
Agreement/Contract:
PROCURE IT Version 3.1 User Guide 6
PROCURE IT Version 3.1 User Guide
1. Head Agreement
2. Customer Contract (Panel Arrangement)
3. Customer Contract (Non-Panel Arrangement)
1. Head Agreement
The agreement between the Contract Authority and the Contractor contains:
• Part 1 – Head Agreement (including Annexures)
• Part 2 – Customer Contract (including Schedules specified to apply in Annexure
1 of the Head Agreement)
• Part 3 – Dictionary
• Part 4 – any Modules and Module Order Forms specified to apply in Annexure 1
of the Head Agreement
2. Customer Contract (Panel Arrangement)
The contract between the Customer and the Contractor where the Products and
Services are purchased under a Panel Arrangement contains:
• Annexure 3 (Product and Service List) to the Head Agreement (if applicable);
• Part 2 – Customer Contract (including any Schedules that are stated as forming
part of the Customer Contract in Item 9 of the General Order Form);
• the Agreement Documents as itemised in Schedule 2 to the Customer Contract
(if any);
• any Additional Conditions (if applicable); and
• Part 3 - the Dictionary; and
• any Modules that are stated as forming part of the Customer Contract in Item 8
of the General Order Form and the corresponding Module Order Forms.
PROCURE IT Version 3.1 User Guide 7
PROCURE IT Version 3.1 User Guide
3. Customer Contract (Non-Panel Arrangement)
The contract between the Customer and the Contractor where the Products and
Services are purchased without a Head Agreement contains:
• Part 2 – Customer Contract (including any Schedules that are stated as forming
part of the Customer Contract in Item 9 of the General Order Form);
• the Agreement Documents as itemised in Schedule 2 to the Customer Contract
(if any);
• any Additional Conditions (if applicable); and
• Part 3 - the Dictionary; and
• any Modules that are stated as forming part of the Customer Contract in Item 8
of the General Order Form and the corresponding Module Order Forms.
PROCURE IT Version 3.1 User Guide 8
PROCURE IT Version 3.1 User Guide
Part 1 - Head Agreement
Where the Procure IT Framework is used for a Panel Arrangement, the Contract
Authority will undertake a procurement process and the successful Contractor(s) will
sign the Head Agreement and go onto the panel. A panel may contain only one
Contractor. The Head Agreement requires that all Eligible Customers who acquire
Products and Services under the Panel Arrangement acquire the Products and
Services using the form of Customer Contract that is set out in the Procure IT
Framework.
The Head Agreement describes the relationship between the Contract Authority and
the Contractor for the administration of the Panel Arrangement, including:
• the Products and Services that can be acquired under the Panel Arrangement;
• how those Products and Services can be updated during the Term;
• the Pricing for the Products and Services;
• which entities are entitled to acquire Products and Services under the Panel
Arrangement;
• which Approved Agents can be used by the Contractor to supply the Products
and Services;
• the Term of the Panel Arrangement;
• the minimum insurance requirements;
• any Performance Guarantee that might apply to Customer Contracts entered
into under the Head Agreement; and
• the general terms and conditions applicable to the relationship
PROCURE IT Version 3.1 User Guide 9
PROCURE IT Version 3.1 User Guide
Important Aspects of the Head Agreement
Survival Clause
This section provides that where a Customer has entered into a Customer Contract
with a Contractor during the Term the Customer may, provided that the Customer first
obtains the written approval of the Contract Authority, and provides a copy of that
approval to the Contractor:
(a) acquire additional Products or Services; or
(b) acquire maintenance or support Services
even after the expiration or termination of the Head Agreement. The consequence of
non-compliance with these conditions is that the purchase will be out of contract. This
means that the Customer will lose any protection under the Head Agreement and
Customer Contract for such things as unsatisfactory product performance and
unsatisfactory service delivery. The Customer will also be unable to rely on the
Contract Authority to invoke the dispute resolution clauses against the Contractor.
Nominee Purchaser
Eligible Customers may use a Nominee Purchaser to enter into a Customer Contract
on its behalf. The Contractor cannot refuse to enter into that Customer Contract solely
on the basis that the Customer Contract will be signed by the Nominee Purchaser as
agent for the Eligible Customer under certain conditions.
It is vitally important for Eligible non government bodies and Eligible Customers to
make it clear that they are intending to purchase Products and Services pursuant to a
Customer Contract made under the Head Agreement in order to gain the contractual
benefits.
Formation of Customer Contract under Head Agreement
Cl 4.5 provides that: A Customer Contract between a Contractor and an Eligible
Customer will be created under this Head Agreement upon:
PROCURE IT Version 3.1 User Guide 10
PROCURE IT Version 3.1 User Guide
• the Eligible Customer and the Contractor agreeing the Order Details in the
Order Documents, and any Additional Conditions for the Products and/or
Services; and
• the Eligible Customer and the Contractor signing the General Order Form,
and will comprise the documents listed in clause 3.8 of Part 2.
Cl 4.6 provides that: The Parties agree that each time the Customer and the Contractor
enter into a Customer Contract, a separate agreement is created between the
Contractor and the Customer which takes effect on the date the General Order Form is
signed by the Eligible Customer and the Contractor.
Cl 4.7 provides that: The Contractor has no obligation to supply any Product or Service
to an Eligible Customer until a Customer Contract for the supply of that Product or
Service has been created in accordance with clause 4.5.
