transport and road research laboratorythe transport research foundation on 1 st april 1996. this...
TRANSCRIPT
TRANSPORT and ROAD RESEARCH LABORATORY
Department of the Environment Department of Transport
TRRL SUPPLEMENTARY REPORT 816
BITUMEN PERMITTIVITY AND TEXTURE DEPTH OF ROLLED ASPHALT: AN EXPERIMENT ON MOTORWAY M4
by
M E Daines
Any views expressed in this Report are not necessarily those of the Department of the Environment or of the Department of Transport
Pavement Materials and Construction Division Highways and Structures Department
Transport and Road Research Laboratory Crowthorne, Berkshire
1983
ISSN 0305-1315
Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation on 1 st April 1996.
This report has been reproduced by permission of the Controller of HMSO. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.
Abstract
1.
2.
°
4.
5.
Introduction
Experimental work
2.1 Site
2.2 Traffic
2.3 Rolled asphalt
2.4 Bitumens
2.5 Mixing
2.6 Laying
2.7 Pre-coated chippings
2.8 Rolling
2.9 Climate
2.I0 Surface texture
2.11 Skidding resistance
Future measurements
Acknowledgements
References
CONTENTS
Page
1
1
2
2
2
2
3
3
5
8
8
9
9
10
11
11
11
© CROWN COPYRIGHT 1983 Extracts from the text may be reproduced, except for
commercial purposes, provided the source is acknowledged
BITUMEN PERMITTIVITY AND TEXTURE DEPTH OF ROLLED ASPHALT: AN EXPERIMENT ON MOTORWAY M4
ABSTRACT
During August 1982 a full-scale experiment was begun with the aim of studying the effect of the permittivity of bitumen on the texture depth of heavily-chipped Marshall-designed rolled asphalts. Seven sections of asphalt were laid and, apart from the differences in permittivity, the asphalts were nominally identical. The experimental sections were laid in all three lanes of Motorway M4, Wiltshire. The changes in texture depth and skidding resistance at the three traffic intensities will be monitored for at least 5 years.
1. INTRODUCTION
Prior to 1976 the only binders that were specified for use in roiled asphalt surfacing on Trunk Roads and Motorways
were Trinidad Lake Asphalt/bitumen and pitch/bitumen blends. These binders had proven 'weathering' ability; as
the asphalt mortar was eroded, the applied chippings and coarse aggregate were re-exposed to enable the texture
depth to be maintained, even under heavy traffic. Petroleum bitumens had been excluded because some produced
slippery surfacings. Green 1 showed that the ability of petroleum bitumens to 'weather ' under the combined
effects of ultra-violet light in sunlight, oxidation, rain and oil deposition f rom traffic was related to the permittivity
of the bitumen. Consequently, 50 pen grade petroleum bitumen was included in the Department of Transport
Specification 2 provided its permittivity was at least 2.650 at 25°C. A requirement for a value of 2.630 for 35 pene-
tration grade bitumen was subsequently included in the Specification 3 and both values included in the revised
edition of BS 3690 published in 1982.
1 The experimental basis of this work was the core-transplant technique m which 200 mm diameter cores of
experimental asphalts made with 50 penetration grade bitumens were inserted in an existing trunk road surfacing.
Several parameters were studied at a number of sites and it was found that the absolute level of texture depth that
developed depended on binder content, type of sand and climate. However, the ranking of bitumens was independent
of these variables and depended on their permittivity. Evidence from a subsequent experiment 4 showed that the
weathering rate was independent of the penetration grade, at least in the range 35 to 70 penetration. Because the
presence of pre-coated chippings would, to some extent, hinder the reliable measurement of the development of
texture depth, most o f the previous work was accomplished using unchipped asphalts containing 30 per cent coarse
aggregate.
Since the publication of that work in LR 777 a number of developments have occurred in rolled asphalt
technology. The use of the Marshall Test, a design method to determine the opt imum binder content for rolled
• asphalt has increased, resulting in a reported slight reduction in binder contents generally. Rates of spread of chippings
have also increased and it is now common to apply them at a rate that covers 70 per cent o f the surface and is
sufficient to achieve a minimum texture depth of 1.5 mm. It is also believed that the rate of deposition of oil from
constant loss lubrication systems has reduced as more efficient systems are now being fitted to commercial vehicles.
