upgrades week – november 2011 goals for the november upgrade week schedule for phase i work...

43
Upgrades Week – November 2011 Goals for the November Upgrade week Schedule for Phase I Work towards TP for Phase II November 2011 J. Nash - CMS Upgrades 1

Upload: rodger-norman

Post on 13-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Upgrades Week – November 2011 Goals for the November Upgrade week

Schedule for Phase I Work towards TP for Phase II

November 2011J. Nash - CMS Upgrades1

Page 2: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

CMS Upgrade Weeks This is the 12th CMS Upgrade “event” Started with Upgrade Workshops

First in Feb 2004 We have held two previous workshops at FNAL

(2008,2009) These have been very successful as workshops Lots of opportunity for discussion Away from CERN we tend to allocate more time for

discussion

November 2011J. Nash - CMS Upgrades2

Page 3: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Reminder: CMS Upgrade Scope

3

Page 4: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

CMS Upgrades Project Status: We have been focused

on producing the Technical Proposal for the first decade of operation Now this part of the

project is moving into construction

We need to begin to prepare a technical proposal for the second decade of operation Increase R&D Take some strategic

decisions20 September 2011J. Nash - CMS Upgrades4

Page 5: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

CSC Factory

Gluing

Winding

CSC assembly

Wire soldering

Component soldering

B904 hall

Page 6: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Assembly and installation trial test of one 10 degree sector happened this week

RPC Assembly/Installation

Page 7: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

New CMS central beampipe

Be

supportBe or AlBe??

oldnew

1630

14501948

SS or AlBe?? SS or AlBe??Be

supportBe or AlBe??

oldnew

1630

14501948

SS or AlBe?? SS or AlBe??

Issues:Impedance, HOM etc: shape OKVacuum stability: static OK, dynamic to doSupport collar on cone at 1630 mm: OKAperture: OK! see today’s presentations.Materials and Construction: work to do:Cones 1450 -->1948 machined from Be or AlBeConsidering replacing SS conical section (up to bellowsjunction with Endcap pipe at 3.12m) with AlBe. AlBe to Be braise to be studiedLighter pipe, as strong, reduces sag, activation and backgrounds, eliminates transition piece.

3120

CMS E & I, for C. Schaefer

support

Page 8: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

3 Disks

Port Cards and POH

End Flange

Space for End Electronics

DC-DC converters

Pipes and Cables

CO2 capillary cooling tubes and flex cables

Service Cylinder

Pixel Upgrade FPIX Service Cylinder

• Layout of CO2 cooling loops is reconsidered each loop goes through DC-DC and Port Cards & POH’s new loop layout with new pressure drops

• Pixel Opto-Hybrids (readout) detailed engineering now

Page 9: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

9

Pixel Upgrade FPIX half-disk

FPIX module 16 pixel ROC Each blade has 2 modules Half disk:

- inner: 11 blades

- outer : 17 blades

- independent mount to service cylinder

allows independent removal

FPIX blade

Outer Assembly Mounts X3

Inner Assembly Mounts X3

SS Tubing Coupling X6 9

new !

new !

Page 10: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

HCAL Upgrade SiPM Recent Results

Pixel dead-time issue solved in 15 Hamamatsu Device 99% cell recovery after 15ns

Dynamic range limitations overcome using large area SiPMs 22k pixels per readout channel 4 optically-mixed tile-fibers per

SiPM First results from new 15

Hamamatsu devices tested with Electro-Optical Decoding Units in H2 test beam at CERN in July are positive Will proceed with establishing HPK

as a baseline for the upgrade Meanwhile continue to qualify

other vendors, final choice by end of 2012

9/9/11D. Baden10

Page 11: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

TCA: AMC13 & HTR HCAL Upgrade helped developed the

CMS-wide Standard for microTCA control within Electronic Steering Group

9/9/11D. Baden11

U. Minnesota developed HCAL Trigger & Readout (HTR)

• Completed 2nd TCA Prototype• Fabricating HTR in India• Much FPGA integration

Page 12: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Calorimeter Trigger Designs

12

• Several prototype uTCA trigger cards have been built and have been shown to work. Working demonstrators at the crate level exist also.

• Two calorimeter trigger architectures are under consideration.• We have organised a review for the two Calorimeter Trigger

architectures. The aim of the review is:1. to select the architecture which best serves CMS for the next

decade.2. Produce a plan for the two relevant groups (Wisconsin-

Imperial) to work together towards the final design.

Page 13: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

ECAL–Trigger Interface - OptoSLB

13

Converts ECAL copper signals to 4.8 GBps optical and allows to keep using the current ECAL Trigger electronics after 2014.

Bought 4 optical devices for evaluation. Design effort for the card has started. First prototypes have been promised late in 2011 early 2012. Production should start in 2012.