Insurance
There is a stipulated amount of insurance provided in Cl 10 in the Head Agreement:
• $10,000,000 in respect of each claim and for the total aggregate liability for all
claims for the period of cover - public liability insurance
• $10,000,000 for the total aggregate liability for all claims for the period of cover -
product liability insurance
• workers’ compensation insurance in accordance with applicable legislation for
all the Contractor’s employees.
It is possible for the Customer to request that the Contractor increase the amount of
cover under any of the policies of insurance stated above. Note that these amounts
cannot be reduced.
Performance Guarantee
For panel arrangements, performance guarantees will usually only be required under
the Head Agreement only. The performance guarantee required under the Head
Agreement will apply to all Government Customers automatically, but Eligible non-
PROCURE IT Version 3.1 User Guide 11
PROCURE IT Version 3.1 User Guide
government bodies will have to enter into their own separate arrangements with the
Contractor.
If the Contract Authority has not required a Performance Guarantee under the Head
Agreement, the Customer may only require one under a Customer Contract if it obtains
the Contract Authority’s consent.
During the term of the agreement the Contract Authority may, on reasonable grounds,
request that the Contractor arrange for a guarantor “approved in writing by the Contract
Authority” to enter into an agreement with the Contract Authority.
There is a Performance Guarantee template located in Annexure 5 of the Head
Agreement and Schedule 9 of the Customer Contract. It is not necessary for these
exact forms to be used.
For non-panel arrangements the Customer may require a performance guarantee.
However, they should be used only where there is a perceived high risk involved in the
purchase e.g. where the Contractor or Approved Agent is located overseas or the
purchase is of a kind that is unique or requires a higher level of technical support. It is
unreasonable to require a Contractor to provide a Performance Guarantee for all
purchases of IT Products and/or Services.
If, when requested, the Contractor does not provide a Performance Guarantee, then
this may be a ground for termination.
Liability
The Contractor’s liability to the Contract Authority will not exceed $250,000 in
aggregate for any and all claims that arise out of, or in connection with, this Head
Agreement.
The Contractor has no financial cap on its legal liability where that liability arises from:
• bodily injury,
• loss of, or damage to, tangible property,
• infringement of a third party’s intellectual property rights or
• breach of the Contractor’s obligation of confidence
PROCURE IT Version 3.1 User Guide 12
PROCURE IT Version 3.1 User Guide
Neither Party is liable to the other Party for any Consequential Loss. Liability will be
reduced proportionately to the extent that either Party contributes to any damage.
Indemnity
The Contractor indemnifies the Contract Authority in the event of any claim against it by
a third party. The Contractor’s liability to the Contract Authority in contract is capped to
$250,000 in aggregate for any and all claims that arise out of, or in connection with, this
Head Agreement, except:
• bodily injury,
• loss of, or damage to, tangible property,
• infringement of a third party’s intellectual property rights or
• breach of the Contractor’s obligation of confidence
Dispute Resolution
All disputes will be solved at a Senior Executive level within 5 days after the aggrieved
Party has submitted an Issue Notice to the other Party. Each Party will be responsible
for their own costs.
If a dispute is not resolved at a Senior Executive Level then the dispute can be
resolved through Expert Determination, subject to the amount in dispute being less
than $100,000.
Termination
Either Party may terminate the Head Agreement for convenience by providing the other
Party at least 60 days notice in writing.
The Head Agreement can also be terminated if the Contractor breaches a provision of
the Head Agreement or in the event that the Contractor becomes insolvent.
PROCURE IT Version 3.1 User Guide 13
PROCURE IT Version 3.1 User Guide
Preparing and Executing a Head Agreement
PROCURE IT Version 3.1 User Guide 14
PROCURE IT Version 3.1 User Guide
Pre-Tender Actions
Step 1: Review Parts 1, 2 and 3
Familiarise yourself with the terms and conditions of the Head Agreement and
any future Customer Contracts.
Step 2: Complete the following items in Annexure 1 Agreemen t Details:
Item 1 Head Agreement Number
Item 2 Contract Authority and Authorised Representa tive
The Contract Authority is the Head of a Government agency which may
procure goods and services for that agency or for other government
agencies consistent with any applicable policies and directions of the
Board, the terms of its accreditation (if any) by the Board, and the
principles of probity and fairness.
Item 4A Modules
Tick any modules which will apply in Item 4A
Item 4B Schedules
Tick any Schedules to the Customer Contract which will apply in Item 4B
Item 7 Insurance Policy Amount (cl 10 of Part 1)
For all Panel arrangements:
• If different from minimum $10 Million, enter Public Liability
Insurance level required in Item 7(a)
• If different from minimum $10 Million enter Product Liability
Insurance Level required in Item 7(b)
Where Services are to be provided:
• If different from minimum $1 Million enter Professional Indemnity
Insurance level in Item 7(c)
Item 8 Codes, Policies, Guidelines and Standards an d other Laws
List policies, etc which the Contractor must comply with. For example:
PROCURE IT Version 3.1 User Guide 15
PROCURE IT Version 3.1 User Guide
• Code of Practice for Procurement
• Implementation Guidelines NSW Government Procurement 1999
• Environmental Management Procurement Guidelines
• Occupational Health and Safety Procurement Guidelines
• SME Policy Framework
Item 9 Expert Determination Amount (cl 18 of Part 1 )
Enter Expert Determination Amount in item 10. If no amount is entered
cl 18.11 provides that the default amount of $100,000 will apply.