These changes may affect the contribution 'weathering' plays in the retention of texture depth and when they are
coupled with the possibility that bitumens may in future have to be manufactured from crude oils drawn from new
or alternative sources, it is highly desirable to re-assess the permissible level o f bi tumen permittivity. This paper
describes the initiation of a full-scale experiment to study the changes in texture depth of a typical modern heavily-
chipped rolled asphalt designed by the Marshall Test and made with bitumens covering a range of permittivities.
2. EXPERIMENTAL WORK
Because the primary object of the experiment was to study the effect of bitumen permittivity on the long-term
retention o f texture depth, the only planned variable was the level of permittivity. As far as was practicable, all
other factors were kept constant. A secondary objective, to study the effect of traffic intensity, was introduced
on learning that the experimental asphalts could be laid on all three lanes of a motorway over a length of about
800 m.
The experiment comprised seven sections of rolled asphalt wearing course, laid as 50 mm thick overlays on
the existing wearing course and covering both the main carriageway and hard shoulder. Each section, of approxi-
mately 120 m, was made with a bitumen denoted by its permittivity level. Because all the asphalts laid were of
the same nominal composition, the concept of a control section did not apply; the performance of each section
will be assessed directly in relation to the others. The experimental surfacings were laid during August 1982 and
the details are given below.
2.1 Site
The site was on M4, near Acton Tundlle, on the eastbound carriageway east of Junction 18 between marker
posts 164/8 and 163/9. The asphalts were laid between 21st and 28th August 1982,the agent authority being
Wiltshire County Council. Figure 1 shows the site o f the experiment and Figure 2 shows the layout of the
experimental sections.
2.2 Traffic
A manual traffic count made on Thursday 9th September 1982 yielded the following results.
TABLE 1
M4 Acton Turville: Daily Traffic Flow*
Lane
Nearside
Centre
Offside
commercial vehicles (>1.5 tonnes)
3,676
759
10
Cars
3,647
6,693
1,603
Total vehicles
7,323
7,452
1,613
Total 3 lanes Westbound 4,615 12,909 17,524
* Basis: 6 a.m. - 10 p.m. count X 1.06
2.3 Rolled asphalt
For the experimental surfacings a crushed 14 m m basalt was used as the coarse aggregate, and the time
aggregate was a blend of 2 parts of crushed Cromhall doleritic limestone and one part of Hilton sand. Crushed
limestone was used as added Idler.
The mixture was designed in accordance with Section 3 of BS 594:1973. For the mortar of free aggregate,
filler and binder, the contractors found the op t imum binder content to be 9.8 per cent and with the 30 per cent
o f coarse aggregate specified, a design binder content o f 7.6 per cent. Verification of the procedure by TRRL gave
a design binder content o f 7.0 per cent; this is however, well within the reproducibility of the test.
2
The specified mix (on analysis) was thus:-
Coarse aggregate
Fine aggregate (crushed limestone/sand)
Filler
Binder
30 per cent
53.4 per cent
9.0 per cent
7.6 per cent
2.4 Bitumens
Seven experimental bitumens were used with permittivities ranging from 2.619 to 2.684. The softening points
were similar at about 52°C but penetrations varied from 36 to 68. The range of bitumens was obtained through the
Ref'med Bitumen Association, representing most of the major suppliers in the U.K.
The bitumens were delivered in tanker quantities of about 17 tonnes, usually on the day prior to laying, to
a 40 tonne c~pacity storage tank reserved for the purpose; delivery was planned in decreasing order o f permittivity,
the bitumens being numbered 1 to 7 corresponding with laid section members. Prior to discharge from the tanker
the storage tank was pumped out to as low a level as was practicable; approximately 1.3 tonne remained as a tank-
bottom. This sequence was followed so that the least change in permittivity occurred on mixing in the storage tank.
Bitumen samples were taken from the delivery tanker during or immediately prior to discharge and also from the
storage tank the following morning during mixing of the asphalt. Results of tests on the bitumen are given in Table 2.