Page 14: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Goals for the November Upgrade Week Refine phase I schedule

Tasks for each of the projects given as homework before the workshop

Use the workshop to refine these schedules, and to look at the dependencies between systems

Come out of the workshop with the start of an overall project schedule To be refined and maintained as we move forward

November 2011J. Nash - CMS Upgrades14

Page 15: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Project Breakdown Define the appropriate high level project tasks

(eg – Front end electronics, cooling…) We will use these tasks as the units for

reporting and tracking the progress on the project

This was very successful during the build of CMS

Important to break the project down in an appropriate way This certainly depends on the project, so no top

down overall requirement for the shape of these

November 2011J. Nash - CMS Upgrades15

Page 16: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Milestones Define a set of milestones for each of the

project tasks Examples

Prototypes ready, TDR ready (the LHCC are waiting for these…), production review, Commissioning

Declare them (at a defined level) to the upgrade project

Discuss how we will monitor and present them

November 2011J. Nash - CMS Upgrades16

Page 17: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Dependencies between projects Look at Links to other projects, and the

machine schedule and how they affect the milestones Take into account links between projects Take into account possible shutdowns now being

considered i.e. TS or LS2 installations We would like everyone to take the latest

“official” schedule for the machine as the basis for when the shutdowns could be

Allow for the possibility of an extended Technical Stop before LS2

November 2011J. Nash - CMS Upgrades17

Page 18: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Longer Term Planning – Sept LHCCLonger Term Planning – Sept LHCC

November 2011 J. Nash - CMS Upgrades 18

Not yet approved!

Page 19: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Costs Cost profile

Look at potential spending profiles for the project Look at impact on delivery

Realistic assessment of arrival of funding

November 2011J. Nash - CMS Upgrades19

Page 20: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Goals for November workshop - Phase II Develop a plan for proceeding with the phase II

project We will need to produce a technical proposal for

phase II (CMS2) on the timescale of around 2014 We need to take strategic decisions which will shape

the future CMS detector These decisions need to be taken by CMS as a whole

with the goal of producing the best instrument for physics measurement at a high luminosity LHC

Proposal: Create a CMS2 project review group High level strategy group Not based in sub-detector Reports to Upgrade Management, and ultimately to the CB

November 2011J. Nash - CMS Upgrades20

Page 21: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Reminder: CMS Upgrade Scope

21

Page 22: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

High Luminosity LHC (HL-LHC) Goals for the High Luminosity Running after

the third technical stop Integrated Luminosity 3000/fb

This to be collected at up to 300/fb-yr Detectors need to cope with high pile-up

Up to an order of magnitude greater than what we are seeing now

Detectors need to cope with high radiation Up to an order of magnitude greater than we

expected for LHC operation

November 2011J. Nash - CMS Upgrades22

Page 23: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Detector ChallengesCMS from LHC to SLHC

9 March 2011J. Nash CMS Upgrade Plans23

10331033

10351035

1032 cm-2 s-1 1032 cm-2 s-1

10341034

The tracker is the key detector which will require upgrading for SLHC Phase 2

The tracker is the key detector which will require upgrading for SLHC Phase 2

Page 24: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Level 1 Trigger

The trigger/daq system of CMS will require an upgrade to cope with the higher occupancies and data rates at HL-LHC

One of the key issues for CMS is the requirement to include some element of tracking in the Level 1 Trigger One example: There may not

be enough rejection power using the muon and calorimeter triggers to handle the higher luminosity conditions at HL-LHC

Adding tracking information at Level 1 gives the ability to adjust PT thresholds

Single electron trigger rate also suffers Isolation criteria are

insufficient to reduce rate at L = 1035 cm-2.s-1

9 March 2011J. Nash CMS Upgrade Plans24

Level 1 Trigger has no discrimination for PT > ~ 20 GeV/c

Level 1 Trigger has no discrimination for PT > ~ 20 GeV/c

Page 25: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Phase II – the Big Projects

A completely new tracking system Able to handle the

very extreme environment High pileup implies

high occupancy and in some areas high radiation exposure

Able to participate in the Level 1 Trigger Decision

New Forward Calorimetry?

New Trigger/DAQ New Electronics

Systems

November 2011J. Nash - CMS Upgrades25

SearchWindow

γ

Page 26: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Technical Proposal in 2014? How long should we spend working on R&D

We have been conducting R&D since around 2006 At some point we need to make decisions about

what directions we will take, and move from R&D phase to a proto-typing phase

November 2011J. Nash - CMS Upgrades26

Page 27: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Peter Sharp CERN CMS Electronics 2004 27

LHCC Meeting March 2004

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Activity 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007

First use of Micro-electronics LEP Si

First use of CMOS Delphi +++

Eurochip / Europractice Electronics Design Tools Continuation of Europractice

Establish CERN MIC Group

Micro-electronics User Group

LEB / LECC Workshops Continuation of Workshops

SSC R&D / DRDC SSC DRDC

Establish Electronics Infrastructure

R&D for LHCC DRDC followed by Experiments

IBM 250 nm Partnership IBM 250nm

Proposed IBM DSM Partnership IBM DSM

Experiment Technical Proposals

Build LHC Experiments R&D Prototypes Production

R&D to Upgrade LHC Experiments R&D

Over View Setting up Electronics InfrastructureR&D for LHC 1 Prototypes Production R&D for SLHC1 2 3 4 5 6 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 2 3