Item 10 Performance Guarantee (cl 11.1-11.8 of Part 1)
Specify if a Performance Guarantee is required in Item 10.
Under cl 11.2 any performance guarantee will apply automatically to all
Customer Contracts signed by Customers (other than Eligible non-
Government Bodies).
Post-Tender Actions
Step 3: Complete Annexure 1, 2 and 3
These Annexures are completed by the contract officer who is preparing the
panel arrangement.
Annexure 1 Head Agreement Details
After tender evaluation, the following items need to be completed:
• Item 3 Contractor and Authorised Representative Det ails
• Item 6 Term
• Commencement date of term
• Last day of term
• Period of extended term (if any)
• Item 10 Performance Guarantee
• May be required for some successful tenderers
PROCURE IT Version 3.1 User Guide 16
PROCURE IT Version 3.1 User Guide
• If required after tender process, tender conditions should
state that performance guarantee might be required
• Item 11 List of Approved Agents (if any)
• Item 12 Liability to Provide Sales Reports
Annexure 2 Head Agreement Documents (if any)
List and append additional documents which will form part of the
agreement, if any. Contract officers may wish to include:
• communications between the Contract Authority and the
Contractor
• the tender received from the Contractor
Annexure 3 Product and Service List
Step 4: Obtain completed Annexures 4 and 5 (if required)
Annexure 4: Deed Poll – Approved Agents
Each Approved Agent (if any) is to complete a Deed Poll.
Annexure 5: Performance Guarantee
To be completed if decided that a Performance Guarantee is required.
The Performance Guarantee is completed by the Contractor and the
Guarantor.
Annexures 6 is not relevant at this stage
Step 5: Pre-complete Schedule 1 to Part 2 (General Order F orm)
(The following Items need to be completed when establishing the panel)
Item 7: Head Agreement
Item 8: Modules
Item 9: Schedules
Step 6: Execute Head Agreement
Prepare and sign the Execution Page.
The Head Agreement is executed as a Deed.
PROCURE IT Version 3.1 User Guide 17
PROCURE IT Version 3.1 User Guide
Part 2 – Customer Contract
The Customer Contract defines the relationship between the Customer and the
Contractor for the supply of Products and Services as described in the Customer
Contract. Where the Customer Contract is made under the Head Agreement:
a. the Products and Services that can be acquired, the Prices at which they can
be sold, and the degree to which the terms and conditions can be varied are
limited by the terms of the Head Agreement; and
b. the Customer is entitled to the benefits of any arrangements that have been
made by the Contract Authority under the Head Agreement in respect to
insurance and any Performance Guarantee.
Entering into a Customer contract (Panel Arrangemen ts)
In order for a Customer Contract to be entered into under the Head Agreement, the
Head Agreement must be cross referenced to Item 7 of the General Order Form.
Entering into a Customer contract (Non-Panel Arrang ements)
For non panel arrangements the Customer Contract is entered into upon the execution
page being signed by both parties (i.e. Contractor and the Customer).
The General Order Form must also be signed.
PROCURE IT Version 3.1 User Guide 18
PROCURE IT Version 3.1 User Guide
Important Aspects of the Customer Contract
Formation of Customer Contract under a Panel Arrang ement
A NSW Procurement officer will normally complete Item 7 of the General Order Form.
If Item 7 is not completed, the Customer will not receive the full benefits and protection
offered by the Head Agreement and Customer Contract.
Clause 3.3 states that parties only need to sign the General Order Form to create the
Customer Contract under a panel arrangement and do not need to sign the Customer
Contract itself.
A Customer Contract between the Contractor and Customer is created upon:
a. the Order Details and any Additional Conditions being completed and agreed by
the parties; and
b. the General Order Form being signed by the Customer and Contractor. Note
that the Customer and Contractor do not need to sign execution page of the
Customer Contract.
Formation of Customer Contract under a Non Panel Ar rangement
The Customer Contract is entered into when the execution page of the Customer
Contract and the General Order Form are signed by both parties (i.e. Contractor and
the Customer).
Note: The following guidelines apply to Customer Contract for both panel arrangement
and non panel arrangement
Inconsistencies
Pursuant to cl 3.9 of the Customer Contract, in case of conflict between documents
comprising the Customer contract, the order of priority of the documents is as
contained in cl 3.8 as follows:
a. any Modules that are stated as forming part of the Customer Contract in Item 8
of the General Order Form and the corresponding Module Order Forms;
b. any Schedules that are stated as forming part of the Customer Contract in Item
9 of the General Order Form other than Schedule 1 (General Order Form),
PROCURE IT Version 3.1 User Guide 19
PROCURE IT Version 3.1 User Guide
Schedule 2 (Agreement Documents), Schedule 3 (Service Level Agreement) or
Schedule 12 (PIPP);
c. any Additional Conditions (if applicable);
d. these clauses 1 to 26;
e. Part 3, the Dictionary;
f. any PIPP agreed by the Parties based on Schedule 12 (PIPP);
g. any Service Level Agreement agreed by the Parties based on Schedule 3
(Service Level Agreement);
h. all other Order Documents;
i. Annexure 3 to the Head Agreement (if applicable); and
j. the Agreement Documents (if any)
Liquidated Damages
For this provision to apply, the Parties must specify in Item 21 of the General Order
Form or the Payment Implementation and Project Plan (PIPP) the “Due Date” for the
performance of certain obligations under the Customer Contract.
