uop capital investment presentation

59
EDS 2004/CI-1 Capital Investment Evaluation Training Services Hello and good morning! My name is Joe Weiszmann and I am from the Solutions and Services Department of UOP. My specialization is the front-end conceptual design and optimization of refinery and petrochemical complexes. I often evaluate the economics and profitability of new refinery projects and of refinery revamps or upgrading projects as part of my work at UOP. This training class is about capital investment evaluation. For the next three hours, I would like to tell you about how to evaluate and select capital projects using the appropriate capital investment evaluation tools.

Upload: amin

Post on 17-Jul-2016

26 views

Category:

Documents


0 download

DESCRIPTION

UOP Capital Investment Presentation

TRANSCRIPT

Page 1: UOP Capital Investment Presentation

EDS 2004/CI-1

Capital Investment Evaluation

Training Services

Hello and good morning! My name is Joe Weiszmann and I am from the Solutions and Services Department of UOP. My specialization is the front-end conceptual design and optimization of refinery and petrochemical complexes. I often evaluate the economics and profitability of new refinery projects and of refinery revamps or upgrading projects as part of my work at UOP.

This training class is about capital investment evaluation. For the next three hours, I would like to tell you about how to evaluate and select capital projects using the appropriate capital investment evaluation tools.

Page 2: UOP Capital Investment Presentation

2

EDS 2004/CI-2

Time Value of MoneyInvestment Evaluation Tools– Net Present Value (NPV)– Breakeven analysis– Internal Rate of Return (IRR)

Project Ranking– Simple payout– Mutually exclusive projects– Sensitivity analysis– Present value ratio

Cash Flow Analysis– Examples

Class Problems

Outline

We will go through the concept of the time value of money. Next, we will go through the three most common investment evaluation tools: net present value, breakeven analysis and internal rate of return.

I will show you which is the correct tool to use for evaluating capital projects. There are several different techniques used for evaluating capital projects, including simple payout, mutually exclusive projects, sensitivity analysis, and present value ratio. We will talk about all of these this morning.

We will then go through a cash flow analysis and work out some examples. We will finish the class with doing some class and homework problems.

Page 3: UOP Capital Investment Presentation

3

EDS 2004/CI-3

Time Line Concept

Income, $

Year 0 1 2 3 4 5

50 50 50 50 50

Investmentor Cost, $ 100 100

The time line concept entails organizing the income and investment (or cost) of a particular project over a selected period of time to be analyzed in terms of the income received and cost incurred during each individual period of time.

Page 4: UOP Capital Investment Presentation

4

EDS 2004/CI-4

Time Line Concept

Income, $

Year 0 1 2 3 4 5

50 50 50 50 500

- Cost, $ -100 0 0 0 0-100

Cash Flow -50 50 50 50 50-100

By subtracting the cost from the income, you get the net cash flow for each period of time. In other words, the cash flow is typically the profit that you make after you subtract your cost and expenses from the income or revenues.

Page 5: UOP Capital Investment Presentation

5

EDS 2004/CI-5

Definition of Cash Flow

Gross revenue or savings- Operating costs- Tax costs- Capital costs

= Cash flow

A more detailed description or definition of cash flow is the money remaining after you subtract all the operating costs (both variable and fixed), tax costs (everyone pays some kind of tax?), and capital costs (e.g. for plant, equipment, buildings, etc., which are typically amortized via depreciation) from the gross revenues or savings, i.e. from the revenue received or the savings achieved.

Page 6: UOP Capital Investment Presentation

6

EDS 2004/CI-6

Invest $100 in Bank A and $100 in Bank B

Bank A pays 20% simple interest at the end of three years

Bank B pays 10% compound interest for three years

Time Value of Money – ExamplePutting Money to Work

Here’s an example of the time value of money. Let’s invest $100 M in Bank A and $100 M in Bank B. Bank A pays 20% simple interest at the end of three years, while Bank B pays 10% compound interest for three straight years. It is just an example of the time value of money.

Page 7: UOP Capital Investment Presentation

7

EDS 2004/CI-7

Year 0 1 2 3

-$100 $120

100*1.2=

Time Value of MoneyBank A

In Bank A, after 3 years, the $100 investment turns into $120 based on using a simple interest rate of 20%.

Page 8: UOP Capital Investment Presentation

8

EDS 2004/CI-8

Year 0 1 2 3

-$100 $133

121*1.1=

$121

110*1.1=

$110

100*1.1=

Time Value of MoneyBank B

In Bank B, we apply a compound interest rate. This interest rate is different from the simple one in that it is compounded each and every year.