25 26 27 28 29 30 31 322008 2009 2010 2011 2012 2013 2014 2015

Continuation of Europractice

Continuation of Workshops

Prototypes Production

R&D for SLHC Prototypes Production4 1 2 3 4 5

Page 28: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Time needed for Phase II R&D There were about 10 years of R&D for the initial

build of CMS Followed by

2 years proto-typing 5 years production-install-commission

To get a new big detector ready by 2022 the timescale of 2014 for a TP just fits. The detectors for phase II are the same scale as major

sub-detectors were for the LHC, and technically more complex

We will need to ensure we are doing enough focused R&D to be ready to make designs and decisions.

November 2011J. Nash - CMS Upgrades28

Page 29: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Tracker Phase II R&D Some of the earliest R&D was on how we

could build a new tracking detector This is an extremely challenging task, and will

certainly have a major impact on our ability to do ANY physics in a High Luminosity Environment

R&D in the tracker project is progressing well, and the Tracker has prepared a phase II upgrade organization

November 2011J. Nash - CMS Upgrades29

Page 30: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Phase II R&D

Activities/topics Overall coordination: D. Abbaneo• Module design Strip module design: A. Messineo• Layout modelling Pixellated module design: R. Lipton• General integration issues• Schedule, planning, priorities• …

Electronics

Activities/topics• Front-End ASICS• Hybrids and interconnects• Data links• FE Driver and Controller Hardware• Electronic System Architecture• Test/commissioning hardware

Coordination: F Vasey

Power distribution

Activities/topics• ASICS evaluation• System development• Integration and system tests

Coordination: K. Klein

Sensors

Activities/topics• HPK sensors• Irradiations• 3-d silicon• Diamonds• …• …

Coordination: A. Dierlamm

Mechanics

Activities/topics• Qualification of materials• 3d modelling• Thermal modelling / lab tests• Deformation analysis• …• …

Coordination: A. Onnela

Upgrade Steering Board

CO2 cooling

Activities/topics• Process qualification• Modelling• Components / system design• Engineering of pixeI system• …• …

Coordination: H. Postema

Trigger simulations

Beam tests

Activities/topics• Hardware development and maintenance• Planning/running tests

Coordination: P. Luukka, L. Spiegel

2/17/11D. Abbaneo30

Page 31: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Tracker R&D – Pt Modules

November 2011J. Nash - CMS Upgrades31

Page 32: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Tracker R&D - Electronics

November 2011J. Nash - CMS Upgrades32

Page 33: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Tracker R&D - cooling

November 2011J. Nash - CMS Upgrades33

Page 34: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Tracking Trigger Task Force Study how a Level 1 trigger could be built

using the tracking detector as input How many Pt modules needed for a Level 1

Trigger? Where do these need to be placed?

At the first FNAL workshop we kicked off the work of this task force with some radical layouts to be studied in order to help answer some of these questions.

November 2011J. Nash - CMS Upgrades34

Page 35: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Tracking performance also studied

November 2011J. Nash - CMS Upgrades35

Page 36: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Studies of different layouts now well advanced

November 2011J. Nash - CMS Upgrades36

Page 37: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Forward Calorimetry task force The second Task force has been asked to

study calorimetry in the forward region What are the requirements from physics for

performance of the forward calorimetry system in the HL environment?

How will the current detectors perform in the HL environment?

How could a new system be constructed?

November 2011J. Nash - CMS Upgrades37

Page 38: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

38

Schematic of Approach

Find rad-hardtechnologies forcalorimetry materialsand photodetectors

Perform simulationsof these channels

Test beam validationsof detector components

Choose final configuration of forward calorimetry based on physics/simulations plus pragmatic considerations such as cost, feasibility of construction and schedule

Important physics channels indicated by real data and theory

Page 39: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

39

Effect of Radiation Damage On / Jet Position

Page 40: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

40

Effect of EM + Hadronic Radiation Damage

and In-Time Pileup onZ ee Events Mass Spectrum

Each runhas 10KMC events.The relativeheights ofeach signalpeak indicates The relativeefficiencies for findingthe ee

Page 41: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

41

Comparison of SiPMs and Ga based PMs vs dose rate

Question: what is this picture look like for protons

Page 42: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Upgrade Workshop Outline

November 2011J. Nash - CMS Upgrades42

Page 43: Upgrades Week – November 2011  Goals for the November Upgrade week  Schedule for Phase I  Work towards TP for Phase II November 2011J. Nash - CMS Upgrades1

Plenary Sessions – Sub-detector contributions Wednesday afternoon

Technical progress on the upgrades Thursday morning

Schedule/Milestones as developed at the meeting Flagging up potential problems issues,

outstanding questions and any lurking potential “showstoppers” Pixel Sensors CSC Panels HCAL SiPm/Front Ends Commissioning of the trigger

November 2011J. Nash - CMS Upgrades43