Liquidated Damages (LDs) are payable by the Contractor to the Customer upon a
delay in meeting a Due Date for a LD Obligation.
LDs are a substitute for damages which might otherwise be awarded by a court in
cases of delay. By agreeing on LDs, the Parties agree at the outset the rate or how
much damages will be payable upon the failure by the Contractor to meet a Due Date.
To be enforceable LDs must be a genuine pre-estimate of the damage likely to be
suffered. The method for calculation of LDs will be important in demonstrating that the
damages claimed are based on a genuine pre-estimate. In calculating LDs, tangible
costs in relation to project delay should be considered (e.g. salaries, rents, daily
revenue losses) and legal advice should be sought.
The Customer is not allowed to terminate the Customer Contract immediately if parties
have agreed in Item 21 of the General Order Form that LD’s will be payable for the late
completion. However, if the Contractor has failed to pay the required LDs within the
specified liquidated damage payment period, then the Customer may terminate the
Customer Contract.
PROCURE IT Version 3.1 User Guide 20
PROCURE IT Version 3.1 User Guide
Mutual Warranties
The Contract Authority, Customer and the Contractor have provided mutual warranties
to each other on things like acting reasonably, acting in good faith and working in a
collaborative manner.
Acceptance Testing
Acceptance Testing is carried out to find errors in a solution that is being developed.
Testing should be undertaken throughout all stages of the development cycle.
Acceptance Tests are critical in that they allow the Customer to determine whether the
Product conforms to the Contract Specifications, works in the Customer’s designated
environment and meets the requirement needs of the Customer.
There are deemed Acceptance provisions. Deemed Acceptance occurs:
• 2 Business Days after delivery, if Order Form does not state that Acceptance
Testing is required (i.e. Default is that no Acceptance Tests are required)
• on the last day of the Acceptance Test Notification Period, if no notice of
rejection or conditional acceptance received
• the Customer fails to perform the Acceptance Tests, other than through the fault
of the Contractor
• the Customer uses the Deliverable in production environment or for business
purposes without the prior written consent of Contractor
The Contractor gets one attempt to re-submit the Deliverable for further Acceptance
Testing prior to the Customer being able to reject the Deliverable.
Payment and Invoicing
If time for payment is not stated in the Order Documents and/or Item 14 of the General
Order Form, the Customer must pay the Contract Price:
• on Actual Acceptance Date (AAD) for Products
• monthly in arrears for Recurring Services other than Services provided under
Modules 2 and 5
• annually in advance for Services provided under Modules 2 and 5
PROCURE IT Version 3.1 User Guide 21
PROCURE IT Version 3.1 User Guide
Performance Guarantee
A Performance Guarantee is agreed between the Contract Authority and the Contractor
under the Head Agreement. It will automatically apply to all Customer Contracts made
under the Head Agreement. If the Contract Authority has not required a Performance
Guarantee under the Head Agreement, the Customer may only require one under a
Customer Contract if it obtains the Contract Authority’s consent.
If there is no Head Agreement, the Customer and Contractor can negotiate the
Customer’s requirement for a Performance Guarantee in the form of Schedule 9 of the
Customer Contract.
Financial Security
The Contract Authority can not ask for a financial security as part of a panel
arrangement. A Customer may require a financial security under a Customer Contract.
Financial Security must be in form of the agreement in Schedule 10, or in the standard
form that is usually provided by the issuing entity.
Whether or not a Financial Security should be required depends upon the Customer
establishing that there are reasonable grounds for the requirement. These may
include:
• the type of Product or Service to be procured and the level of complexity
involved in the procurement;
• the Contractor’s experience in providing such Deliverables;
• the financial viability of the Contractor;
• the Contractor’s dependence on Specified Personnel, third parties or sub-
contractors to fulfil the requirement; or
• the Contractor’s capacity and resources.
Insurance
The levels of insurance cover are agreed between the Contract Authority and the
Contractor under the Head Agreement. However, if a Customer requires a higher
insurance cover than what is provided in the Head Agreement, the Customer is able to
specify the higher amount in the General Order Form.
PROCURE IT Version 3.1 User Guide 22
PROCURE IT Version 3.1 User Guide
Limitation of Liability
Limiting or capping liability is achieved by placing an upper limit on the liability the
Contractor would otherwise have under the Contract. The innocent Party will be
responsible for some of the losses in the event that the limit of liability is exceeded.
Customers will need to ensure that they cover this risk either with appropriate
insurances or ensure that they are able to manage this risk appropriately under the
terms of the Contract. Otherwise such risks, if realised, will be a liability that the
Customer must bear under its allocated budget.
There is no requirement to conduct a risk assessment to determine the level of cap. Cl
18.1 provides that a Contractor’s liability to the Customer is:
a) limited in the aggregate for all claims arising out of the contract.
b) based on a multiple of the Contract Value of the type of Product or
Service from which the claim arose (not the total contract price payable
under the Customer Contract), with a minimum of $100,000
Note that Contract Value refers to individual value of products or services but not to the
total Contract price.
