Unitization and enhanced recovery
techniques
Unitization and Enhanced Oil Recovery
• Unitization Process
• Units Approved
• EOR Results
• Bakken Development
• Bakken EOR Potential
Bruce E. Hicks
Assistant Director
NDIC-DMR-OGD
Bismarck, ND
600 East Boulevard Ave. - Dept 405
Bismarck, ND 58505-0840
(701) 328-8020 (701) 328-8000
North Dakota Department of Mineral Resources
https://www.dmr.nd.gov/ndgs/ https://www.dmr.nd.gov/oilgas/
Unitization and Enhanced Oil Recovery
• Unitization Process
• Units Approved
• EOR Techniques & Results
• Bakken Development
• Bakken EOR Potential
Unitization Process
NDCC Sec 38-08-09.3
• Project substantially increases oil recovery
• EOR unnecessary for approval
• Voluntary and Statutory Units – both require Commission approval
Unitization—Statutory Approval
NDCC Sec 38-08-09.5
• 60% mineral interest owner approval
• 60% working interest owner approval
• NDIC approval
Unitization and Enhanced Oil Recovery
• Unitization Process
• Units Approved
• EOR Techniques & Results
• Bakken Development
• Bakken EOR Potential
Units Approved
• 127 Units approved – 124 EOR w/fluid injection
• Most water injection
• high pressure air (8)—fire flood
• also propane, CO2, polymers, N2, + other fluids
– 3 created to increase reserves w/o injection • Little Missouri-Pierre Unit—shallow gas reservoir
• Cedar Creek-Pierrre Unit—shallow gas reservoir
• Corral Creek-Bakken Unit
Bakken Units
• Corral Creek-Bakken Unit – Effective 1-1-2012
– 30,884 acres
– increased reserves over 5 million barrels of oil
– 81 wells originally planned
– 122 wells drilled currently
– 194 wells currently planned
– EOR not planned initially • EOR only after due notice and hearing
• Grail-Bakken Unit – 24,947 acres
– failed to achieve 60% MIO approval
Unitization and Enhanced Oil Recovery
• Unitization Process
• Units Approved
• EOR Techniques & Results
• Bakken Development
• Bakken EOR Potential
Unitization and Enhanced Oil Recovery
• Conventional Oil Reservoir
– Primary 15% recovery
– Secondary add 15% recovery
– Tertiary add 10% recovery
– 40% recovery of Original Oil in Place (OOIP)
• Unconventional Oil Reservoir – Bakken-Three Forks Formations
– 3% Primary recovery / well
– Secondary & Tertiary recovery ?
NORTH DAKOTA – 190 DRILLING RIGS – Jan 2013
Cedar Hills South Red River B Unit
Conventional Oil Reservoir
88 original wells (1H/640)
316 million barrels OOIP
Primary: 8% recovery of OOIP
26 million bo
wells not fraced
NORTH DAKOTA – 190 DRILLING RIGS – Jan 2013
Cedar Hills South-RR ”B” Unit
• EUR w/o EOR = 26 mil bo
• current Incremental = 74 mil bo
• current oil cum = 101 mil bo
Incremental Oil Determination
• establish historical decline
• project baseline decline w/o EOR
• calculate oil above the base
Incremental oil due to EOR
Cedar Hills South Red River B Unit
Unitization and Enhanced Oil Recovery
• Unitization Process
• Units Approved
• EOR Techniques & Results
• Bakken Development—encourages EOR – Uniform Spacing—orderly development
– Energy Corridors
• Bakken EOR Potential
NORTH DAKOTA – 190 DRILLING RIGS – Jan 2013
NORTH DAKOTA – 191 DRILLING RIGS – DECEMBER 2014
Current drilling activity is focused
in Mountrail, Dunn, McKenzie, and Williams Counties.
NORTH DAKOTA – 190 DRILLING RIGS – Jan 2013
NORTH DAKOTA – 35 DRILLING RIGS – MARCH 2016
Current drilling activity is focused
in Mountrail, Dunn, McKenzie, and Williams Counties.
NORTH DAKOTA – 27 DRILLING RIGS – APRIL 2016
Current drilling activity is focused
in Mountrail, Dunn, McKenzie, and Williams Counties.
WELLS
• 13,012 wells producing (Feb 2016)
• 10,898 Bakken (84%)
• 40,000 additional development wells
• 100 rigs – another 20 years
• Bakken Pool: 4 targets = more wells
Unitization and Enhanced Oil Recovery
• Unitization Process
• Units Approved
• EOR Techniques & Results
• Bakken Development
• Bakken EOR Potential
Bakken/Three Forks EOR Potential
• Pilot projects – CO2 injection
– water injection
– projects small-scale and usually inconclusive
– further testing must be conducted
• > 300 billion barrels OOIP – every 1% of EOR = 3 billion barrels