The interest rate is applied to the investment every year, as long as the money is kept invested or deposited in the bank.

The value of your $100 with compound interest is calculated using the formula shown here. After three years, your $100 becomes $133.

Page 9: UOP Capital Investment Presentation

9

EDS 2004/CI-9

Investment evaluation will show us if an investment gives us a good return on our money.

Investment Evaluation

The next section will introduce the three most common methods of investment evaluation: net present value, breakeven analysis, and internal rate of return.

Page 10: UOP Capital Investment Presentation

10

EDS 2004/CI-10

The Cost of Capital (or money) is the rate of return that could be realized on similar alternative investments of equivalent risk.

This foregone rate of return is the standard to which we compare all our investments.

Cost of Capital

The cost of capital is an important principle that underlies all investment evaluation work.

What else could we be doing with our money (that would involve only the same amount of risk)?

Page 11: UOP Capital Investment Presentation

11

EDS 2004/CI-11

Investment Evaluation Tools

Net Present Value (NPV)Breakeven AnalysisInternal Rate of Return (IRR)

Let’s now look at the three most common investment evaluation tools: NPV, Breakeven Analysis, and IRR.

Page 12: UOP Capital Investment Presentation

12

EDS 2004/CI-12

Net Present Value (NPV)

Net Present Value is the total value of a project, revenues minus costs, brought backward to the first year at a specified rate of interest per year.

More explanation (plus examples) are provided on the following slides.

Page 13: UOP Capital Investment Presentation

13

EDS 2004/CI-13

j = Period of time, usually a yearCj = Cash flow in the time period j

I = Interest rate ( = cost of capital)n = Number of time periods, years

NPV = Σ Cj / (1 + i) j

where 0 < j < n

Net Present Value (NPV)(continued)

The NPV of a project is the summation of all the discounted cash flows over all of the time periods to be evaluated.

Page 14: UOP Capital Investment Presentation

14

EDS 2004/CI-14

Net Present Value (NPV)(continued)

I want to have $2,000 at the end of 5 years. The interest rate is 12%.

How much do I have to invest in year 1?

Here is an example. Can anyone tell me the answer?

Page 15: UOP Capital Investment Presentation

15

EDS 2004/CI-15

Income, $

Year 0 1 2 3 4 5

0 0 0 0 0 2000

NPV 0 0 0 0 0

-NPV 0 0 0 0 2000

- Cost, $

Cash Flow

NPV = 2000 / (1+0.12)5

NPV = $1135 (to be invested at the beginning of the year)

Net Present Value (NPV)(continued)

Let’s go through the calculation, step by step, as shown above.

Page 16: UOP Capital Investment Presentation

16

EDS 2004/CI-16

Net Present Value (NPV)(continued)

To make 12% on my investment:-X + 2000 / (1+0.12)5 = 0

X = $1135This is also called the Breakeven Price

Income, $

Year 0 1 2 3 4 5

0 0 0 0 0 2000

X 0 0 0 0 0

-X 0 0 0 0 2000

- Cost, $

Cash Flow

Another way to look at it:

The breakeven price is based on determining the initial investment required @ 12% to obtain @ $2000 at the end of five years.

If you had to invest more than $1135, you would be losing money; if you had to invest less than $1135, you would be gaining money. However, if you had to invest exactly $1135, then you would be breaking even. Hence, $1135 is called the breakeven price in this example.

Page 17: UOP Capital Investment Presentation

17

EDS 2004/CI-17

Net Present Value – Example

Income, $

Year 0 1 2 3 4

0 50 40 30 20

100 0 0 0 0

-100 50 40 30 20

- Cost, $

Cash Flow

What is the NPV of this project using a cost of capital of 15%? What is the Breakeven Investment cost?

Here is another example of calculating NPV that I suggest you try working on (without turning over just yet).

Page 18: UOP Capital Investment Presentation

18

EDS 2004/CI-18

Worksheet for NPV Example

NPV = Σ Cj / (1 + i) j

NPV = -100 / (1+0.15)0 +50 / (1+0.15)1 +40 / (1+0.15)2 +30 / (1+0.15)3 +

20 / (1+0.15)4

NPV = -100 + 43 + 30 + 20 + 11

NPV = $4

Please go through the calculation and make sure you could do it yourself.