TABLE 2
Properties of bitumens
Bitumen
1
2
3
4
5
6
7
Penetration 25°C
DT ST R
68 62 41
44 49 38
49 49 41
48 53 37
50 51 36
50 46 37
36 38 32
Softening Point °C Permittivity 25°C
DT DT
52.5
53.5
51
52
52
51.5
53.5
ST R
52 58.5
53.5 59.5
50.5 54.5
51.5 58
52 56.5
52 57.5
53 57
2.684
2.646
2.659
2.648
2.641
2.626
2.619
ST R
2.684 2.698
2.653 2.730
2.664 2.698
2.651 2.709
2.645 2.681
2.630 2.662
2.622 2.652
DT: sampled from delivery tanker on arrival
ST: sampled from storage tank during mixing
R: bitumen recovered from second lorry load laid on nearside lane
2.5 Mixing
The asphalts were mixed in a new Marini plant, capable of 100 t/h, sited at Cromhall Quarry, about 13 miles
from the road site. The plant was fitted with 200 t total capacity hot storage hoppers. Mixing of experimental
asphalts commenced at about 6 a.m., and 100 tonnes of asphalt were mixed and stored prior to discharge into
delivery lorries. The plant was then switched to providing material for another contract for about 1 hour and
subsequently a further 100 tonnes of experimental asphalt was produced, using up the remainder of the experi-
mental bitumen. The asphalts were mixed at a target temperature of 190°C. Samples were taken from the delivery
3
lorries at the plant for analysis by the Contractor. Their analyses are given in Table 3. From these results, binder
contents varied by up to -+0.5 per cent from the target figure.
TABLE 3
Analysis of asphalt samples taken at mixing plant
Section and Lane
Section 1
Offside
Centre
Nearside
Section 2
Offside
Centre
Nearside
Section 3
Offside
Centre
Nearside
Section 4
Offside
Centre
Nearside
Section 5
Offside
Centre
Nearside
Section 6
Offside
Centre
Nearside
Section 7
Offside
Centre
Nearside
Coarse Aggregate
%
30.9
29.3
32.7
33.0
30.9
27.1
27.9
31.2
34.1
28.1
30.9
29.9
34.5
30.3
32.2
27.7
28.7
28.1
29.9
30.7
29.1
Filler* %
8.4
8.6
8.6
8.4
8.7
9.0
8.9
9.5
9.8
8.9
9.2
9.7
9.8
9.6
9.1
11.2
9.7
10.1
9.1
9.4
10.0
Binder* %
7.6
7.4
7.7
7.7
7.1
7.4
7.3
7.4
7 3
7.6
7.7
7.6
7.7
7.6
7.6
7.2
7.5
7.4
7.9
8.1
7.6
Average 30.3 9.3 7.5
Analysis by ARC at Cromhall Quarry. Bottle method (binder by difference)
The samples were taken from the second lorry load destined for each lane section.
* Adjusted to 30 per cent stone content.
4
2.6 Laying
Laying usually commenced after 8 a.m., starting with the offside lane, laying in the direction of traffic flow.
Approximately three 18 t lorry loads of asphalt were laid per lane-length of about 110 m. The Blaw-Knox paver
laid the asphalt as an overlay, nominally 50 mm thick on the existing wearing course. A number of cracks up to
about I0 mm wide, were generally evident throughout the length of old surfacing; these were not grouted prior to
surfacing. If the adjacent strip was laid immediately following the previous one, the longitudinal joint was painted
with hot bitumen without being first cut-back. I f laying did not follow immediately all joints were cut before
painting. The beginning and end of each section • was cut at about 70 ° to the direction of the traffic at the request
of the Agent Authority, as this was believed to improve the riding quality at the joints. However, this necessitated
hand-laying asphalt at the start of each section, and there has been some fretting in these areas, together with some
10 m or so of poor longitudinal profde.
The temperature of the asphalt was monitored as delivered, when leaving the paver and in the mat when first
roiled; the values recorded are given in Table 4. Samples of asphalt were taken f rom the screws of the paver for
the middle lorry load for each lane length. Analysis results are given in Tables 5 to 7. The thickness of the
uncompacted asphalt mat leaving the paver was monitored by a simple depth gauge. Results are given in Table 8.