For example if the Contract is for the purchase of computers for $1 Million and software
for $ 500,000, the contract price is $1.5 million. The contract value is $1 Million for
computers and $500,000 for the software as separate items. If there is a fault in the
software the contractor’s liability is limited to 2 times $500,000.
The above default applies for all transactions except “Prescribed Use” and “over $20m
contract value”. In these cases, the parties must agree a new cap.
The cap is divided in three categories:
• Non-Recurring Services or Product, two times the Contract Value;
For example, systems integration services (i.e. combining hardware and
software to complete a project) where the cost of the hardware is $1 Million and
the cost of the software is $500,000. If there is a fault in the software the
contractor’s liability is limited to 2 times $500,000.
• Short Term Recurring Services, the Contract value;
PROCURE IT Version 3.1 User Guide 23
PROCURE IT Version 3.1 User Guide
For example, if an IT consultancy service for a period of less than 12 months is
being procured and the value is $500,000, then the contractor’s liability for a
claim will be $500,000.
• Recurring Services other than Short Term Recurring Services.
For example,
(a) If the claim arose after 12 months, then it is the value of the services for a
period of the previous12 months.
(b) If the claim arose before the first 12 months expires, then the amount is
equal to the monthly average times 12.
Capped Liability under Procure IT is subject to a number of exclusions under clause
18.5, e.g. personal injury, breach of privacy, confidence and infringement of IP.
Any kind of fees, LD’s or losses should be taken into account as offset to any claims of
liability.
Indemnity
Each Contractor’s indemnity is subject to the exclusion of consequential loss,
proportionality and the obligation to mitigate losses. The Contractor is provided with
the right to defend any third party claim (subject to government policy to the contrary)
or reasonably agree to the final settlement of the third party claim.
The privacy and IP claim indemnity have uncapped liability, however, there are a
number of exceptions to the IP indemnity as provided in clause 19.5, e.g.
any open source software that forms part of the Del iverable;
any Intellectual Property Rights including Moral Ri ghts, material or thing provided by any person other than the Contrac tor or its Personnel, including any Customer Supplied Items;
any modification of the Deliverable by any person o ther than the Contractor or its agents.
Third party indemnity claims are subject to the capping clause but is also subject to the
uncapped heads of damage, e.g. a third party claim arising from a defective product
would have a cap of 2 times contract value, unless the claim is for death or bodily
injury.
PROCURE IT Version 3.1 User Guide 24
PROCURE IT Version 3.1 User Guide
Intellectual Property
The default position is in favour of the Contractor owning the IP in software developed
under Procure IT. Customers may still be able to retain intellectual property based on
the following reasons (as referred to in the Commonwealth Guidelines):
• State security and/or strategic interest
• law enforcement
• Public interest
• where the IP applies to a critical Government ICT system
• where the IP includes personal information
• where the underlying IP is wholly or predominantly owned by the
Commonwealth before entering into the service agreement.
Where the contractor retains ownership of the IP, the Customer retains a transferable,
irrevocable royalty free license to use the IP.
A Customer should remember that any IP it owns is an asset, which must be
inventoried and protected proactively from infringement.
Dispute Resolution
Clause 24.11 prescribes a default figure over which the expert determination process
will not be used to resolve the dispute. The default figure for the Customer Contract is
$ 250,000. The Parties can put in any figure (which may be higher or lower than
$250,000) in item 41 of the General Order Form. The default figure applies if Item 41 is
not completed. Any dispute the value of which is less than $ 250,000 must be
determined by expert determination.
Clause 24.12 provides that where Parties unable to agree on the amount claimed, the
amount in dispute will be calculated by way of average.
Clause 24.13 provides that in the event, a party has terminated the Customer Contract
for a substantial breach or fundamental breach, the dispute resolution process does not
apply.
PROCURE IT Version 3.1 User Guide 25
PROCURE IT Version 3.1 User Guide
Termination
Termination for convenience is only available to the Customer. Either Party can
terminate for cause.
PROCURE IT Version 3.1 User Guide 26
PROCURE IT Version 3.1 User Guide
Customer Contract - Schedules
Schedule 1 General Order Form
This Schedule includes the order details that relevant to the Customer Contract. It must
be signed as an agreement.
Schedule 2
This Schedule is to include all documentation (including any supplemental terms and
conditions agreed to by the Customer, accepted tenders, offers or quotes from the
Contractor, and any letter of acceptance or award issued by the Customer) between
the Customer and the Contractor.
Schedule 3
This is merely a guide for Service Level Agreement
Schedule 4
This Schedule lists the procedure for changing Project Implementation and Payment
Plan or any part of the Customer Contract.
Schedule 5
This Schedule contains Escrow Deed.
Schedule 6
This Schedule is a Deed Poll enabling the Approved Agents to provide the Products
and/or Services to Customer on behalf of the Contractor under the Customer Contract.
Schedule 7
It is a form of Statutory Declaration for Subcontractor to complete.
Schedule 8
This Schedule contains Deed of Confidentiality.
Schedule 9
This Schedule sets out the Performance Guarantee.
Schedule 10
This Schedule sets out details of financial security.
PROCURE IT Version 3.1 User Guide 27
PROCURE IT Version 3.1 User Guide
Schedule 11
This Schedule sets out the dispute resolution procedures.