Page 19: UOP Capital Investment Presentation

19

EDS 2004/CI-19

At the beginning of year 1, the value of this project is $4 at a 15% rate of interest. This means I make 15% interest on my $100 investment over a 4 year period, plus $4 extra. The interest rate on this investment is, therefore, greater than 15% per year.

This project is attractive if the cost of capital is 15% (or less). The net present value of the project is calculated to be plus $4 at a 15% rate of interest.

Page 20: UOP Capital Investment Presentation

20

EDS 2004/CI-20

Breakeven analysis is determining the value of any parameter which allows a specified rate of return to be achieved from an investment.

The parameter may be the initial investment cost, project lifetime, annual revenue, selling price of a product, or % utilization of plant.

Breakeven Analysis

Breakeven analysis can be applied to lots of other parameters, for example the plant throughput required to just breakeven. See above for other examples of the parameters that can be studied as part of a breakeven analysis of a project.

Page 21: UOP Capital Investment Presentation

21

EDS 2004/CI-21

Breakeven Investment Cost

Income, $

Year 0 1 2 3 4

0 50 40 30 20

X 0 0 0 0

-X 50 40 30 20

- Cost, $

Cash Flow

NPV = 0 = -X / (1+.15)0 + 50 / (1+.15)1 + 40 / (1+.15)2

+ 30 / (1+.15)3 + 20 / (1+.15)4

0 = -X + 43 + 30 + 20 + 11X = $104

In the breakeven analysis above, we want to find out what our maximum investment cost should be to just meet our accepted 15% rate of return. This is calculated as shown above with the NPV set equal to zero.

Page 22: UOP Capital Investment Presentation

22

EDS 2004/CI-22

For a Rate of Return of 15% on this investment, I could invest up to $104. This is then the Breakeven Investment Cost for this particular project. Any additional cost would lower the Rate of Return to less than 15% which would not be acceptable.

This is just another way of saying the same thing.

Page 23: UOP Capital Investment Presentation

23

EDS 2004/CI-23

Income, $

Year 0 1 2 3 4

0 50 40 30 20

100 0 0 0 0

-100 50 40 30 20

- Cost, $

Cash Flow

NPV = -100 / (1+.20)0 + 50 / (1+ .20)1 + 40 / (1+ .20)2

+ 30 / (1+ .20)3 + 20 / (1+ .20)4

= -100 + 42 + 28 + 17 + 10= - $3

The IRR is between 15% and 20%.

What is the NPV at 20%?

Here’s an example that calculates the project NPV at a cost of capital of 20%. The NPV for this project is now minus $3.

This means that the discount rate used is now too high for this project. You are asking for too much return from this investment.

The rate of return is thus somewhere between 15% and 20%.

Page 24: UOP Capital Investment Presentation

24

EDS 2004/CI-24

Internal Rate of Return (IRR)

Rate of Return or interest rate of a project

Calculated through trial and error

Let’s now talk about internal rate or return or IRR as it is routinely called.

Page 25: UOP Capital Investment Presentation

25

EDS 2004/CI-25

Internal Rate of Return (IRR)(continued)

j = Period of time, usually a yearCj = Cash flow in time period jr = Internal Rate of Return unknownn = Number of periods, usually years

Assume a value for “r” and calculate formula. The project’s IRR is the value of “r” that gives an answer of zero NPV.

0 = Σ Cj / (1 + r) j

where 0 < j < n

This is the formula for calculating the internal rate of return (IRR) of a project. The calculation is normally an iterative process, even for a computer.

Page 26: UOP Capital Investment Presentation

26

EDS 2004/CI-26

Income, $

Year 0 1 2 3 4

0 100 100 120 140

-200 -150 0 0 0

-200 -50 100 120 140

- Cost, $

Cash Flow

at r = 15%- 200/(1+.15)0 - 50/(1+ .15)1 + 100/(1+ .15)2

+ 120/(1+ .15)3 + 140/(1+ .15)4

- 200 - 43 + 76 + 79 + 80 = - $8

at r = 10%- 200/(1+.10)0 - 50/(1+ .10)1 + 100/(1+ .10)2

+ 120/(1+ .10)3 + 140/(1+ .10)4

- 200 - 45 + 83 + 90 + 96 = + $24

What is the IRR of this project?

Here is an example the calculates an IRR of a project. As you can see, it is trial and error approach.