TABLE 4
Asphalt temperatures
Asphalt Temperatures (°C)
Delivery Lorry Leaving •Paver (average) Rolling (start) Section Lane
Load 1
1 NS 155 C 163 OS 158
2 NS - C 169 OS 155
3 NSt 160 C 171 OS 160
4 NS 170 C 180 OS 159
5 NS 165 C 169 OS 152
6 NS 180 C 180 OS 168
7 NS 172 C 182 OS 182
Load 2
171 166 160
170 172 * 164
178 166
188 170 167
170 162 160
180 185 172
170 194 180
Load 3
163
168
164 165
189 168 172
165 165 170
181 180 166
185 180
Load 1
140 145 140
130 150
145 150 140
147 162 148
150 150 140
175 170 152
165 175 174
Load 2 Load 3
150 160 160 152 147 145
155 150 165 155
147 152 155 150 145. 155
175 178 156 150 159 160
160 157 153 146 150 160
165 168 172 173 163 153
165 180 176 165 166
Range* * Ave rage
115-150 143 115-152 144 120-140 130
110-130 121 115-160 126 130"145 137
100-140 125 1 1 0 - 1 3 4 125 100-143 124
110-142 125 117-140 130 103-148 119
128-155 142 110-146 131 114-156 136
123-151 135 122-149 136 107-155 134
100-147 130 125-150 136 123-149 138
NS = nearside C = centre OS = offside * Non-experimental 35 pen asphalt laid approximately 4 0 - 6 4 m from start of section. ** The lower values represent the cooler starts and ends of laid loads. t Chipping spreader breakdown. Asphalt hand-chipped from about 1 0 - 2 4 m f rom start of section, and rolled
cool (104°C). 3-hour delay before remainder of mixed asphalt laid. 5
TABLE 5
Analysis of wearing course samples
Nearside Lane
Measured/ Corrected
Constituent 1
Coarse aggregate Measured 32.2 % Corrected 30.0
Fine aggregate Measured 52.4 % Corrected 54.2
Filler % Measured 8.1 Corrected 8.3
Bitumen % Measured 7.3 Corrected 7.5
Notes: 1. 2. 3.
Section
2 3 4 5
23.3 28.9 28.5 31.3 30.0 30.0 30.0 30.0
57.8 53.4 54.0 52.0 53.5 52.5 52.9 53.1
11.1 9.8 9.7 9.2 10.4 9.7 9.5 9.3
7.8 7.9 7.8 7.5 7.1 7.8 7.6 7.6
6 7
27.2 25.9 30.0 30.0
54.4 56.6 52.2 53.3
10.7 9.2 10.4 8.8
7.7 8.3 7.4 7.9
Analysis by DTp Materials Testing Laboratory using sieve-shaker method (dry-sieving basis). Each section comprised three lorry loads: the sample was taken from the second load. Constituents corrected to a coarse aggregate content of 30 per cent.
TABLE 6
Analysis of wearing course samples
Centre Lane
Constituent Measured/ Corrected
Coarse aggregate Measured % Corrected
Fine aggregate Measured % Corrected
Filler % Measured Corrected
Bitumen % Measured Corrected
Notes: 1. 2. 3.
1 2*
25.5 (34.4) 30.0 (30.0)
57.3 (49.9) 53.8 (53.5)
9.2 (8.0) 8.7 (8.4)
8.0 (7.7) 7.5 (8.1)
Section
3 4 5
28.4 27.6 31.0 30.0 30.0 30.0
54.0 55.0 52.2 52.8 53.0 53.4
9.8 9.3 9.2 9.6 9.1 9.1
7.8 8.1 7.6 7.6 7.9 7.5
6 7
26.0 34.2 30.0 30.0
55.3 48.2 52.1 51.6
10.6 10.0 10.2 10.4
8.1 7.6 7.7 8.0
Analysis by DTp Materials Testing Laboratory using sieve-shaker method (dry-sieving basis). Each section comprised three lorry loads; the sample was taken from the second load. Constituents corrected to a coarse aggregate content of 30 per cent.
* Sample was taken from section 2NX.
6
TABLE 7
Analysis of wearing course samples
Offside Lane
Constituent Measured/ Corrected
Coarse aggregate Measured % Corrected
Fine aggregate Measured % Corrected
Filler % Measured Corrected
Bitumen % Measured Corrected
Notes: 1. 2. 3.