Schedule 12
Only meant as a guide, it includes Order Details relating to the implementation of a
project and associated payment arrangements which is included in a Customer
Contract if stated in Item 20 of the General Order Form.
PROCURE IT Version 3.1 User Guide 28
PROCURE IT Version 3.1 User Guide
Change Control
The Customer must be aware of:
1. Schedule 4 Variation Procedures; and
2. Protected Clauses (apply to panel arrangement): the Contract Authority’s
written consent must be obtained prior to varying a Protected Clause:
a) Additional Conditions (clause 3.2(b))
b) Clause 3.6 and 3.7
c) Intellectual property Rights (clause 13)
d) Privacy (clause 15)
e) Insurance (clause 16)
f) Liability (clause 18)
g) Indemnities (clause 19)
h) Conflict of Interest (clause 20)
i) Notice of Change in Control (clause 23.3)
j) Dispute Resolution (clause 24 and Schedule 11)
k) Termination (clause 25)
l) Assignment and Novation (clause 26.3 to 26.6)
m) Applicable law (clause 26.18)
PROCURE IT Version 3 User Guide 33
PROCURE IT Version 3.1 User Guide
Preparing and Executing a Customer Contract
PROCURE IT Version 3 User Guide
34
PROCURE IT Version 3.1 User Guide
Preparing and Executing a Customer Contract under P anel
Arrangement
Step 1
a. Browse Annexure 3 of Head Agreement to check Products and Services that
can be acquired and the prices at which they can be sold via smartbuy.
b. Browse through the Customer Contract template for terms and conditions under
which the Customer and Contractor must perform their obligations.
Step 2 Complete General Order Form (Schedule 1)
There are a number of important provisions in the Customer Contract relevant to
the General Order Form that have been agreed between the Contract Authority and
the Contractor under the Head Agreement. However, some items could be
changed by the Customer in this Schedule 1, e.g.
• Levels of insurance,
• Ownership of Intellectual Property,
• Expert Determination Amount,
• Cap of liability,
• Payment term,
• Deemed period of acceptance if no Acceptance Testing is required,
• Date by which the Performance Guarantee must be provided
The following outlines the important items that the Customer may need to complete,
but please note :
A. If the order is a straight forward and/or low value order for hardware, software
or services where the maximum value of the order can be calculated with
certainty (i.e. the maximum amount payable is set out in the “Total Amount
Payable” box in Item 11, then the Parties may use a shortened version of the
General Order Form and any Module Order Form.
PROCURE IT Version 3 User Guide
35
PROCURE IT Version 3.1 User Guide
The shortened version of the General Order Form must :
• Include all the Items that are set out in clause 3.4 of the Customer Contract. (i.e. Items 1, 4, 7 (if there is a Head Agreement), 8, 10, 11, 12 and 13);
• Include any other Items (if any) that the Parties agree;
• Be in the same form and structure (even if some Items are omitted);
• Ensure that the Items that remain are have the same number or heading as the number of heading in this pro forma General Order Form
• Include the following as a title:
“General Order Form. Schedule 1 to the Customer Co ntract (which is Part 2 of the Procure IT Framework)”
• Include the following text above the signature box;
“This General Order Form is part of the Customer Co ntract and incorporates all Parts, terms and conditions and ot her documents listed in clause 3.8 of Part 2 as if repeated in fu ll in this General Order Form.”
• Be signed by both parties.
• Cross reference and include the relevant Order Details from any Module Order Form and any details from the Module Order Forms that are required to describe the Products or Services.
B. Items 16 to 43 are likely to be needed for large value orders and/or complex
purchases such as software development, systems integration, web services,
managed services, and telecommunications services etc.
If the Parties require one or more of the Items 16 to 43 for any other type of
purchase, then these can be added to the General Order Form.
a. Items 1-6
These items require parties to include names and services address
information and details of authorised representatives.
b. Item 7 Head Agreement
For Panel Arrangement, Item 7 must be completed to include:
PROCURE IT Version 3 User Guide
36
PROCURE IT Version 3.1 User Guide
• Relevant Head Agreement number;
• Terms of the Head Agreement;
• Level of insurance under Head Agreement
• Performance Guarantee, if appropriate
c. Item 8 Modules
Check Item 4A in Annexure 1 of the Head Agreement, tick any Modules
which will apply to the Customer Contract in Item 8
d. Item 9 Schedules (pre filled by NSWP)
Check Item 4B in Annexure 1 of the Head Agreement, tick any Schedules
which will apply to the Customer Contract in Item 9.
Note: If Schedule 2 is ticked, all documentation (including any supplemental
terms and conditions agreed to by the Customer, accepted tenders, offers or
quotes from the Contractor, and any letter of acceptance or award issued by
the Customer) between the Customer and the Contractor must be itemised in
Schedule 2 in descending date order.