Page 27: UOP Capital Investment Presentation

27

EDS 2004/CI-27

Example – What is the IRR of the following project?

Income, $

Year 0 1 2 3

0 30 40 50

100 0 0 0

-100 30 40 50

- Cost, $

Cash Flow

Here is another example for you to work on (without turning over just yet).

Page 28: UOP Capital Investment Presentation

28

EDS 2004/CI-28

What is the IRR of this Project?Calculation

at r = 15%-100/(1+.15)° + 30/(1+.15)1 + 40/(1+.15)2 + 50/(1+.15)3

-100 + 26 + 30 + 33 = - $11

at r = 10%-100/(1+.10)° + 30/(1+.10)1 + 40/(1+.10)2 + 50/(1+.10)3

-100 + 27 + 33 + 38 = - $2

at r = 8%-100/(1+.08)° + 30/(1+.08)1 + 40/(1+.08)2 + 50/(1+.08)3

-100 + 28 + 34 + 40 = + $2

The internal rate of return is 9%

Here is the calculation of the internal rate of return (IRR) for this example.

Page 29: UOP Capital Investment Presentation

29

EDS 2004/CI-29

Project Ranking

Simple Payout

Mutually Exclusive Projects

Sensitivity Analysis

Present Value Ratio

Let’s now move on and go over methods for ranking and prioritizing projects.

Page 30: UOP Capital Investment Presentation

30

EDS 2004/CI-30

Simple payout is the number of years it will take to pay back an investment at the initial operating gross margin. Simple payout takes no account of inflation, nor of the time value of money.

Example:– Gross margin in year 1 = $700 MM/year– Total investment in project = $1,400 MM– Simple payout = $1,400/$700 = 2 years

Simple Payout

Simple payout is (as it says) simple. It is widely used and quite a useful concept, but beware of the pitfalls explained on the next few slides.

Page 31: UOP Capital Investment Presentation

31

EDS 2004/CI-31

Payout Example #1

Project A

NPV @ 15% minimum rate of return = $15and the IRR ∼ 23%Payout = 2 years

Cash Flow -100 50 50 50

0 1 2 3Year

This is example #1 of using simple payout. Do you agree with the NPV, IRR and Payout figures worked out above? If yes, then turn over to example #2.

Page 32: UOP Capital Investment Presentation

32

EDS 2004/CI-32

Payout Example #2

Project B

NPV @ 15% min rate of return = - $13and the IRR = 0%Payout = 1 year

Cash Flow -100 100 0 0

0 1 2 3Year

Here again, I suggest you check the NPV, IRR and Payout numbers worked out above. The point is that the Payout in Example #2 is better (half as long) than in Example #1, but everything else is obviously much worse.

Page 33: UOP Capital Investment Presentation

33

EDS 2004/CI-33

Simple Payout

Simplest economic evaluation method

Takes NO account of the time value of money

Penalizes long term projects

Benefits quick projects

Must emphasize that the Simple Payout approach should not be used as a tool for making decisions on a project. It is basically a very rough screening tool.

Page 34: UOP Capital Investment Presentation

34

EDS 2004/CI-34

Project Ranking

Mutually exclusive alternatives– Only 1 project can be accepted

Non-mutually exclusive alternatives– Ranking several projects

It is important to decide up-front whether or not the projects you are evaluating are mutually exclusive. It affects the correct choice of evaluation method.

A common example of mutually exclusive projects is when there are two or three different options for revamping of a particular plant. Only one of the revamp options can be implemented - a decision is required.

Page 35: UOP Capital Investment Presentation

35

EDS 2004/CI-35

Mutually Exclusive Alternatives

The goal is to choose the one project that gives the investors the largest return on their money– The project with the largest NPV using the minimum

rate of return– The project with the highest incremental IRR

• Calculate each project’s individual IRR; must be higher than the minimum rate of return

• Calculate the incremental IRR between projects; this too must be higher than the minimum rate of return

• The project which has the highest incremental IRR will give the largest return on the investment

For mutually exclusive projects, beware of using IRR, unless you go through the whole of the procedure above and calculate the incremental IRR between the projects as well as all the other numbers as per normal.

Page 36: UOP Capital Investment Presentation

36

EDS 2004/CI-36

Mutually Exclusive Alternatives

Income, $ 0 0 0 370- Cost, $ 200 0 0 0Cash Flow -200 0 0 370

0 1 2 3

Project B

Year

Income, $ 0 50 60 70- Cost, $ 100 0 0 0Cash Flow -100 50 60 70

0 1 2 3

Project A

Year

Here is an example of two mutually exclusive projects, A and B. Which of these projects should be implemented?