1 2
27.3 30.4 30.0 30.0
56.3 53.6 54.2 53.6
9.0 8.4 8.7 8.4
7.4 7.6 7.1 7.6
Section
3 4
31.1 27.2 30.0 30.0
52.1 53.0
55.7 53.5
9.3 9.2 9.4 8.9
7.5 7.9 7.6 7.6
5 6 7
28.6 2 7 9 31.2 30.0 30.0 30.0
53.8 54.2 52.0 52.6 52.5 53.0
9.6 10.2 9.0 9.5 10.0 9.1
8.0 7.7 7.8 7.9 7.5 7.9
Analysis by DTp Materials Testing Laboratory using sieve-shaker method (dry-sieving basis). Each section comprised three lorry-loads; the sample was taken from the second load. Constituents corrected to a coarse aggregate content o f 30 per cent.
T A B L E 8
Tonnages and thicknesses
Section Lane
1 NS C OS
2 NS C OS
3 NSt C OS
4 NS C OS
5 NS C OS
6 NS C OS
7 NS C OS
Average thickness* (ram)
Tonnage ~ ) Nea~ide Centre Offside Overall
of lane of lane of lane
- 57 52 53 54 - 5 2 5 5 5 4 5 4 - 5 5 5 5 5 3 5 4
- 52 49 49 50 43.0 56 52 5 3 54
- RoUed depth 50--52 51
- 61 51 52 54 48.9 54 52 54 53 48.8 51 51 54 52
48.6 57 51 52 53 53.5 52 52 56 53 49.6 56 55 55 55
4 8 3 55 51 51 52 53.1 53 51 52 52 49.3 53 53 52 53
50.3 55 51 52 53 48.9 56 54 56 55 49.6 53 53 53 53
39.7 ** 55-.7 54.9
53 54 56
53 55 55
56 57 54
54 55 55
NS = Nearside C = Centre OS ~- Offside
* Behind paver, before being chipped and compacted. ** 1st part started with load 3 of centre lane; a further part load was used to finish off. t See footnote to Table 4. Load 2 laid too thick for 1st 10 m; raked off and rolled at 125°C.
2.7 Pre-coated chippings
These were 20 m m Craig-yr-Hesg (PSV 6 8 - 7 0 ) applied with a Bristowes spreader. The rate-of-spread was
moni tored with 5 x 300 m m square trays laid across the lane width. Three sets of measurements were made per
lane per section, and the target rate o f spread necessary to achieve 70 per cent coverage of chippings was checked
daily. Results are given in Table 9; the average overall rate of spread was 13.0 kg/m 2 , slightly lower than the target
rate o f spread of 13.8 kg/m 2 .
During the measurement of rate-of-spread, the chippings were not replaced on the 300 mm square test area
coincident with the wheelpath. This provided three unchipped areas of asphalt per lane-section that will enable the
relationship between the retention of texture depth by the chipped asphalt and the development of texture by the
unchipped asphalt, to be studied.
T A B L E 9
Rates of spread of chippings (kg/m 2)
Section Lane
1 2 3 4 5 6 7
Nearside
Centre
Offside
Hard shoulder
12.6
12.5
13.2
11.3
12.8
13.0
13.1
12.7
12.9
14.4
12.0
12.4
13.7
12.7
13.3
13.6
13.1
13.4
14.1
12.8
12.4
11.6
Note: Each value is the mean of 3 groups of at least 5 trays.
Target rate o f spread
Date kg/m 2
20/8/82 13.5 21/8/82 14.0
21/8/82 13.2
23/8/82 13.7
25/8/82 14.0
28/8/82 14.2
Overall average 13.8 kg/m 2 for 70 per cent coverage rate
2.8 Rolling
Target rate of spread 13.8 kg/m 2
Actual overall average 13.0 kg/m 2
ie. actual coverage was 13.0
13.8 - - x 70 per cent = 66 per cent
Rolling was carried out by two 8 - 1 0 tonne tandem rollers and was controlled to achieve, as far as was
practicable, the same rolling conditions for each section and a texture depth of 1.5 ram. Initial rolling was in half
roller-width strips, rolling the but t edge first. The roller was held back until the asphalt mid-layer temperature was
8
140°C or less; because of high delivery temperatures coupled with warm ambient conditions and a 50 mm thick
layer, this sometimes resulted in a long mat being laid before roiling could commence. Final rolling on these
occasions had to be delayed by up to an hour.