Do not use Schedule 9. If required, it has been completed in the Head
Agreement between Contractor Authority and Contractor.
e. Item 11 Common Details
Specify the product, quantity, and unit price for simple purchases.
f. Item 18 Site Inspection and Maintenance
Specify whether the Contractor is to provide a Site Specification. In most
instances the Customer would prepare the Site in accordance with an
approved Site Specification (if there is one) or any other requirements
specified here unless there are particular environmental requirements for the
Deliverable, which the Customer is unable to provide. In which case, if
appropriate, the Contractor should be noted here.
g. Item 21 Liquidated Damages
PROCURE IT Version 3 User Guide
37
PROCURE IT Version 3.1 User Guide
For this provision to apply, Customer must specify here or the PIPP the “Due
Date” for the performance of certain obligations under the Customer
Contract, together with the calculation of the amount.
h. Item 31 Customer’s Compliance with Standards, Co des and Law
In addition to any legislative or policy requirements that the Contractor
should comply with, Customer should also reference those legislative and
policy requirements to which the Customer is subject. Customer should
remember that if it is required to comply with a code, policy or guideline, it
will still be held to account regardless of whether those policies are relevant
to an obligation that has been contracted out.
Standards can be used to benchmark performance expectations under the
Customer Contract and can be referenced in the Service Level Agreement
as a measure of quality. Of greater importance is the warranty given by the
Contractor under clause 9.3 that the Deliverables conform to the standards
specified in the Order Documents.
i. Item 32 Acceptance Testing
Customer needs to specify the period required following delivery of the
Deliverable as required by the order Documents when the Actual Acceptance
Date for a Deliverable occurs, if a Deliverable is not to undergo Acceptance
Tests. The deemed period is 2 business days.
j. Item 34 Intellectual Property
If applicable, the Customer is to specify any IP that the Customer will own.
Unless stipulated to the contrary in here, the default position is in favour of
the Contractor owning the IP in software developed under Procure IT.
k. Item 36 Insurance
The levels of insurance have been agreed between Contract Authority and
Contractor in the Head Agreement. Customer only needs to specify here if a
higher limit of cover is required by the Customer Contract.
l. Item 37 Performance Guarantee
PROCURE IT Version 3 User Guide
38
PROCURE IT Version 3.1 User Guide
This item is not required to complete for panel arrangement. If a performance
guarantee is required, it has been agreed in the Head Agreement. However,
if no performance guarantee is provided in the Head Agreement, the
Customer thinks it is necessary to have one under the Customer Contract,
the Customer needs to obtain Contract Authority’s approval prior to fill in this
item 37.
m. Item 38 Financial Security
Customer needs to specify if a Financial Security is required, and when to be
provided.
n. Item 39 Limitation of Liability
The best estimate of the Contract Value must be inserted here for the
purpose of determining the capped amount of liability, if the maximum
amount that the Customer is legally required to pay is not capable of
calculation.
Alternatively, the Customer can specify different cap of liability here, if it is for
Prescribed Use or over $20m contract value.
o. Item 41 Dispute Resolution
Customer needs to specify the threshold amount for issues to be resolved by
expert determination if default figure in the Head Agreement is deemed not
appropriate.
p. Item 43 Additional Conditions
If the Parties consider that the Agreement does not cover a particular issue
or does not cover the issue to the extent desired by the Parties, they may
insert additional conditions here. A proviso applies in that should the
additional conditions be contrary to a Protected Clause, the Contract
Authority must provide its prior written consent to the additional conditions for
them to be valid and legally enforceable.
PROCURE IT Version 3 User Guide
39
PROCURE IT Version 3.1 User Guide
Step 3 Sign General Order Form
a. The completed General Order Form must be signed as an agreement.
The General Order Form is part of the Customer Contract and incorporates
all Parts, terms and conditions and other documents listed in clause 3.6 of
Part 2 as if repeated in full in this General Order Form.
b. It is optional to execute the Customer Contract. If preferred, parties can
execute the Customer Contract in addition to the signing General Order
Form.
PROCURE IT Version 3 User Guide
40
PROCURE IT Version 3.1 User Guide
Preparing and Executing a Customer Contract under N on Panel
Arrangement (Agency Specific)
For agency specific arrangement, only Part 2 Customer Contract is needed. No Head
Agreement is required in this instance.
Pre Tender Actions
Step 1 Review Part 2 and 3
Familiarise yourself with the terms and conditions of the Customer Contract.
Step 2 Complete the following items in Schedule 1 G eneral Order Form
A. Only items 1-3, 8-9 (and Item 33 if paying by credit card) need to be
prefilled when it is a small value and/or simple straightforward purchase
for hardware, software and services where the value of the purchase
can be calculated with certainty (i.e. the maximum amount payable is
set out in the “Total Amount” box in Item 11). Item 7 is not required for
Agency Specific arrangement.
The shortened version of the General Order Form must :
• Include all the Items that are set out in clause 3.4 of the Customer Contract. (i.e. Items 1, 4, 7 (if there is a Head Agreement), 8, 10, 11, 12 and 13);
• Include any other Items (if any) that the Parties agree;
• Be in the same form and structure (even if some Items are omitted);
• Ensure that the Items that remain are have the same number or heading as the number of heading in this pro forma General Order Form
• Include the following as a title:
“General Order Form. Schedule 1 to the Customer Co ntract (which is Part 2 of the Procure IT Framework)”
• Include the following text above the signature box;
PROCURE IT Version 3 User Guide
41
PROCURE IT Version 3.1 User Guide
“This General Order Form is part of the Customer Co ntract and incorporates all Parts, terms and conditions and ot her documents listed in clause 3.8 of Part 2 as if repeated in fu ll in this General Order Form.”
• Be signed by both parties.
• Cross reference and include the relevant Order Details from any Module Order Form and any details from the Module Order Forms that are required to describe the Products or Services.