How should we evaluate this situation? This is not straight forward, but the test tomorrow will include a question like this.

Page 37: UOP Capital Investment Presentation

37

EDS 2004/CI-37

Mutually Exclusive Alternatives Net Present Value

at r = 15%-100/(1+.15)° + 50/(1+.15)1 + 60/(1+.15)2 + 70/(1+.15)3 -100 + 43 + 45 + 46 = + $34

at r = 15%-200/(1+.15)° + 370/(1+.15)3 -200 + 243 = + $43

Minimum rate of return is 15%

Project A

Project B

Please go through the calculations. Do you agree with the NPV numbers shown above? If not, please ask for further explanation of this.

Page 38: UOP Capital Investment Presentation

38

EDS 2004/CI-38

Mutually Exclusive Alternatives Internal Rate of Return

at r = 30%-100/(1+.30)° + 50/(1+.30)1 + 60/(1+.30)2 + 70/(1+.30)3

-100 + 38 + 36 + 32 = + $6

at r = 35%-100/(1+.35)° + 50/(1+.35)1 + 60/(1+.35)2 + 70/(1+.35)3

-100 + 37 + 33 + 28 = - $2

at r = 33%-100/(1+.33)° + 50/(1+.33)1 + 60/(1+.33)2 + 70/(1+.33)3

-100 + 38 + 34 + 30 = + $2

Project A

Again, please go through the calculations. Find the right IRR number for project A - it has to be 34% - agreed?

Page 39: UOP Capital Investment Presentation

39

EDS 2004/CI-39

Mutually Exclusive AlternativesInternal Rate of Return

at r = 20%-200/(1+.20)° + 370/(1+.20)3 -200 + 214 = + $14

at r = 25%-200/(1+.25)° + 370/(1+.25)3 -200 + 189 = - $11

at r = 23%-200/(1+.23)° + 370/(1+.23)3 -200 + 199 = - $1

Project B

And for Project B, the IRR is very close to 23% - agreed?

Page 40: UOP Capital Investment Presentation

40

EDS 2004/CI-40

Mutually Exclusive Alternatives

Cash Flow of B -200 0 0 370

0 1 2 3

Project B

Year

Cash Flow of A -100 50 60 70Cash Flow B-A -100 -50 -60 300

0 1 2 3

Project A

Year

Again, please go carefully through the calculation. Check that you agree with all of the cash flows ( + & - ) shown for project B minus project A.

Page 41: UOP Capital Investment Presentation

41

EDS 2004/CI-41

Mutually Exclusive Alternatives Incremental Rate of Return

at r = 15%-100/(1+.15)° - 50/(1+.15)1 - 60/(1+.15)2 + 300/(1+.15)3

-100 - 43 - 45 + 197 = + $9

at r = 20%-100/(1+.20)° - 50/(1+.20)1 - 60/(1+.20)2 + 300/(1+.20)3

-100 - 42 - 42 + 174 = - $10

Therefore, the incremental rate of return is approximately 17%, which is above our minimum rate of return. Project B is the project that will give the highest return on our money.

Project B - Project A

And finally, one last IRR calculation and the end result is that project B is better than project A - just like the NPV figures showed us in Slide 37.

The reason for all this is that many people look almost solely at IRR and project A has the higher IRR but project B is definitely better.

If you are a little confused at this point, go back to Slide 35 and work through the numbers carefully one more time. It will then become much clearer.

The next slide provides a summary of this project comparison.

Page 42: UOP Capital Investment Presentation

42

EDS 2004/CI-42

Project Comparison

Project A

Project B

Project B-A

0 -100 -200 -1001 50 0 -502 60 0 -603 70 370 300

Net Income 80 170 90NPV @ 15% 35 43 8IRR 34% 23% 17%

Year

BestIRR

BestNPV

Winneris B

When evaluating mutually exclusive projects, you can subtract the cash flows of project A from those of project B. If the NPV of B minus A is positive, then project B is the winner. If it is negative, then go with project A.

In summary, always select the project with the higher or highest NPV.

