tweddle place storm and sanitary upgrades … · tweddle place storm and sanitary upgrades project...

14
Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015

Upload: others

Post on 02-Jun-2020

13 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Tweddle Place Storm and Sanitary Upgrades

Project Update to Millbourne Community

November 19, 2015

Page 2: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

2015 Construction Progress

Slide 2

Page 3: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Slide 3

Page 4: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Project Activities to Date

• Finalizing detailed design drawings • Preparing tender documents for 2016

• 2015 - TP2A.1 – 89 Street construction

Slide 4

Page 5: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

2015 Construction Progress

Slide 5

Page 6: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

2016 Work Plan

Slide 6

Page 7: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Construction Staging

• 2016 – TP4, MB1A, access ~ 6 months • 2016 and 2017 – dry pond expansion, access

Slide 7

Page 8: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Slide 8

2016-2017

2018 (pending available funding)

Page 9: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Living Wall Demonstration Project

Slide 9

Page 10: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Living Wall Demonstration

• Planted additional 2000 willows • Completed noise monitoring

– Conclusion: Living wall slightly better • Water costs higher than expected

– Dry summer – Compensate for water shut off

• 186 questionnaire responses received

Slide 10

Page 11: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

What respondents liked most

Slide 11

Page 12: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

What respondents liked least

Slide 12

Page 13: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Next Steps

• Update pond design and associated works based on feedback

• Procure sewer construction contractor – March 2016

• Procure dry pond expansion contractor – June 2016

• Close land agreements – April 2016

Slide 13

Page 14: Tweddle Place Storm and Sanitary Upgrades … · Tweddle Place Storm and Sanitary Upgrades Project Update to Millbourne Community November 19, 2015. 2015 Construction Progress . Slide

Questions, Comments or Concerns

Contact: Diane Wirtz, Project Manager [email protected] 780.944.5975

Slide 14