Item 1 Name of Customer
Item 2 Service Address
Item 3 Customer’s Representative
Item 8 Modules
Tick any modules which will apply
Item 9 Schedules
Tick any schedules which will apply
B. The following items also need to be prefilled for complex purchases
such as software development, systems integration, web services,
managed services, and telecommunications services etc.
If the Parties require one or more of the Items 16 to 43 for any other
type of purchase, then these can be added to the General Order Form.
Item 17 Performance Review Procedures
Specify if a service and performance review/s of the Contractor’s
performance of the Customer Contract is required
Item 19 Implementation Planning Study
Specify whether the Contractor must provide an implementation
planning study
Item 21 Liquidated Damages
Specify whether LD is applicable
PROCURE IT Version 3 User Guide
42
PROCURE IT Version 3.1 User Guide
Item 22 Customer Supplied Items (CSI) and Customer Assistance
Specify each CSI to be provided by the Customer
Item 23 Escrow
Specify whether an escrow is required, if software development is
involved.
Item 24 Business Contingency Plan
Specify if a Business Contingency Plan is required
Item 25 Secrecy and Security
Specify any secrecy or security requirements that the Contractor and its
Personnel must comply with
Item 29 Quality Standard Accreditation
Specify any quality standard accreditation arrangements the Contractor
must hold during the Contract Period
Item 30 Contractor’s Compliance with Standards, Cod es and Laws
Specify any laws, codes, policies, or guidelines the Contractor must
comply with
Item 31 Customer’s Compliance with Standards, Codes and Laws
Specify any laws, codes, policies, or guidelines the Customer must
comply with
Item 33 Credit/Debit Card
Specify whether there is any credit/ debit card or electronic facility that
the Customer may use to pay the Contractor
Item 34 Intellectual Property
Specify who will own the IP created in the software.
Item 35 Confidentiality
Specify whether Contractor must arrange for its Subcontractors to
execute a Deed of Confidentiality substantially in the form of Schedule 8
– Deed of Confidentiality
PROCURE IT Version 3 User Guide
43
PROCURE IT Version 3.1 User Guide
Item 36 Insurance Requirements
Specify the levels of insurance cover required. The default levels have
been provided in the Customer Contract. However, the Customer is able
to negotiate with Contractor for any higher amount of cover.
Item 37 Performance Guarantee
Specify whether a Performance Guarantee is required
Item 38 Financial Security
Specify whether a Financial Security is required
Item 40 Performance Management Reports
Specify whether such reports are required
Item 41 Dispute Resolution
Specify the threshold amount for issues to be resolved by expert
determination. If it is not filled, the default amount will apply.
Post Tender Actions
Step 3 Complete all unfilled items in Schedule 1 af ter tender
evaluation
A. Complete items 1-15 (except Item 7) for simple straightforward purchase
for hardware, software, and services where the value of the order can
be calculated with certainty (i.e. the maximum amount payable is set out
in the “Total Amount” box in Item 11); and
B. Items 16 to 43 also need to be completed for complex purchases such
as software development, systems integration, web services, managed
services, and telecommunications services etc.
Step 4 Complete Schedule 2 Agreement Details (if applicable) Step 5 Obtain completed Schedule 6, 9 and 10 (If ap plicable):
PROCURE IT Version 3 User Guide
44
PROCURE IT Version 3.1 User Guide
� Schedule 6 Deed Poll – Approved Agents
Each Approved Agent (if any) is to complete a Deed Poll
� Schedule 9 Performance Guarantee
To be completed by the Contractor and the Guarantor. However, this
is example only, parties can use such other document reasonably
acceptable to the Customer.
� Schedule 10 Financial Security
This is example only, it can be in the standard form that is usually
provided by the issuing entity
Step 6 Sign General Order Form
Step 7 Sign Customer Contract
PROCURE IT Version 3 User Guide
45
PROCURE IT Version 3.1 User Guide
Part 3 – Dictionary
The following is the list of newly included defined terms:
1. Acceptance Test Notification period
2. Acceptance Test Data
3. Acceptance Test Period
4. Agreement Documents
5. Annexure
6. Approved Agent
7. Authorised representative
8. Bespoke User Documentation
9. Bundled Software
10. Business Day
11. Contract Value
12. Defects List
13. Due Date
14. Estimated Contract Price
15. Existing Material
16. General Order Form
17. Hardware
18. Head Agreement
19. Head Agreement Details
20. Head Agreement Documents
21. Insolvency Event
22. LD Obligation
PROCURE IT Version 3 User Guide
46
PROCURE IT Version 3.1 User Guide
23. Licensed Software
24. Material
25. Material Adverse Event
26. Minor
27. Module Order Form
28. Non-Recurring Services
29. Order Documents
30. Part
31. Payment Period
32. Prescribed Use
33. Procure IT Framework
34. Protected Clauses
35. Recurring Services
36. Related Company
37. Reseller
38. Short Term Recurring Services
39. Tax
40. User Documentation
PROCURE IT Version 3 User Guide
47
PROCURE IT Version 3.1 User Guide
Part 4 - Modules
To be added.
Each Module has its own Order Form that should be completed in addition to the
General Order Form.
Modules cannot be added without the consent of the Contract Authority. However,
Modules can be deleted without the Contract Authority’s consent.