Page 43: UOP Capital Investment Presentation

43

EDS 2004/CI-43

Sensitivity AnalysisProject

AProject

BProject

B-A0 -100 -200 -1001 50 0 -502 60 0 -603 70 370 300

Net Income 80 170 90NPV @ 15% 35 43 8IRR 34% 23% 17%

Year

Sensitivity AnalysisNPV NPV NPV

Discount Rate

5% 62.5 119.6 57.110% 47.6 78.0 30.315% 34.9 43.3 8.420% 23.8 14.1 -9.725% 14.2 -10.6 -24.830% 5.8 -31.6 -37.4

This is an example of a sensitivity analysis (that looks at the effect of the discount rate on NPV). The next slide is a graphical plot of these numbers.

Page 44: UOP Capital Investment Presentation

44

EDS 2004/CI-44

Sensitivity Analysis(continued)

-40-20

020406080

100120

5% 10% 15% 20% 25% 30%

Project A Project B Project B-A

Graphically, you can see the range on the x-axis of the cost of capital (up to about 17%) where selecting Project B (the red line) instead of Project A (the blue line) creates the higher NPV and is, therefore, the better choice.

Page 45: UOP Capital Investment Presentation

45

EDS 2004/CI-45

Non-Mutually Exclusive Alternatives

The goal is to rank several potential projects by economic return to give higher priority to the projects with highest return on investment

– Present Value Ratio = NPV / PWNC• NPV = Net Present Value• PWNC = Present Worth Net Cost

(calculated at the minimum rate of return)

.The other situation is when we have a whole set of completely independent projects from which to select and there is enough money to invest in several of them.

Which projects represent the best use of our money available for investment?

Page 46: UOP Capital Investment Presentation

46

EDS 2004/CI-46

Present Worth Net Cost (PWNC)

PWNC = Σ Εj / (1 + i) j

where 0 < j < n

j = Period of time, usually a yearE = Expenditure in time period jI = Interest rate ( = cost of capital)n = Number of time periods, years

The formula only covers the period of time during which expenditure (E) is incurred. It works out the “Present Worth” of the expenditure or “Net Cost” required for each of the possible projects.

Page 47: UOP Capital Investment Presentation

47

EDS 2004/CI-47

Present Worth Net Cost (PWNC)

Income, $ 0 50 110 120- Cost, $ -100 -100 0 0Cash Flow -100 -50 110 120

0 1 2 3

PWNC = +100/(1+.15)° + 50/(1+.15)1

PWNC = $143

Year

.

Here is an example of calculating the Present Worth Net Cost. Look at the Cash Flow figures in red above and discount only these two negative numbers back to the initial time period to calculate the Present Worth Net Cost.

Page 48: UOP Capital Investment Presentation

48

EDS 2004/CI-48

Net Present Value (NPV)

Income, $ 0 50 110 120- Cost, $ -100 -100 0 0Cash Flow -100 -50 110 120

0 1 2 3

NPV = -100/(1+.15)° - 50/(1+.15)1 + 110/(1+.15)2 + 120/(1+.15)3

NPV = -100 - 43 + 83 + 79NPV = + $19

Year

This is the calculation of the project’s NPV exactly as per normal.

Page 49: UOP Capital Investment Presentation

49

EDS 2004/CI-49

Present Value Ratio

Income, $ 0 50 110 120- Cost, $ -100 -100 0 0Cash Flow -100 -50 110 120

0 1 2 3

Present Value Ratio = Net Present Value / Present Worth Net CostPresent Value Ratio = 19 / 143 = 0.13

Year

And now the Present Value (PV) Ratio can be calculated as shown above.

Page 50: UOP Capital Investment Presentation

50

EDS 2004/CI-50

Non-Mutually Exclusive Alternatives

To rank several projects, order the projects by their present value ratio

ProjectPresent

Value Ratio RankABCD

0.131.210.370.04

3124

This is an example of ranking projects based on PV ratio analysis. The higher the PV ratio the better the project.

Page 51: UOP Capital Investment Presentation

51

EDS 2004/CI-51

Project Ranking Example

Project E

Project F

Project G

0 -2000 -2000 -2000 -20001 1000 0 20000 02 1000 2000 -21000 10003 5000 5000 0 100000

Net Income 5000 5000 -3000 99000

NPV @ 15% 2,913 2,800 (488) 64,508IRR 68.2% 60.1% 19.2% 273%

Payout, years 2 2 0.1 3PV ratio 1.46 1.40 -0.03 >32

YearProject

H

There are many interesting points to think about if you go through the example above comparing projects E, F, G, and H. Simple payout gives a completely wrong set of answers, whereas, the PV ratio method works perfectly.