2.9 Climate
Weather conditions, including temperature and wind speed, were monitored to provide an estimate of the
time available for compaction. The estimated compaction times given in Table 10 range from 16-21 minutes and
were well in excess of the 10 minutes reckoned to be the lower limit for satisfactory compaction as suggested by
Br0wn 5. It should be noted that the compaction time includes the time between the material being laid and the
application of pre-coated chippings, time that is not available for rolling.
TABLE 10
Weather and estimated times for compaction
Section Date laid Wind km/h
Temp. o C
Weather
Remarks
Estimated time for
compaction* (rain)
1 21/9[82 8 13 Dry and sunny 17.1
2 23/9/82 11 16 Dry, sunny intervals 16.8
3 24/9182 12 13 Gusty, early rain, cloudy and 16.2 heavy rain during laying of nearside lane. Asphalt steam- heaving
4 25/9/82 5 14 High cloud and drying from 17.9 overnight rain
5 26/9/82 10 14 Dry and sunny at site (but 16.7 raining hard at mixing plant)
6 27/9/82 5 14 Wet surface initially but dry 17.9 and sunny later
7 28/9/82 0 - 5 16 Dry and sunny 21.0-18.2
* Predicted time to cool from a mid-layer initial laid temperature of 150°C, to 100°C, for a layer thickness of
50mm.
2.10 Surface texture
After the surfacings had cooled sufficiently, texture depth was determined for each lane in each section.
Ten sand patches at 10 m spacing were measured in the nearside wheelpath and 10 patches at 5 m spacing along
a 50 m diagonal were also determined. The surface texture was monitored along the same two lines with a
prototype portable hand-operated texture meter. Sand-patch results, given in Table 11, show significant differences
in initial texture depths between sections, but it is changes from these values that will be observed. All the work
complied with the requirements of Departmental Standard HD/3/80.
9
TABLE 1 1
Initial surface textures
Sand-patch texture depth: means o f l O tests (mm)
Lane
Hard shoulder
Nearside
Centre
Offside
Position
50 m Diagonal 100 m Wheelpath
50 m Diagonal 100 m Wheelpath
50 m Diagonal
100 m Wheelpath
50 m Diagonal 100 m Wheelpath
* 5 tests near end of section
** Wheelpath on NX 35 pen
1.41 1.75
1.30 1.60
1.49
1.57
2
D
D
1.86 1.80
1.97* (2.00) ** 2.14
1.68 1.60 1.55 1.59
D
1.79 1.49
1.51
1.73
1.78 1.76
Section
3 4
1.87 2.15
1.69
1.73
1.40 1.56
5 6
1.38 1.84 1.71 2.13
1.92 1.54
1.82 1.79
1.68 1.71 1.39 1.74
7
2.07 1.78
1.73
1.85
1.47 1.32
2.11 Skidding resistance
Measurements of sideway-force coefficient, at 50 km/h (SFCs o) were made in the nearside lane a week after
opening to traffic, and also a month later. Results are included in Table 12. No interpretation should be placed on
these early results except that the initial skidding resistance of all the sections is satisfactory.
T A B L E 12
Sideway force coefficient (SFCs o)
Section
NX (old surfacing)
1
2
3
4
5
6
7
NX (new surfacing)
" Sideway force coefficient
3/9/82*
0.59
0.64
0.64
0.63
0.62
0.63
0.61
0.60
0.59
12/11/82"*
' 0.55
0.53
0.54
0.55
0.54
0.55
0.53
0.55
0.54
* After 1 week of traffic
** After 11 weeks of traffic
NX: Non-experimental surfacing up to and after experimental work.
1 0
3. F U T U R E M E A S U R E M E N T S
The following measurements are to be made at 6-monthly intervals, during the Spring and Autumn for at least the next five years.
1) Texture depth by sand-patch and texture meter. 2) Sideway force coefficient at 50 km/h.