Page 52: UOP Capital Investment Presentation

52

EDS 2004/CI-52

Cash Flow Analysis

The final section of this session is intended to answer the question - “Where do all the cash flow numbers come from?” and to lead into a real-life 1999 example of a residue upgrading refinery project evaluation for you to work on.

Page 53: UOP Capital Investment Presentation

53

EDS 2004/CI-53

Cash Flow Analysis

Net Income or Gross Margin- Expenses- Taxes- Interest- Capital charges

= Net Cash Flow

}Costs

This definition is critically important. All of the costs must be brought into the calculation and deducted from the revenue, income, or receipts.

Page 54: UOP Capital Investment Presentation

54

EDS 2004/CI-54

Sample Economic Evaluation

$MM(U.S.)

Year 0 1 2 3 4 5 6 7 8 9 10 1Net Cash Flow (350) (500) (79) 365 378 396 367 381 397 367 383 479Cum. Cash Flow (350) (850) (929) (564) (185) 211 578 959 1,356 1,723 2,106 2,585

Economic Evaluation:Net Present Value

Interest rate, i 5% 10% 15% 20% 25% 30% 35%

NPV at i, $MM 1,604 968 542 250 45 (102) (209)

Internal Rate of Return 26%

Simple Payout 4.5 years

Please also refer to the hand-out showing the calculation of the Net Cash Flow numbers summarized above.

Page 55: UOP Capital Investment Presentation

55

EDS 2004/CI-55

Financial Functions in Excel

Net Present Value (NPV)= NPV (interest rate, cash flow range)

+ cash flow in year 0Notes: do not discount the cash flow for year 0

cash flow range is for years 1 to n

Internal Rate of Return (IRR)= IRR (cash flow range, guess of IRR)Note: cash flow range is for years 0 to n

I suggest you try using these functions the next time you are in Excel.

Page 56: UOP Capital Investment Presentation

56

EDS 2004/CI-56

Financial Functions in Lotus

Net present value (NPV)= @ NPV (i, range) + cash flow in year 0

where i = the minimum rate of return and range = the cash flows in years 1 to n

Internal Rate of Return= @ IRR (i, range)

where i = a starting guess for the IRR andrange = the cash flows in years 0 to n

Does anybody still use Lotus? Well just in case there’s someone back there!

Page 57: UOP Capital Investment Presentation

57

EDS 2004/CI-57

UOP’s Electric Mop Project

Pilot Production and Test Marketing– Period of 1 year– Investment of $125,000– 50% chance of success

Build Production Plant– Investment of $1,000,000– Annual cash flow of $250,000– or only $75,000 if the test fails– 20 year project life

High Risk Project– Use 25% discount factor

Is This A Good Project?Is This A Good Project?

Interesting class problem? The answer is far from being obvious!.

Page 58: UOP Capital Investment Presentation

58

EDS 2004/CI-58

NPV Analysis

Cash Flows, $000 ExpectedYear 0 -125 - 125Year 1 50% of -1000 and 50% of 0 - 500Year 2 50% of 250 and 50% of 0 125Year 3 50% of 250 and 50% of 0 125…Year 21 50% of 250 and 50% of 0 125

NPV = -125 - ( 500 / 1.25 ) + Σ ( 125 / 1.25^t )NPV = -129.6

Negative NPV = Not A Good Project?Negative NPV = Not A Good Project?

The approach should be to first of all work out the expected cash flow in each period of time. Then calculate the NPV using an appropriate cost of capital in view of the risk involved. However, the next slide shows a different approach to this problem.

Page 59: UOP Capital Investment Presentation

59

EDS 2004/CI-59

Decision Tree AnalysisInvest 1,000 in Full Scale Plant

Don’t Invest

Actual NPV = (-125) + (0.5 * 565)/(1.25) = $101

Invest 1,000 in Full Scale Plant

Success(50%)

Failure(50%)

Test(Invest 125)

Don’t TestStop

Don’t Invest

NPV = - 1,000 + Σ ( 250 / 1.15 ^t )t = 20

t = 1

Stop NPV = 0

NPV = 565

NPV = - 1,000 + Σ (75 / 1.15 ^t )

NPV = - 531

Stop NPV = 0

t = 20

t = 1

The right way to analyze the problem is through a decision tree analysis. The key difference now is that after the test marketing in year 1, there will be much less risk involved and a lower rate of return would then be acceptable.