3) Rut depths and longitudinal profiles. 4) Visual inspections (annually at Ftrst and then biennially).
It is unlikely that significant conclusions relating to permittivity and texture depth retention will be apparent for some years. Although the sections comprised materials that were nominally the same, except for their binders,
differences in initial texture depths and other properties roay have to be taken into account in interpreting long-
term trends.
4. A C K N O W L E D G E M E N T S
The co-operation and assistance of the following organisations is gratefully acknowledged. The County Surveyor
of Wiltshire and his staff; the Regional Controller ( R & T) South West; and the Refined Bitumen Association.
The laying work was carried out by Amey Roadstone Corporation, Frome, Somerset.
This report was prepared in the Pavement Materials and Construction Division of the Highways and
Structures Department, TRRL. (Division Head: Mr G F Salt).
.
.
.
.
.
5. R E F E R E N C E S
GREEN, E H. An acceptance test for bitumen for rolled asphalt wearing course. Department of the Environ- ment, Department of Transport, TRRL Report LR 777. Crowthorne, 1977 (Transport and Road Research
Laboratory).
DEPARTMENT OF TRANSPORT. Specification for Road and Bridge Works. Amendment to specification
for bitumen binder in rolled asphalt wearing course. Department of Transport Technical Memorandum H1/7Z London, 1977 (Department of Transport).
DEPARTMENT OF TRANSPORT. Specification for Road and Bridge Works. Rolled Asphalt Wearing
Course Departmental Standard HD/2/79, London, 1979 (Department of Transport).
DAINES, M E. The weathering of 35 pen and 70 pen bitumens in rolled asphalt. Department of the Environment, Department of Transport, TRRL Working Paper MM 62. Crowthome, 1980 (unpublished).
BROWN, J.R. The cooling effects of temperature and wind on rolled asphalt surfacings. Department of the Environment, Department of Transport, TRRL Report SR 624, Crowthorne, 1980 (Transport and Road
Research Laboratory).
11
Luckington
Badminton
Old Sodbury
B4040
SITE OF EXPT.
Tormarton
0 I 0
1 2kin ! J
I
1mile
North Wraxall
Fig. 1 Locat ion of pe rm i t t i v i t y experiment on the eastbound carriageway of M4 at Acton Turville
T
q
~D
L~
~D
r~
e~ 0
"0
0 .-J
0
X Z
r ~
, , ,o
E
LU O~
LU
E
L U g - -
LU ~-~
"E C~ f~
t -
o . o
0
. I
cD
D_ O ~ t¢ D c- "O
-~ ~, 8 o
(3) Dd8041326 1,400 1/84 HPLtd S o ' ton G3371 P R I N T E D I N E N G L A N D
ABSTRACT
Bitumen permittivity and texture depth of rolled asphalt: an experiment on motorway M4: M E DAINES: Department of the Environment, Department of Transport, TRRL Supplementary Report 816: Crowthome, 1983 (Transport and Road Research Laboratory). During August 1982 a fuU-scale experiment was begun with the aim of studying the effect of the permittivity of bitumen on the texture depth of heavily-chipped Marshall-designed rolled asphalts. Seven sections of asphalt were laid and, apart from the differences in permittivity, the asphalts were nominally identical. The experimental sections were laid in all three lanes of Motorway M4, Wiltshire. The changes in texture depth and skidding resistance at the three traffic intensities will be monitored for at least 5 years.
ISSN 0305-1315
ABSTRACT
Bitumen permittivity and texture depth of rolled asphalt: an experiment on motorway M4: M E DAINES: Department of the Environment, Department of Transport, TRRL Supplementary Report 816: Crowthorne, 1983 (Transport and Road Research Laboratory). During August 1982 a full-scale experiment was begun with the aim of studying the effect of the permittivity of bitumen on the texture depth of heavily-chipped Marshall-designed rolled asphalts. Seven sections of asphalt were laid and, apart from the differences in permittivity, the asphalts were nominally identical. The experimental sections were laid in all three lanes of Motorway M4, Wiltshire. The changes in texture depth and skidding resistance at the three traffic intensities will be monitored for at least 5 years.
ISSN 0305-1315